International Water Mist Conference, Istanbul October 22-23, 2014 The background and development of the guidelines in IMO Resolution A.

Similar documents
RESOLUTION MSC.265(84) (adopted on 9 May 2008) AMENDMENTS TO THE REVISED GUIDELINES FOR APPROVAL OF SPRINKLER SYSTEMS EQUIVALENT TO THAT REFERRED TO

IMO UNIFIED INTERPRETATIONS TO SOLAS CHAPTER II-2 AND RELATED FIRE TEST PROCEDURES

IMO LIST OF DOCUMENTS ISSUED IN CONNECTION WITH THE FORTY-SEVENTH SESSION OF THE SUB-COMMITTEE ON FIRE PROTECTION AGENDA FOR THE FORTY-SEVENTH SESSION

4 June This circular supersedes MSC/Circ.914. *** I:\CIRC\MSC\01\1272.doc

IMO WORK PROGRAMME. Central control stations and safety centres on passenger ships. Submitted by Argentina and ICCL

REVISED GUIDELINES FOR THE DESIGN AND APPROVAL OF FIXED WATER-BASED FIRE-FIGHTING SYSTEMS FOR RO-RO SPACES AND SPECIAL CATEGORY SPACES

IMO. 4 June 1999 GUIDELINES FOR THE APPROVAL OF ALTERNATIVE FIXED WATER-BASED FIRE-FIGHTING SYSTEMS FOR SPECIAL CATEGORY SPACES

GUIDELINES FOR THE APPROVAL OF EQUIVALENT FIXED GAS FIRE-EXTINGUISHING SYSTEMS, AS REFERRED TO IN SOLAS 74, FOR MACHINERY SPACES AND CARGO PUMP-ROOMS

PROCEDURES FOR APPROVAL OF LIFE-SAVING APPLIANCES AND FIRE SAFETY SYSTEMS, EQUIPMENT AND PRODUCTS

Requirements for ships carrying hydrogen and compressed natural gas vehicles

26 June 2001 GUIDELINES ON ALTERNATIVE DESIGN AND ARRANGEMENTS FOR FIRE SAFETY

Large-scale fire sprinkler tests with the AutoStore compact storage system

IMO. Resolution A.952(23) Adopted on 5 December 2003 (Agenda item 17) GRAPHICAL SYMBOLS FOR SHIPBOARD FIRE CONTROL PLANS

IMO DEVELOPMENT OF MODEL PROCEDURE FOR EXECUTING SHIPBOARD EMERGENCY MEASURES. Fire-fighting drills. Submitted by the Republic of Korea

Approval of water mist systems in buildings

IMO FP 53 Report. Lloyd s Register report on the 53 rd session of IMO Fire Protection Sub-Committee. 16 th March, 2009

Can we use knowledge and experience from other sectors to prove Water mist s suitability for land applications? UK Water Mist Seminar 8th March 2016

MSC Guidelines for Watermist Fire Suppression Systems Procedure Number: E1-03 Revision Date: 02/16/2017

MSC Guidelines for Automatic Sprinkler Systems

This document is a preview generated by EVS

IMO COMPREHENSIVE REVIEW OF THE FIRE TEST PROCEDURES CODE

Technical Information

INFORMATION BULLETIN No. 150

IMO. Resolution A.951(23) Adopted on 5 December 2003 (Agenda item 17) IMPROVED GUIDELINES FOR MARINE PORTABLE FIRE EXTINGUISHERS

Part 6 Additional class notations Chapter 6 Additional fire protection for passenger vessels

Fire Detection and Fire Fighting Testing and Approval on Railway Vehicles

RESOLUTION A.752(18) adopted on 4 November 1993 GUIDELINES FOR THE EVALUATION, TESTING AND APPLICATION OF LOW-LOCATION LIGHTING ON PASSENGER SHIPS

Global Requirements for the Fire Protection of Ships. Dr Janet Murrell Warrington Certification Ltd

