ClearFire. Startup Guide. Model CFH. Horizontal Steam Boiler

Similar documents
HCLEARFIRE. High-efficiency, modular steam boiler HP

ClearFire - Hydronic Startup Report

VCLEARFIRE. High-Efficiency, Commercial Steam Boiler Horsepower

LGB Gas fired boiler

Model 60200FR Gas Primary Control Data Sheet

User s Information Manual Models: ER152, ER202, ER252, ER302, and ER402

CSD-1 COMMERCIAL BOILER CONTROLS

User s Information Manual Models: 45, ,000 Btu/hr

LATTNER BOILER COMPANY 9.5 HP Low-NOx Installation and Start-Up Checklist for Dry Cleaners

TO DO IF YOU SMELL GAS

User Manual Models: 502, 752, 1002, 1302, 1501, 1701, and 2001 Up To 5:1 Turndown

SAMPLE SPECIFICATION FOR RIELLO ARRAY MODULATING BOILER

Table Of Contents. Clearfire Condensing Boiler Model CFC

User s Information Manual

Model Universal Oil Primary Control

Power Flame Incorporated

prestige Condensing Water Boiler SERVICE TECHNICIAN S TROUBLE SHOOTING GUIDE TSG-PRESTIGE Date revised: 11/10/08

R7910A SOLA (Hydronic Control) and R7911 SOLA (Steam Control) Systems

USER'S INFORMATION MANUAL

!!! Sample Written Program For Your Company. For BOILER SAFETY. Provided By:!!!

Model CFW ClearFire Gas High-Efficiency Hydronic Boiler Operation and Maintenance Manual

prestige Condensing Water Boiler SERVICE TECHNICIAN S TROUBLE SHOOTING GUIDE TSG-SOLO-9/04

USER'S INFORMATION MANUAL

MODEL M5M. High-Efficiency Packaged Watertube Boiler MMBTU

Power Flame Incorporated

OPERATING INSTRUCTIONS MANUAL (Please retain for future reference) FVN/P-400 INDIRECT FIRED SPACE HEATERS

USER'S INFORMATION MANUAL

USER'S INFORMATION MANUAL

R7910A SOLA (Hydronic Control) and R7911 SOLA (Steam Control) Systems

ClearFire Economizer Model ECF Integral or External. Addendum to manuals CFH and CFV

OPERATING INSTRUCTIONS MANUAL (Please retain for future reference) F-1500T DUAL FUEL CONSTRUCTION HEATER

USER'S INFORMATION MANUAL

SERVICE AND INSTALLATION MANUAL MODELS HDO(H) OIL FOR YOUR SAFETY

User s Information Manual

100T399-SOLA SUPPLEMENT TO INSTALLATION & OPERATION MANUAL INCLUDED WITH WATER HEATER (SERIAL NUMBERS BEGINNING LK AND LATER)

ECLIPSE INFORMATION GUIDE

OPERATING INSTRUCTIONS MANUAL (Please retain for future reference) F-400T DUAL FUEL CONSTRUCTION HEATER

OPERATING INSTRUCTIONS MANUAL (Please retain for future reference) FVN/P-400 INDIRECT FIRED SPACE HEATERS

HEATEC TEC-NOTE. Operation and maintenance Heatec thermal fl uid heaters industrial series IMPOPRTANT NOTICE! CONTENTS. Publication No.

PART 0 A/E INSTRUCTIONS 0.01 DESIGN REQUIREMENTS

Model CB-LE. Packaged Boiler HP. Operation, Service, and Parts Manual /09. and Model CB Ohio Special HP

southbend A MIDDLEBY COMPANY INSTALLATION AND OPERATION MANUAL CG214 (E) CG314 (E) CG414 (E) CG220 (E) CG320 (E) CG325 (E) GAS BOILERS MODELS:

CONVERSION TO PROPANE MANUAL M-Series Condensing Boiler. Wall-Mounted, Gas-Fired Boiler

Service Manual Models: 1.0, 1.3, and 1.5

Suggested Specification: Benchmark 1.5 Low NOx Gas-Fired Hydronic Boiler(s)

Cclearfire HIGH EFFICIENCY, COMPACT CONDENSING BOILER 500-3,300 MBTU

Owner s Guide Installation & Operation

Series 300 VTB. Installation Instructions

SUPER HIGH EFFICIENCY WATER HEATERS SUPPLEMENT TO INSTRUCTION MANUAL P/N (Replaces pg. 2 in instruction manual.) CONGRATULATIONS!

