EMERGENCY POWER SYSTEMS

Similar documents
16620 EMERGENCY POWER SYSTEMS

SECTION EMERGENCY POWER SYSTEMS

B. Section Transfer Switches: Automatic transfer switch.

Brown University Revised June 29, 2012 Facilities Design & Construction Standards SECTION ELECTRICAL DESIGN CRITERIA

ENGINE GENERATORS AND ACCESSORIES

SECTION AUTOMATIC TRANSFER SWITCHES PART 1 - GENERAL

SECTION AUTOMATIC TRANSFER SWITCHES

PANELBOARDS & BUILDING DISTRIBUTION

SECTION GENERATOR PARALLELING CONTROLS

NEC Requirements for Standby Power Systems. New England Building Officials Education Association Annual Conference October 5, 2015

SECTION AUTOMATIC TRANSFER SWITCHES

Replacement of Fire Pump and Generator Upgrade, H Building, Sexton Campus

SECTION AUTOMATIC TRANSFER SWITCHES

SECTION ISOLATED POWER SYSTEMS

A. This Section includes transfer switches rated 600 V and less, including the following:

2.07 Permit Application Checklist for Diesel Generators, Diesel Fire Pumps, and Fuel Tanks Serving Generators and Fire Pumps (2016)

Guide Specification Model CTG Automatic Transfer Switch

1.1 REFERENCES.1 American National Standards Institute/National Fire Protection Association (ANSI/NFPA).1 ANSI/NFPA 20, Centrifugal Fire Pumps.

16721 FIRE ALARM AND DETECTION SYSTEMS

SECTION PANELBOARDS. A. Drawings and general provisions of the Contract, including General and Supplementary Conditions, apply to this Section.

WORKING DRAFT OF COMMITTEE MEETING OUTPUT

SPECIFICATION MICROMIST FIRE SUPPRESSION SYSTEM WITH SHP-PRO CONTROL PANEL

16721 FIRE ALARM AND DETECTION SYSTEMS

GPS 140 NEC Requirements for Generators. Professional Development Seminar Series NEC Requirements for Generators

SUGGESTED SPECIFICATION For Series 300 Manual Transfer Switches (3MTS)

WEST VIRGINIA UNIVERSITY

CAN/ULC-S INTEGRATED SYSTEMS TESTING OF FIRE PROTECTION AND LIFE SAFETY SYSTEMS

SECTION PANELBOARDS Painting Wire and Cable Overcurrent Protective Devices.

The following information shall become and form part of the contract documents.

ELECTRICAL - V DESCRIPTION 16.1 GENERAL

Healthcare Emergency Power Supply Systems. Maintenance and Testing

FIRE ALARM AND DETECTION SYSTEMS

CAN/ULC S Integrated Systems Testing of Fire Protection and Life Safety Systems and Fire Protection Commissioning

VACUUM BREAKER MEDIUM VOLTAGE AUTOMATIC TRANSFER SWITCHES

SECTION P01 LIGHTING AND APPLIANCE PANELBOARDS - A-SERIES

CONTENTS. B. System Design and Performance Requirements

Moreno Valley Fire Department Fire Prevention Bureau. New and Existing Fire Alarm & Signaling Systems Guideline

GARCIA GALUSKA DESOUSA Consulting Engineers

NFPA Updates (c) 2015 SSR, Inc. All rights reserved Florida AHCA Conf

HIGH-RISE RETROFIT ORDINANCES - NO and NO

Revitalize Building Mechanical Systems (4619)

LIGHTING CONTROLS

Diesel Fuel System Report

Update all extract references to NFPA documents (including NFPA 72) in Chapter 3 and related annex material to the latest editions.

DONALD H. BERG, ARCHITECT

APPENDIX H (DESIGN SUBMISSION CRITERIA)

SMALL WORKS PROJECT REQUEST FOR SEALED BIDS

LABORATORY AIR COMPRESSORS AND VACUUM PUMPING SYSTEMS

Alex Masterton, PE Electrical Engineer Reviewer AHCA Neal Boothe, PE Electrical Engineer/Principal

IMPORTANT NOTICE BUILDERS AND CONTRACTORS WORKING IN NORTH RICHLAND HILLS, TEXAS. June 17th, 2016

C. ASME Compliance: Fabricate and label water chiller heat exchangers to comply with ASME Boiler and Pressure Vessel Code: Section VIII, Division 1.

