Nuts and Bolts (or Gravel and Asphalt) of the Main Street Project

Similar documents
University Park Subdivision Street Assessment Report

Project will Replace: Utilities Curb Pavement Lighting. City of Madison

DESIGN PUBLIC HEARING MAY 10, 2018 GRANBY TOWN HALL FIRST FLOOR CONFERENCE ROOM 10 WEST STATE STREET GRANBY, MASSACHUSETTS 7:00 PM FOR THE PROPOSED

Main Street Reconstruction From Ninth Line to Stouffer Street. Town of Whitchurch-Stouffville. Public Information Centre

PennDOT Public Meeting. S.R. 3044, Section A01 Castle Shannon Boulevard Roadway Improvement Project

West Dennis Center: Bass River to Old Main Street. West Dennis Business District: Old Main Street to Dennis Commons

PARKLET PROPOSAL PACKAGE & PROCESS

The Illinois Department of Transportation and Lake County Division of Transportation. Route 173, including the Millburn Bypass

Concluding Improvement Recommendations and Opinions of Probable Cost (calculated in may 2010 construction rates).

2016 REVISIONS COMMENT FORM RULES AND REGULATIONS FOR CONSTRUCTION IN THE PUBLIC WAY COMMENT PERIOD: JUNE 1 TO JUNE 30, 2015

New York Avenue Streetscape and Trail Project Public Meeting #1 Summary

Specification and Construction Plans For: South Bethany Landscaping Improvement Plan Contract Number T

Focus Group First Meeting Belfountain Community Centre Tuesday June 29, :00 p.m. to 9:00 p.m.

WELCOME! 8 8:30 6: TH STREET IMPROVEMENTS. Open House. Presentation & Q&A

City of Richmond. Engineering Design Specifications

September 28, 2017 Wentworth Avenue (CR 8) Sidewalk Improvements Open House

F. Driveways. Driveways which provide access to off-street parking or loading from public streets shall comply with the following:

3.13. Development Guidelines

DESIGN PUBLIC HEARING APRIL 24, 2018 MUNICIPAL OFFICE BUILDING HARDWICK, MASSACHUSETTS 7:00 PM FOR THE PROPOSED

CONFORMED AGREEMENT INCORPORATED REVISIONS PER AMENDMENT DATED: APRIL 2, 2013 FOR REFERENCE

STANDARD SPECIFICATIONS Book 2 ENGINEERING DRAWINGS INCLUDES ADDENDUMS

FDOT D4 Complete Streets

MAIN STREET RECONSTRUCTION PROJECT PRE-CONSTRUCTION PUBLIC INFORMATION SESSION AGENDA

Cottage Grove Road Reconstruction. City of Madison Engineering

Berkshire Regional Planning Commission Clearinghouse Review Report

Report or technical documentations of the target areas in Siauliai

PAVING GRID OUTSTANDING DURABILITY

IOWA HIGHWAY 57 / WEST 1 ST STREET STUDY PUBLIC INFORMATIONAL MEETING APRIL 22, 2014

Municipality of Anchorage, Alaska Parks & Recreation Department

This page left intentionally blank.

Public Hearing. Charlotte County-Punta Gorda MPO - Meeting Rooms A and B March 14, open house at 4 p.m., formal presentation at 5 p.m.

Final Report: Appendix C. LID Parking Lot Design and Teaching Tool at Bridgewater State University, Bridgewater Supporting Information

Pennsy Greenway Trail

5. LOW IMPACT DEVELOPMENT DESIGN STANDARDS

Metropolitan Area Planning Council 60 Temple Place, Boston, Massachusetts fax

Town of Millbury Department of Public Works

Public input has been an important part of the plan development process.

COMPLETE GREEN STREET CHECKLIST

Const. ROADS - Description

GYPSUM PARKWAY CORRIDOR ENHANCEMENT Gypsum, Colorado. Schematic Design January 2015

Transportation Systems and Utility Infrastructure

TOWN COUNCIL / PLANNING COMMISSION

CITY OF DAVIS DESIGN REVIEW INFORMATION CHECKLIST

COLERAIN TOWNSHIP ZONING COMMISSION Regular Meeting Tuesday, October 18, :00 p.m.