ProLine XE Combi Boiler

Section B7 CLEARFIRE MODEL CFV BOILERS CONTENTS

BGH Series Hot Surface Ignition Control

Diocese of Cleveland Facilities Services Corporation

USER S INFORMATION MANUAL

Low pressure boiler* inspection and maintenance

User s Information Manual

OPERATING INSTRUCTIONS MANUAL (Please retain for future reference) FVN/P-400 INDIRECT FIRED SPACE HEATERS

HIGH EFFICIENCY FIRETUBE CONDENSING GAS BOILER

INSTALLATION AND OPERATION MANUAL GAS SKILLETS MODELS: GTS-30 GTS-40

EBC 10 Fan Control USA CAN. Product Information. ... Chapter 1+2. Mechanical Installation. ... Chapter 3. Electrical Installation. ...

Revitalize Building Mechanical Systems (4619)

Owner s Guide Installation & Operation

OPERATING INSTRUCTIONS MANUAL (Please retain for future reference) F-1000T DUAL FUEL CONSTRUCTION HEATER

Operating Instructions

User s Information Manual

User s Information Manual Models:

50M Integrated Single or Two-Stage HSI Integrated Furnace Control Kit INSTALLATION INSTRUCTIONS

95M-200. Gas-Fired Direct Vent Modulating Hot Water Boiler. Control Manual And Troubleshooting Guide. P/N , Rev.

Trinity Tft/Lx Model #s: Tft60-399/Lx Version Date:

GOLD. User s Information Manual. Water Boiler Series 4

CLEAVER-BROOKS MODEL FLX PACKAGED BOILER

OPERATING INSTRUCTIONS MANUAL (Please retain for future reference) FVN/P-400 INDIRECT FIRED SPACE HEATERS

.2 Section Waste Management and Disposal..4 Section Vibration Isolation and Seismic Control Measures.

USER'S INFORMATION MANUAL

CLEARFIRE - MODEL CFH HP Steam Horizontal Boiler

If the information in this manual is not followed exactly, a fire or explosion may result causing property damage, personal injury or loss of life.

AFUE 95% Heating Input 50,000 to 200,000 Btuh

DIVISION FINNED WATER-TUBE BOILERS

DIVISION FINNED WATER-TUBE BOILERS

DIVISION FINNED WATER-TUBE WATER HEATERS

ADC150 Automatic Draft Control

This document was created with FrameMaker 4.0.4

CCLEARFIRE CONDENSING FIRETUBE BOILER DESIGNED FOR MAXIMUM HYDRONIC SYSTEM EFFICIENCY 500 TO 3,300 MBTU

Internet Version for Reference Only INDUCED DRAFT COMMERCIAL WATER HEATERS SUPPLEMENT INSTRUCTIONS TO PART #

INSTALLATION, OPERATING & MAINTENANCE INSTRUCTIONS FOR 350 SERIES CIRCULATION HEATERS

User s Information Manual Models:

Operating instructions

CLEARFIRE - MODEL CFV HP Steam Vertical Boiler

Installation, Operation and Service Manual

Service Manual Models: 1.0, 1.3, and 1.5

User s Information Manual Models:

DIVISION FINNED WATER-TUBE BOILERS

Tankless Water Heater

SERIES VAC Microprocessor-Based Direct Spark Ignition Control with Inducer Blower Relay FEATURES APPLICATIONS SPECIFICATIONS DESCRIPTION

OPERATING AND MAINTENANCE MANUAL

LGB COMMERCIAL GAS BOILER. Versatile combustion control systems. Made with Weil-McLain quality COMMERCIAL GAS BOILER APPLICATIONS INCLUDE:

User s Information Manual

R- RH- and RHC-Steam Boiler Models (RB-Series)

GP COMBUSTION EQUIPMENT INC 100 Sheldon Dr., Units 16/17 Cambridge, Ontario N1R 7S7. Model C Forced Draft Burners. Natural Gas or Propane MODEL C10

Universal Fire Tube Boiler Wall Mount Models

Transcription:

ClearFire Model CFH Horizontal Steam Boiler Startup Guide 750-293 www.cleaverbrooks.com

