SAMUEL CLEMENS ADDITIONS & RENOVATIONS (10-30-2017) BUDGET - $ 72,000,000 2020 PROJECTED COMPLETION DATE ARCHITECT MARMON MOK GENERAL CONTRACTOR Bartlett Cocke CONSTRUCTION MGMT. AG CM 18% COMPLETE
SAMUEL CLEMENS ADDITIONS & RENOVATIONS As part of the Bond 2016 Program, Samuel Clemens High School Additions and Renovations will consist of expansion of square footage and renovation of existing spaces to meet current educational/industry standards. Some main points regarding scope of work included in this project: New Event Center (connected to Beard Gym) to house new auditorium, new auxiliary gym, new choir and dance areas, new locker rooms and support spaces. New Career & Technology (CTE) Building (near Baseball Field) to house welding, woodshop, floral design, small animal, and other learning spaces, including new classrooms. The existing Auxiliary Gym will be renovated to include additional CTE classrooms and labs, including a new culinary kitchen, health occupations spaces and other learning areas. The existing auditorium will be removed and the courtyard space will be enlarged. New Front Addition (facing Elbel Rd.) which will include new classrooms and new administration and support spaces. Renovation of JROTC spaces and existing spaces. Additional renovated spaces throughout the building, such as art rooms, teacher work spaces, nurse s clinic. Additional parking space, to include new parking along Elbel and near stadium. ESTIMATED PROJECT COMPLETION SPRING 2020.
SAMUEL CLEMENS ADDITIONS & RENOVATIONS SCHEDULE ACTION/EVENT PROJECTED DATE FINAL DESIGN APPROVED (BOT) January 2017 BIDS OUT FOR CONTRACTORS February 22, 2017 BIDS RECIEVED March 30, 2017 EVALUATION OF BIDS March 30 April 5, 2017 CONTRACTOR RECOMMENDATION TO BOT April 18, 2017 NOTICE TO PROCEED May 24, 2017 PROJECT COMPLETION February 2020 ONGOING ACTIVITIES CTE Building MEP Rough-ins Exterior Masonry Waterproofing Site work Event Center Drilling Piers Steel erection to start up Classroom / Admin Add Steel erection to start up
SAMUEL CLEMENS ADDITIONS & RENOVATIONS
SAMUEL CLEMENS ADDITIONS & RENOVATIONS Career, Technology, and Engineering Building New Career, Technology, and Engineering building has MEP rough-ins, interior insulation & drywall, exterior masonry, and site work on-going Located near baseball field on what used to be old tennis courts. This building will house welding, woodshop, small animal and other Career & Technology classes. 10-30-2017
SAMUEL CLEMENS ADDITIONS & RENOVATIONS Classroom and Administration Addition New Classroom and Administration addition. Structural steel delivered on site, erection to follow. This building will be an addition to the front of the main high school front entry. This building will include nineteen instructional classrooms and support additional administration offices 10-30-2017
SAMUEL CLEMENS ADDITIONS & RENOVATIONS Auxiliary Gym Addition New Auxiliary Gym addition has structural steel being erected. This building will be an addition to Beard Gym and the future Event Center Gym will support as the new practice gym and seat approximately 300 people 10-30-2017
SAMUEL CLEMENS ADDITIONS & RENOVATIONS Event Center New Event Center continues with drilling piers, installing utility infrastructure, and final excavation activities. New Event Center Excavation. This area will consist of; new auditorium, new dance/cheer studio, new choir room and new locker room facilities. Beard Gym HVAC units placed on existing locker rooms. 10-31-2017
SAMUEL CLEMENS ADDITIONS & RENOVATIONS Buffalo Drive Parking Lot New Buffalo Drive Paring Lot is underway with excavation and grading activities ongoing. New Parking Lot on the NE side of the property along Buffalo Drive will bring added parking spaces for the Clemens students. 10-30-2017
SAMUEL CLEMENS ADDITIONS & RENOVATIONS CTE Building 1. MEP Rough-ins 2. Exterior masonry 3. Interior paint 4. Site work Classroom /Admin Addition 1. Steel erection to start up Auxiliary Gym 1. Structural steel erection Event Center 1. Drilling Piers 2. Steel erection to start up Two Week Look Ahead
SAMUEL CLEMENS ADDITIONS & RENOVATIONS Anticipated Substantial Completion Dates: D and S-Wing Remote Admin Offices August 2017 Northeast Parking Addition...December 2017 New CTE Building...January 2018 Front Classroom and Administration Addition...August 2018 ROTC Renovation...Fall 2018 New Event Center January 2019 Existing Administration Renovation.January 2019 Renovate Existing Auxiliary Gym into Culinary/HOSA Labs August 2019 A-Wing Renovation...August 2019 B-Wing Renovation...December 2019 Front Parking and Flat work..march 2020
SAMUEL CLEMENS ADDITIONS & RENOVATIONS