Photovoltaic Specialists: Job Task Analysis

Similar documents
NATIONAL ELECTRICAL CODE (NEC) & NFPA 70E ARC FLASH ELECTRICAL SAFETY

SECTION SOLAR PHOTOVOLTAIC (PV) POWER GENERATION SYSTEM

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 11/06/2018

SECTION AUTOMATIC TRANSFER SWITCHES

SECTION ENCLOSED CONTROLLERS

TABLE OF CONTENTS CHAPTER 5 SPECIAL OCCUPANCIES CHAPTER 1 GENERAL RULES... 19

9/7/2010. Chapter , The McGraw-Hill Companies, Inc. AND BONDING. 2010, The McGraw-Hill Companies, Inc.

TABLE OF CONTENTS CHAPTER 1 GENERAL RULES CHAPTER 2 WIRING AND PROTECTION... 51

SECTION AUTOMATIC TRANSFER SWITCHES PART 1 - GENERAL

PROTECTING AGAINST ARC FLASH HAZARDS

CUSTOMIZED TEACHER ASSESSMENT BLUEPRINT ELECTRICAL POWER AND TRANSMISSION INSTALLERS. Test Code: 5922 Version: 01

Chapter 1 General...9 Article 100 Definitions...11 Article 100 Questions Article 110 Requirements for Electrical Installations...

*************************************************************************** SECTION D50 ELECTRICAL 02/18

SUMMARY: Policy Title: Electrical Safety Work Practice Program. Policy Number: UNIV-EHS 430 Policy Approved: January 2014

Photovoltaic (Solar) Array Installation Guide

VeriSafe Absence of Voltage Tester The safe way to verify the absence of voltage

NFPA 70E Edition Update

The safe way to verify the absence of voltage.

SECTION SECURITY TESTING AND COMMISSIONING

2014 National Electrical Code & NFPA 70E/Arc Flash

.4 Do complete installation in accordance with latest Electrical Bulletins of the local inspection authority.

SECTION AUTOMATIC TRANSFER SWITCHES

Entry Level Assessment Blueprint Electrical Construction Technology

SECTION DIGITAL, ADDRESSABLE FIRE-ALARM SYSTEM

SECTION ELECTRICAL IDENTIFICATION

ELECTRICAL CURRICULA OUTLINE CORE CURRICULUM 2015

NATIONAL TRAINING BOARD (ELECTRICIAN) REGULATIONS 2008 BR 54/2008 NATIONAL OCCUPATIONAL CERTIFICATION ACT :38

PERMIT APPLICATION REQUIREMENTS FOR NON-RESIDENTIAL ROOF MOUNTED PHOTOVOLTAIC SYSTEMS

SECTION (16460) - LOW-VOLTAGE TRANSFORMERS

VACUUM BREAKER MEDIUM VOLTAGE AUTOMATIC TRANSFER SWITCHES

GPS 140 NEC Requirements for Generators. Professional Development Seminar Series NEC Requirements for Generators

KINGS COUNTY JAIL EXPANSION PHASE III COUNTY OF KINGS SECTION

SECTION CENTRAL BATTERY INVERTERS. A. This Section includes fast-transfer central battery inverters with the following features:

SECTION C. Section Cable Trays for Electrical Systems: Additional identification requirements for cable tray systems.

SECTION PANELBOARDS. A. Drawings and general provisions of the Contract, including General and Supplementary Conditions, apply to this Section.

Dependable Solutions for Gas Detection

Emery County Senior Center Green River 06/07

Overview of Significant 2017 NEC Changes

NZQA unit standard version 1 Page 1 of 6. Install, maintain and repair of telecommunications optical fibre network infrastructure

PIP PCTPA001 Testing of Process Analyzer Systems

Guide to Compliance with the Electrical Workplace Safety Standards in the United States

NFPA 70E Electrical Safety & Arc Flash Training

A. Product Data: For each electrical identification product indicated. B. Comply with 29 CFR and 29 CFR

TABLE OF CONTENTS CHAPTER 2 WIRING AND PROTECTION CHAPTER 1 GENERAL RULES... 19

National Electrical Code

Pilz Safety Lockout System (PSLS)

