THE FOLLOWING IS AN EXCERPT FROM THE 2011 CITY OF SEATTLE STANDARD SPECIFICATIONS WITH MINOR CORRECTIONS MADE TO SECTION 9-03.SEATTLE.

An Introduction to Soil Stabilization for Pavements

asphalt applications European Asphalt Standards and their application in the UK mpa asphalt Asphalt Information Service Mineral Products Association

5. LOW IMPACT DEVELOPMENT DESIGN STANDARDS

VALLEY COUNTY MINIMUM STANDARDS FOR PRIVATE ROAD DESIGN AND CONSTRUCTION

CONSTRUCTION SPECIFICATION FOR RIP RAP, ROCK PROTECTION AND GRAVEL SHEETING

CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF INTERLOCKING CONCRETE PAVERS

155 ASPHALT SURFACING AND ASPHALT RECYCLING EQUIPMENT SECTION 155 ASPHALT SURFACING AND ASPHALT RECYCLING EQUIPMENT

World-Class. Solutions

COMPACTING SPECIMENS USING THE TEXAS GYRATORY COMPACTOR (TGC) PART I COMPACTING SPECIMENS USING THE TGC. Test Procedure for

STS Directory Accreditation number: STS 0329

SECTION PLANTING SOIL for SOIL CELLS. This specification defines material and performance requirements for soils which are to be used

SECTION SOIL PREPARATION

APPLICATION BRIEF. Model 4140/4141 Gyratory Compactor Specimen Preparation in Superpave Mix Design. April 2009

GRAND ARBOR RESERVE GRAND ARBOR RESERVE, LLC ULIAN KISSIOV D'ONOFRIO KOTTKE & ASSOC., INC.

STS Directory Accreditation number: STS 0030

Road Soil. Curtis F. Berthelot Ph.D., P.Eng. Department of Civil Engineering. Road Soil Introduction

Aggregates Table 1 No. Title Options

Deconstruction Reuse and Recycling Plan May 5, 2017

Asphalt Mixing Plants. & Asphalt Recycling. Asphalt Mixing Plants. Batch Plants Batch Plant Tour. Batch Plant Operation. Batch plant.

The following general requirements will be met for all planter box installations:

MAGNUM MAX ASPHALT PLANTS

State of Nevada Department of Transportation Materials Division

RSMX VSI Rotor Centrifugal Crusher. The cubicator for crushing and shaping

SECTION 02230BP AGGREGATE BASE

PLANNED UNIT DEVELOPMENT & PLANNING APPROVAL STAFF REPORT Date: April 4, 2013

511 - RIP RAP - OPSS 511 ROCK PROTECTION - OPSS 511 GRAVEL SHEETING - OPSS 511 GEOTEXTILE - OPSS 511

Limestone Cements. Why are we doing this? What are they? What s in it for you? Limestone Cements, Holcim (US) Inc.

UNIFIED FACILITIES GUIDE SPECIFICATIONS

HEATEC PRODUCTS AND SERVICES THAT EXCEED YOUR EXPECTATIONS

1. Which of the five checklists in the Municipal Construction Stormwater Site Inspection Toolkit will you use to document this inspection?

Specification for Road Works Series Introduction

Two-Lift Concrete Paving & Use of Geotextiles as a Bond Breaker

VERTICAL SHAFT IMPACT CRUSHERS EXCEPTIONAL MINERALS BENEFICIATION CAPABILITIES

FEB 2016 COUNTY MAP NTS

EC-11 COMPOST. Greenville County Technical Specification for. 1.0 Compost. 1.1 Description

This section covers the planting of seed, sod, trees and vegetation.

SKAPS GEOTEXTILE SUBSURFACE DRAINAGE

CHAPTER 3 ASPHALT CONCRETE PLANTS

Ames City Hall Campus: Stormwater Improvements

PMB AND RECYCLING RECYCLING ON A HIGH PERORMANCE LEVEL EXPERIENCES FROM GERMANY

DRIVABLE GRASS GUIDELINE FOR PLANTED INFILL INSTALLATION

STS Directory Accreditation number: STS 0099

Research Road Map. 4. Quiet Pavements

Stormwater Control Plan: Small (Tier 1) Land Development Project

The Laboratory is qualified to update standards identifying the test procedures.

The Laboratory is qualified to update standards identifying the test procedures.

Public Notice. REQUEST FOR QUOTES Town of Woodstock Downtown Parking Lot Improvement Project Landscape Material. June 22, ADDENDUM NO.

SECTION CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

5 Technical Characteristics

The planning and zoning board held workshops on January 11, 2016, January 18, 2016 and January 25, 2016 to discuss the issue.