WATER MIST FIRE PROTECTION SYSTEMS FOR INDUSTRIAL CABLE TUNNELS AND TURBINE HALLS

Notice on the implementation of the amendments to the FSS Code in resolution MSC.339(91)

C-01 FIRE DECKS AND BULKHEADS

Shipboard incinerators with capacities up to 4000 kw

Table EXIT ACCESS TRAVEL DISTANCE a OCCUPANCY SYSTEM SYSTEM. A, E, F-1, I-1, M, b,d R, S-1. B c. F-2, S-2, U c

CERTIFICATE OF FIRE APPROVAL

M E M O R A N D U M. Diane Matthews, Administrator, Technical Projects. NFPA 101 First Draft Letter Ballot (A2014)

RESOLUTION MSC.44(65) (adopted on 11 May 1995) STANDARDS FOR FIXED SPRINKLER SYSTEMS FOR HIGH SPEED CRAFT

IMO INTERPRETATIONS OF FIRE PROTECTION-RELATED PROVISIONS OF THE HSC CODE

The Protection of Machinery Spaces by means of the Local Application of Water Mist. Dr. Tim R. Nichols CPhys FIFireE

Guideline No.: C-02(201510) C-02 FIRE DOORS. Issued date: October 20,2015. China Classification Society

CERTIFICATION BULLETIN

Circuit Breakers JANUARY The electronic pdf version of this document found through is the officially binding version

Changes to the 2018 Joint Commission Comprehensive Accreditation Manual for Hospitals (CAMH)

How to know if a residential or domestic water mist system is performance compliant to BS 8458:2015?

This regulation outlines procedures to be followed for fire drills and all school event decorations.

ISO INTERNATIONAL STANDARD. Ships and marine technology Lowlocation lighting on passenger ships Arrangement

National Fire Protection Association. 1 Batterymarch Park, Quincy, MA Phone: Fax:

CFD Simulation of the Water Mist Effect on Fire

26 June 2001 *** I:\CIRC\MSC\1007.DOC INTERNATIONAL MARITIME ORGANIZATION 4 ALBERT EMBANKMENT LONDON SE1 7SR

Fire Sprinklers Working Group Final Report

SCHULTE & ASSOCIATES Building Code Consultants 880D Forest Avenue Evanston, IL /

1. Revise and A to read as follows:

Protection of Rack Stored Exposed Expanded Group A Plastics with ESFR Sprinklers and Vertical Barriers

Copy of article submitted to Fire Safety Engineering for publication January/February 2009

IMO FP 54 Agenda Preview (Updated version)

ISO INTERNATIONAL STANDARD. Fire protection Automatic sprinkler system Part 9: Requirements and test methods for water mist nozzles

ClassNK Technical Information No. TEC-0838 (iii) The dormant period, visual indication, first stage audible alarm, second stage remote audible alarm a

RADAR REFLECTOR STANDARD FOR CERTIFICATION. DET NORSKE VERITAS Veritasveien 1, N-1322 Høvik, Norway Tel.: Fax:

SOUND RECEPTION SYSTEM

A. Hydraulic calculations shall be prepared in accordance with Chapter 23 of NFPA 13 with the following exceptions:

Ensuring safe passage HI-FOG for underground stations

CAN/ULC S Integrated Systems Testing of Fire Protection and Life Safety Systems and Fire Protection Commissioning

DRY CHEMICAL POWDER SYSTEM REQUIREMENTS TO COMPLY WITH THE LATEST IMO IGC CODE AND EUROPEAN COUNCIL CLARIFICATIONS

Australian Standard. Water mist fire protection systems System design, installation and commissioning AS

DEALING WITH FIRE SAFETY

Applicable international instruments for construction, performance and testing requirements 1

MARINE GYRO COMPASS STANDARD FOR CERTIFICATION. DET NORSKE VERITAS Veritasveien 1, N-1322 Høvik, Norway Tel.: Fax:

California Fire Code (CFC) Part III contains requirements. Building and Equipment Design Features PART. Chapters 5 through 19

NFPA 101 Life Safety Code Culture change 2012

EC-Type Examination (Module B) Certificate. A.1/3.11 b "B" dass divisions, fire integrity

National Fire Protection Association

IMO CCC1 Summary Report on the developments of the IGF Code

CAN/ULC-S1001, INTEGRATED SYSTEMS TEST OF FIRE PROTECTION AND LIFE SAFETY SYSTEMS

The Science Behind Water Mist Protection of Typical Building Hazards

TetraTek, Inc. Regulatory. Compliance. Emergency Response. Nuclear Facility Compliance. Compliance. Fire Protection.