IEC and NCCER Mapping for Year 1

Ground Fault Protection Improvement Study

2012 Edition. Tech Topics: Standards & Codes. Note 4, Issue 1. Points of Interest: Introduction. Background. Changes to Definitions in Article 100

SECTION GENERATOR PARALLELING CONTROLS

Brown University Revised June 29, 2012 Facilities Design & Construction Standards SECTION ELECTRICAL DESIGN CRITERIA

ELECTRIC and NEON SIGN STANDARDS. By Randy Wright RKW CONSULTING

NZQA unit standard version 2 Page 1 of 6. Perform installation and maintenance of telecommunications radio systems and services

HESNI ANNUAL CONFERENCE May 3, 2012 Aramark Conference Center, Downers Grove

SEL Arc-Flash Solutions

PANELBOARDS & BUILDING DISTRIBUTION

RISKTOPICS. Photovoltaic systems

Entry Level Assessment Blueprint Electrical Construction Technology

1. Distribution panelboards. 2. Lighting and appliance branch-circuit panelboards. 3. Load centers.

PV Standards Activities SEIA Codes and Standards Workshop. Scott Jezwinski Business Development Manager Sep 12, 2016

BUILDING PERMIT APPLICATION REQUIREMENTS FOR GROUND MOUNTED PHOTOVOLTAIC SYSTEMS

Arc Flash Analysis: IEEE Method versus the NFPA 70E Tables July 2017 / 1910DB1702

SEL Arc-Flash Solutions

Changes to NFPA 70E. - The Role of PdM &Safe PdM Work Practices. Tim Rohrer Exiscan LLC

SECTION ISOLATED POWER SYSTEMS

Safety requirements for voltage testing instruments

SECTION AUTOMATIC TRANSFER SWITCHES

Electrical Tech Note 107

NECA S System Approach to Electrical Safety for NFPA 70E

Introduction Consultant shall incorporate the material in the DSS into the project specifications.

A. This Section includes transfer switches rated 600 V and less, including the following:

Electrical Hazards and NFPA-70E: Protecting Your Employees

Quality assurance and safety aspects. Dipl.Ing. Udo Siegfriedt DGS-Berlin Brandenburg

APPENDIX - L INTERNATIONAL RESIDENTIAL CODE ELECTRICAL

MODEL B2 INSTALLATION MANUAL

NECA. Standard for Electrical Safety in the Workplace

Revisions for the 2011 National Electrical Code - Part 4

SECTION GAS-FIRED RADIANT HEATERS

Roof Mounting System. Installation Manual. Standard (XRS) and Light (XRL) Rails with Integrated Grounding *ETL Listed Per UL Edition v1.

SECTION 2 NEC REFERENCES SECTION 1 LOW-VOLTAGE AND POWER- LIMITED SYSTEMS...1. CHAPTER 1 GENERAL Introduction...35

FLUSH MOUNT INSTALLATION MANUAL

SECTION IDENTIFICATION FOR ELECTRICAL SYSTEMS

Electrical Safety Compliance: NFPA 70E

Implementing an Energized Electrical Work Program. SESHA Hill Country Chapter. Brett Jay Davis, PE Zephyr Environmental Corporation

2017 NEC Presented by: Russ LeBlanc

FIREFLY II PLUS RELEASE DEVICES INSTALLATION MANUAL

Installing the Cisco ONS FAP-4 Fuse Alarm Panel

Safety Function: Single-beam Area Access Control (AAC)

ELECTRICAL. Level One. Competencies / Objectives MODULE ORIENTATION TO THE ELECTRICAL TRADE MODULE ELECTRICAL SAFETY

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

Product Bulletin. VeriSafe Absence of Voltage Tester. The Safe Way to Verify the Absence of Voltage.

