Christopher Kelly Technical Report Three

Similar documents
Technical Assignment 3

Technical Report Three

TECHNICAL REPORT 3 Mechanical Systems and Existing Conditions Northfield Mental Healthcare Center Northfield, Ohio

The Creative and Performing Arts High School (CAPA) Pittsburgh, PA 11/11/2002 Andrew Tech Mechanical Option Prof. S. A. Mumma

Technical Assignment 3 11/15/04. Executive Summary

UNIVERSITY OF MISSOURI Heating Ventilating and Air-Conditioning (HVAC) 2016 Q1

4. OVERVIEW OF MECHANICAL SYSTEM

(2.1) Design Conditions...5 (2.2) Ventilation Requirements..5 (2.3) Heating and Cooling Loads...6

Technical Report #3 Mechanical Systems Existing Conditions Evaluation

Technical Investigation, Part Three Elizabeth C. Krauss Mechanical Option September 18, 2013

11/2 ORT THREEE. Virtua Repla. acement Hospi. ital. Voorhees NJ. Justin Prior. Mechanical

The Ed Roberts Campus

COMcheck Software Version Mechanical Compliance Certificate

Existing Mechanical System Operation

Architectural Engineering Senior Thesis Mechanical System Redesign

2009 Washington State Non-Residential Energy Code Scott Rushing, PE, LEED AP - Rushing Company Lisa Rosenow, CSBA, LEED AP NEEC

ENGINEERING BULLETIN. Overview of Chilled Beam Technology. Purpose. Summary. Theory

Terminal. Las Vegas, NV. Technical

Mechanical Technical Report 3. Mechanical Systems Existing Conditions Evaluation

SECTION SEQUENCE OF OPERATIONS FOR HVAC CONTROLS

SECTION HVAC TABLE OF CONTENTS PART 1 - SYSTEM DESCRIPTION / OUTLINE SPECIFICATIONS FILED SUB BID PROJECT OVERVIEW...

B. Use UT Austin specifications and equipment schedule format for HVAC equipment where available.

TECHNICAL REPORT 3: Mechanical Systems and Existing Conditions. Michael Morder Mechanical Option Advisor: Dr. William Bahnfleth

ASHRAE JOURNAL ON REHEAT

7. MECHANICAL SYSTEM DESIGN

A. Base Bid: 1. Heating Contractor provide: a. Control sequences for HVAC systems, subsystems, and equipment.

Appendix 13. Categories of Cooling and Heating systems

GARCIA GALUSKA DESOUSA Consulting Engineers

HVAC 101. The Basics of Heating, Ventilation and Air Conditioning

AIR-CONDITIONING SYSTEMS AND APPLICATIONS. Abdullah Nuhait Ph D. King Saud University

1080 Marina Village Parkway, Suite 501 Alameda, CA (510) Fax (510) HVAC DESIGN INTENT

Dehumidifying with Dedicated Outdoor Air

SECTION SEQUENCE OF OPERATIONS FOR HVAC CONTROLS

Andrea Borowski The Pennsylvania State University University Park, PA November 11, 2002 Consultant: Dr. Bahnfleth Technical Assignment M-3

Mechanical Redesign, Proposal Elizabeth C. Krauss Mechanical Option September 18, 2013

EADQUARTERS. Technical Report One. Stephanie Kunkel Mechanical Option

ASHRAE Illinois Chapter 2015 Excellence in Engineering Awards

Technical Assignment 3. Mechanical Systems Existing Conditions Evaluation

Computing Services Center

DIVISION 23 - HVAC HVAC

CARRIER edesign SUITE NEWS. Modeling 100% OA Constant Volume Air Systems. Volume 6, Issue 1. Page 1 Modeling 100% OA Constant Volume Air Systems

INTRODUCTION TO: ASHRAE STANDARD 90.1, HVAC System Requirements for Reducing Energy Consumption in Commercial Buildings

