VALLEY VIEW POND Q&A. This item will be discussed under the First Reading portion of the agenda at the July 17, 2012 Village Council meeting.

Similar documents
Benefits of Native Vegetation. Presented by: Mary Beth Falsey DuPage County Senior Wetland Technician

Stormwater Regulations & Considerations Morse Study Area. Pam Fortun, P.E. CFM Senior Stormwater Treatment Engineer Engineering Services Division

OPERATIONS & MAINTENANCE MANUAL FOR POST CONSTRUCTION MEASURES

Weston s Wetlands, Stormwater, & Open Space

Buckingham Lake Berkshire Pond Raft s Pond

WET PONDS INSPECTION & MAINTENANCE CHECKLIST

5. FINAL DEVELOPMENT PLAN APPROVAL MENORAH MEDICAL CENTER OFFICE BUILDING Vicinity of the southwest corner of 119 th Street and Nall Avenue

Alternatives Analysis Summary Memorandum

When planning stormwater management facilities, the following principles shall be applied where possible.

KENT COUNTY STORMWATER MAINTENANCE DISTRICT STORMWATER BMPs MAINTENANCE TASKS AND RESPONSIBILITIES GUIDANCE DOCUMENT BIO-RETENTION FACILITIES

Mosquito Control Guidelines

Part 4: CRS Stormwater Management Activity (450) and Urban Flooding Best Practices

SOIL EROSION AND SEDIMENT CONTROL

Mosquito Control Guidelines

Mosquito Control Guidelines

WAKE COUNTY STORMWATER MAINTENANCE CHECKLIST

BASS PONDS, MARSH, & WETLAND HABITAT RESTORATION PROJECT

Outflow to Saw Mill Run

13. PRELIMINARY PLAT NO MILLS FARM - Vicinity of the southeast corner of 159 th Street and Quivira Road

City of Petersburg, VA Stormwater Utility Frequently Asked Questions

Design Considerations for Open Channel and Detention Pond Design. Howard Redfearn, City of Mansfield

North Branch of Cypress Creek Ecological Restoration: A Comprehensive Approach to Stream Restoration

Manor Ponds, Sheffield

Weston Conservation Commission

CITY OF HOLLY SPRINGS STORMWATER UTILITY FREQUENTLY ASKED QUESTIONS

Town of Essex Small Site Erosion Control Guide

Maintaining Your Neighborhood Stormwater Facilities

Stormwater Utility and Connection Fees

Working with nature to manage your stream

ADDENDUM TO BIOLOGICAL SCOPING SURVEY REPORT, BOTANICAL SURVEY AND WETLAND DELINEATION

Checklists. Project Name: Location: File Number: Date of Submittal: Reviewer: Date: Applicant: Contact Name: Phone Number:

Homeowners Guide to Stormwater BMP Maintenance

Lake and Stream Restoration Project

Draft Rhode Island Stormwater Design and Installation Standards Manual

Severn River Sub-Watershed: BMP 09-Retrofit

Summer Public Education and Outreach Campaign Toolkit

Problem Understanding

The Conservation Foundation

C-12. Dry Pond. Design Objective

Maintaining Your Neighborhood Stormwater Facilities How to identify stormwater facilities and keep them working

4. Contractor (and subcontractors if applicable) certification statement(s)

The following principles guide the development of goals and strategies to protect and promote these amenities:

Erosion Control for Home Builders in the. City of Jacksonville

Project: Developer/Designer: Reviewer: I. Narrative: 1. Project Description: Describes the nature and purpose of the land disturbing activity.

elm creek Watershed Management Commission

Welcome to Proper Maintenance of

2

PRELIMINARY DRAINAGE REPORT LATHAM 200 MMSCFD GAS PROCESSING PLANT

Florence County Small Commercial Land Disturbance Permit Application

Tips for Maintaining and Enhancing Stormwater Management Areas

Improving an Urban Watershed The Past, Present and Future of Addison Creek

Conservation in South Jersey Being Creative with Restoration

Just The Basics: Illicit Discharge. What does it mean to me?