The open space system should provide connective elements, relate to natural resources, and enhance the suburban character of the landscape..

Lambeth Main Street Streetscape Improvements

PLANNING COORDINATING COMMITTEE

VALLEY COUNTY MINIMUM STANDARDS FOR PRIVATE ROAD DESIGN AND CONSTRUCTION

P A V E R S Are they really the same? The 3-P s and how they relate to storm water management

Below the trestle lie artifacts of past industry along the Cobbossee Stream. South end of the trestle, at the proposed trailhead area.

GUIDELINES FOR PERMEABLE SIDEWALK-LANDSCAPING PERMIT

CITY OF PORTSMOUTH PLANNING DEPARTMENT. MEMORANDUM To: From:

Appendix G. Detailed Design

Technical Bullet Series on Clay Brick Pavers

VILLAGE OF MOUNT PROSPECT 2016 STREET RESURFACING PROGRAM Frequently Asked Questions (FAQ s)

3.1 Survey Monument Preservation Guidelines for New and Reconstruction Projects. B. After construction and prior to recording Notice of Completion:

MPRD s Keith Mione (Community) Park Midlothian Road Entrance Traffic Signals

Maplewood Avenue Downtown Complete Street Project

Derby-Shelton Bridge Pedestrian and Bicyclist Enhancements [1]

Prince William Street Project (Grant Avenue to Wellington Road)

Town of Windham. Planning Department 8 School Road Windham, ME voice fax

open house 3 CITY OF SALEM Downtown Streetscape Plan

At Your Disposal CUP Amendment, Lot 20, Village Service Commercial, at 128 Bastille Dr. (PLN17-208)

ORDINANCE NO

III - design standards

Asbury Chapel Subdivision Sketch Plan

Fall 2017 Construction Update

ROANOKE STREET IMPROVEMENTS CHRISTIANSBURG, VIRGINIA VDOT PROJECT # U R24 UPC #:

Monroe Street Reconstruction. Public Preconstruction Meeting February 21, 2018

Introduction Post Construction Stormwater Management Performance Requirements

Town of Yucca Valley Capital Improvement Projects Report July 24, 2014

The Center Street Project

Anderson Memorial Bridge Rehabilitation Project Boston/Cambridge

Introduction Post-Construction Stormwater Management Performance Requirements

Revocable Street Privilege

To qualify for federal Transportation Enhancement (TE) funds a project must meet two basic federal requirements:

FOR IMMEDIATE RELEASE DATE: FRIDAY, AUGUST 31, Road Commission of Kalamazoo County Weekly Project Updates HAVE YOU SIGNED UP?

PRELIMINARY PLAT DESIGN REQUIREMENTS Updated 4/8/2016

INTRODUCTION EXISTING CONDITIONS

CITY OF MANHATTAN BEACH DEPARTMENT OF COMMUNITY DEVELOPMENT. TO: Parking and Public Improvements Commission

The Capital Design Advisory Committee St. Mary s College of Maryland & Historic St. Mary s City

Title 11 Streets and Sidewalks

North Loop Paving. December 18th, Street Reconstruction Project. Forrest Hardy, Transportation Planner Minneapolis Public Works

Access Management: An Overview

Appendix I. Access Management & Land Use Zoning Strategies Memo

Public Information Centre. Welcome

OVERMOUNTAIN VICTORY TRAIL BURKE CALDELL CORRIDOR FEASIBLITY STUDY REQUEST FOR QUALIFICATIONS CALDWELL COUNTY PATHWAYS

understanding Green Infrastructure In Zoning

Capital Projects impacting Odenton Town Center

ARTICLE IX SPECIAL PERMIT USES

McDonald s Restaurant - Purcellville Town of Purcellville Special Use Permit Statement of Justification July 24, 2014