SCHOOL DISTRICT PALM BEACH COUNTY BUILDING DEPARTMENT PLAN REVIEW CHECK LIST -- ELECTRICAL

Building Division 201 SE 3 rd STREET (Second Floor) OCALA, FL Phone: (352) BUILDING CODE GUIDELINES FOR ELECTRICAL INSPECTIONS

CAN/ULC-S1001, INTEGRATED SYSTEMS TESTING OF FIRE PROTECTION & LIFE SAFETY SYSTEMS Simon Crosby, LEL, CET, CFPS October 21, 2015

CONTENTS AUTOMATIC TRANSFER SWITCHES

DIRECTIVE NO: D-B

Bold items are particular to the City of Euless

SECTION PACKAGED ROOFTOP AIR CONDITIONING UNITS

UFGS (November 2008) UNIFIED FACILITIES GUIDE SPECIFICATIONS

STATEMENT OF WORK I. SCOPE OF WORK:

SECTION GAS-FIRED RADIANT HEATERS

Brighton Area Fire Authority

SECTION ENCLOSED CONTROLLERS

UltraLITE Model ELU Centralized Emergency Lighting Inverter 4.2 KW- 5 KW

C. Shop Drawings: For boilers, boiler trim, and accessories. Include plans, elevations, sections, details, and attachments to other work.

Part I Extraction Process Equipment

The Owner will provide the QEI inspection and certification services.

TONY ESPOSITO LIGHTING/ELECTRICAL TECHNICAL REPORT II SEPTEMBER 15, 2011 HUNTER S POINT SOUTH INTERMEDIATE SCHOOL AND HIGH SCHOOL QUEENS, NY

Rancho Cucamonga Fire Protection District Prevention Bureau Standard

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

UNIFIED FACILITIES GUIDE SPECIFICATIONS

SECTION CENTRAL BATTERY INVERTERS. A. This Section includes fast-transfer central battery inverters with the following features:

SECTION LABORATORY EQUIPMENT CONSTRUCTION STANDARD PART 1: GENERAL Scope of Standard

KINGS COUNTY JAIL EXPANSION PHASE III COUNTY OF KINGS SECTION

SECTION AIR COILS

University of Houston Master Construction Specifications Insert Project Name

SECTION NURSE CALL SYSTEM

NFPA CODE TESTING & INSPECTION. Requirements & Recommendations for. Licensed Florida Hospitals, Ambulatory Surgery Centers,

SAMPLE SPECIFICATION FOR RIELLO ARRAY MODULATING BOILER

SECTION COMMERCIAL-KITCHEN HOODS

POWER GENySYS P ROJECT E XPERIENCE I NFORMATION - D ISTRIBUTED G ENERATION

SECTION Fire Pumps

Kidde Nitrogen Inert Gas Clean Agent Fire Suppression System

SECTION LOW VOLTAGE POWER PANELBOARDS - SPECTRA

SECTION ROTARY-SCREW WATER CHILLERS

Best Practices for Specifying Emergency Power Systems

SECTION INTRUSION DETECTION

MINOOKA FIRE PROTECTION DISTRICT Fire Prevention Bureau Fire Inspector Rodney Bradberry

Are there any policies regarding outlets that contain USB ports?

National Electrical Code

TABLE OF CONTENTS CHAPTER 1 GENERAL RULES CHAPTER 2 WIRING AND PROTECTION... 51

15900 HVAC INSTRUMENTATION AND CONTROLS

PWGSC Ontario MULTIPLEX FIRE ALARM SYSTEM Sect Region Project Page 1 Number R

PRINTED: 06/09/2017 FORM APPROVED CENTERS FOR MEDICARE & MEDICAID SERVICES OMB NO (X2) MULTIPLE CONSTRUCTION A. BUILDING 03 - A BUILDING

A. Shop Drawing submittals shall include, but not be limited to, the following:

FIRE & LIFE SAFTEY STANDARD

INSPECTION AND TESTING FORM

B. Provide factory test, startup by a supplier authorized by the equipment manufacturer(s), and on-site testing of the system.