DRAFT NFPA 805 TRANSITION PILOT PLANT OBSERVATION GUIDANCE

CHAPTER 61G15-32 RESPONSIBILITY RULES OF PROFESSIONAL ENGINEERS CONCERNING THE DESIGN OF FIRE PROTECTION SYSTEMS

CAN/ULC-S INTEGRATED SYSTEMS TESTING OF FIRE PROTECTION AND LIFE SAFETY SYSTEMS

First Revision No. 6-NFPA [ Section No. 2.2 ]

rpsa FIRE PROTECTION ENGINEERS

GROUNDING AVOIDANCE SYSTEM (GAS)

ASTM F25 SEMINAR Fire Testing for SOLAS and Navy Vessels New Test Procedures and Materials Approval Process

H gh-p led Combust ble Storage. Application Guide 2009 Edition

Report on First Revisions with Statement June 2014 NFPA 101

Gerd Koffmane, Henrik Hoff, AP Sensing GmbH, Böblingen

TECHNICAL COMMITTEE ON FIRE CODE

High Ceiling Protection

ClassNK Technical Information No. TEC-0453 Attachment (1) to ClassNK Technical Information No. TEC-0453 Guidance on SOLAS Chapter II-2 as amended in 2

Notice No. 7. Rules and Regulations for the Classification of Ships, July Issue date: March Working together for a safer world

Resolution: FR-2-NFPA Statement: The new language requires the action completed by NFPA 557 be prepared by a person that is approved.

NFPA 45 NFPA 211 NFPA 1600

OFFSHORE SUPPORT VESSELS 2014

IMO Resolution MSC 61(67): Annex 1: Part 2

Report on First Revisions with Statement June 2014 NFPA 101

Hot Issues in Fire Engineering 28 February 2012

The Situation. Modeling Storage Occupancies Under Sloped Ceilings. Concerns (Elevation View) The Concerns 4/29/ NFPA Conference & Expo

HI-FOG for Ro-Ro and Special Category spaces

MAIB SAFETY BULLETIN 2/2010. Failure of fixed high expansion foam system to extinguish fire on board the passenger ferry Oscar Wilde

WATER MIST CONVENTION AND EXHIBITION

MEMORANDUM. NFPA Technical Committee on Fire Code (FCC-AAA) Subject: NFPA 1 Proposed Tentative Interim Amendment (TIA) No.1045

Public Input No. 4-NFPA [ Section No. 4.2 ] Statement of Problem and Substantiation for Public Input. Submitter Information Verification

Transcription:

International Water Mist Conference, Istanbul October 22-23, 2014 The background and development of the guidelines in IMO Resolution A.800(19) Magnus Arvidson SP Fire Research SP Technical Research Institute of Sweden

Personal introduction Graduated Fire Protection Engineer from University of Lund in 1989. Employment as a fire protection consultant 1989-1991. Employed at SP Fire Research since October 1991. Joined my first IMO Fire-Protection Sub-Committee meeting, FP38 in 1993. Participated in the technical committee that developed the first edition of NFPA 750, published in 1996. Participated in the CEN committee on water mist fire protection systems 1998-2010.

What is IMO Resolution A.800(19)? Title: REVISED GUIDELINES FOR APPROVAL OF SPRINKLER SYSTEMS EQUIVALENT TO THAT REFERRED TO IN SOLAS REGULATION II-2/12 The document was published by the International Maritime Organization (IMO) in 1995 and contains: Installation guidelines. Appendix 1: Component manufacturing standards. Appendix 2: Fire test procedures. IMO is the United Nations specialized agency with responsibility for the safety and security of shipping and the prevention of marine pollution by ships.