Design Around Waterways and Wetlands

What is stormwater runoff? Why is it a problem? Available Financial Incentives for Stormwater BMP s Downspout Disconnection - up to $20

Operation & Maintenance of Stormwater Management Facilities

ATTACHMENT 1 WILSON MINE LECROY AREA SEMIPERMANENT DEWATERING SYSTEM

POLE BRIDGE ROAD NEAR FIVE LOT FARM

Information for File # MHK

APWA Expo August 27, Ground Water Recharge With Storm Management: A Sustainable Development

Paul D. Ralph, BES, RPP, MCIP, Commissioner, Development Services Department. Proposed Storm Water Pond Maintenance Fee

Lesson 2: Stormwater Best Management Practices (BMPs)

Project: Mooney Lake Preserve Received: Location: 300 Sixth Ave. N., Orono Complete: Noticed:

Sustainable Stormwater Management through Green Infrastructure. Jersey City Public School #5

Use of Best Management Practices

City of Spring Hill Storm Water Utility Frequently Asked Questions

City of Waco Stormwater Management Regulations

STORMWATER UTILITY FREQUENTLY ASKED QUESTIONS

Operations and Maintenance Plan

CITY OF URBANA STORMWATER UTILITY FEE FREQUENTLY ASKED QUESTIONS

Storm Water Quality and Shoreline Restoration Improvements - Grant Funding Request City of Mound Carlson Park Bolton & Menk Project No.

THE VILLAGE OF LOMBARD TERRACE VIEW POND STORMWATER IMPROVEMENTS FEASIBILITY STUDY

STORM WATER UTILITY FREQUENTLY ASKED QUESTIONS

TOWNSHIP OF LOGAN SOIL & FILL IMPORTATION AND PLACEMENT APPLICATION SUBMITTAL CHECKLIST

Appendix R - Management Plan for the Buffers and Stormwater Management Facilities

Tale of Two Cities: Exploring How Two Communities are Using Green Infrastructure to Reduce Flood Risk

ions nts July 1, 2019 The utility answers to some increase: Q: A: rainwater Q: A: areas any the total by

Constructed Stormwater Wetlands

Stormwater Management Plan (SWMP) Revision Date: 11/05

FURTHER TO EXECUTIVE COMMITTEE MEETING #11/12 To be held on Friday, January 11, 2013

Rule D Wetland and Creek Buffers

Urban Conservation Practice Physical Effects ESTABLISHMENT, GROWTH, AND HARVEST NUTRIENT MANAGEMENT

STORMWATER MANAGEMENT FACILITIES/STORMWATER PONDS - What Are They?

The Commissioner of Engineering and Public Works, the Director of Public Works and the Director of Development / Transportation Engineering recommend:

The Napa River Flood Protection Project

PROJECT SCOPE OF WORK CITY OF TOWN AND COUNTRY STORMWATER PROGRAM

Ben Powell, Clemson Extension

Key elements : Filter Strips must be designed within parameters required by the Fort Wayne s Development Standards/Criteria Manual.

Neighbourhood Guide. For Cambridge Residents In New Neighbourhoods

Executive Committee Meeting Addendum. #7/15 July 3, :30 A.M. HEAD OFFICE, 101 EXCHANGE AVENUE, VAUGHAN Members:

City of Easton Storm Water Program Development Project Frequently Asked Questions August 27, 2018

Leduc Industrial Outline Plan SE W4

OP Council Resolution June 16, Planning and Development Services

GENERAL INFORMATION What is Stormwater? What is a stormwater utility? What is an impervious surface?

Peoria has a tremendous opportunity to get sewer overflows under control and fight stormwater runoff head-on

Things People Never Seem to Understand about Pond Management. Stew Metzler SEHAC October 5, 2011

Appendix D - Technical Design Criteria for BMPs

Guiding Landowners in Stream Restoration. The Science, Practice & Art of Restoring Native Ecosystems 2015

Urban Water Management and Soils (ESRM 311 & SEFS 507)

Urban Water Management (ESRM 311 & SEFS 507) Cougar Mtn Regional Wildland Park & Lakemont Blvd, Bellevue WA

Transcription:

VALLEY VIEW POND Q&A This item will be discussed under the First Reading portion of the agenda at the July 17, 2012 Village Council meeting. 1. Please provide a history of the pond including Village maintenance activities. Date Action Village Expense 1977 Village approves Valley View Estates Subdivision. The Downers Grove Park District agrees to own and maintain the pond provided that the pond is constructed to certain predetermined standards. 1978-1987 Developer attempts to construct the pond according to the Village and Park District standards. 1988 Village accepts ownership of the pond in response to litigation filed by the developer against the Park District and the Village. 1992 Village installs rip-rap around the perimeter of the pond to reduce erosion. $48,698 2006 Village dredges the east side of the pond near the inlet and replaces the stormwater pipe $39,500 that feeds the pond. 2009 Village installs two aerators to improve water quality. $11,689 2009 Village performs aquatic algae control $2,860 2010 Village explores hydraulic and mechanical dredging of the pond. 2010 Village performs algaecide to reduce algae in the pond $328 2010 Village manually removes algae. $6,869 2010 Aerator electricity $1,274 2010 Aerator parts $1,217 2010 Village performs 40 hours of maintenance on the aerator $850 2011 Village consultant prepares concept report on dredging methods and approximate cost. $667 2011 Village consultant prepares a report on the condition and characteristics of the pond sediment. 2011 Village consultant prepares report exploring the potential of naturalizing the pond as an alternative to dredging. $6,500 $3,984 2011 Aerator electricity $985 2011 Village performs 40 hours of maintenance on the aerator $850 2012 Village consultant prepares a supplemental report on the condition and characteristics of the pond sediment. $3,155 Expense Total $129,426 1