Functional Performance Test

This Addendum includes the following changes and clarifications to the Contract Documents:

Transcription:

263213 EMERGENCY POWER SYSTEMS PART 1: GENERAL 1.01 SUMMARY A. Section includes: 1. University guidelines for the installation of Emergency Power Systems (EPS). 2. Addresses the design and installation of an engine-driven generator to support facility emergency and standby loads. B. Related Sections 1. Section 263251 Emergency Lighting Systems 1.02 SYSTEM DESIGN CONSIDERATIONS A. Typically, an engine-driven generator with automatic transfer switching shall provide emergency power for the facility building life safety systems. B. Building life safety systems shall be connected to the generator system in accordance with all applicable codes. These include, but are not limited to: 1. Fire alarm and detection system 2. Security and card access systems 3. Emergency exit and egress lighting 4. Fire Pump and jockey pump 5. Smoke purge fans 6. Laboratory fume hoods / fans 7. Elevators (when used as means of egress) C. Critical mechanical equipment shall be considered for connection to the generator system to avoid building freeze-up or flooding. This includes, but is not limited to: 1. Heating system pumps 2. Condensate return pumps 3. Sewage ejector pumps 4. Building Automation System (BAS) 5. BAS control air compressors D. Consideration shall also be given to other Owner equipment loads such as: DATE: 11/16/17 DATE: 11/16/17 Page 1 of 13

1. Incubators 2. Refrigerators and coolers 3. Ultra-low laboratory equipment 4. Outdoor Blue Lights (EM Phones) fed from the building E. If one generator is used to supply both emergency and non-emergency (legally required or optional standby) loads, dedicated transfer switches for each type of load will be required per Code. F. For small buildings or facilities (those with minimal emergency loads), a lifecycle cost analysis (including maintenance costs) should be performed to determine if battery pack sources or a generator set source would be the most cost effective source for emergency systems. 1.03 SYSTEM DESIGN PLANNING A. For major Emergency Power Supply System (EPSS) renovations (such as EPSS revisions or replacement) and new system designs, consultant shall engage Cornell University s Facilities Engineering (CU FE) via the Cornell Project Manager to determine the overall scope of the work before commencing design. B. Coordinate the following system design elements with the Project Manager and representatives from CU FE in a basis of design document: 1. List applicable Codes and Standards with Editions used in the system design, including applicable versions of the Building Code of New York State, NFPA 72, NFPA 70, and the Elevator Code. Identify building occupancy type. 2. Develop and identify overall design considerations: a. EPS Indoor or outdoor location; b. EPS Sound attenuation level; c. EPS Type of fuel supply; d. Automatic Transfer Switch (ATS) type (i.e. open transition, closed transition, bypass/isolation) e. Types of loads to be connected to the EPS; f. EPS Monitoring and connection to supervising station, i.e. Digitize. 3. Location of EPS, ATS, branch circuit panels, and remote annunciator. 4. Routing of generator exhaust piping. 5. Special systems considerations (i.e. fire pumps, elevators, atrium smoke purge, closed transition ATS and associated circuit breaker shunt trip requirements and/or load shedding schemes.) DATE: 11/16/17 DATE: 11/16/17 Page 2 of 13

C. Consultant shall maintain an up-to-date list of each load considered and categorize by load type (Emergency, Legally Required or Optional Standby) connected within the facility. Consultant shall coordinate the final generator sizing with the Project Manager and CU FE using manufacturer software sizing program. Provide the final data to Project Manager and Cornell FE prior to the completion of the construction documents. 1.04 SUBMITTALS A. To ensure compliance with the intent of this standard, all new EPSS final designs and associated contract submittals shall be reviewed by CU FE. B. One (1) copy of new EPS submittal shall be sent to the CU FE for review and comment prior to releasing final approved submittals to the contractor. Submittals shall contain the following information: 1. Product information for all installed components, such as the EPS, ATS size and type; fuel storage tank(s), outdoor enclosure, exhaust silencer, annunciator. 2. System labeling materials and methods as described in this section. C. Refer to CU Design and Construction Standard 260500 Basic Electrical Requirements for additional submittal requirements. D. All information on the generator and fuel tank data shall be listed as required on Cornell University s Environmental Health & Safety (EH&S) Fast Facts: Emergency Generator and Fire Pump Projects. This document will be provided by the Cornell Project Manager or CU FE upon the request of the Consultant. 1.05 AS-BUILT INFORMATION A. At completion of the project, Engineer of Record shall provide a complete set of EPSS As-Built information that includes the following information prior to the closeout of the project: 1. EPS and EPS Annunciator(s) locations 2. Emergency Power Panel locations 3. Special Systems Interface locations 4. Complete EPSS diagram that depicts wiring between EPS and all EPSS components. Such detail shall include all major equipment and their locations (approved room number designation), power wiring connections, and interconnections to other special systems as designed per this standard. 5. Completed Commissioning documentation (Startup List) DATE: 11/16/17 DATE: 11/16/17 Page 3 of 13