Improper installation, adjustment, service, or maintenance can cause equipment damage, personal injury, or death. Refer to the Operation and Maintenance manual provided with the boiler. Be sure the fuel supply which the boiler was designed to operate on is the same type as specified on the boiler name plate. To minimize the possibility of serious personal injury, fire or damage to the equipment, never violate the following safety rules. Always keep the area around the boiler free of combustible materials, gasoline, and other flammable liquids and vapors Never cover the boiler, lean anything against it, stand on it, or in any way block the flow of fresh air to the boiler. NOTE to equipment owners, operators, and maintenance personnel: This guide is not a short-cut to safe and efficient boiler operation. Operating an improperly commissioned boiler can result in increased fuel costs and may shorten the life of the equipment or produce a hazardous condition. All personnel involved in operating or maintaining the boiler should read the manual in its entirety. Should overheating occur or the gas supply valve fail to shut off, do not turn off or disconnect the electrical supply to the boiler. Instead turn off the gas supply at a location external to the boiler. Do not use this boiler if any part has been under water. Immediately call your Cleaver-Brooks service representative to inspect the boiler and to replace any part of the control system and any gas control which has been under water. The installation must conform to the requirements of the authority having jurisdiction or, in the absence of such requirements, to UL 795 Commercial-Industrial Gas Heating Equipment and/or the National Fuel Gas Code, ANSI Z223.1 The boiler and its individual shutoff valve must be disconnected from the gas supply piping system during any pressure testing of that system at test pressures in excess of 1/2 psi (3.5 kpa). The boiler and its gas connection must be leak tested before placing the boiler in operation. Notice Refer to CFH Operation and Maintenance Manual - CB Part Number 750-295 Where required by the authority having jurisdiction, the installation must conform to the Standard for Controls and Safety Devices for Automatically Fired Boilers, ANSI/ASME CSD-1. 2 Part No. 750-293

1 - BEFORE STARTUP Your Cleaver-Brooks boiler has been factory fire-tested and the control system pre-configured for a troublefree startup. To help ensure a successful lightoff and reliable operation, certain initial conditions should be observed. Do not attempt to place the boiler into service without verifying that all connections - fuel, steam and water piping, electrical connections, stack, and combustion air provisions - have been installed properly and in accordance with any applicable codes or regulations. SURFACE BLOWOFF STEAM OUTLET STACK OUTLET CHEMICAL FEED COMB. AIR/ DIRECT VENT GAUGE GLASS DRAIN WATER COLUMN DRAIN CHEMICAL FEED FEED WATER GAS SUPPLY BLOWDOWN Figure 1 CFH Connections 1.1 Operating Conditions The installation site should be as free as possible from vibration, dust, and corrosive media The controllers should be located as far as possible from sources of electromagnetic fields, such as frequency converters or high-voltage ignition transformers Control panel must be connected to earth ground. For electrical wiring requirements, see wiring diagram provided with the boiler or in the CFH manual. Boiler room ambient conditions Relative humidity Ambient temperature range Storage temperature range Combustion air temperature < 85% non-condensing 0 o C to 50 o C / 32 o F to 122 o F -20 o C to 60 o C / -4 o F to 140 o F 0 o C to 50 o C / 32 o F to 122 o F Specifications Input power 115 VAC single phase 60Hz Recommended operating steam Up to 135 psig (150# design) pressure Up to 13.5 psig (15# design) Gas pressure requirements See Table 1! Warning When using direct vent combustion in cold climates, special care must be taken to observe combustion air temperature limits. Failure to follow this precaution may lead to equipment damage or unsafe operation. Part No. 750-293 3