Easy to use, initiate test with the push of a button No additional tools required Provides visual alert to abnormal power conditions

NEC Requirements for Standby Power Systems. New England Building Officials Education Association Annual Conference October 5, 2015

Electrical Safety Program

NECA S System Approach to Electrical Safety for NFPA 70E

17 TH APRIL 2017 Switch Board Monitoring Protecting Switchboard. Courtesy of ABB. Paul Lee

SECTION COMPRESSED-AIR EQUIPMENT FOR LABORATORY FACILITIES

Control Panel. 1.0 GENERAL SCOPE OF WORK Introduction... 2

PROFILE. industrial services rental trading

Watt-Muncher Load Bank Manual WATT-MUNCHER. Portable Load Bank. 6 June 2018 Simplex Service Page 1 of 13

Transcription:

Photovoltaic Specialists: Job Task Analysis Photovoltaic Design, Photovoltaic Installer, Photovoltaic Commissioning & Maintenance September 2017 V. 09.17 www.nabcep.org Raising Standards. Promoting Confidence.

Introduction This document presents a comprehensive Job Task Analysis (JTA) for PV Specialists who perform decision making roles with respect to the design, installation and commissioning & maintenance of Photovoltaic (PV) systems. NABCEP Specialist Credentials all relate to PV installation. The PV Design Specialist, PV Installer Specialist and the PV Commissioning and Maintenance Specialist Certifications each focus on one domain from the NABCEP PV Installation Professional classification system. The Exams were formulated by Subject Matter Experts with input from a wide range of individuals working in the industry. Who Are NABCEP PV Specialists? PV Design Specialist (PVDS) Experts at configuring the electrical design of a project. In assessing the project site, PVDS will be able to design both the mechanical and electrical design components with confidence, accuracy and safety. PV Installer Specialist (PVIS) Highly competent with all aspects of PV installation including DC and AC PV system conductors and grounding and bonding systems. As with all NABCEP credentials, safety standards and plans are of critical importance. PV Commissioning and Maintenance Specialist (PVCMS) NABCEP PVCMS Specialists combine the skill sets of operations, maintenance and commissioning tasks into one job specialty. Exceptional application of verification protocols and preventive and corrective maintenance operations are key to this Certification. Scope of the JTAs NABCEP Certified PV Specialists work in a variety of responsible roles on PV installation jobs. Varying sizes and complexities of installations calls for a wide range of duties required of any PV Installation Professional. The NABCEP Specialist Exams are designed to narrow the scope of duties while elevating the competency of the specified technology. Task Steps & Knowledge Individuals who achieve a NABCEP Specialist Certification will be familiar with and capable of executing all the tasks listed in the specific examination content outline below. These tasks may not be performed on every project but they are an important part of a body of knowledge. Pg. 2

Content Domains and Examination Specifications PV Design Specialist Description Percent of Test Review customer expectations... 12% Review project criteria... 12% Assess project site...15% Configure mechanical design...13% Configure electrical design...17% Configure system monitoring, control, and communications design... 7% Prepare project documentation... 8% Secure permits and approvals... 8% Adapt system design... 8% PV Installer Specialist Description Percent of Test Develop safety plan... 8% Safeguard against hazards... 10% Install raceways... 7% Install electrical equipment... 8% Install DC PV system conductors... 8% Install AC PV system conductors... 8% Install grounding & bonding... 10% Complete utility interconnection point... 8% Install system monitoring, control, and communication hardware... 3% Install battery equipment... 7% Install ground-mounted structure... 5% Install building-mounted system... 8% Install PV modules... 8% PV Commissioning & Maintenance Specialist Description Percent of Test Review or develop commissioning protocol... 10% Complete visual and mechanical inspection... 12% Conduct mechanical tests... 8% Conduct electrical tests...15% Verify system operation... 10% Confirm project completion... 8% Orient end user to system... 8% Verify system operation and performance... 8% Perform preventive maintenance... 10% Perform corrective maintenance... 10% Pg. 3