6. Approved Routine EPSS Testing Job Plan PART 2: PRODUCTS 2 2.01 EMERGENCY POWER SUPPLY (EPS) A. System Installation Considerations 1. An engine-driven generator shall be located in a room or enclosure designed for the purpose. Assembly shall meet all requirements of UL and engine emissions must meet applicable EPA requirements. 2. The EPS shall be separated from other areas as required by Code for the isolation of hazards. 3. The EPS should be installed as close as practicable to the normal (utility) electric service to reduce the amount of cabling required to transfer switch(es). 4. EPS control panel, including metering/display and emergency stop switch shall be located to allow for ease of access and viewing of EPS conditions. Note that some installations may require the remote location of the control panel as the panel is usually located on top of the generator housing end of the EPS, and where the EPS has a subbase tank and/or located outdoors, the control panel could be over 8 0 AFG. 5. If locating the ATS in the same room as the EPS, locate the ATS(s) closest to the egress door. Do not locate ATS in an area that requires personnel to travel around or over the generator set for access. 6. Allow a minimum of three feet around the sides and generator end of the EPS for service and to ensure free flow of generator cooling air. For a 480V generator, provide a minimum of four feet working clearance in front of the generator control panel, circuit breaker, and any other electrical parts requiring examination, adjustment, servicing, or maintenance while energized per NEC 110.26(A). 7. An adequate supply of combustion air and cooling air shall be provided for the emergency generator room. Manufacturer s recommendations for air supply and exhaust shall be determined and facilities designed according to these recommendations. 8. Supply air shall be taken from outdoors. 9. If necessary, provide a heat source such as a unit heater to keep room at an acceptable ambient room temperature. 10. For outdoor located units, a battery heater, water jacket heater, and/or carburetor heater may be required. Consult with manufacturer and Cornell FE for guidance. 11. Provide motorized dampers on all ducts/openings, interlocked to operate (open) on generator run. Provide fire ratings on all assemblies as required by Code. DATE: 11/16/17 DATE: 11/16/17 Page 4 of 13

2.02 FUEL SUPPLY 12. EPS shall be supplied with accessible coolant and oil drains with valving. Locate to allow for ease of maintenance. 13. The generators engine shall meet all of the requirements and limitations listed in the Cornell EH&S document Fast Facts: Emergency Generator and Fire Pump Projects. A. General 1. Priority for selection of the EPS fuel supply type shall be given for the EPSS to meet Code required transfer times (i.e. to power egress lighting will need to meet 10 second start and transfer time, NFPA 110, Level 1, Type 10). 2. Fuel capacity for EPS Class (run time) shall be adequate for a minimum of (4) hours at EPS full load unless otherwise dictated by Code. 3. Larger fuel capacities shall be discussed with CU FE and the Project Manager, but are generally no longer than (8) hours due to long-term fuel storage quality concerns. In addition, the University has the ability to bring the cogeneration facility on-line for large-scale needs within (4) hours in the event of a utility outage for central campus. 4. Fuel supply installations shall meet all applicable Codes and Standards. B. Diesel Fuel 1. The main campus fuel supply Ultra-Low Sulfur Diesel (ULSD) tank for all campus generators is located at Palm Road. ULSD fuel information can be obtained from the Project Manager. Sulfur content must not exceed 15 ppm. Cetane index or aromatic content as follows: minimum cetane index of 40, or maximum aromatic content of 35 volume percent. 2. Storage tanks for individual EPS shall be sub base type or remotely located within a facility. All tanks shall be UL Listed and dual-wall type unless otherwise coordinated with the Project Manager and CU FE. 3. Tanks shall be installed to allow for access and visual inspections. 4. Fill ports shall be equipped with a mechanical whistler audible alarm. Automated solenoid valves interlocked with the fuel system to prevent overfill of the remote internal building tank is discouraged. 5. Consultant shall design diesel type EPSS so that it will run with a minimum of 30% loading. This shall be accomplished by properly sizing the generator to accommodate the current emergency/legally required/optional standby load in the building plus 25% future capacity. Otherwise, the use of smaller, paralleled generators and paralleling switchgear should be considered (preferred if sufficient loading cannot be added at the onset), or supplemental electric resistance load banks should be included in the design (not preferred) to maintain a 30% minimum load during monthly testing. DATE: 11/16/17 DATE: 11/16/17 Page 5 of 13