1.2 Gas Piping A manually operated shut-off valve and pressure regulator are provided as standard on the Model CFH boiler. It is recommended to install an approved gas filter or strainer in the gas supply line to the boiler. Please inquire with the local gas supply company. The boiler shall be installed such that the gas ignition system components are protected from water (dripping, spraying, etc.) during appliance operation and service. If building supply gas pressure is greater than 1 psig (27.8 WC), an upstream regulator with overpressure protection and proper gas venting will be required and must be piped to a safe point of discharge. All gas piping and components to the boiler gas train connection must comply with NFPA 54, local codes, and utility requirements as a minimum. Only gas approved fittings, valves, or pipe should be used. Standard industry practice for gas piping is normally Schedule 40 black iron pipe and fittings. See Table 1 for CFH gas pressure requirements. Table 1 CFH gas pressure requirements Boiler HP Minimum pressure required at gas train connection 10 7.2" w.c. 15 7.3" w.c. 20 7.5" w.c. 25 7.7" w.c. 30 8.5" w.c. 40 11.0" w.c. 50 10.0" w.c. 60 10.0" w.c. Max. pressure 28 w.c. Note: To measure supply pressure at the CFH gas valve, use the test port on the valve inlet flange (see below). Do not use the leak test cocks to measure gas pressure. 1.3 Flue Gas Connection The flue gases from the ClearFire boiler are removed via a gas-tight, temperature and corrosion resistant flue gas pipeline. Only flue gas systems approved and tested by the relevant region or province are to be connected to the ClearFire boiler. Refer to flue piping manufacturer for proper installation and sealing instructions. See also Chapter 3 in the CFH Operation and Maintenance manual. 1.4 Boiler Water-Side Connections A pressure relief valve (safety valve; Figure 2), provided with the boiler, must be installed in the mounting provided and piped to a safe point of discharge. Use pipe sealing compound and a flat sided wrench when securing the safety relief valve. Do not use a pipe wrench and do not over tighten the relief valve. The safety valve must be mounted in a vertical position so that discharge piping and code-required drains can be properly piped to prevent buildup of back pressure and accumulation of foreign material around the valve seat area. Connection to the main steam header is made at the nozzle projecting upward from the boiler shell. Feedwater is introduced through the piping assembly installed on the side of the boiler vessel. Connections are provided for optional chemical feed, surface blowoff, and overflow. Figure 2 Pressure Relief Valve 4 Part No. 750-293

1.5 Electrical Connections Refer to Figure 3 and Figure 4 for CFH wiring and cable connections. See also wiring diagram on page 13. A qualified electrician or service technician must make the electrical connections to the boiler; all local electrical and building codes should be adhered to. Refer to wiring diagram provided with the boiler or in the CFH manual. Ensure all required customer connections are properly made. Main power (115 VAC single phase 60Hz) and any remote wiring should be brought to the left side of the control panel and terminated at the appropriate terminals provided. Controls for the boiler feed pump (or feedwater valve if applicable) should be wired to control panel terminals 6 and 7. Customer connections and power wiring CB Falcon Ignition Transformer (Panel cover removed) Blower Power Cable Cable Harness (Burner Controls) Blower Signal Cable Flame Rod Cable Figure 3 Control panel cable connections NOTICE The blower signal wiring must be isolated from the blower power wiring and the high voltage ignition cables. Figure 4 CFH wiring and cable connections Part No. 750-293 5

1.6 Safety Controls Users should take note of the safety controls installed as standard on the Model CFH. Minor adjustments to the initial factory settings of some controls may be necessary for your particular installation. It is required to test all controls for proper functioning prior to starting the boiler for the first time. Stepby-step procedures for testing the controls can be found in the CFH manual (Chapter 4 - Commissioning). The primary flame safety control is the CB Falcon, which monitors the flame signal by means of an ionization electrode installed in proximity to the burner canister. Other Combustion Safety Controls (see Figure 5) include the following: Combustion Air Proving Switch Low Gas Pressure Switch High Gas Pressure Switch Dual Safety Shut-off Valve (SSOV) Depress all manual reset buttons for all controls prior to starting the boiler. Figure 5 Combustion Safety Controls at Burner Flame Rod (Ionization Electrode) Combustion Air Proving Switch High Gas Pressure Switch Dual SSOV Low Gas Pressure Switch Water Level Controls (see Figure 6) The primary Low Water Cutoff and pump control level probes are mounted in an external water column. The Auxiliary Low Water Cutoff is mounted in the boiler vessel or optional external column. Control boards for the LWCO and ALWCO are located in the boiler control panel. The ALWCO includes a panel-mounted reset/test switch. ALWCO LWCO & Pump Control ALWCO Control CB Falcon Controller w/reset LWCO Figure 6 Water Level Controls Control panel interior 6 Part No. 750-293