Element Z General Design Requirements Existing Facilities Information

2009 IECC Commercial Mechanical Requirements

HVAC Controls Upgrades: Requirement Details ( )

HVAC 101. H V A C S y s t e m s

MID MICHIGAN COMMUNITY COLLEGE HARRISON CAMPUS Harrison, Michigan 2015 MASTER PLAN

CONTENTS. B. System Design and Performance Requirements

Mechanical System Redesign. Dedicated Outdoor Air System. Design Criteria

HVAC Controls Upgrades: Requirement Details ( )

Submitted to. Texas A&M University-Corpus Christi The Texas A&M University System. Submitted by. Yeqiao Zhu Dan Turner David Claridge

Technical Assignment 1

THIS IS A DESIGN GUIDE NOT A SPECIFICATION. Montgomery County Public Schools Facilities Guide DIVISION 15 MECHANICAL

Case Study: Furman University Charles H. Townes Center for Science. Michael K. Mantai, PE, CCP President System WorCx

Tech Report III. Technology and Engineering Development (TED) Building. Thomas Jefferson National Accelerator Facility.

APPLICATION GUIDE BEAMS

Challenges and Methods of Estimating a Conceptual HVAC Design

Energy-Efficient Makeup Air Units BY HUGH CROWTHER, P.ENG., MEMBER ASHRAE

Mechanical Technical Report 1. ASHRAE Standard 62.1 Ventilation Compliance Evaluation

August 15, 2013 Page 1 of 19

INTRODUCTION HVAC BASICS AND HVAC SYSTEM EFFICIENCY IMPROVEMENT SECTION O 4/19/2012

HVAC Mandatory Provisions Part II, Page 1

Selected Laboratory Energy Efficiency Measures

Union County Vocational - Technical Schools Scotch Plains, New Jersey

National Institutes of Health Building 37 Modernization Bethesda, Maryland MECHANICAL DEPTH EXISTING MECHANICAL SYSTEM

Submitted to. Texas A&M University at Galveston The Texas A&M University System. Submitted by. Yeqiao Zhu Dan Turner David Claridge

FLORIDA A&M UNIVERSITY PERFORMANCE CONTRACT SCOPE OF WORK

Madeira City Schools Madeira, Ohio. HVAC Assessment. December 2011 (Revised February 2012)

Retrocommissioning Findings Summary: Building X #1 Priority: Major Comfort/Control Problems

Florida Department of Transportation

Daikin Blueprint: Delivering Hot Water with a Chiller

High Efficiency Heating and Cooling Systems for Community Colleges Kirk Mescher, PE, LEED AP Principal ICCCFO

MT. AIRY MIDDLE SCHOOL CARROLL COUNTY PUBLIC SCHOOLS

Introduction to HVAC. American Standard Inc Air Conditioning Clinic TRG-TRC018-EN

ASHRAE Region VI CRC Track III: Session 3 Ventilation Energy Recovery. Steven T. Taylor, PE Principal Taylor Engineering

PINNACLE SERIES DEDICATED OUTDOOR AIR SYSTEM ENERGY EFFICIENT DEHUMIDIFICATION

General HVAC Recommendations

TECHNICAL REPORT III Mechanical Systems Existing Conditions

DACC Health Sciences Building Air Handler Assessment/Study

System Components with ` Emphasis on Packaged Rooftop Application and Installation. Jerry Cohen President Jacco & Assoc.

Civil Engineering Building

MECHANICAL, ELECTRICAL, PLUMBING, AND FIRE PROTECTION CONDITIONS FACILITIES MASTER PLAN MAY

BOOK 1 OVERVIEW RD2XIN INSTALLATION AND OPERATION MANUAL. Table of Contents ABOUT BOOK 1:

DADANCO Technical Paper

Senior Thesis Centre Community Hospital East Wing Addition - Proposal Keith Beidel Mechanical Option 12/05/02 1

b.) Technical Information:

CARRIER edesign SUITE NEWS. Interpreting High (Low) Peak Design Airflow Sizing Results for HVAC. Equipment Selection.