C. Natural Gas Fuel 1. Note that natural gas fuel supply is not readily available on central campus. 2. Natural gas service shall be obtained downstream from the facility main building pressure regulator and meter. 3. No natural gas piping shall be installed underground/below grade. 4. Provide electronic interlocks / valving to ensure gas supply to unit is shut off when generator is not running. 5. If a natural gas generator is considered for the project, the designer must first check with the utility to ensure that adequate natural gas pressure is available at the site for the proposed generator. 6. Consultant must evaluate loads in the building to be served by the natural gas generator to ensure that a natural gas generator can provide adequate service and voltage response to expected load changes within the facility. For emergency power application, the consultant must ensure that the designed emergency power system meets the response requirements of NFPA 110 for Level 1, Type 10 systems. D. Other Fuel Supply Types 2.03 ENCLOSURE 1. Other fuel types may be considered based upon EPS location, site conditions and access / availability of fuel resources. Coordinate with CU FE and Project Manager. A. Consideration and approval of outdoor EPS unit locations shall be reviewed and coordinated with the Cornell University Architect. This will require the consultant to schedule a site visit and walk through and/or photo renderings of the proposed equipment. B. Review enclosure paint finish with University Architect. Note that a non-standard manufacturer finish may be required to enhance aesthetics, and could result in additional lead time on the equipment. C. Outdoor enclosures shall be sound attenuated; coordinate specific db(a) limits with CU FE during design. Provide hoods as required to meet required sound levels. D. Generator exhaust piping and muffler shall be installed and contained within the enclosure. The exhaust outlet only shall be extended through the enclosure. E. General skin-tight enclosure is standard. Review walk-in type with CU FE if additional electrical equipment is necessary to support the EPSS prime mover. DATE: 11/16/17 DATE: 11/16/17 Page 6 of 13

F. Review installations of maintenance GFCI convenience receptacle(s) and/or interior enclosure lighting inside enclosures with Project Manager and Cornell FE. 2.04 GENERATOR EXHAUST A. Generator exhaust piping shall be installed to minimize the possibility of exposing the public to noxious gases. It is preferred to have a vertical discharge to allow for the gas plume to rise quickly. Maintain safe distances from building air intakes, keep away from loading docks. B. Avoid rain caps or other devices that limit plume rise on exhaust stacks. Although widely used, conical rain caps are not necessarily effective at preventing rain from infiltrating the exhaust system because rain does not typically fall straight down. Alternate design options are presented in the ASHRAE Handbook HVAC Applications. C. Where generator engine sets are installed indoors, it is preferred to route the exhaust piping within the building until the outlet exits to the exterior wall or roof. Provide all necessary insulation and fire ratings to accommodate the installation. D. Provide air modeling dispersion analysis of the generator exhaust system to ensure acceptable levels are maintained. Coordinate the design criteria with the Project Manager and CU FE. E. The generators engine shall meet the requirements of 40CFR Part 60, Subpart iiii for diesel (compression ignition), and Subpart jjjj for spark ignition (natural gas, gasoline) engines. F. Supplemental means shall be considered to reduce emissions through the installation of catalytic converters if the dispersion analysis cannot meet design criteria. 2.05 BATTERIES/CHARGING SYSTEM A. Type NiCad or sealed lead acid type. Consultant shall review total ownership costs (including disposal and/or recycling fees) and provide recommendation to CU FE prior to final equipment selection. B. Battery charger output shall be monitored, alarm condition shall be sent to Cornell EMCS. DATE: 11/16/17 DATE: 11/16/17 Page 7 of 13

