Lake Oswego to Portland Transit Project. Lessons Learned. John Cullerton Senior Project Manager, URS 2012 APTA/TRB Light Rail Conference

Similar documents
UPDATE ON THE INDEPENDENCE BOULEVARD AREA PLAN. Citizen Advisory Group Meeting March 3, 2011

Midtown Corridor Alternatives Analysis. Appendix A - Initially Considered Alternatives Screening

12/9/2013. HOLLYWOOD/PINES CORRIDOR PROJECT AMPO 2013 Annual Conference October 24, Our Perspective. Broward.

Chapter 1.0 Introduction

CITY S GOALS DRIVE MODE CHOICE IN WINSTON-SALEM, NC

Railyard Alternatives and I-280 Boulevard Feasibility Study. MTA Board Meeting May 6, 2014

The GATEWAYS Sub Area Master Plan. City of Walker

D2 Subway Project Development. Stakeholder Committee October 24, 2018

Route 110 Alternatives Analysis

I. DESCRIPTION OF PROPOSED ACTION... 1 A. General Description... 1 B. Historical Resume and Project Status... 2 C. Cost Estimates...

Knoxville Area Transit (KAT) Transit Development Plan Corridor Analysis

Atlanta BeltLine Corridor Environmental Study. Scoping Meeting August 2008

P3 IS FOR PARTNERSHIPS, PLACEMAKING, AND POLICY:

METRO Gold Line BRT CBAC Meeting. August 23, 2018

Relief Line Project Assessment

Route 1 Corridor Study

Eglinton West LRT Update

Corridor Management Committee. September 29, 2017

Shift Rapid Transit Public Participation Meeting May 3, 2017

Harlem Avenue Corridor Plan: Corridor Planning Across Municipal Boundaries

Promoting Economic Development Through Upfront SEPA Review: Lessons from South Downtown Tacoma

RESOLUTION NO. R Refining the route, profile and stations for the Downtown Redmond Link Extension

2. AGENCY COORDINATION AND PUBLIC INVOLVMENT

City of Lake Oswego Transportation System Plan Update PLAN AND POLICY REVIEW, PART 2

Urban Form Case Studies

TOD 203 CORRIDOR PLANNING and TOD

Ashland BRT Environmental Assessment: logos of CTA, CDOT, Chicago Department of Housing and Economic Development

The Need to Develop a Transit Ready Community

Date: April 10, 2017 City Council Work Session April 24, 2017: Status Report on the Comprehensive Plan Update and Transportation Master Plan

Point A Point B Point C Point D. City of Hapeville Public Meeting July 25, 2017

Scope of Services. River Oaks Boulevard (SH 183) Corridor Master Plan

MURRAY CENTRAL STATION MASTER PLAN Central Station Area of Influence and Site Analysis

TO: Denver Planning Board FROM: Analiese Hock, Senior City Planner DATE: March 13, 2018 RE:

Dallas CBD Second Light Rail Alignment (D2)

Dallas CBD Second Light Rail Alignment (D2)

Realities and Assets in an In-Town Shopping Center

Proposed Comprehensive Plan Strategies DRAFT for discussion June 28, 2017

Eastern Terminus TECHNICAL MEMORANDUM CENTRAL BROWARD EAST-WEST TRANSIT ANALYSIS BROWARD COUNTY, FLORIDA

Gold Line Bus Rapid Transit Transit Oriented Development (BRTOD) Helmo Station Area Plan

Transportation Committee

BALLARD TO DOWNTOWN SEATTLE

Metro Orange Line Extension Four Years Early and $61 Million Under Budget

Northwest LRT Downtown to. Northwest Edmonton Study. Public Workshops

Relief Line Project Assessment

Route 5 Corridor Land Use and Transportation Plan

Early in the scoping process, several groups submitted a letter that reflected our collective values for Sound Transit 3. These values include:

John M. Fleming Managing Director, Planning and City Planner. Old East Village Dundas Street Corridor Secondary Plan Draft Terms of Reference

SCARBOROUGH RAPID TRANSIT ENVIRONMENTAL PROJECT REPORT CHAPTER 2 PROJECT DESCRIPTION. Table 2-4: North Segment Alignment Analysis 2-21

