Arlington Public Schools Purchasing Office

Similar documents
NOTICE TO ALL FIRMS. Bid RFI Questions and Answers

RE: Clark East Tower Renovations DATE: November 16, 2015 Ypsilanti, Michigan

Springpoint Architects, pc SECTION Childcare Center Architect s Project No TABLE OF CONTENTS Monroe County Comm. Sch. Corp.

PROJ. NO SECTION PAGING, SPEAKERS AND HARD-WIRED CLOCK SYSTEMS

Element C Interiors Interior Construction

DOCUMENT ADVERTISEMENT FOR BIDS

ADDENDUM #1: MODIFICATIONS AND ADDITIONS TO CONTRACT DOCUMENTS

TERRACE VIEW APARTMENTS

New School Construction: Safe School Opening. OAR and IOR Joint Training February 17, 2005

Library stacks and records storage 150 LB/SF live load

Lock Department. Ben Riding. Assistant Hardware Supervisor Maintenance and Operations. Voice: Fax:

Garfield Elementary School Feasibility Study for New Library Building Project Number A C

TERRACE VIEW APARTMENTS

Attendees/Absentees. Derek Gallagher DG. Delano Secondary School Additions and Renovations June 6, 2016 Technology User Group Meeting Minutes

Electronic Safety and Security

TERRACE VIEW APARTMENTS

M001. Revenue Services ISSUED FOR CONSTRUCTION SEPTEMBER. 2, East State Parkway Schaumburg, Illinois Do Not Scale Drawings

SPACE TYPE: CHILD CARE

ADDENDUM NO. 1 BID-CONTRACT DOCUMENTS FOR. RFP No Professional Design Services for CCC Le-Jao Student Resource Center

TERRACE VIEW APARTMENTS

HMC ARCHITECTS 2495 Natomas Park Drive, Studio 100 Sacramento, California ADDENDUM NO. 3

Briar Crest Elementary

TERRACE VIEW APARTMENTS

2015 Building Condition Survey Summary Mosaic Associates Architects 02/19/16

SPACE TYPE: JUDICIAL CHAMBER

ADDENDUM NO. 1. for. MARQUETTE HOUSING COMMISSION Pine Ridge Apartments Fire Alarm Replacement Project #A1140. Marquette, Michigan.

ATTACHMENT A - ITEM DETAIL

TERRACE VIEW APARTMENTS

Columns REF, RESPONSIBLE and COMPL TD are provided for your numbering, assignments and control. REF ISSUE RESPONSIBLE COMPL TD

ALABAMA. Downloaded

Item No. Description 1. BID PROPOSAL FORM Make the following revisions: a. Replace the BID PROPOSAL FORM with the attached BID PROPOSAL FORM.

FEE SCHEDULE Construction Services and Permitting

TERRACE VIEW APARTMENTS

Parts for Avery Dennison ST9000 TM Plastic Staple Attacher Old Style

VOTER BOND REFERENDUM 2018 SUMMARY OF WORK PROPOSED

COSMETOLOGY September 30, 2010

SECTION RECORD DOCUMENTS and FIELD ENGINEERING

DIVISION 10 SPECIALITIES

Design Review of Facility Improvement Projects

HOT WORK PERMIT PROCEDURES

Florida Department of Transportation

Memphis Housing Authority High Rise Fire Alarm Upgrades. Questions from Contractors (Through Addendum #2) Communications Systems, Inc.

ENVIRONMENTAL HORTICULTURE: AGRISCIENCE AND BIOTECHNOLOGY September 30, 2010

Florida Department of Transportation 1000 NW 111 th Avenue, Room 6203 Miami, Florida

Town of Cicero Local Code Amendments

PLATTEVILLE MIDDLE SCHOOL

3.2.4 OFFICE FACILITIES

Yes, any other system must be clean agent, and the Fire Alarm Control Panel must be a single addressable Fire Alarm Control Panel.

PUR933- Christmas Decoration Installation Addendum 1. Pricing:

DOCUMENT T CAWTHRA SHELTER RENOVATIONS, 2500 CAWTHRA ROAD, CITY OF MISSISSAUGA, PROJECT E ADDENDUM 2

ELECTRICAL SYSTEMS ASSESSMENT Hanover High School

Campus Wide Fire Alarm Repairs

ADDENDUM NO. 1. PREPARED BY: Justin Scott DATE PREPARED: 05/25/2018. PROJECT: Centerville-Washington Park District Park Operations Facility

CITY OF PORTSMOUTH Department of Public Works MUNICIPAL COMPLEX FIRE ALARM. Bid # Addendum #1

STATEMENT OF WORK ELECTRICAL REPAIR / MAINTENANCE BUILDING PROJECT FDC RACCOON CREEK STATE PARK (BEAVER COUNTY)

SECTION REGULATORY REQUIREMENTS. A. Relationship between Code, Ordinances, Standards and Contract Documents

Riverview West Side Elementary 160 Isabel Avenue East

The following information shall become and form part of the contract documents.