2.06 REMOTE ANNUNCIATOR PANEL A. Remote annunciator panel operation and features shall be similar to the main control panel operation and features. B. Conform with NFPA 110, Level 1 for required alarm and pre-alarm conditions (applies to Level 1, Level 2, and Optional Standby generators). C. Remote annunciator panel enclosures shall be similar to the main control panel enclosures, panel covers, and trim rings. (Note: Keyed locks for remote annunciator panels shall be keyed the same as the main control panel) However, this panel shall be flush-mounted unless approved for surface mounting by the Architect of Record. D. Coordinate the mounting of the remote annunciator with building support staff. Locate in an area that can observe and report conditions, such as adjacent to the fire alarm annunciator or control panel. 2.07 TRANSFER SWITCH(ES) A. General B. Types 1. All transfer switches shall be automatic unless otherwise coordinated. The transfer switch unit shall be electrically operated and mechanically held. The electrical operator shall be a nonfused mechanism, momentarily energized. 2. The switch shall be positive double-throw operation. All main contacts shall be silver composition. Switches rated 600 amperes and above shall have segmented, blow-on construction for high withstand current capability and be protected by separate arcing contacts. 1. Provide switched neutral (4-pole) type ATS for all 480Y/277V systems with ground fault protection; review applicability for 208Y/120V systems with ground fault protection and provide information to CU FE. 2. Open Transition general use and preferred in most installations. 3. Closed Transition a. Must be pre-approved by the Cornell Energy & Sustainability Department (Cornell Utilities) before proceeding to design. b. Consider where routine testing would be disruptive to facility research and/or occupants. c. Coordinate the installation of this type of equipment with CU FE; a central record of this type of ATS is managed. DATE: 11/16/17 DATE: 11/16/17 Page 8 of 13

d. Installation of this type of ATS requires that a shunt trip be installed on the EPS output breaker feeding the closed transition ATS to prevent the continued supply of power from the generator if the two sources are paralleled for longer than 100 milliseconds. 4. Bypass/Isolation utilize in large research buildings. 2.08 SYSTEM IDENTIFICATION/LABELING A. Provide lettered plates for the following equipment, components, and accessories. The plate shall contain the equipment identification (custom panel number, area served), as well as power circuit source and breaker number. 1. Power Panels served by EPS 2. Normal (utility) circuit breakers serving automatic transfer switches 3. Automatic Transfer Switches 4. Remote annunciators B. Label shall be red plastic, lamicoid engraved plated or approved equal. (Note: ALL lettered plates shall be reviewed and approved by Cornell University s Project Manager prior to installation) C. Standard naming of ATS: 1. NEC defined Article 700 load ATS-EM_ (sequential number as suffix if more than one ATS installed) 2. NEC defined Article 701 load ATS-LR_ (sequential number as suffix if more than one ATS installed) 3. NEC defined Article 702 load ATS-OS_ (sequential number as suffix if more than one ATS installed) 2.09 ACCEPTABLE MANUFACTURERS A. The equipment, components, and accessories shall be as approved below by Cornell University s Facilities Engineering Electrical Section. Requests for authorization to substitute, vary, or change the approved equipment, components, or accessories of the approved manufacturer may be submitted, in compliance with Cornell University s Design and Construction Standards (see Division 01 - General Requirements), to CU FE Electrical Section prior to the Contractor s submission of the invitation-for-bid proposal. B. Approved EPS manufacturers: 1. Caterpillar 2. Cummins 3. Kohler 4. No other manufacturers will be considered DATE: 11/16/17 DATE: 11/16/17 Page 9 of 13

