Caithness HVDC Switching Station Pre Application Consultation Event. August 2016

Similar documents
Introduction. Who we are. Purpose of this public consultation

Caithness HVDC Switching Station Consultation

Rannoch 132 / 33 kv Substation Extension

Dorenell Wind Farm 132 kv Grid Connection

Scottish Hydro Electric Transmission Visual Impact of Scottish Transmission Assets (VISTA) Inverness 11 November 2015

Our approach to the design and routeing of new electricity transmission lines

HUNGERFORD SOLAR FARM

Welcome to the Public Consultation Exhibition

Slough International Freight Exchange Proposals, Colnbrook+

Land at Rampton Road. Cottenham

Linden Homes Proposals for land off Ringwood Road, Verwood

Assessing the impact of smallscale wind energy proposals on the natural heritage

Consultation Document Southern Section. Project LT68 Orkney Grid Connection. October 2018

PROPOSED RESIDENTIAL DEVELOPMENT LAND AT GREEN LANE, YARM

Public Consultation. Land at Monks Farm, North Grove. Welcome

SEABANK 3. Interim Landscape and Design Statement

Development of land adjacent to Braggs Farm Lane and Rumbush Lane, Dickens Heath. Welcome. Today s exhibition. The proposal site

Welcome to our exhibition

TOWN AND COUNTRY PLANNING (SCOTLAND) ACT 1997

ABOUT CALA HOMES CALA HOMES

Urban Growth Boundaries

LAND EAST OF SUDBURY ROAD, HALSTEAD PUBLIC CONSULTATION. Proposed Residential Development

Perth and Kinross Council Development Management Committee 8 June Pre-Application Report by Development Quality Manager

WELCOME. Land North of STEVENAGE. We would like to thank you for attending our public exhibition today.

FOR SALE RESIDENTIAL DEVELOPMENT OPPORTUNITY BLAIRTUMMOCK EASTERHOUSE

HORNSEA PROJECT THREE OFFSHORE WIND FARM

HISTORIC MARINE PROTECTED AREAS SCAPA FLOW AND QUEEN OF SWEDEN

LAND OFF TOLLBAR WAY, HEDGE END PUBLIC CONSULTATION. Proposed Residential Development

Replacement Golf Course Facilities and Residential Development, Churston. Environmental Statement Non-Technical Summary

1. Local Plan Context

LAND EAST OF HORNDEAN. 1. Welcome. Morrisons supermarket. Keydell Nurseries A3(M)

Looking Forward. Tuesday 22 nd April 2018

Grantham Southern Quadrant Link Road Environmental Statement

Community Garden Licence

Welcome to our Public Consultation

WELCOME. Welcome and thank you for visiting today.

BRIDGE OF DON MASTERPLAN & PLANNING SUMMARY

North Adelaide Playspace and Pocket Orchard

WELCOME TO THE NEW WILTON PARK

1.0 INTRODUCTION. Brantham Industrial Area Regeneration - Factory Lane - Brantham

WELCOME SMDA

Scotland s 2020 Biodiversity Challenge: Loch Lomond & The Trossachs National Park Authority Delivery Agreement

Welcome to our public exhibition

Land at Wester Bogie Farm, Kirkcaldy Introduction & Purpose of Consultation

Central Lake Ontario Conservation Conservation Lands Master Plan

HS2 Interchange Station Design

Haydock Point. Welcome

Welcome. Land adjacent Sandy Lane WALTHAM CHASE THE PROPOSED SITE

Statement of Community Involvement LAND OFF SOUTHDOWN ROAD HORNDEAN, HAMPSHIRE

Welcome to our public exhibition

UTT/17/2075/FUL - (BERDEN) (Referred to Committee by Councillor Janice Loughlin. Reason: In the Public Interest)

TOWN AND COUNTRY PLANNING ACT 1990 (AS AMENDED).

Application Guide. Should you have any questions on the Outline Application please contact:

INTRODUCTION. Welcome to the third round of information events on the emerging Yorkshire Energy Park proposals. THE CONSULTANT TEAM WHERE IS THE SITE?