Limit Controls (see Figure 7) The operating and high pressure limit controls are externally mounted to the boiler casing. For control settings and testing instructions, see the boiler operation manual. HLC OLC! Warning The Model CFH is factory tested. Nevertheless, all burner safety controls should be checked upon installation, prior to initial firing. Failure to verify burner control functioning could result in severe bodily injury or death. For detailed procedures on how to test the safety controls, see the boiler Operation and Maintenance Manual. Figure 7 Limit Controls 1.7 Filling Boiler Ensure that all feedwater equipment is properly installed and any feed pumps, valves, etc. are in good working order. Begin with the control panel DEMAND switch and the CC-BLOWER switch (see Figure 8) in the OFF position. Open the boiler vent valve (see Figure 9). Turn the Control Circuit/Blower Switch ON to enable the feedwater control circuit. If the CB Falcon icon does not appear on the display when the CC/Blower switch is turned on, see STARTING THE BOILER below. With the vent valve open, entrapped air will be allowed to escape while the boiler fills with water. Do not close the vent valve until water is visible in the gauge glass. The feed pump will shut off when water reaches the Pump Off probe level. Check to ensure that no leaks appear at any pipe connections and correct if water leaks are noticed.! Important Figure 8 Control Panel Switches The use of soft water is highly recommended. Failure to observe this recommendation can lead to dangerous operating conditions, and may result in damage to the boiler. If necessary, your Cleaver-Brooks representative can provide additional information regarding your water softening requirements. Vent Valve Feedwater Inlet Gauge Glass Figure 9 Filling the Boiler Part No. 750-293 7

2 - STARTING THE BOILER Ensure boiler has been filled with water (see above - 1.7 Filling Boiler). The DEMAND switch should be in the OFF position. When the Control Circuit/Blower switch is turned ON, the Home page will appear on the CB Falcon display, showing the boiler control icon. It may take a short time for the display/controller to initialize before the Falcon icon appears. If the Falcon icon does not appear, open the control panel and verify that the controller is receiving power. The green POWER LED should be lit (see Figure 10). If the controller is powered on but still does not appear on the display, refer to manual. If unable to resolve the problem, contact your CB representative. Falcon controller icon HOME PAGE POWER LED Figure 10 Home Page; Falcon power indicator 2.1 Controller Configuration The CB Falcon controller is factory pre-configured with default parameter settings for the Model CFH. Prior to starting the boiler, verify that the factory default settings are correct for your application. See the boiler operation manual (Chapter 4 - Commissioning) for the parameter list and parameter change procedure. Changing the Setpoint The default steam pressure setpoint should be changed at this time to suit your application. Press the CB Falcon icon on the Home page. The Overview screen will appear. On the bottom row of screen buttons press <Operation> to access the Operation screen (Figure 11). Note: The Home icon at the upper left of the display screen always returns to the Home Page. The Back icon at the upper right displays the previous screen. Press the yellow highlighted setpoint display. A numeric keypad will appear. Press <Clear> to clear the current value, enter the appropriate setting using the numeric keypad, and press <OK>. 8 Part No. 750-293

Figure 11 Changing the setpoint 1 3 4 2 To change the steam pressure setpoint: 1. Press the yellow highlighted setpoint display window. 2. Clear the current value. 3. Enter the desired value. 4. Press <OK>. 2.2 Initiating Burner Sequence Note: Some features of the CB Falcon controls are password protected. Service level password = 9220. When ready to start the boiler, navigate to the Operation screen (see Changing the Setpoint above). BURNER SWITCH button! Warning Before initial startup, check for blockages in the flue venting or vent terminations. Inspect the burner and furnace for any contamination or blockages. Figure 12 Operation screen Turn the <Burner switch> screen button to ON. The burner is now enabled. Part No. 750-293 9