2. What is the difference between the Valley View Estates Pond and Barth & Prince Ponds? Barth and Prince Ponds, which are owned by the Downers Grove Park District, are subject to an Intergovernmental Agreement (IGA) between the Village and the Park District executed in 1987. The IGA states that the Village and District will work together to maintain bodies of water owned by either party. Specifically, the Park District is responsible for: Maintaining shrubs, grass and trees and other land areas Maintaining the edge of the water area including prevention and repair of land erosion Maintaining District owned equipment located on a public lake site Maintaining water quality, including control of aquatic vegetation, pollution due to stagnation and mosquitoes. The Village is responsible for: Maintaining stormwater structures Periodic removal of accumulated silt Establishment of measures to control and alleviate silt accumulation Pursuant to the agreement, the Village is currently working with the Park District to address accumulated silt in Barth Pond. Valley View Estates pond is not subject to the agreement as it came into Village ownership in 1988 and was not added to the list of ponds subject to the agreement. Therefore, the Park District has not participated in the maintenance of the pond. 3. Are there options between dredging and the naturalization option? Yes. The Village has developed a potential concept plan (see below) that incorporates some additional open water with some naturalized areas. Due to the lack of a re-established creek channel, however, staff feels that additional implementation of upstream sediment and debris collection would be necessary. The estimated cost of this hybrid approach with a larger expanse of open water would be between $700,000 to $800,000. Ultimately, this option would fill with sediment over time and create shallow stagnant pools similar to what currently exists in the pond. While this the hybrid option may be more desirable in the short term, it does not result in a long-term sustainable solution. NATURALIZED/OPEN-WATER-HYBRID CONCEPT PLAN 2

4. What are the existing and proposed normal and high water elevations of the pond? The approximate pond elevation is 744.7 (feet above sea level) and the flood elevation is approximately 752.5. Depending on the option that is selected, the normal pond elevation will either stay the same, or be lowered roughly 1 foot in the immediate area of the project. Lowering the normal pond elevation may slightly lower the post-project flood elevations, but not significantly because the pond has a large tributary area and is located in the upper reaches of the floodplain. The project will not produce increased flood elevations or frequencies. The fill that will be placed in the naturalization option will be entirely below the normal pond elevation and as such, will not take away any flood storage capacity. 5. How will this project affect the groundwater? If the full naturalization option is selected and the pond outlet is lowered, there is a chance that the normal groundwater elevation in the immediate area of the pond could be slightly lowered, depending on the soil s characteristics of the surrounding properties. This change would be minimal, however. 6. Will this project impact the existing retaining walls on the surrounding properties? This project will have little to no effect on the surrounding retaining walls, since there will be more storage and flood elevations will not be increased. 7. How was the Village s dredging estimate developed? Due to the technical nature of this project, the Village conferred with several consultants with specialties in this area. The original concept report that was prepared by Village consultants (True North, V3 and Living Waters), analyzed both mechanical dredging and hydraulic dredging. Hydraulic dredging was estimated to be the most economical option, with an estimated cost of $412,000. This was based on an estimated amount of 6,000 cubic yards (CY) of clean sediment. After receiving two reports analyzing the existing sediment, the estimated amount of sediment was revised to between 7,000 and 10,000 CY to achieve a total pond depth of 5 to 6. Using 8,400 CY of sediment to be removed, and adding $50 per CY due to the environmental requirements of the sediment disposal, the total estimate increased to approximately $968,800. 8. Is stormwater being illegally drained from 75th Street into Robey Pond? No. To staff s knowledge, there are no areas outside the normal tributary area draining into this pond. The tributary area to Robey Pond is roughly 400 acres. This area includes portions of 75th Street, Fairview Avenue, Main Street, and Lemont Road. According to the Village s records, there are several storm sewer systems that drain portions of these roads and the surrounding development toward Prentiss Creek via Robey Pond. These sewer systems drain into the pond through five separate outlet pipes, each of which will be analyzed during final design to ensure optimum outflow into the basin, with minimal maintenance. This situation has existed this way for many decades. Robey Pond is on Prentiss Creek and as the lower property, has the obligation of taking stormwater from higher ground. The new widening work currently being undertaken by DuPage County along 75th Street will follow existing drainage patterns as well. The County has built underground detention and water quality features into that project, which will not alter the stormwater drainage to Robey Pond. 9. Will the proposed improvements increase the mosquito population? Mosquitoes breed in standing, stagnant water. This can happen anywhere and in urbanized areas most often occurs in storm sewer systems, backyard tire-swings, bird baths, wooded areas, baby pools, open water ponds, dry detention basins, and anywhere else water is allowed to form shallow stagnant pools. A properly designed wetland basin can help reduce the mosquito population by providing a habitat for mosquito eating birds, like purple martins, and other wildlife such as dragonflies, which eat an enormous number of mosquitoes. 10. If the pond were naturalized, would residents be able to fish? No. The naturalization option does not include areas for fishing. 3