CATEGORIES PER PV SPECIALTY EXAM PV Design Specialist (PVDS) PVDS Task 1: Review Customer Expectations a. Equipment location b. Aesthetic concerns c. Electric loads assessment (e.g., new construction, multi-modal and stand-alone systems) d. System functionality and performance requirements e. Value engineering PVDS Task 2: Review Project Criteria a. Authorities having jurisdiction criteria (e.g., codes, standards, covenants, and regulations) b. Electric service provider criteria (e.g., utilities, co-ops, third-party providers) c. Construction plan sets and project specification documents PVDS Task 3: Assess Project Site a. Characteristics of appropriate array locations b. Characteristics of viable roof surfaces c. Live and dead load characteristics of PV arrays d. Common roof structural design e. Drilling and trenching equipment capabilities f. Characteristics of appropriate equipment locations g. Types of electrical services h. Point of interconnection i. Raceway installation parameters j. Effect of obstructions k. Construction site hazards l. Characteristics of appropriate staging/lifting/ access locations m. Shading analysis tools and techniques n. Azimuth measurement tools o. Magnetic declination p. Slope tools and techniques q. Building use and dimensions r. Effects of wind exposure s. Required site information documentation PVDS Task 4: Configure Mechanical Design a. PV system performance simulation software b. Basic algebra, geometry, and trigonometry calculations (e.g., area, slope, inter-row shading, withdrawal loads) c. Characteristics of racking systems d. Fastener selection criteria (e.g., types, sizes) e. Structure attachment criteria (e.g., spacing, quantity, type) f. Waterproofing and flashing methods and materials g. Existing and allowable loads (e.g., snow load, seismic) h. Design principles of ground mount foundations i. Effect of PV module tilt and orientation j. Characteristics of PV module technologies k. Methods for equipment racking and/or installation l. Criteria for placement of energy storage systems m. Pathways and setbacks (e.g., walkways, clearances, accessibility) Pg. 4

PV DESIGN SPECIALIST (PVDS) PVDS Task 5: Configure Electrical Design a. Inverter selection criteria (e.g., types of inverters, DC to AC ratio) b. String size calculations and layout c. DC circuit sizing formulas (e.g., PV source and output circuits, battery cables) d. AC circuit sizing formulas (e.g., inverter output circuit, feeders) e. Module level power electronics (MLPE) f. Voltage drop calculations g. Methods of interconnection (e.g., supply-side connection, load-side connection) h. Conductor properties and types i. Raceway selection criteria and calculations j. Raceway installation methods k. Source circuit combining methods (e.g., combiner boxes, wire harnesses) l. Overcurrent protection selection criteria m. Electrical enclosure selection criteria n. Panelboard selection criteria o. Disconnect selection criteria p. Grounding system criteria and components q. Rapid shutdown equipment and methods r. Arc-fault protection equipment and methods s. Characteristics of battery technologies t. Characteristics of charge controllers u. Characteristics and components of AC coupled systems v. Energy storage system sizing and performance calculations w. Power requirements of auxiliary systems (including backup power) Pg. 5

PV Installer Specialist Examination (PVIS) PVIS Task 1: Develop Safety Plan a. OSHA requirements (e.g., fall protection, competent/ qualified person, reporting of incidents) b. NFPA 70E (National Fire Protection Association Standard for Electrical Safety in the Workplace) c. Personal protective equipment (PPE) (e.g., specific equipment required for project, maintenance of PPE) d. Material safety data sheet (MSDS) e. Emergency response resources and protocols f. Weather event response actions g. Specific equipment and training required for site h. Elements of an effective safety meeting PVIS Task 2: Safeguard Against Hazards a. NFPA 70E (National Fire Protection Association Standard for Electrical Safety in the Workplace) b. OSHA CFR 29 1926 safety standards c. Proper care and use of safety equipment (e.g., life cycle, defects, storage) d. Proper care and use of test equipment (e.g., life cycle, defects, storage) e. Proper care and use of power tools (e.g., life cycle, defects, storage) f. Safe work practices * Effectively implementing the site specific safety plan PVIS Task 3: Install Raceways a. NFPA 70 (NEC) articles for use, installation, and construction specifications for raceways and associated fittings b. Raceway manufacturer specifications and installation requirements c. Proper raceway selection and sizing d. Proper installation and labeling of raceways per NFPA 70/AHJ requirements (e.g., expansion joints, physical protection) e. Neat and workmanlike manner of installation of raceways f. Plan sets and schematics * Confirming raceway routing per plans and client input Pg. 6