The School District of Philadelphia Administration Headquarters Shell and Core Renovations 440 North Broad Street Philadelphia, PA

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

BOOK 1 OVERVIEW RD2XRT INSTALLATION AND OPERATION MANUAL. Table of Contents ABOUT BOOK 1:

F.W. Olin Physical Science Laboratory

1 - This title will copy onto other forms Date

SECTION SEQUENCE OF OPERATIONS FOR BUILDING CONTROLS

RAMAPO COLLEGE OF NEW JERSEY CCA0803 PHASE II HOUSING REHABILITATION 2012

The Ed Roberts Campus Berkeley, CA

DIVISION 15 MECHANICAL

Submitted to. Texas A&M University at Commerce The Texas A&M University System. Submitted by. Guanghua Wei Craig Campbell David Claridge Dan Turner

COMcheck Software Version Review Mechanical Compliance Certificate

THE PENNSYLVANIA STATE UNIVERSITY SCHREYER HONORS COLLEGE DEPARTMENT OF ARCHITECTURAL ENGINEERING RUTGERS ACADEMIC BUILDING ANDREW KOFFKE SPRING 2015

The M & V Guided Recommissioning Process. Energy & Water Conservation Program. September 2015 MOO

Transcription:

Christopher Kelly Technical Report Three Mechanical Systems and Existing Conditions Evaluation SALK HALL ADDITION The University of Pittsburgh, Pittsburgh Christopher Kelly, Mechanical Option Professor James Freihaut, Advisor Fall 2010, Senior Thesis Design Project

TABLE OF CONTENTS Executive Summary.3 Mechanical Systems Description Introduction...4 Design Objectives and Requirements...4 Site and Budget..4 System Initial Cost.5 Lost Space..5 Energy Sources..6 Design Air Conditions...6 Equipment Summaries...7 System Operation Air Side Schematics and Operation Strategy 10 Chilled Water Loop Schematics and Operation Strategy..11 Hot Water Loop Schematics and Operation Strategy...13 Data Found in Previous Reports Ventilation Requirements.15 Thermal Loads and Energy Use...16 LEED Analysis...19 Overall Evaluation......21 2

Executive Summary This report summarizes the existing conditions of the mechanical systems found within the Salk Hall Addition. The University of Pittsburgh designed the addition to existing Salk Hall in order to accommodate increased learning in the Schools of Dental Medicine, Pharmacy, and the Graduate School of Public Health. Many factors influenced the design of the building, namely the constraints imposed by its laboratories and their support spaces. This is the final technical report within the Architectural Engineering Senior Thesis program. After reviewing this report, it will be clear how the mechanical systems operate within the Salk Hall Addition. The existing systems have been evaluated and have been determined to meet the criteria set forth by ASHRAE design standards as well as the University of Pittsburgh s lab standard. It will become clear, however, that the conventional VAV system designed for the Salk Hall addition could be improved. Keep in mind that the current design has been simulated and operates within an acceptable range of the per unit operating cost of neighboring buildings on campus. However, the current VAV system could be improved by using condensing boilers and heat recovery chillers. This design could ultimately provide free reheat for the terminal reheat coils in the VAV units. Chilled beam systems have also recently been proposed for laboratory designs. These options will be explored in the final proposal as well as in the AE Senior Thesis design phase next semester. 3