Proposed St. Vital Transmission Complex

Linden Homes Proposals for land east of Glebe Farm, Sawtry

Thank you for coming. We want to hear your views on proposed improvements to the A1 between junction 65 (Birtley) and junction 67 (Coal House).

HARDWICK GREEN, King s Lynn. Welcome to our Exhibition. What are your views? Introduction to the site and proposals. About us

Inform you of the purpose and scope of the study for PTH 100 and a proposed future St. Norbert Bypass;

New Homes at Winton East

GUIDELINES FOR THE ROUTEING OF NEW HIGH VOLTAGE OVERHEAD TRANSMISSION LINES

The Place Solar Farm

Eastern City District Plan

PETERHEAD PORT AUTHORITY ENVIRONMENTAL STATEMENT. Non-Technical Document

Welcome to our public exhibition

CAIRNGORMS NATIONAL PARK AUTHORITY

CENTRAL BEDFORDSHIRE COMMITTED TO WORKING TOGETHER WITH LOCAL COMMUNITIES

Wind energy development in the South Pennines landscape

Planning Permission. Change of use on upper floor from bunkhouse to 2 no. flats 99

26/Old Dominion Task Force

Cape Environmental Assessment Practitioners(Pty)

HORNSEA PROJECT THREE OFFSHORE WIND FARM

April 11, 2016 Park Board Chair and Commissioners General Manager Vancouver Board of Parks and Recreation New Brighton Salt Marsh - Preferred Concept

PE1564/G. Petitioner Letter of 4 September th September Dear Mr Sharratt,

Natural Heritage Guidance and Information. 6 th of December 2007 Brendan Turvey

Welcome to our exhibition

CALA HO ME S WELCOME

Newcourt Masterplan. November Exeter Local Development Framework

Carterton Construction Ltd is bringing forward plans for up to 85 new family homes and extra care facilities on land east of Burford.

List of Policies. SESPlan. None applicable. Consolidated Scottish Borders Local Plan 2011: POLICY G1 - QUALITY STANDARDS FOR NEW DEVELOPMENT

Kibworth Harcourt. Introduction. Introduction

Full Name /title*. Address 1. Address 2 Post Code* *.. Phone* *Required fields for draw

SOUTH CAMBRIDGESHIRE DISTRICT COUNCIL. Planning and New Communities Director

SH1 link to Matakana Road

Dogger Bank Creyke Beck: Community Working Group. 25 th October 2012

The Moors at Arne Project, Managing Coastal Change

LAND AT WEST YELLAND. Environmental Statement Non-Technical Summary Welbeck Strategic Land LLP

Story Homes. Land at Thirsk Road, Kirklevington. An Introduction to Story Homes. Our Foundations. Commitment to Consultation.

Master Environmental Servicing Plan & Secondary Plan

North York Moors National Park Authority Planning Committee

A VISION FOR BLAIRGOWRIE

Welcome to our public consultation

vision & process willowburn, tarves community engagement 04/18

3.1 This evidence is based on the landscape and visual impact assessment included in Chapter 10 and Appendix I of the EIS.

WHERE DO WE GROW FROM HERE?

HS2 Environment. Protecting the environment

Linden Homes Land at Hill Place Farm, East Grinstead

DINBVfZGH THE CITY OF EDINBURGH COUNCIL

Welcome. Proposals for land at Smug Oak Lane BRICKET WOOD

Public Information Centre #1

Transcription:

Caithness HVDC Switching Station Pre Application Consultation Event August 2016

Introduction Who we are Purpose of this public consultation Other SSE Businesses SHE Transmission are proposing to submit a planning application for our proposed Development of a High Voltage Direct Current Switching Station in Caithness. As part of a suite of consultations to date, this consultation is intended to inform members of the public of the proposal and allow for feedback and comment on these proposals prior to finalising details for our planning application. Scottish Hydro Electric Transmission Plc (SHE Transmission) Scottish Hydro Electric Power Distribution Plc (SHEPD) Scottish Hydro Electric Transmission (SHE Transmission) is part of the SSE group and owns and maintains the high voltage electricity network that serves the north of Scotland. In total we maintain about 5,000km of overhead lines and underground cables easily enough to stretch across the Atlantic from John O Groats all the way to Boston in the USA. Our network crosses some of the UK s most challenging terrain including circuits that are buried under the seabed, are located over 750m above sea level and up to 250km long. The landscape and environment that contribute to the challenges we face also give the area a rich resource for renewable energy generation. There is a high demand to connect from new wind, hydro and marine generators which rely on SHE Transmission to provide a physical link between the new sources of power and electricity users. SHE Transmission is delivering a major programme of investment to ensure that the network is ready to meet the needs of our customers in the future. What is the difference between Transmission and Distribution? Electricity Transmission is the transportation of electricity from generating plants to where it is required at centres of demand. The Electricity Transmission network, or grid, transports electricity at very high voltages through overhead wires, underground cables and subsea cables. The transmission network connects large scale generation, primarily renewables, to central and southern Scotland and the rest of Great Britain. The Electricity Distribution network is connected into the Transmission network but the voltage is lowered by transformers at electricity substations, and the power is then distributed to homes and businesses through overhead lines or underground cables. Overview of Transmission projects Dounreay Mybster Orkney Gills Bay Spittal Shetland Our responsibilities As we are the only company that owns an electricity transmission network in the north of Scotland we are closely regulated by the energy regulator Ofgem. We are issued with a licence to operate and we must adhere to the terms of the licence. For this reason we operate on a very separate basis to other SSE businesses. Our licence stipulates that we must develop and maintain an efficient, co-ordinated and economical system of electricity transmission. Western Isles Existing infrastructure Completed Under construction Potential development Advanced planning Skye Kintyre Mossford Arran Beauly Lairg Fort William Dalmally Fort Augustus Hunterston Loch Buidhe (Bonar Bridge) Knocknagael Denny Moray Firth Tomatin Perth Kincardine Blackhillock Kintore Aberdeen Peterhead

Project Overview Scottish Hydro Electric (SHE) Transmission is required to develop proposals for a new electrical connection which will link Shetland to the Scottish mainland for the first time. Viking Wind Farm, located on Shetland, has contracted with National Grid plc to connect to the transmission network by 2021. As Shetland is not currently connected to the National Grid, construction of a new subsea cable is required. SHE Transmission has proposed that a High Voltage Direct Current (HVDC) marine cable will run from Weisdale Voe in Shetland to Noss Head in Caithness. The Shetland HVDC circuit would be used primarily to transport large volumes of energy to Caithness and onwards to the Blackhillock Substation in Moray, it could also be used to improve electrical resilience for Shetland. The Blackhillock Substation, near Keith, has a HVDC Converter Station which can change energy from DC to AC for onward transmission via the existing transmission network. A key element of the project requires the development and construction of a HVDC Switching Station which would connect the Shetland HVDC cable with a HVDC cable presently being constructed between Caithness and Moray. The Switching Station requires to be located close to the HVDC marine cable landfall site, at Noss Head. Given the coastal environment, all the switching station equipment will require to be housed in a building. All connections to the building will be via underground cable, no new overhead lines are required as part of this development. The Switching Station will become a strategic point in the HVDC network and will allow the flow of power to be switched between different cables, or circuits. The proposed Switching Station at Noss Head will connect three HVDC circuits including: one underground HVDC circuit connecting to Spittal in Caithness, one mainly subsea circuit connecting to Shetland and one mainly subsea circuit connecting to Moray. The project team have also designed space for any future HVDC connections.

The development process The chart below shows the main stages of the development process and the opportunities there will be for local people and others to give feedback as site selection, design and environmental work progresses. All dates are indicative at this early stage. Spring Summer 2015 September 2015 Search to identify multiple potential sites and carry out preliminary assessments First Pre-Application Consultation Carry out consultation with the statutory authorities and public on the multiple sites February 2016 March 2016 April 2016 Consider the feedback from consultation and identify a preferred site Develop an outline design for the preferred site, including landscaping proposals Second Pre-Application Consultation Carry out consultation with the statutory authorities and public on the outline design Submit Proposal of Application Notice to the Highland Council May 2016 Consider feedback from consultation and continue to develop the design Carry out detailed environmental surveys and assessments to inform planning application Summer 2016 Final Pre-Application Consultation Carry out final pre-application consultation with the statutory authorities and public on the detailed design and environmental assessments Consider any final feedback on detailed proposals Autumn 2016 Submit planning application to the Highland Council October 2016 2017 Submit Need Case and Project Assessment to Ofgem for approval Statutory Consultation Highland Council will carry out a statutory consultation following submission during which representations can be made directly to the planning authority Determination of planning application Construction phase will be approximately two years Subject to consents, pre-construction works begin on site Completion of Switching Station Construction