5. Rebranded equipment manufactured by equipment manufacturers other than those listed above will not be considered. C. Acceptable Automatic Transfer Switch (ATS) manufacturers: 1. Russelectric (preferred) 2. Zenith 3. ASCO 4. As supplied by the EPS manufacturer PART 3: EXECUTION 3 3.01 SYSTEM COMMISSIONING A. EPSS Startup list to be provided to CU FE for review and approval prior to startup. See Section 3.03. B. All testing shall be performed per the requirements for NFPA 110 for Level 1 systems. C. All testing (i.e. Startup, Function, and Routine) shall include, but not be limited to, documentation of test date, start/stop time, hour meter readings, and purpose of test. D. Acceptance Testing: 1. Provide minimum (5) working days prior notice to the Project Manager and the Cornell FE Electrical Section Generator Program Manager. 2. Complete and submit EPSS Startup Checklist to Project Manager. 3. Contractor to provide portable load bank sized for output of generator set. 4. Contractor shall supply adequate fuel for testing and shall fill tank to capacity upon completion of all acceptance testing. 5. Building load shall not be used for ANY load testing. 6. Documentation of the tests shall be provided to the Cornell Project Manager for archiving purposes. A copy of the test report shall also be provided to CU FE. E. Owner Training 1. Provide access by Cornell maintenance personnel for alarm and fault conditions. Train Owner personnel on EPS operation and troubleshooting of the EPS control panel. 2. Provide (4) hour training of the EPSS, including execution of the EPSS monthly testing job plan. 3. Provide contact information to the Owner for EPS control system software upgrade/purchase. DATE: 11/16/17 DATE: 11/16/17 Page 10 of 13

3.02 ROUTINE EPSS TESTING PROGRAM A. The University has implemented a campus-wide EPSS program, which includes the scheduling and testing of the EPSS as required by the BCNYS and NFPA 110. B. The routine exercising and operation of the equipment is administered through the campus asset management system, and consists of a custom job plan for each EPSS. C. Consultant shall be responsible to coordinate the development, initial execution and the delivery of the accepted monthly test routine to the Project Manager. D. Completed job plan shall be submitted to CU FE for review and approval, upon which time it shall be entered into the asset management system for implementation by the Cornell Shops. 3.03 EPSS START-UP A. General 1. EPSS start up shall conform to the requirements of the most current adopted version of NFPA 110 for Level 1 systems. This shall include, but not be limited to a load test and cold-start test. 2. Verification of all alarm and trouble conditions shall be verified and recorded. 3. Load bank equipment, connections, fuel and all associated labor costs for the EPSS startup shall be provided by the installing contractor. B. Function Test 1. EPSS shall be function tested before final acceptance by the Owner. This may be performed as a black start (utility power shall be disconnected from the building and the EPSS permitted to start the facility standby loads). 2. Any and all interlocks, load shed and other load management schemes including, but not limited to shunt trip schemes associated with fire pumps and/or closed transition ATS switches and permanent load bank controls shall be tested as a complete system to ensure proper operation. 3. Load on the EPSS and on each ATS shall be recorded. 4. ATS transfer times shall be recorded. C. Closeout Documents 1. Provide copies of all test information to Project Manager, including: a. EPSS startup, alarm and trouble condition verification DATE: 11/16/17 DATE: 11/16/17 Page 11 of 13

b. Generator Data (See 3.03D) c. ATS Data (See 3.03E) d. Function Test Data i. Interlocks ii. Load Shed iii. Other load management schemes e. EPSS running load (metered kw) f. ATS load(s) (metered amperes) g. ATS transfer time(s) 2. Provide small scale drawings (letter or 11 x17 size) that depicts the As- Built location of: a. EPS b. ATS(s) c. All utility supply circuit breakers serving ATS d. All standby power panels 3. Record As-Built Drawings of the EPSS system, including a. One-line electrical drawing of the EPSS system showing the generator, ATS switches, emergency/standby power panels, circuits, and critical loads. b. Emergency panelboard details and directories c. Load shed and load management system wiring and logic diagrams D. GENERATOR DATA Manufacturer Date Installed Model Output kw/ kva Serial # Fuel Type Diesel Tank Size (gallons) Run Time at Full Load (hrs) Voltage/Phases Location (Room) DATE: 11/16/17 DATE: 11/16/17 Page 12 of 13

E. ATS DATA (Provide for each ATS installed) Manufacturer Date Installed Model Rating A Serial # Type Voltage/Phases Location (Room) DATE: 11/16/17 DATE: 11/16/17 Page 13 of 13