Starting point: The Scandinavian Star fire, 7 April, 1990 Arson fire. 158 fire deaths. Revealed that current fire safety requirements were outdated.

Aftermath: New requirements by the International Maritime Organization (IMO) In December 1992, IMO adopted a comprehensive set of fire safety amendments, applicable to both new and existing passenger ships. The amendments required: The installation automatic sprinkler and smoke detection systems in accommodation and service spaces, stairways enclosures and corridors. The upgrading of fire safety bulkheads to non-combustible materials. Improved methods for assisting escaping persons, such as use of low location lighting.

Aftermath: New requirements by the International Maritime Organization (IMO) The amendments applies to ships in international traffic, carrying more than 36 passengers. Ships were required to fulfil the requirements according to the following time schedule: New ships constructed after October 1, 1994. Ships constructed prior to SOLAS 1974 by 1997. Ships constructed in accordance with SOLAS 1974 by the year 2005 or within 15 years of construction, whichever came later.

FP36 (1991) The Sub-Committee on Fire Protection was instructed to develop guidelines for the approval of equivalent sprinkler systems on passenger ships. The installation of automatic sprinkler systems is described in SOLAS regulation II-2/12. The regulation had not been updated since 1974 and lacked the subsequent advances that had been made in sprinkler technology. This had resulted in a demand for the recognition of equivalent sprinkler systems.

FP37 (1992) The United States submitted two documents to the meeting: Document FP37/8/4 that contained a draft revision to regulation II-2/12, reflecting the current state of proven automatic fire sprinkler system technology, including for examples pipe sizing by hydraulic calculation techniques, the use of fast-response sprinkler technology, appropriate water application rates, sprinkler spacing and operating pressure, the size of sprinkler sections, etc. Document FP37/8/5 that contained a proposal of the use of more economical automatic sprinkler systems, that incorporated the new technology of fast-response sprinklers and non-metallic piping material.

FP37 (1992) Sweden submitted a document, FP37/8/1 that discussed equivalent sprinkler systems. The document contained two annexes: Annex 1 that listed draft basic installation requirements. Annex 2 that contained draft fire test procedures. The draft fire test procedures covered fire scenarios in passenger cabins and public spaces, including a malfunction of a cabin sprinkler where the sprinklers in the attached corridor were required to prevent fire spreading from the cabin of origin.

FP37 (1992) The document submitted by Sweden had been developed within a small working group that consisted of representatives from: The Swedish Maritime Administration. The Swedish Shipowners Association. Det Norske Veritas. The Swedish Rescue Services Board. SP Technical Research Institute of Sweden. One manufacturer, i.e., Marioff OY from Finland. The Working Group at FP37 was instructed, with highest priority, to develop a draft Assembly resolution on equivalent sprinkler systems, based on these documents.

The adoption of IMO Resolution A.755(18) During its 18 th Assembly meeting in November 1993 the submittal from FP37 was considered and Resolution A.755(18), containing guidelines for the approval of sprinkler systems equivalent to that referred to in SOLAS Regulation II-2/12, was adopted. The guidelines set forth 22 principal requirements for equivalent sprinkler systems, including that: Sprinklers should have fast-response characteristics. The area of operation should be 280 m 2. The system should be sized using a hydraulic calculation technique. Two sources of power should be available. The system must be capable of operation using sea water.

The adoption of IMO Resolution A.755(18) Relative to the performance of the systems it was required that: The system should be capable of fire control and fire suppression under a wide variety of fire loading, fuel arrangement, room geometry and ventilation conditions. In addition, it was required that: The system and its components should be designed and installed in accordance with international standards acceptable to the Organization, and manufactured and tested to the satisfaction of the Administration. However, at this point of time, no such international installation or testing standards existed.