APPLICATION FORM SITE PLAN REVIEW REGULATIONS TOWN OF CONWAY, NH

MARINA BAY NEIGHBORHOOD PRESENTATION. City of Richmond Officer Bradley A. Moody Memorial Underpass. April 11, 2012

VEHICULAR AND PEDESTRIAN CIRCULATION

APPENDIX G: TOWN ORDINANCE REVIEW

CITY OF BOYNTON BEACH SE 1 ST STREET COMPLETE STREETS IMPROVEMENTS

DESIGN CRITERIA PACKAGE

5.1 Commercial and Industrial Development. (Effective April 1, 2006)

SECTION 4(f) DE MINIMIS DOCUMENTATION

John Portman Boulevard Corridor

Transcription:

Nuts and Bolts (or Gravel and Asphalt) of the Main Street Project

What is the Main Street Project? The Main Street Project is a roadway project that addresses pavement, infrastructure and safety issues along Main Street between Sears Road and Park Street.

Poor subsurface The road is at failure. The road was never properly constructed. Pavement Issues

Poor subsurface To properly repair the roadway the project will replace 20 of material under the road surface with 12 of new gravel and 8 of asphalt. Pavement Issues

Pavement Issues The existing pavement structure consists of sandy materials and asphalt Sand moves and rolls (think of walking on beach sand) Even with an average of 5 of asphalt, the road is still failing

Pavement Issues Poor base allows too much deflection in the roadway which creates cracks. Eventually the cracks turn into pot holes

Pavement Issues The Town can continue to seal cracks, fill pot holes, lay large patches of asphalt or lay asphalt over the entire road, but it won t last if the base is not repaired.

Pavement Issue Example This section of Main Street was overlaid with a layer of asphalt in 2011. No work was done on the base. It has cracked, and has had multiple pot holes filled.

Pavement Issues If we pave over the existing base: Cracks will appear within a year Pot holes will appear within 5 years The road surface will be at a higher elevation, which will affect the sidewalk elevation and driveways

Infrastructure/Pavement Issues On many roads the Town will reclaim the asphalt, which means we will crush it and mix it in with the base. As you can see from the graphic, the surface of the road stays at the same elevation. The road has to be graded in order to not raise the road higher than adjacent driveways and sidewalks.

Infrastructure/Pavement Issues Along Main Street some sidewalks are already below the road grade. The road will be re-graded 6-12 lower in those and other locations. Asphalt, on average, is 5 thick on Main Street. The Town s reclaim process only mixes the top 6 of roadway. Reclaim is NOT an option for this project.

Pavement Issues Full Depth Construction The proposed road structure removes 20 inches of material and replaces it with good gravel and new asphalt The layers of the base and pavement structure help give the roadway strength

Full Depth Reconstruction Will repair the roadway base and provide a strong foundation Is expensive but long lasting, and the best construction for this project

Drainage without good drainage the road will continue to be at failure. Proper drainage helps keep the road base and pavement strong. Infrastructure Issues

Drainage poor drainage also leads to puddles and safety concerns along the roadway Infrastructure Issues

Safety Issues The project addresses pedestrian, bicycle and vehicular safety Increases Pedestrian Safety by: Installing granite curbing on existing sidewalks to create a vertical separation between vehicles and pedestrians Shortening crossings at intersections Introducing a road shoulder as a buffer between pedestrians and vehicles Using contrasting colors at crosswalks Installing new sidewalks Increases Bicycle Safety by: Introducing a road shoulder for bike use Increases Vehicular Safety by: Creating a left turn lane at each approach to the Routes 85 & 30 intersection