Town of Excelsior, Sauk County, Wisconsin DRIVEWAY ORDINANCE

AASHTO M Subsurface Drainage

PMB AND RECYCLING EXPERIENCES FROM GERMANY

SECTION REGULATORY REQUIREMENTS. A. Relationship between Code, Ordinances, Standards and Contract Documents

23 EA , , , , , , , LF , , ,596.

The planning and zoning board considered amending the zoning code to address plantings and alteration of the swale.

SECTION 900 TURF ESTABLISHMENT

The planning and zoning board held workshops on January 11, 2016, January 18, 2016 and January 25, 2016 to discuss the issue.

SECTION STRUCTURAL SOIL

V-Pack Stack Temperature Control System ASTEC THE V-PACK. Stack Temperature Control System

MECHANICAL STABILIZATION OF A DELTAIC CLAYEY SOIL USING CRUSHED WASTE PERIWINKLE SHELLS.

TRI-LAKES MONUMENT FIRE PROTECTION DISTRICT

Responsible Care Product Stewardship for Refrigerants

P A V E R S Are they really the same? The 3-P s and how they relate to storm water management

PERFORMANCE EXAM CHECKLIST

CITY OF CLEVELAND GREEN DESIGN GUIDELINES

Section Specification for Geotextile Used in Permanent Erosion Control Application

ABBREVIATIONS. Dwg LID of 1. Abbreviations

LIVERPOOL JOHN MOORES UNIVERSITY

STABILIZATION OF SUBGRADE BY USING FLY ASH RELATED TO ROAD PAVEMENT THICKNESS DESIGN AT JALAN JAYA GAD1NG

SMSHE Southeastern Michigan Society for Healthcare Engineering

Schedule of Accreditation issued by United Kingdom Accreditation Service 2 Pine Trees, Chertsey Lane, Staines-upon-Thames, TW18 3HR, UK

V-Pac Stack Temperature Control System ASTEC T H E V- PA C

County of Fairfax, Virginia

Early Asphalt Plant. Batch Plant 12/9/14 PLANTS & PRODUCTION. Plants and Production. Basic Functions of Plants. Types of Facilities

PTSPAS Product Assessment Certificate in accordance with Equivalent Scheme MCHW SHW Volume 1 Clause and

CHAPTER 4 EXPERIMENTAL WORK 4.1 GENERAL

UE 3 CONSTRUCT SUSTAINABLE SIDEWALKS

HEATEC POLYMER BLENDING SYSTEMS

Stormwater Retrofits Made Practical City of Eugene Oregon. Doug Singer, P.E., CSM Principal Civil Engineer City of Eugene Public Works

INSPECTION AND TEST REPORT FOR ROAD AND PAVING. Area / Location : Drawing No. : Rev. :

ATTACHMENT L. Provision C.3.c.i.(1)(b)(vi) Specification of soils for Biotreatment or Bioretention Facilities

317)

Append LCCO 10.8 Emissions from Fuel-Burning Equipment

Specification of Soils for Biotreatment or Bioretention Facilities

8 th Ave NW LID Retrofit

TERREWALKS Installation Manual

ASPEN GROVE PROJECT NO. 53B2390 D-1 DETAIL STANDARD NOTES CITY OF MADISON

FHWA INVEST. And the Harbor Bridge Project

REFINEMENT OF THE HOT MIX ASPHALT IGNITION METHOD FOR HIGH LOSS AGGREGATES

Refrigerant Standards

Official Journal of the European Union

DRIVEWAY REGULATIONS

E R O S I O N C O N T R O L

APPENDIX J PERFORMANCE STANDARDS FOR GRAVEL MINE, PIT MINE, OR QUARRY

Driveway Regulations TOWN OF FREMONT ROCKINGHAM COUNTY NEW HAMPSHIRE

SECTION 808 PLANTING TREES, SHRUBS AND OTHER PLANTS

H-1456, H-1466, H-1471 & H-1473 Instruction Manual

Permeable Interlocking Pavers

Transcription:

Acceptance of Recycled Materials North Central Asphalt User/Producer Group February 4 th, 2009

Why Recycle? Save Natural Resources Asphalt Cement Aggregates Environmental Sustainability Be Green Manufacturer Pressure Political Pressure

Wisconsin s Position Our State s governors have historically emphasized environmental issues WisDOT has tried to be proactive not reactive Adopt materials if the use is determined to be engineeringly sound Standardly implement their use as contractor option Typically start conservatively

Everything but the Kitchen Sink For base course material we allow: Crushed concrete Reclaimed asphaltic pavement Reprocessed material Waste material for which a commercially demonstrated process uses the material as a raw material.