Turn the control panel DEMAND switch to LOC (local). The burner sequence should now begin. To verify that the sequence is in progress, check the Burner state display on the Operation screen. If operating normally, the controller should advance through the steps in the burner sequence (see Figure 13). Note: The <Burner switch> screen button enables the burner, but will not by itself start the lightoff sequence. In order for the burner to start, the following must be true: <Burner switch> screen button is ON All control circuit interlocks are satisfied A demand for steam exists (example: DEMAND switch is on LOC and steam pressure is below setpoint) Once started, the boiler will continue running until demand is met, an alarm condition occurs, or until manually shut down. Before leaving the boiler unattended, ensure all safety controls have been checked and boiler operational settings are properly set, Burner Sequence: STANDBY (burner switch off or no demand) SAFE STARTUP PREPURGE DRIVE TO PURGE (prove fan purge rate) PREPURGE MEASURED PURGE TIME (30 sec default) PREPURGE DRIVE TO LIGHTOFF (prove lightoff rate) PREIGNITION TEST DIRECT BURNER IGNITION RUN (release to modulating control) Figure 13 Burner Sequence As part of the initial safety checks, a flame failure test should also be performed to verify that the controls are able to respond properly to a loss of flame: Disconnect the flame rod cable and attempt to start the burner. The CB Falcon should lock out, indicating Lockout 109 Ignition Failure. Reconnect flame rod cable after test. The CB Falcon requires a manual reset to resume operation after a lockout. 3 - MANUAL OPERATION Certain circumstances - such as setting combustion - require operating the boiler in manual mode. To enter manual mode, use the following procedure: 1.On the CB Falcon Operation screen, press the Firing Rate display in the Modulation section. 2. A numeric keypad will appear, showing the current firing rate and operating mode.* 3. Under Firing rate control select Manual in Run. 4. Press <Clear> to clear the current RPM value. 5. Enter the desired RPM setting using the numeric keypad. 6. Press <OK>. The display will return to the Operation screen and the burner will modulate to the chosen firing rate. *Use Manual in Run for normal manual operation. In Manual in Run and Standby mode, the burner will not operate. Use this mode for testing blower operation without firing the boiler. Figure 14 10 Part No. 750-293

Notice The CFH has been factory tested at 1000 ASL and tuned for 5-6% excess O 2. To ensure optimum combustion throughout the firing range, the O 2 % should be verified and if necessary adjusted to the proper levels. This procedure involves manually firing the burner while using a combustion analyzer to monitor O 2 %. Low and high fire adjustments are made at the main gas valve. See the CFH Operation and Maintenance manual for a detailed procedure. Note: If an alarm or lockout occurs during startup or operation, see the boiler Operation and Maintenance manual If any of the following conditions occur: Loss of flame Excessive or unusual noise Flame appears irregular when viewed through sight glass Frequent low water shutdowns Cease boiler operation. See the Troubleshooting section in the CFH manual or consult your authorized CB representative. Repeated nuisance low water shutdowns may indicate a problem with the boiler feed system and/or water level controls. 4 - POST STARTUP Review Chapter 4 - Commissioning in the CFH manual. Ensure all safety checks have been performed according to instructions. Set high gas pressure switch to 50% higher than operating gas pressure at low fire. Set low gas pressure switch to 50% lower than operating gas pressure at low fire. Check the draft on the outlet stack and compare to acceptable limits (-0.25 to +0.25 inches WC). Operating outside of acceptable limits could result in light off and flame failure problems. Verify gas pressure remains within limits shown in Table 1. A new boiler should be cleaned by boil-out prior to being placed into service. See Chapter 4 of the CFH manual for boil-out procedure. 5 - LOCKOUTS, HOLDS, AND ALERTS To assist in monitoring boiler operation, the CB Falcon control system employs messages of three types: Lockouts, Holds, and Alerts. Lockouts and Holds indicate interruptions in boiler operation, whether occurring as part of the normal operating sequence or due to an abnormal condition. Lockouts require a manual reset to continue operation, while Holds do not. A Hold will automatically clear when the hold condition is removed or satisfied. The most recent Lockouts are stored in CB Falcon memory and may be accessed through the Lockout History. Holds are not logged in memory. Note: Before attempting to restart the boiler after a Lockout, identify and correct the Lockout condition. Part No. 750-293 11

Alerts indicate conditions or events which, while not preventing boiler operation, may nevertheless be of interest in evaluating boiler performance or operating conditions. Examples include certain operator actions, out-of-range configuration data, controller internal status reports (e.g. timers, counters, memory read/write activity), and recycle events. Alerts require no operator acknowledgment and are for informational purposes only. The most recently occurring message (Lockout, Hold, or Alert) is displayed in the alarm banner on the Overview screen (see Figure 15). Press this banner to access the Alert or Lockout History, where a list of the most recently occurring Alerts/Lockouts can be viewed. Alarm Banner Figure 15 Alarm Banner To obtain more information for a particular message, press that item in its respective history list. For Alerts, burner cycle and hours of operation at the time of occurrence will be displayed. For Lockouts, in addition to cycle and hours the screen will show on/off status of all interlocks at the time of the lockout. This information can be used to help pinpoint the cause of a particular Lockout. If the boiler is left unattended after a startup, the Alert/Lockout History can be consulted to determine whether the boiler has been running normally or if operation has been interrupted due to a fault condition. 12 Part No. 750-293

Figure 16 CFH Wiring Diagram Part No. 750-293 13