Florence High School / Middle School Page 1 of 3 Florence, WI

MUKWONAGO SCHOOL DISTRICT CAPITAL IMPROVEMENT / MAINTENANCE STUDY

CLEVELAND HEIGHTS UNIVERSITY HEIGHTS CITY SCHOOL DISTRICT MONTICELLO & ROXBORO MIDDLE SCHOOLS INTERIOR DESIGN


DONALD H. BERG, ARCHITECT

Addendum # 2 Wicomico County Circuit Court Second Floor Renovations Date of Addendum: 2/6/2017

Forest Hills Facilities Plan

MEDIA CENTER September 30, 2010

SECTION FIRE DETECTION AND ALARM

ADDENDUM # 2 TO RFP #

Project No Belleville Fire Hall/Headquarters and Emergency Operations Centre Section Belleville, Ontario Page 1 of 10

AGENDA. 1. Call to Order. 2. Approval of Minutes. 3. Approval of Invoices and Commitments. 4. Review Updated Site Analysis and Permitting

ADDENDUM #3. Chauncey Wilmore Senior Procurement Officer March 22, 2016 ALL PROSPECTIVE FIRMS

PALO ALTO HIGH SCHOOL. Palo Alto Unified School District SCHEMATIC DESIGN TO DESIGN DEVELOPMENT TRANSITION MEETING. 21 January 2010, 12:30pm-2:00pm

350 Pine Street, Suite 720 Edison Plaza Beaumont, TX Fax

SUWANNEE RIVER WATER MANAGEMENT DISTRICT REQUEST FOR BID NO. 15/16-003AO FIRE ALARM SYSTEM INSTALLATION AND MONITORING.

Building Name: Our Lady of Sorrows Date: July 10, 2013

SANTA FE COUNTY IFB# PW/KE CONSTRUCTION FOR THE SANTA FE MOUNTAIN CENTER KITCHENETTE AND OFFICE SPACE ADDENDUM #2

room data sheet ORANGE HALL 341 GORE AVENUE, VANCOUVER, BC 1/8 RESIDENTIAL ROOM RM DIVISION ELEMENT REQUIREMENT

SECTION GENERATOR PARALLELING CONTROLS

City of La Puente REQUEST FOR PROPOSAL ADDENDUM NO. 1

2014 Bond Project Guide

MARY CRAPO CENTER Miller Road, Swartz Creek, Michigan

Master Facility Planning Update School Board Meeting May 26, 2016

A X LWR 09/23/13 gaps at sills and head conditions are needing to be cleaned.

PSR-BENEFICIAL OCCUPANCY- T&I TRAINING. Testing & Inspection (T & I) Directive

RENO-TAHOE INTERNATIONAL AIRPORT RENO-TAHOE AIRPORT AUTHORITY PURCHASING AND MATERIALS MANAGEMENT

GREENVILLE-SPARTANBURG AIRPORT DISTRICT REQUEST FOR PROPOSALS FOR DEVELOPMENT SERVICES FOR GSP AIR CARGO FACILITY PHASE 1

Beaufort County Community College. Maintenance and House Keeping Plan

SECTION : FIRE PROTECTION SYSTEMS

VERIFICATION OF FIRE ALARM SYSTEMS

PROJECT NO. CWA SEPTEMBER 24, 2014 ADDENDUM NO. 6 BESSEMER RECREATION & WELLNESS CENTER

CITY OF FARMINGTON 800 Municipal Drive Farmington, NM (505) Fax (505)

DESIGN AND CONSTRUCTION STANDARDS SPECIFICATION GUIDELINES

Tualatin Valley Fire & Rescue Finance Department SW 70 th Ave., Tigard, OR Phone: , Fax:

Sidney, Ohio 1204 FORMAL ISSUANCE OF CERTIFICATE OF SUBSTANTIAL COMPLETION... ON OR BEFORE JULY 30, 2015.