But Close 301.2.4.4 By-Product Materials (1) The contractor may provide an aggregate with one of the following by-product materials mixed with crushed gravel, crushed concrete, or crushed stone up to the listed maximum percentage, by weight. BY-PRODUCT MATERIAL MAXIMUM PERCENTAGE (by weight) Glass 12 Foundry slag 7 Steel mill slag 15 Bottom ash 8 Pottery cull 7

Out with the Old Specifications controlling the use of RAP were similar to most others 460.2.5 Reclaimed Asphaltic Pavement Materials (1) The contractor may use up to 35 percent RAP material in lower layer and base mixtures and up to 20percent in upper layer mixtures. Ensure that the combined RAP and virgin aggregate conforms to aggregate requirements of table 460-2.

Out with the Old 460.2.6 Recovered Asphaltic Binders (1) Establish the percent of recovered asphaltic binder from RAP for the mixture design according to AASHTO T 164 using the appropriate dust correction procedure. If test results indicate a change in the percent of recovered asphaltic binder from RAP, the contractor or the engineer may request a change in the design recovered asphaltic binder from RAP. Accompany that request with at least 2 recent RAP extractions from the contractor's mixture design laboratory supporting that change. (2) The contractor may use up to 25 percent RAP for lower layers and up to 20 percent RAP for upper layers without changing the asphaltic binder grade. If using more than that amount of RAP, furnish binder with a low temperature rating one grade lower than the contract designates, unless testing indicates the resultant binder meets the grade the contract originally specified.

In with the NEW Specifications previously allowed the use of only RAP New update allows use of FRAP, RAP, and RAS FRAP: Fractioned reclaimed asphaltic pavement - Material resulting from cold milling or crushing existing asphaltic pavement processed to control gradation properties. RAP: Reclaimed asphaltic pavement - Material resulting from cold milling or crushing existing asphaltic pavement. RAS: Recycled asphalt shingles - Waste material from a shingle manufacturing facility, either new or used material salvaged from residential roofing operations, or any combination of these materials ground to ensure that 100 percent will pass a ½ sieve and processed to remove deleterious material.

Recycled Asphaltic Materials Reminder: All Wisconsin DNR requirements must also be met for the use of these products Covered in standard specifications under 107.1(1) At all times, observe and comply with all applicable federal and state laws and administrative rules, codes, local laws, ordinances, and regulations that affect the conduct of the work, and applicable orders or decrees of bodies or tribunals having jurisdiction or authority over the work. New requirements are based on % binder replacement instead of % by weight as used in the past

Recycled Asphaltic Materials Where are the new requirements located? Requirements are in ASP-6 (Additional Special Provision) ASP s are located following the special provisions in WisDOT Highway Construction proposals The new ASP 6 will be effective for all contracts starting with the January 2009 bid letting

New Specification 460.2.5 Recycled Asphaltic Materials (1) The contractor may use recycled asphaltic materials from FRAP, RAP, and RAS in HMA mixtures. Stockpile recycled materials separately from virgin materials and list each as individual JMF components. (2) Control recycled materials used in HMA by evaluating the percent binder replacement, the ratio of recovered binder to the total binder. Conform to the following: MAXIMUM ALLOWABLE PERCENT BINDER REPLACEMENT RECYCLED ASPHALTIC MATERIAL LOWER LAYERS UPPER LAYER RAS only 20 15 RAP only 35 20 FRAP only 35 25 RAS and RAP 30 20 RAS and FRAP 30 25 RAS, RAP, and FRAP 30 25 (3) Ensure that the combined recycled and virgin aggregate conforms to the requirements of table 460-2 and to the gradation requirements of table 460-1.

New Specification 460.2.6 Recovered Asphaltic Binders (1) Establish the percent of recovered asphaltic binder from FRAP, RAP, and RAS for the mixture design according to AASHTO T 164 using the appropriate dust correction procedure. If production test results indicate a change in the percent of recovered asphaltic binder, the contractor or the engineer may request a change in the design recovered asphaltic binder. Provide at least 2 recent extractions from the contractor's mixture design laboratory supporting that change. (2) The contractor may replace virgin binder with recovered binder up to the maximum percentage allowed under 460.2.5 without changing the asphaltic binder grade. If using more than the maximum allowed under 460.2.5, furnish test results indicating that the resultant binder meets the grade the contract originally specified.

How Do We Accept? Our philosophy is to accept as close to final product as possible Accept as similar to same item with no recycle as possible Modify or eliminate tests as required Learn and adjust as we go