FP38 (1993) Sweden submitted a document, FP38/3/3 with a revised proposal for fire test procedures for equivalent sprinkler systems : 12 m 2 cabin with Pullman bunk beds, connected to a 1 m wide and 12 m long corridor. A number of fire scenarios inside the cabin were proposed, with and without an open cabin doorway, different positions of the point of ignition, an arson fire, etc. One scenario simulated the malfunction of the sprinkler inside the cabin. For the corridor fire tests, the fire source consisted of a pile of small pieces of mattress material, positioned between two sprinklers. For the public space fire tests, a fire source that consisted of two sofas made of polyether mattresses arranged in a steel frame support was suggested.

FP38 (1993) The acceptance criteria for the cabin and corridor tests were, at least partly, based on reference tests with standard sprinklers. The proposal lacked fire test procedures and fire test sources relevant for shopping or storage areas on board ships. Additionally, the United States submitted a short document, FP38/3/4, where they suggested that the test standard used for residential sprinklers appears to be suitable for testing systems for use in cabins on board ships.

FP38 (1993) During the process of the development of the fire test procedures, a standard fire scenario in ISO/DIS 6182-1 was tested at SP in Sweden. However, it was judged that the performance was too scenario specific. As no final proposal was developed, it was decided at the Sub-Committee meeting to form a correspondence group to further develop appropriate fire test procedures for the equivalent sprinkler systems.

The work of the correspondence group (1994) Parts of the correspondence group met once, at the US Coast Guard headquarters in Washington D.C. in February 8, 1994. At that meeting, additional test data using standard sprinklers were presented to the group. The tests were conducted with the fire source suggested for public spaces, i.e. two sofas placed back-to-back. For some of the tests, however, the test set-up was further expanded to include a total of four sofas placed together. A total of nine tests were conducted at either 2.5 m or 5 m ceiling height and the number of sprinklers that activated, the fire damage and ceiling gas temperatures were recorded.

The work of the correspondence group (1994) The meeting resulted in a number of proposed changes to the fire test procedures: The classification system of different occupancies provided by SOLAS regulations should be used - and there should be a clear correlation with the fire test hazard classification. A larger sized cabin was included in the fire test procedures, i.e. the Luxury cabin test. The suggested maximum size of the cabin was 24 m 2 with a square test compartment and two doorway openings. The suggested fire test source was the residential fuel package used by Underwriters Laboratories, Inc. or FMRC, Factory Mutual Research Corporation.

The work of the correspondence group (1994) The width of the corridor was increased, from 1 m to 1.5 m. Consensus was reached that no sprinklers in the corridor should be allowed to activate during a cabin test. The group agreed to add one or more tests simulating a corner public space fire scenario. The group discussed the advantage of a component malfunction test with a lower acceptance criterion, similar to the approach with the disabled cabin nozzle test. For the public space fire tests, several group members expressed their concern that the fire load was inadequate.

Technical report by the Factory Mutual Research Corporation (FMRC) Shortly after the meeting, FMRC distributed a preliminary technical report with comments to the draft fire test procedures in document FP38/3/3, although most of the content of the report had been discussed at the meeting. The preliminary technical report by FMRC also discussed shopping and storage areas. Based on a program sponsored by the National Fire Sprinkler Association (NFSA) and conducted by FMRC in 1989, an Ordinary Hazard fuel package had been developed. This scenario was suggested to be used.

FP39 (1994) Document FP39/3/6 contained the report from the Correspondence Group and was submitted to the meeting. The document summarised the conclusions by the group, however, it did no contain any detailed fire test procedures. Such a document was brought to the informal pre-meeting that was held on the Sunday afternoon prior to the start of the IMO meeting week. The document contained all changes proposed by the Correspondence Group, including the proposed fuel package for shopping and storage areas. Test results were presented proving that the open public space fire test source could activate six sprinklers. The discussion on the adequacy of this particular fire source could therefore be put aside. Component test (nozzles only) procedures were suggested, based on UL 199. A draft document was submitted to the sixty-fourth session of the Maritime Safety Committee (MSC 64) for consideration and approval.