PV INSTALLER SPECIALIST (PVIS) PVIS Task 4: Install Electrical Equipment a. NFPA 70 (NEC) articles for use, installation, and construction specifications for equipment and associated fittings b. Equipment manufacturer specifications and installation requirements c. Neat and workmanlike manner of installation of electrical equipment d. Proper installation and labeling of equipment per NFPA 70 requirements e. Plan sets and schematics * Confirming equipment suitability and placement per plans and client input * Providing and maintaining access and working space around all electrical equipment * Interpreting construction plans (e.g, electrical plans, schematics, line diagrams) PVIS Task 5: Install DC P System Conductors a. NFPA 70 (NEC) articles for use, installation, and construction specifications for DC conductors b. NFPA 70E (National Fire Protection Association Standard for Electrical Safety in the Workplace) c. Equipment manufacturer specifications and installation requirements d. Appropriate conductor installation and pulling practices e. Wire management in a neat and workmanlike manner f. Termination and connection per manufacturer specifications * Conducting field verification of proper conductor identification, size, color, type, and rating * Properly identifying and labeling DC conductors per plan set and NFPA 70 requirements * Conducting string sizing and string configuration er plans and manufacturer specifications PVIS Task 6: Install AC PV System Conductors a. NFPA 70 (NEC) articles for use, installation, and construction specifications for AC conductors b. NFPA 70E (National Fire Protection Association Standard for Electrical Safety in the Workplace) c. Conductor manufacturer specifications and installation requirements d. Appropriate conductor installation and pulling practices e. Wire management in a neat and workmanlike manner f. Termination and connection per manufacturer specifications * Conducting field verification of proper conductor identification, size, color, type, and rating * Properly identifying and labeling AC conductors per plan set and NFPA 70 requirements Pg. 7

PV INSTALLER SPECIALIST (PVIS) PVIS Task 7: Install Grounding and Bonding Systems a. NFPA 70 (NEC) articles for use, installation, and construction specifications for grounding and bonding b. Proper installation of bonding and bonding jumpers c. Grounding systems and certifications (e.g., UL 2703, integrated bonding) * Conducting field verification of existing grounding electrode systems * Installing proper system grounding per NFPA 70 and manufacturer specifications (grounding electrode conductor [GEC]) * Installing proper equipment grounding per NFPA 70 and manufacturer specifications (equipment grounding conductor [EGC]) PVIS Task 8: Complete Utility Interconnection Point a. NFPA 70 (NEC) articles for use, installation, and construction specifications for utility interconnection b. OSHA safety standards c. NFPA 70E (National Fire Protection Association Standard for Electrical Safety in the Workplace) d. Calculation and verification of OCPD overcurrent protection device (OCPD) and disconnecting means e. Effective and efficient communication regarding shutdown and inspection processes f. Proper termination of conductors per manufacturer specifications g. Local electric service provider requirements for interconnection h. Methods of interconnection * Effectively implementing the site-specific safety plan PVIS Task 9: Install System Monitoring, Control, and Communication Hardware a. NFPA 70 (NEC) articles for use, installation, and construction specifications b. Cable manufacturer specifications and installation requirements c. Monitoring equipment manufacturer specifications and installation requirements * Confirming monitoring equipment placement per plans and with client * Conducting field verification of final system configuration * Conducting field verification of proper cable identification, size, type, and rating * Installing equipment per manufacturer specifications and approved plan sets * Preparing monitoring system for commissioning d. Neat and workmanlike installation of monitoring equipment e. Types and methods of data communication hardware f. Manufacturer specifications and approved plan sets g. Termination and connection per manufacturer specifications Pg. 8