EASEMENT BREAKDOWN SUMMARY QUANTITY LAND AREA PERMANENT ROADWAY EASEMENTS 30 10,934 BUSINESS 8 2,078 GOVERNMENT 4 1,119 NON-PROFIT BUSINESS 2 1,173 NON-PROFIT CHURCH 2 1,096 NON-PROFIT SCHOOL 8 4,730 PRIVATE RESIDENCE 6 738 PERMANENT UTILITY EASEMENTS 25 16,140 BUSINESS 3 11,781 GOVERNMENT 2 628 NON-PROFIT BUSINESS 3 221 NON-PROFIT CHURCH 2 373 NON-PROFIT SCHOOL 8 993 PRIVATE RESIDENCE 9 2,144 TEMPORARY EASEMENTS 67 105,863 BUSINESS 13 17,162 GOVERNMENT 11 22,649 NON-PROFIT BUSINESS 1 7,284 NON-PROFIT CHURCH 3 2,592 NON-PROFIT SCHOOL 18 31,788 PRIVATE RESIDENCE 21 24,388 Easements The Special Town Meeting vote is to allow Selectmen to negotiate easements. There are 6 permanent easements from private residences needed to accommodate the road or sidewalk. These total 738 SF. Four of these locations currently accommodate road or sidewalk. Two locations are new because of the project. One of the permanent utility business easements is for the drainage basin. TOTAL 122 132,937

Costs? The project is currently funded through the Transportation Improvement Program (TIP) The total project cost is $7.2M which is fully funded by the TIP (State and Federal money). Southborough is part of the Boston Region Metropolitan Planning Organization (MPO). The MPO determines which projects get funded through the TIP. The MPO consists of 22 members from neighboring Towns, Cities and some State Agencies. Engineering costs have all been reimbursed through the State s Chapter 90 program ($750k to date) Appraisals for easements will be funded through the State s Chapter 90 program, which are reimbursed funds. Payment for easements will also be funded through the State s Chapter 90 program, which will be reimbursed.

What Happens at Woodward? Project includes: New sidewalk to Woodward School on the east side of Cordaville Road Improved sidewalk on the west side of Cordaville Road Delineated School Zone on Main Street at Woodward path crossing

Historical Commission s Requests Preserve and place the stone marker at the west end of the Common. Extend existing railing and granite posts on the Common, replicate existing for additional footage. Use Ground Penetrating Radar along the Common s retaining wall and along the stone wall of the Old Burial Grounds. When reconstructing the Common s retaining wall mark all capstones and return and re-use in same relative position in the wall. Reset granite watering trough in the same relative place in the wall alignment. Reset the granite block steps in the same relative position in the wall alignment. Do not disturb the Veteran s of All Wars Memorial. Relocate original Common Street road signs as close to their existing positions as possible.

Deerfoot looking East

Looking toward the library east on Main Street (Standing at Middle Road)

The Main Street and Route 85 Intersection The Main Street and Route 85 Intersection design includes a left turn lane on each approach. The intersection, when built, will be smaller than the Southville Road and Route 85 intersection. Southville/85 Main/85

Looking East From Common

From Library's northern driveway looking south

From Library's northern driveway looking south

Library Looking South (compared to Southville)

Looking North from Cordaville Rd

Cordaville Looking North (compared to Southville)

Looking West From Across from Community House

Henry Knox Memorial

Across from Public Safety looking west

Near Woodward walkway looking east

What if we don t pass the Easement Article? At a minimum we have to fix the road with full depth reconstruction, make the sidewalks safe and meet the Americans with Disabilities Act (ADA) standards: Tree protection/removal $20,000 Roadway and sidewalk sub-base replacement, grading and paving $2,030,000 Curb Work, new and reset $390,000 Water work due to grade changes $243,000 Drainage work, install new and repair existing $690,000 Drainage basin at Parkerville $49,000 Wall work at Parkerville $58,500 Loam and seed $50,000 Road signs and paint $55,000 Traffic management (cones, barrels, construction signs, etc.) $80,000 Contractor mobilization $120,000 Construction Oversight* $415,000 Utility work (reset poles)* $95,000 Police details* $30,000 10% contingency (* items not included in contingency) $376,500 TOTAL $4,702,000

Special Town Meeting October 18, 2016 Trottier School -7pm For More Information: southboroughtown.com/mainstreet or contact DPW 508-485-1210 kgalligan@southboroughma.com