South King County High Capacity Transit Corridor Report. Figure Other Infrastructure

Por favor, levanten la mano si necesita traduccion en espanol Please raise your hand if you need Spanish translation

Welcome. Green Line LRT. Beltline Alignment Options. Stay engaged! Follow the Green Line story at calgary.ca/greenline

COMMUNITY OPEN HOUSE. March 28, 2012

Transforming Saint John s Urban Heart -

FATAL FLAW ANALYSIS. March 2014 FINAL. DRAFT Febru

SH 199 Corridor Master Plan. Community Meeting No. 2 May 31, 2017

Fifth and Detroit Street Design May 2017 Capital Improvements Committee. DOWNTOWN Street Design

master plan of highways bus rapid transit amendment

Jim Harkins DUNDEE WATER FRONT CIRCULATOR DUNDEE WATER FRONT CIRCULATOR. Specialists in Affordable & Sustainable Tramways. A short presentation by

Northern Branch Corridor SDEIS March Table of Contents

West Broadway Transit Study Initial Screening of Alternatives Memo

Planning for TOD Implementation at a Corridor Scale

City of Hermosa Beach Administrative Policy #

CHAIR AND MEMBERS CIVIC WORKS COMMITTEE MEETING ON JULY 17, 2017

Transportation Working Team Duane Diggs, Co-Chair (VOICE Buffalo) Kelly Dixon, Co-Chair (GBNRTC) Paul Ray, Facilitator (UB Regional Institute)

International Blvd. TOD Plan Public Workshop #1

MODEL ACCESS MANAGEMENT PLAN MINNESOTA TRUNK HIGHWAY 7 COMPREHENSIVE PLAN AMENDMENT (HUTCHINSON SEGMENT)

Agenda. Introductions and Overview Study Purpose Study Approach Key Analysis Components Study Context Development Activity ( )

Draft Evaluation of Alignment Alternatives Methodology and Results Report. 3 nd Draft. May 2011(rev June 17, 2011)

POCKET COMMUNITY PLAN

Seattle Transit Master Plan

Optimize. Innovate. Deliver. Engineering the Future of Bus Rapid Transit

Urban Planning and Land Use

Evaluation Criteria. Detailed Evaluation Criteria

Tyvola & Archdale Transit Station Area Plan. June 5, 2008

Regional Transportation District

Isabel Neighborhood Plan: Alternatives

AUTO CIRCULATION & PARKING

Planning and New Starts Development Committee. February 25, 2016

HIGH-SPEED RAIL PROGRAM UPDATE. Gilroy Unified School District & Gilroy City Council September 24, 2018 Gilroy City Council Chambers, Gilroy, CA

Tier 1 Analysis August 21, North-South Corridor Study

Sprawling urban development and auto-dominated streets

Connecting Key Activity Centers with High Quality Bus Service

Rapid Transit Implementation Working Group

Southwest Light Rail Transit (LRT) A corridor of opportunity

Midtown Greenway Land Use and Development Plan Executive Summary

A community driven catalyst for an equitable, healthy, (economically viable and environmentally) sustainable corridor

CHAPTER 7: Transportation, Mobility and Circulation

SUBJECT: Waterfront Hotel Planning Study Update TO: Planning and Development Committee FROM: Department of City Building. Recommendation: Purpose:

EXPANDING THE NETWORK ALEXANDRIA, VIRGINIA

Reshaping The City: New Visions for Urban Transport. Trent Lethco, Associate Principal Allison Davis, Senior Planner Vicent Risica, Planner Arup

Infrastructure Engineering Planning Construction Suite 300 Minneapolis, MN Tel: Fax:

Tysons Circulator Study: Process and Preliminary Results Summary. March 2012

2030 Transit System Plan Refresh

Ryoko Iizuka Finance, Economics and Urban Department

Status Update (2006 vs. Now) Citizen s Advisory Committee February Plan for Prosperity