ATTACHMENT A - Services Specifications

ADDENDUM NO. 1 FDVA-ITB B ITB TITLE: Bennett SVNH Nurse Call System ISSUE DATE: March 27, 2014

New Brunswick Campus Operations Service Guide. Maintenance repair or replacement in

Document Information Cover Sheet

Educational Furniture Range

4.0 SERVICES AND SCHEDULE

Transcription:

Arlington Public Schools Purchasing Office NOTICE OF ADDENDUM NO. 1 Issued on March 30, 2018 TITLE: ITB NO.: YORKTOWN HIGH SCHOOL INTERIOR MODIFICATIONS PROJECT 57FY18 ITB CLOSING DATE PRIOR TO 2:00 P. M., (LOCAL PREVAILING TIME) ON AND TIME: APRIL 06, 2018 The following information is provided to help with the preparation of Bids: Q1. What type of fire alarm system is existing? I remember Simplex Grinnel was discussed at the prebid- are we to include FA work in the drawings? I think it was discussed at the prebid that APS has already contracted this work. A1. APS has contracted design and submission of permit. Contractor to pull trade permit for installation and contract with Simplex Grinnell for installation. Q2. What is the clock system type? A2. Existing clock system is a semi-flush mounted master time/program clock with rear mounted relays and terminal. Synchronized clocks to be provided are Simplex Series 6310, to be compatible with the existing synchronized system, which is to be expanded to accommodate renovations. Q3. Can new electrical be surface mounted if the termination is on block? A3. Yes, wiremold is allowed on block walls only. Q4. Should the contractor retain a structural engineer for the operable partition? A4. Yes. Q5. Is Paragon an allowable casework subcontractor? A5. Yes. Q6. Do window shades go on all new storefronts? A6. Storefronts serving areas other than circulation, vestibules, or corridors are to receive roller shades. Such areas include, but are not limited to, teaching spaces, offices, conference rooms, workrooms and drop-ins.

Q7. There is work shown in the library on sheet A410 at the windows, but that area is NIC on sheet A101. Please confirm if that work is a part of this project. A7. Confirmed - library windows are to receive roller shades as shown on drawings. Q8. How many windows in the library receive shades, if they are in the scope of work? A8. The 5 windows shown at the exterior wall facing the courtyard, plan north within the library, receive roller shades. Q9. What is the slab-to-slab height? A9. The slab-to-slab height is 14-8. Q10. Please confirm that the bottom of slab condition for all slabs above the slab on grade is a corrugated metal, per the partition details on A001. A10. Confirmed - existing drawings show composite slab and deck at floor levels above slab on grade. Q11. There is no place on the bid form for the unit price for cord reels as referenced in 012200 Unit Prices specification and tied to the allowance we must include. Please advise. A11. No allowance or unit price. In contract. Q12. Reference 1.5.C 013100 Project Management and Coordination; please confirm BIM / Coordination Drawings will not be required on a project of this nature. A12. Correct. Section to be omitted from spec. Q13. Reference 013233 Photographic Documentation; please confirm photographs by a professional photographer will not be required for a project of this nature, and that the project manager or superintendent may act as the photographer. A13. Correct, not required for this project. Superintendent may act as photographer. Q14. Please confirm AISC Certification is a requirement on this project per 051200 specification, the extent of structural steel on this project is minimal, it may be difficult to get AISC participation considering the size of the scope. A14. Required. Q15. Please reference full size roller shade extra materials requirement per 1.6 of 122413 Roller Window Shades; on a project of this nature this means we must provide three shades for every window opening; is this what is intended? Please clarify, this requirement is something we see with new school construction but with the limited amount of added openings it does not make as much sense on a project of this nature. A15. Attic stock is 3 of each shade type. Q16. H1/A411 shows a new wall at the east library classroom elevation, however, the note on this plan and corresponding A1/A411 detail make this wall appear as if it is existing to remain. Please advise. A16. Plan east wall of APS-140E has existing openings roughly from ceiling to sill height. Scope of work includes infilling existing opening with GWB partitions as indicated on new work plan H1/A411, with storefront provided above as shown on L10/A411. Refer to A501 for storefront types. Q17. Please confirm, per A601 schedule, that the vented gym lockers will be furnished by the owner, and that the general contractor is only responsible for installation. A17. In the base bid, the general contractor is responsible for the installation of owner provided lockers, including blocking, anchorage and base. The add alternate holds general contractor responsible for providing and installation of lockers.