The Site Preferred construction access (to be determined in consultation with The Highland Council) Site boundary for planning purposes Site area once works complete Site selection The project development team have selected the preferred site following review of economic, technical and environmental factors, whilst considering the views of members of the public. All factors were considered in balance throughout the site selection process to arrive at a short-list of four sites in late 2015. Following these studies, and taking into account feedback received during the public consultations in September 2015 and March 2016, the site as shown above was selected. In addition, the project team acknowledge that access for construction traffic through the communities of Broadhaven, Papigoe and Staxigoe is possible although not preferred. In light of this, the project development team are investigating alternatives to route construction traffic via Ackergill and along a newly constructed access route.

Environmental Considerations SHE Transmission s preferred site is close to the low point on the minor road between the airport and Noss Farm. It is a landscape of open, gently rolling fields. The building will be partly dug into the slope and the land around mounded up gently to provide a degree of screening, particularly from the minor road to Noss Head. Given the open nature of the landscape, the building will be quite widely visible a noticeable addition to the landscape but it will be aligned with the existing field pattern and located away from the scenic coastal views. The site consists of two arable fields and is used as part of the farm s rotation programme. However, due to intensive agricultural management, the site is of relatively low ecological interest. There would be some disturbance to local recreational use of the minor road between Staxigoe and Noss Head during construction. Key Considerations Advantages Relatively low in the landscape, the site would be prominent locally but not particularly intrusive in the wider landscape Limited effects on cultural heritage interests Little effect on local ecology or wildlife, and the opportunity for some biodiversity improvement No specific engineering or technical constraints at the site The site is close to the HVDC cable landfall site Disadvantages Loss of about ten hectares of agricultural land Disruption to minor road during construction Relatively widely visible

Design Construction compound. Fully restored and returned to landowner on completion Mounding up to 3 m above existing ground level Indicative site layout +36 m Security fence at edge of dug-in platform Outer boundary fence: Caithness flag dyke to match local detail +35 m Building platform 24.9 m (dug in average 6 m) Ridge height 45.9 m Mounding up to 6 m above existing ground level +35 m Species-rich grass Clumps of scrub woodland Section A Section A Cross Section Section B Section B +24 m SUDS pond 50 40 30 20 Long Section section A Building design: The building will be approximately 21m high at its highest point, 150m long and 50m wide (70 x 500 x 165 ). We have prepared the indicative design shown here for our planning application in principle. The final design will be agreed at a detailed planning stage as part of the formal planning process but we seek comment on the design and the colour options prior to our planning submission. Site design: The building will be dug into the slope between about 3m on the low side and 8m on the high side and landscape mounds between 3m and 6m high formed around it. This will reduce the apparent height of the building and partially screen it, particularly in views from the road to Noss Head. 50 40 30 20 Section Cross Section B Clumps of native trees and scrub will be planted around the building and the grass areas will be seeded as wildflower meadows. In the long term the trees and scrub should provide more screening similar to the trees around Noss Farm. The planting will also provide additional cover for wildlife and the wildflower seeding Long section will increase local biodiversity. 50 40 30 20

Viewpoints Viewpoint 2 Viewpoint 6 Viewpoint 3 Viewpoint 5 Viewpoint 4 Viewpoint 1 (off the map - Thrumster) Visualisations: The next three boards show the proposed building viewed from the viewpoints shown on the map above. They show the development on completion with the proposed landscape mounding but before any scrub and trees have grown enough to be noticeable.