Concerns about the availability of polyether mattresses During the intervening months between FP39 and MSC 64, various tests were conducted using the draft fire test procedures. An inaccuracy in the description of the material specified for the polyether mattresses used for the cabin and corridor and public space fire tests was revealed. Tests conducted at VTT in Finland indicated that it was difficult to find non-fire retardant mattresses that fulfilled the Cone calorimeter values given in the fire test procedures. It was therefore suggested that the specification of the polyether mattresses should be changed and the Finnish delegation submitted a proposal to MSC 64 about this.

MSC 64 (1994) During the meeting, the decision was made to revise the specifications of the polyether mattresses to increase the availability of suitable material. The acceptance criteria that previously had been established was no longer valid. The intention was therefore to provide guidelines for fire test laboratories how to conduct reference sprinkler tests. The sprinkler and the installation were specified as follows: ISO 6182-1 type spray pendent with: K-factor: 80 (metric), 15 mm sprinkler Time Response Index RTI 120 (metric) Water density 5 l/m2/min Spacing 4 m Installation according to SOLAS II-2/12

Reference sprinkler tests (1995) SP and VTT agreed to collaborate on establishing performance criteria with standard sprinklers. Beginning of 1995, they independently carried out reference sprinkler tests with two types of standard response spray sprinklers that fulfilled the requirements given above. A limited number of tests were conducted with sprinklers having fast-response characteristics. On the basis of the results, a collaborative project was undertaken in defining recommended acceptance criteria for the accommodation and public space fire tests.

Heat Release Rate 5000 Open public space 4000 Corner public space Heat Release Rate [kw] 3000 2000 1000 0 0 5 10 15 Time [min]

5000 Heat Release Rate 4000 Open public space Corner public space Heat Release Rate [kw] 3000 2000 Ultra Fast Fast Medium 1000 Slow 0 0 1 2 3 4 5 6 Time (min)

FP40 (1995) Several documents related to the test procedures for equivalent sprinkler systems were submitted to the meeting: Finland and Sweden submitted a joint document, FP40/5/8, that summarised the outcome of the reference sprinkler tests and provided suggested acceptance criteria. The United Kingdom submitted a document, FP40/5/6, with similar information, based on direct contact with VTT. Finland submitted a document, FP40/5/4 which discussed the correlation between the occupancy classification and the fire tests. The United States submitted a document, FP40/5/2, where they argued that fire tests should be amended to ensure that appropriate levels of life safety and vessels protection are provided by the equivalent systems. However, the document did not contain any specific suggested amendments.

The adoption of IMO Resolution A.800(19) The guidelines for approval of equivalent sprinkler systems was adopted at the 19 th IMO Assembly that was held in November 1995 as Resolution A.800(19) which marked the end of the work that started in 1991.

In summary The Scandinavian Star fire occurred in 1990. The Sub-Committee on Fire Protection was instructed to develop guidelines for approved equivalent sprinkler systems in 1991. IMO adopted a comprehensive set of fire safety amendments, applicable to both new and existing passenger ships in 1992. IMO Resolution A.755(18) containing guidelines for approved equivalent sprinkler systems was adopted in 1992. With these requirements as the basis, the process of developing fire test procedures and a component manufacturing standard for nozzles started at FP38 in 1993. IMO Resolution A.800(19) was published in 1995.

In summary The fire test procedures covers the wide variety of fire load, fuel arrangement, room geometry and ventilation conditions typically found on board passenger ships, by using the following different fire test scenarios: Cabin fire tests. Corridor fire tests. Luxury cabin fire tests. Open and corner public space fire tests. Shopping & Storage area fire tests. The acceptance criteria are directly or indirectly based on the performance of standard sprinklers. The component tests (nozzles only) were adopted from UL 199.

Acknowledgement The work has been partly financed by Ultra Fog AB in Sweden, which is gratefully acknowledged. The review and input on the content of the paper by Maarit Tuomisaari of Marioff Corporation Oy is also gratefully acknowledged.

Brandposten: News from SP Fire Research www.sp.se