The following changes are made to ITB 57FY18 and form part of Addendum 1: 1) Modifications to Specifications: a) CHANGE 275117 MODIFIED SOUND AND INTERCOMMUNICATION SYSTEMS, DATED 9 MARCH 2018 AS FOLLOWS: REVISED SPECIFICATION b) CHANGE 013233 MODIFIED PHOTOGRAPHIC DOCUMENTATION, DATED 9 MARCH 2018 AS FOLLOWS: QUALIFIED PHOTOGRAPHER REQUIREMENT REMOVED. PROJECT MANAGER OR SUPERINTENDENT MAY ACT AS PHOTOGRAPHER. c) CHANGE 013100 PROJECT MANAGEMENT AND COORDINATION, DATED 9 MARCH 2018 AS FOLLOWS: DIGITAL MODEL CONFLICT ANALYSIS REQUIREMENT REMOVED. d) CHANGE - 087100 MODIFIED DOOR HARDWARE, DATED 9 MARCH 2018 AS FOLLOWS: CORRECTED DOOR HARDWARE SET #5, AND ADDED DOOR HARDWARE SET #8 FOR PANIC HARDWARE AT SCIENCE CLASSROOM DOORS. e) CHANGE - 092900 GYPSUM BOARD, DATED 9 MARCH 2018 AS FOLLOWS: ADD 2.4C Vinyl Corner Guards. 2) Modifications to Drawings: a) CHANGE G002: MODIFIED SHEET G002, DATED 9 MARCH 2018 AS FOLLOWS: UPDATED SHEET LIST AND SHEET COUNT. b) CHANGE G004: MODIFIED SHEET G004, DATED 9 MARCH 2018 AS FOLLOWS: RENAMED APS-141D TO WORKROOM, IN RESPONSE TO PERMIT. c) CHANGE A101: MODIFIED SHEET A102, DATED 9 MARCH 2018 AS FOLLOWS: RENAMED APS-141D TO WORKROOM, ADDED 6 ADDITIONAL LOCKABLE TEACHER STORAGE UNITS. d) CHANGE A410: MODIFIED SHEET A410, DATED 9 MARCH 2018 AS FOLLOWS: RENAMED APS-141D TO WORKROOM, ADDED 6 ADDITIONAL LOCKABLE TEACHER STORAGE UNITS. e) CHANGE A411: MODIFIED SHEET A411, DATED 9 MARCH 2018 AS FOLLOWS: ADDED WALL DISPLAY SHELVING ALONG SHARED WALL BETWEEN CLASSROOM AND LIBRARY, FACING LIBRARY. f) CHANGE A423: MODIFIED SHEET A423, DATED 9 MARCH 2018 AS FOLLOWS: REVISED EMERGENCY EYEWASH AND SHOWER ELEVATION, ADJUSTED CEILING HEIGHT AT SCIENCE CLASSROOM ENTRY. g) CHANGE A501: MODIFIED SHEET A501, DATED 9 MARCH 2018 AS FOLLOWS: ADDED DOOR HARDWARE SCHEDULE, CLARIFIED ROLLERSHADE LOCATIONS AT DOORS AND STOREFRONTS, UPDATED DOOR SCHEDULE.

h) CHANGE A502: MODFIED SHEET A502, DATED 9 MARCH 2018 AS FOLLOWS: ADDED ROLLERSHADE DETAIL FOR DOORS WITH GLAZING. i) CHANGE A511: MODIFIED SHEET A511, DATED 9 MARCH 2018 AS FOLLOWS: ADDED CLOCK LOCATION AT TEACHING WALL, REVISED NOTES FOR CLOCK LOCATIONS WHERE NO TEACHING WALL IS PRESENT. j) CHANGE - A601: MODIFIED SHEET A601, DATED 9 MARCH 2018 AS FOLLOWS: UPDATED SCHEDULES. k) CHANGE - A910: MODIFIED SHEET A910, DATED 9 MARCH 2018 AS FOLLOWS: UPDATED SHEET LEGEND, UPDATED PLC FF&E LAYOUT, l) CHANGE - A920: MODIFIED SHEET A920, DATED 9 MARCH 2018 AS FOLLOWS: UPDATED SHEET LEGEND, REVISED SCIENCE FF&E LAYOUT. m) CHANGE - A930: MODIFIED SHEET A930, DATED 9 MARCH 2018 AS FOLLOWS: UPDATED SHEET LEGEND, REVISED ASSISTANT PRINCIPAL FF&E LAYOUT, UPDATED TEACHER WORKROOM LAYOUT. n) CHANGE - P000: MODIFIED SHEET P000, DATED 9 MARCH 2018 AS FOLLOWS: UPDATED P8.A PLUMBING FIXTURE SCHEDULE FOR EMERGENCY EYEWASH AND SHOWER PROVIDED DETAIL FOR CONNECTIONS AT EMERGENCY EYEWASH AND SHOWER PROVIDED SPECIFICATION FOR TMV.E FOR REVISED EMERGENCY EYEWASH AND SHOWER o) CHANGE E000: MODIFIED SHEET E000, DATED 9 MARCH 2018 AS FOLLOWS: UPDATED LIGHTING COMPLIANCE REPORT. p) CHANGE E101: MODIFIED SHEET E101, DATED 9 MARCH 2018 AS FOLLOWS: PROVIDED PUBLIC ADDRESS (PA) SYSTEM RACK LOCATION. q) CHANGE E210: MODIFIED SHEET E210, DATED 9 MARCH 2018 AS FOLLOWS: ADDED OR RELOCATED WALL CLOCK TO BE ABOVE TEACHING WALL IN r) CHANGE E211: MODIFIED SHEET E211, DATED 9 MARCH 2018 AS FOLLOWS: ADDED CALL BUTTON. ADDED OR RELOCATED WALL CLOCK TO BE ABOVE TEACHING WALL IN s) CHANGE E212: MODIFIED SHEET E212, DATED 9 MARCH 2018 AS FOLLOWS: t) CHANGE E214: MODIFIED SHEET E214, DATED 9 MARCH 2018 AS FOLLOWS: RELOCATED CURTAIN DIVIDER KEY SWITCHES. u) CHANGE E217: MODIFIED SHEET E217, DATED 9 MARCH 2018 AS FOLLOWS: ADDED CALL BUTTONS