11. Please provide the results of the soils tests. The soils testing reports are on the Village website. 12. Could the Village prepare a Call for Bids for the dredging option? A Call for Bids could be prepared for a dredging option, but due to staff time constraints during the construction season, we would likely need to hire a consultant to help us prepare the documents. It is not generally advisable to publicly bid a project that the Village does not fully intend to construct. The Village may have difficulty finding contractors who are willing to spend the time preparing a bid and the costs may not be as competitive as if it was a fully funded and supported project. If a more refined cost estimate for the dredging option is desired, staff recommends hiring one or two consultants/contractors to prepare detailed cost estimates for comparison purposes. The estimated cost for this work is $5,000. 13. What kind of maintenance activities and costs are expected once the project is completed? These activities can vary based on site conditions, but typically they will include selective herbiciding, periodic mowing, and overseeding. It is not likely that prescribed burning would be used in this residential setting, but it could be one additional option. Maintenance will likely be in the $5,000 to $10,000 range per year. 14. Can the Village provide photos of naturalized areas that are close to residential property? Attached are some images of naturalized areas that are immediately adjacent to residential property. 4

5

6

7

8

15. How much would it cost if the Village created a Special Service Area so that the residents would pay for the incremental cost of dredging the pond? The Village could create a Special Service Area (SSA) to cover the incremental cost of dredging the pond. The incremental cost is estimated to be $427,000 (The cost of dredging, $950,000, minus the cost of naturalization, $523,000). If an SSA is created, an additional amount would be levied on the property tax bills for all properties located within the SSA boundaries. The amount paid by each property owner would depend on the taxable value of their property. Staff has identified four options for an SSA. In all options, staff has assumed a term of 20 years and an annual interest rate of 3.1%, an amount equal to the Village s cost of borrowing money. The amount of money to be paid off and the number of contributing properties varies in each option. Option 1: Properties Abutting the Pond, Incremental Cost Only - In this option, the 34 properties abutting the pond property would be included in the SSA boundaries. The amount to be paid would be only the incremental cost between naturalizing the pond and dredging the pond. No reserve for future dredging would be included. Therefore, another SSA would likely have to be created in 2033 if the pond were to be dredged again at that time. Option 2: Properties Abutting the Pond, Incremental Cost Plus a Reserve for Future Dredging - In this option the 34 properties abutting the pond property would be included in the SSA boundaries. The amount to be paid would be the incremental cost between naturalizing the pond and dredging the pond and an additional amount that would provide funding for the dredging of the pond in 2033. Option 3: All Properties in Valley View Estates, Incremental Cost Only - This option is the same as Option 1 but with all 137 properties in the subdivision included in the SSA boundaries. Option 4: All Properties in Valley View Estates, Incremental Cost Plus a Reserve for Future Dredging - This option is the same as Option 2, but with all 137 properties in the subdivision included in the SSA boundaries. Option 1 Option 2 Option 3 Option 4 Principal Amount $427,000 $1,581,688 $427,000 $1,581,688 Total Annual Payment $28,967 $57,734 $28,967 $57,734 Average Annual Payment Per Property $852 $2,550 $213 $638 Minimum Annual Property Payment $390 $1,169 $99 $298 Maximum Annual Property Payment $1,149 $3,440 $1,022 $3,059 9