Mechanical Systems Description Introduction The scope for the Salk Hall Addition includes the construction of a new research tower of approximately 81,100 gross square feet connected to the existing Salk Hall. The project will create the much needed additional research laboratories and related ancillary spaces for the Schools of Dental Medicine, Pharmacy, and the Graduate School of Public Health. Design Objectives and Requirements The project scope includes renovations, upgrades, extensions, expansions and/or replacement of the following systems: HVAC, electrical, fire protection, water, waste, telecommunications, data, security, controls, and laboratory specialty systems in Salk Hall and the Salk Hall Annex. The underlining goals are to improve system function and increase energy efficiency, meet applicable Codes, and accommodate upgrades and the expansion of the buildings research, teaching, administrative, and auxiliary facilities. Site and Budget The site for the proposed Salk Hall Addition is located on the University of Pittsburgh s main campus and is situated within the 4 th Ward of the City of Pittsburgh, Pennsylvania. The proposed site is located within a square city block bounded to the north by Allequippa Street, to the east by Sutherland Drive, to the south by Terrace Street, and to the west by Darragh Street. The city block is approximately 6.5 acres in size and consists of two properties owned by the University of Pittsburgh. The proposed project area is currently under conditions of an existing bituminous asphalt pavement parking lot with a heavily wooded hillside. Total building construction is estimated to cost around $42 million. 4

System Initial Cost The estimated cost for the HVAC system in the Salk Hall Addition is about $3.5 million. This value would yield a unit cost of $43.15 per square foot. The estimated cost of the plumbing system is around $1 million. The estimated first costs of the HVAC and plumbing systems are $225,000 and $44,000, respectively. The total cost of the combined HVAC and plumbing systems is around 10.7% of the estimated total building cost. Lost Space The lost space due to mechanical systems is summarized in the following table. The first floor and the mechanical penthouse hold a majority of the HVAC and plumbing equipment. Shaft area was calculated on a floor by floor basis since shaft openings have accordingly as the ducts were sized to yield a minimum duct construction cost while still maintaining an appropriate aspect ratio. Mechanical Spaces Floor Lost Space (GSF) Type % Total 1 1730 Equipment Room 20.00% 2 150 Shafts 1.70% 3 250 Shafts 2.90% 4 250 Shafts 2.90% 5 250 Shafts 2.90% Penthouse 6000 Equipment Room 69.50% Total 8630 100% 5

Energy Sources The Salk Hall Addition receives its chilled water, processed steam, and electrical power from campus plants at the University of Pittsburgh. The following table outlines the rates delivered to Ballinger in 2008. These are peak demand rates and are the same rates used in the energy simulation conducted in Technical Report 2. Energy Generation Rates Type Rate Units Electric 0.084 $/kwh Steam 1.700 $/Therm CHW 0.706 $/Therm Design Air Conditions The outdoor design conditions for Salk Hall can be obtained in the ASHRAE Fundamentals 2009 Handbook. Summer design criteria for all areas will be 91 F dry bulb and 72 F wet bulb. The winter design criteria will be 3 F dry bulb as per the ASHRAE Fundamentals 0.4 / 99.6% condition for Pittsburgh, Pennsylvania. The summer ambient air design wet bulb temperature for the cooling towers will be 77 F. The table below describes the indoor design conditions for each type of space in the Salk Hall Addition. Room Type Offices, Meeting Rooms, Conference Rooms Summer DB ( F) Max. Summer Relative Humidity (%) Winter DB ( F) 72 50 72 Laboratories 72 60 72 Lab Support Rooms 72 60 72 Lab Personnel Corridors 72 60 72 Tele-data Rooms 74 50 70 Lab Linear Equip. Corridor 74 60 74 6