Chapter 13 Learning Guide Urban Patterns

Planning for TOD Implementation at a Corridor Scale

Right-of-Way Acquisitions and Relocations Technical Memorandum

Bypass #16 - Bend Parkway (new alignment for US 97) (MP )

Asheville Design Center March 2010

Transcription:

Lake Oswego to Portland Transit Project Lessons Learned John Cullerton Senior Project Manager, URS 2012 APTA/TRB Light Rail Conference

Overview Project Location and Context Corridor History and Project Background Project Development Public Engagement Redefining the Streetcar Connections to the Downtowns ROW Conflicts and Physical Constraints Project Status

Portland Streetcar System

Portland Streetcar

Lake Oswego to Portland Project Location

Corridor History Rail line opened in mid 1880s Built to move timber, iron ore and people First passenger service began in 1887 Operated as passenger service until 1929 Freight service continued until 1980s Limited excursion trolley service continues today

Tunnel Location

Project Background Rail line purchased from SP by government consortium in 1988 In 1996 ODOT determined expanding roadway not feasible Streetcar extended to South Waterfront in 2006 Consortium decides time is right to study an HCT connection using rail line

State Hwy 43 Parallel Route

South Waterfront Streetcar Extension

Project Development AA and DEIS Metro and TriMet managed the project in coordination with Cities of Lake Oswego & Portland URS Lead consultant for both AA & DEIS Portland Streetcar Inc. provided project oversight No clear direction on who would own/operate the line

Project Alignment North end (Portland) Rail corridor vs. in-street Existing condo and commercial development Some redevelopment opportunities

North End In-Street Alignment

North End Rail Alignment

Project Alignment Middle section Parks Riverside homes Private Crossings Trestles/tunnel

Middle Section: Parks and Riverside Homes

Middle Section: Private Crossings

Middle Section: Tunnel and Trestles

Project Alignment South end (Lake Oswego) Planned redevelopment of light industrial area Developing suburban downtown Good redevelopment opportunities

South End: Suburban Center

Public Engagement Citizen Advisory Committee Design Workshops Individual Resident Outreach Neighborhood Opposition Hired Political Strategist and Traffic Engineer Former U.S. Senator Political Issue in Lake Oswego

Redefining How Streetcar Operates Public Perception of Streetcar Urban circulator Relatively slow Frequent stops Urban/high density

Urban Streetcar in Portland

Redefining How Streetcar Operates Proposed Extension Rapid Streetcar Higher speed (17 mph compared to 8 mph) Less frequent stops (1/2 mile and greater) Condos, single-family, suburban

Streetcar Simulation

Indirect Connections to Downtowns Downtown Portland Direct connection to PSU Transfer or walk required to access employment/retail center Faster and more reliable, but less direct than current bus service

Downtown Portland

Indirect Connections to Downtowns Downtown Lake Oswego Modern/redeveloping suburban downtown Station access requires crossing high traffic state highway Major activity centers several blocks away 300 space park and ride

Downtown Lake Oswego

Downtown Lake Oswego

Design Issues, Right-of-Way Conflicts and Physical Constraints Costs increase when designed to operate as frequent corridor service Double-tracking Retaining walls Physical separation Park-and-ride lot Proximity to condominiums/homes Management plan for driveway crossings Visual, noise, safety concerns Tunnel rehabilitation Trestle replacement Adjacent bridge replacement project - coordination

Project Location

Refinement Phase Reduce costs Fewer park-and-ride spaces Station modifications More single-tracking Fully develop a minimum operable segment

Project Status DEIS completed in 2010 Lake Oswego and Portland city councils select streetcar as LPA with conditions Refinement Phase Final Report in early 2012 addressing conditions Action on project is deferred Last week s election brought anti-streetcar majority to LO City Council

Key Lessons Learned Need a strong political champion for the project Decide on owner/operator before getting too far Owner/operator will need to live with key decisions: Cost Operations Design Identify key community leaders and engage with them early

Key Lessons Learned (cont d) Use designers/architects in small group meetings with affected property owners and residents Clearly communicate how project differs from urban circulator streetcar Optimize one-seat rides linking key origins & destinations

Thank You John Cullerton URS Corporation john.cullerton@urs.com