ADDED OR RELOCATED WALL CLOCK TO BE ABOVE TEACHING WALL IN v) CHANGE E218: MODIFIED SHEET E218, DATED 9 MARCH 2018 AS FOLLOWS: w) CHANGE E219: MODIFIED SHEET E219, DATED 9 MARCH 2018 AS FOLLOWS: x) CHANGE E220: MODIFIED SHEET E220, DATED 9 MARCH 2018 AS FOLLOWS: ADDED CALL BUTTONS ADDED OR RELOCATE WALL CLOCK TO BE ABOVE TEACHING WALL IN y) CHANGE E223: MODIFIED SHEET E223, DATED 9 MARCH 2018 AS FOLLOWS: ADDED CALL BUTTON z) CHANGE E224: MODIFIED SHEET E224, DATED 9 MARCH 2018 AS FOLLOWS: aa) CHANGE E225: MODIFIED SHEET E225, DATED 9 MARCH 2018 AS FOLLOWS: ADDED CALL BUTTON ADDED OR RELOCATED WALL CLOCKS TO BE ABOVE TEACHING WALL IN CLASSROOMS. bb) CHANGE E226: MODIFIED SHEET E226, DATED 9 MARCH 2018 AS FOLLOWS: ADDED CEILING SPEAKERS. cc) CHANGE E228: MODIFIED SHEET E228, DATED 9 MARCH 2018 AS FOLLOWS: ADDED CALL BUTTONS & CEILING SPEAKERS dd) CHANGE E229: MODIFIED SHEET E229, DATED 9 MARCH 2018 AS FOLLOWS: ADDED CALL BUTTONS & CEILING SPEAKER. ee) CHANGE - F101, F102, F103: MODIFY FIRE PROTECTION DRAWINGS DATED 9 MARCH 2018 AS FOLLOWS: NO EXISTING SPRINKLERHEADS TO BE REUSED. PROVIDE NEW SPRINKLERHEADS IN LIEU OF EXISTING TO BE REUSED WHERE SHOWN. PROVIDE GUARD COVERS IN ALL NEW STORAGE ROOMS. REVISED DRAWINGS WILL NOT BE PROVIDED IN ADDENDUM 1. ff) ADD FA101: ADDED SHEET FA101, DATED 30 MARCH 2018: ADDED TO CLARIFY FIRE ALARM SCOPE. gg) ADD FA102: ADDED SHEET FA102, DATED 30 MARCH 2018: ADDED TO CLARIFY FIRE ALARM SCOPE. hh) ADD FA103: ADDED SHEET FA103, DATED 30 MARCH 2018: ADDED TO CLARIFY FIRE ALARM SCOPE.

A copy of the pre-bid Conference Attendance Record will be made available on Monday, April 2. Please find link to download Addendum 1 below: https://infoexchange.quinnevans.com/userweb/login/login.aspx This Addendum No. 1 must be signed, dated and received in the Purchasing Office prior to the date and time stated above OR acknowledgment of receipt of this Addendum may be noted on the Bid Form on Page 3. NAME OF VENDOR: ADDRESS: SIGNATURE: DATE: ISSUED BY: David J. Webb, C.P.M. Director of Purchasing Telephone: (703) 228-6127 Cell: (703) 328-5591 Email: david.webb@apsva.us