PV INSTALLER SPECIALIST (PVIS) PVIS Task 10: Install Battery Equipment a. NFPA 70 (NEC) articles for use, installation, and construction specifications for batteries b. OSHA safety standards c. NFPA 70E (National Fire Protection Association Standard for Electrical Safety in the Workplace) d. Proper installation of batteries and battery equipment (e.g., labeling, spill kits, enclosure, ventilation) e. Neat and workmanlike manner of installation of battery equipment f. Proper conductor installation, routing, identification, size, color, type, and rating g. Proper battery handling, storage, future maintenance, and installation techniques * Implementing the site-specific safety plan * Confirming battery equipment placement per plans and client input * Installing batteries and battery-related equipment per manufacturer specifications * Conducting field verification of proper conductor identification, size, color, type, and rating PVIS Task 11: Install Ground-Mounted Structure a. NFPA 70 (NEC) b. Authorities having jurisdiction criteria (e.g., codes, standards, zoning, covenants, regulations) c. OSHA safety standards d. Ground-mounted structure manufacturer specifications and installation requirements e. Module manufacturer mounting specifications and installation requirements f. Foundation and structural elements (e.g., geotechnical requirements) g. Construction and assembly of PV structure and racking h. Neat and workmanlike manner of installation i. Coordination of foundation, trench, and pad inspections j. Location of underground utilities (e.g., call ahead, underground locator services) k. Environmental impact (e.g., protected species, water management) l. Site protection and restoration (e.g., straw and seed) m. Earth moving equipment * Managing excavation to design specifications (e.g., trenching, piers, foundations) Pg. 9

PV INSTALLER SPECIALIST (PVIS) PVIS Task 12: Install Ground-Mounted Structure a. Authorities having jurisdiction criteria (e.g., codes, standards, zoning, covenants, regulations) b. OSHA safety standards (fall protection, hoisting, scaffolding) c. Racking manufacturer specifications and installation requirements d. Roofing systems manufacturer specifications, warranty, and installation requirements e. Mounting surface compositions (e.g., tile, composite, membrane, metal) f. Mounting surface and structure protection and restoration g. Array layouts per location (e.g., inter-row shading, electrical efficiency) h. Neat and workmanlike manner of installation i. Types of roofing system construction j. Lightning protection systems k. Staging materials and equipment (e.g., roof or other structure loading, security) l. Waterproofing building penetrations * Effectively implement the site-specific safety plan * Interpreting and applying approved design (e.g., engineered drawings, manufacturer specifications) * Installing points of attachment to roof manufacturer requirements PVIS Task 13: Install PV Modules a. NFPA 70E (National Fire Protection Association Standard for Electrical Safety in the Workplace) b. OSHA safety standards (e.g., fall protection, ladder use, lifting) c. Neat and workmanlike manner of installation (e.g., coplanar, square) d. Manufacturer specifications for installation of modules e. Proper module handling and preparation f. Proper wire management methods and materials g. Termination and connection per manufacturer specifications h. Grounding and bonding (e.g., integrated grounding, bonding washers, lugs) i. Regional considerations (e.g., animal guarding, ice and snow, wind) * Effectively implementing the site-specific safety plan * Conducting field verification of equipment selection (e.g., nameplate, racking compatibility) Pg. 10

NABCEP PV Commissioning & Maintenance Specialist (PVCMS) PVCMS Task 1: Review or Develop Commissioning Protocol a. Applicable standards (e.g., manufacturer recommendations, building system, IEC 62446-1, performance testing) b. NFPA 70E (National Fire Protection Association Standard for Electrical Safety in the Workplace) c. Contract requirements and intent of design d. Project-specific requirements e. Test equipment PVCMS Task 2: Complete Visual and Mechanical Inspection a. Project design b. Manufacturer requirements c. NEC and local AHJ requirements d. Electric service provider requirements (e.g., disconnecting means, interconnection method, equipment location, labeling requirements) * Verifying installation per project design and requirements PVCMS Task 3: Conduct Mechanical Tests a. Installation per torque specifications b. Field testing (e.g., pull on driven piles, soil test, concrete slump test) c. Witness testing (e.g., module wind or snow loading) PVCMS Task 4: Conduct Electrical Tests a. Proper use of diagnostic tools (e.g., multimeter, insulation resistance tester) b. Insulation resistance testing c. Polarity testing d. DC string open circuit voltage (Voc) testing e. DC string maximum power current (Imp) testing f. DC string short circuit (Isc) testing g. Continuity testing h. Ground resistance test i. Wire termination torque verification j. AC voltage testing k. Witness testing (e.g., functionality of relay, communication to utility, anti-islanding) Pg. 11