Visualisations Viewpoint 1, view from the A99 just north of Thrumster (Colour option A used for demonstration purposes) Viewpoint 2, view from the A99 southeast of Reiss (Colour option A used for demonstration purposes)

Visualisations Viewpoint 3, Ackergill (Colour option A used for demonstration purposes) Viewpoint 4, Staxigoe War Memorial (Colour option A used for demonstration purposes)

Visualisations Viewpoint 5, from the corner of the minor road to Noss Head (Colour option A used for demonstration purposes) Viewpoint 6, from the end of the track to Noss Farm (Colour option A used for demonstration purposes)

Building Colour Options Option A: Detailed grey, light roof Option B: Shades of green, dark roof Option C: Shades of grey, light roof This board presents the preferred building design with three colour options for your consideration and comment. This viewpoint is 4 Staxigoe War Memorial. We would appreciate you providing your preference by completing a comments form.

Building Colour Options Option A: Detailed grey, light roof Option B: Shades of green, dark roof Option C: Shades of grey, light roof This board presents the preferred building design with three colour options for your consideration and comment. This viewpoint is 5 from the corner of minor road to Noss Head. We would appreciate you providing your preference by completing a comments form.

Building Colour Options Option A: Detailed grey, light roof Option B: Shades of green, dark roof Option C: Shades of grey, light roof This board presents the preferred building design with three colour options for your consideration and comment. This viewpoint is 6 from end of track to Noss Farm. We would appreciate you providing your preference by completing a comments form.

What happens next and how can I have my say? Thank you for taking the time to find out about our proposals for the Caithness HVDC Switching Station. We appreciate all feedback and thank you for taking the time to provide your comments. You can complete a feedback form today, or you can post it back to us at the address provided. Information can also be provided by our Community Liaison Manager upon request. Feedback submitted to SHE Transmission as part of the pre-application consultation process will be used to inform our submission to the Highland Council as the relevant Planning Authority. Any feedback received at this stage will be presented in a Pre Application Consultation Report submitted with our planning application. You will also have the opportunity to make formal representation to our planning application once it is submitted. That consultation will be carried out by The Highland Planning Authority. The application will be available to view at the relevant Council Offices and also online through The Highland Councils online planning webpages. Please provide any comments to us by 9 September 2016. Get in touch with our Community Liaison Manager: Neil Anderson Email: neil.anderson@sse.com Phone: 07500 912 506 Write: Neil Anderson SHE Transmission Inveralmond House 200 Dunkeld Road Perth, PH1 3AQ The project is in the advanced development stage and we openly welcome comments and feedback to help us refine our proposal. We are very keen to ensure that members of the community understand our proposal as it will be taken forward to a planning application made to The Highland Council. Comments can be submitted as follows: At the exhibition today Complete a Comment Form and give it to a member of the team. By post Complete a Comments Form and post it to our Liaison Manager (details opposite). By email Complete a Comments Form and email it to our Liaison Manager (details opposite). Information can also be posted out to you by our Liaison Manager upon request.

Your comments Thank you for taking the time to attend this Pre Application Consultation. In order to record your views and improve the effectiveness of our consultation, please complete this short feedback form. Please complete in BLOCK CAPITALS Name Address Telephone Email Do you understand the need for the project? Yes No Comments Has the consultation information been clear and easy to understand? Yes No Comments Do you have any comments on our preferred proposals for the Caithness HVDC Switching station design? Comments

Can you please tell us you preferred colour option as detailed in the three information boards titled Building Options? Please indicate your preference by ticking a box, below. Option A: Detailed grey, light roof Option B: Shades of green, dark roof Option C: Shades of grey, light roof Do you have any additional comments in regards to the colour options? Comments Do you have any comments on the proposed access route for construction traffic? The proposed route is detailed on information board titled, The Site. Comments Do you have any other feedback for the Project Development team? Comments Thank you for taking the time to complete this form. If you would like your comments to remain anonymous, please tick this box Any information given on this comments form may be used and published as part of SHE Transmission s consultation report. By completing this comments form you consent to SHE Transmission using this information for these purposes. By providing contact details you consent to SHE Transmission contacting you in relation to this proposal. Your details will not be used for any other purpose. If you wish your comments to remain anonymous, please tick the box at the end of this form. Please note that comments made to SHE Transmission are not representations to the Council as planning authority at this stage. The opportunity for lodging representations will be when the application is formally submitted to the Council for formal consideration.