PV COMMISSIONING & MAINTENANCE SPECIALIST (PVCMS) PVCMS Task 5: Verify System Operation a. Manufacturer startup procedure b. Acceptance test and/or performance verification test c. Impact of site conditions on testing (e.g., cell temperature readings, plane of array irradiance, power output) d. Proper use and calibration requirements of testing equipment * Programming system electronics (e.g., charge controller set points, firmware updates, monitoring system connection, inverter) * Calculating expected electrical parameters and comparing to measured values PVCMS Task 6: Confirm Project Completetion a. Finalized documentation (e.g., commission report, signed permits, permission to operate [PTO], photographs) b. Close-out procedures (e.g., punch lists, contract reconciliation, demobilization) c. Owner sign-off requirements (e.g., appropriate site condition, customer satisfaction) d. Accounting requirements (e.g., payment approval, billing, cost coding) e. Warranty and owner s documents (e.g., manuals, specification sheets, signed permits) f. Equipment identification requirements (e.g., labeling, tags, signage) g. Operation instructions and/or training for owner h. Lien release i. Warranty terms and coverage j. System design, operation, and performance metrics (e.g., performance ratio) PVCMS Task 7: Orient End User to System a. Safe startup, operation, and shutdown procedures b. Emergency procedures c. Location of components d. Monitoring access * Explaining system operation and limitations (e.g., training, operational indicators) * Reviewing system and project documentation with end user Pg. 12

PV COMMISSIONING & MAINTENANCE SPECIALIST (PVCMS) PVCMS Task 8: Verify System Operation Performance a. Access to system monitoring, control, and communications platform(s) b. Platform settings and alert mechanisms c. Indicators of failure, underperformance, or false alarms d. Interpretation of performance data e. Seasonal impacts on system performance f. Site weather data source g. Climate data and impact on performance h. Data monitoring system capabilities and instrumentation quality i. Performance analytics (e.g., trends) j. Remote diagnostics solutions (if available) PVCMS Task 9: Perform Preventative Maintenance a. Site access protocol b. NFPA 70E (e.g., lock-out/tag-out) c. Site-specific safety requirements d. Site specific O&M procedure e. Periodic visual and mechanical inspection f. Instrumentation calibration g. Mounting system degradation, failure points and causes (e.g., loose connections, corrosion, displacement) h. Module failure points and causes (e.g., signs of overheating, damage to J-Box, discoloration) i. Electrical equipment failure points and causes (e.g., vermin, debris, ventilation, water intrusion) j. Wiring system degradation, failure points, and causes (e.g., unsupported conductors, connector failure, loose terminations, physical damage to raceway) k. Battery system degradation, failure points, and causes (e.g., cable terminations, corrosion, capacity testing, deformation of battery) l. Site factors affecting performance (e.g., module soiling, vegetation impacts, shading) m. Array testing (e.g., Voc, Isc, Imp, fuse continuity testing) n. Comparison of whole system performance to predicted values PVCMS Task 10: Perform Corrective Maintenance a. Site access protocol b. NFPA 70E (e.g., lock-out/tag-out, personal protective equipment [PPE]) c. Site-specific safety requirements d. Methods for diagnosing failure or low performance (e.g., multimeter, monitoring system, thermal imager) e. Methods of repair or replacement f. Field modification and equipment substitution g. System cleaning (e.g., snow removal, dust/ pollen removal) * Verifying effectiveness of corrective measures Pg. 13

NABCEP s mission is to support, and work with, the renewable energy and energy efficiency industries, professionals, and stakeholders to develop and implement quality credentialing and certification programs for practitioners. #0702 ISO/IEC 17024 Personnel Certification Program NABCEP s PVIP and SHI Certifications are North America s only renewable energy personnel certification that has been ANSI accredited to the internationally recognized ISO/IEC 17024 standard. NABCEP wishes to acknowledge and thank the following individuals for their contribution in developing these JTAs: Beth Copanas Greg Demarse Kevin Flaws Chris Giannoumis Jeff Gilbert Mark Gillespie James Hasslebeck Bob Hattier Dell Jones Jeff Laukhart Ernie Pritchard Cathy Redson Doug Sabetti Phil Schneider Rob Smith Bob Solger Andy Walker North American Board of Certified Energy Practitioners 56 Clifton Country Road, Suite 202 Clifton Park, NY 12065 800-654-0021 / info@nabcep.org / www.nabcep.org Pg. 14