Equipment Summaries Air side Equipment Three identical 29,000[CFM], 100% outdoor air, air handling units on the penthouse level will serve all air conditioned spaces throughout the building. The three AHUs will have mainfolded supply ducts. The exhaust air will pass through the AHUs energy recovery wheels, exchange energy with the supply air, and discharge through roof mounted exhaust fans. Outdoor air will be drawn through wall louvers on the north side of the building into a double wall, accessible plenum. There are 280 terminal units that support both the supply and exhaust airflow distributions. This sum of units includes the commercial VAV boxes, fan powered boxes, and venturi style Phoenix Laboratory Valves. AHUs are comprised of the following components: Outdoor air intake plenum with an automatic isolation damper Filter section with MERV 7 (30% efficient) 4 inch deep pre filters and MERV 14 (90% efficient) 12 inch deep final filters. Total heat energy recovery wheel section (Purge 3220 [CFM]) Steam preheat coil section Supply fan section with VFD (blow through configuration) Sound attenuator section Humidifier section Chilled water cooling coil section (450 fpm maximum face velocity) Discharge plenum section Exhaust air intake plenum The following table, which excludes the supply fans in each air handler, summarizes the fan schedule for the Salk Hall Addition. Fan Schedule Tag Type Location CFM EF 1A Induced Flow Roof 31500 EF 1B Induced Flow Roof 31500 EF 1C Induced Flow Roof 31500 7

EF 1D Induced Flow Roof 31500 SF 2 Propeller Main Electric Room 10000 EF 2 Propeller Main Electric Room 10000 SF 3 SWSI Mechanical Level 10000 EF 4 Centrifugal 3rd Floor Roof 3000 EF 5 Propeller Generator Room 3500 EF 6 Centrifugal Roof 535 EF 7 Centrifugal Roof 300 Water Side Equipment The building s chilled water will be supplied by the Peterson Event Center chiller plant. 6 supply and return pipes will connect to the campus system adjacent to the Peterson Event Center plant. The P.E.C. Chiller Plant will be expanded as part of this project. The plant expansion will include a primary pump, 1200 ton chiller, and an 1100 ton cooling tower. The designed chilled water will be at a supply temperature of 42 F and a return temperature of 58 F. An increase in the chilled water supply temperature above 42 degrees may cause a room temperature excursion above the room temperature set point. The designed condenser water supply temperature will be at 85 F while the return temperature is designed to be 95 F. The following table outlines the HVAC pump design characteristics. HVAC Pump Schedule Tag Type Location GPM Head RPM P 1A Base Mounted End Suction First Floor 240 80 1750 P 1B Base Mounted End Suction First Floor 240 80 1750 P 2A Horizontal Split Case First Floor 600 70 1750 P 2B Horizontal Split Case First Floor 600 70 1750 P 3A Base Mounted End Suction Mechanical Level 70 80 1750 P 3B Base Mounted End Suction Mechanical Level 70 80 1750 P 4 Base Mounted Mechanical Level 60 70 1750 P 5 Inline Split Coupled First Floor 29 40 1750 P 6 Inline Split Coupled First Floor 21 40 1750 P 7 Inline Split Coupled First Floor 12 40 1750 P 11 Horizontal Split Case P.E.C. 1920 45 1750 8

The Peterson Event Center houses both the cooling tower and water cooled chiller associated with the Salk Hall addition. The cooling tower is of an induced draft design and processes 3000 [GPM]. The design entering water temperature is 90.6 degrees Fahrenheit and the design leaving temperature is 80.6 degrees Fahrenheit. The centrifugal chiller has a capacity of 1200 tons and uses R 123 as its refrigerant. 9

Christopher Kelly Technical Report Three 2010 System Operation Schematics (Air Side) Schematic 1 (AHUs & Exhaust Fans) Above is a schematic of the air handling units located in the penthouse and the associated exhaust fans which are located on the roof. The diagram shows the west shaft in which supply and exhaust duct reside. The west shaft serves the laboratory spacess while the east shaft serves thee administrative and office spaces. Each shaft, as well as each air handling unit, includes an airflow measuring station to ensure designed airflows are being met. 10

Christopher Kelly Technical Report Three 2010 Air-Side Control Strategy The laboratory airflow control system will be based on Phoenix Controls Analog air valves with Automated Logic BAS DDC controllers performing the laboratory airflow and laboratory temperature control. Phoenix Controls CAV air valves, provided with airflow feedback cards, will be utilized for fume hood exhaust service to maintain a constant face velocity across the fume hood opening. Phoenix Controls VAV supply air valve, providedd with airflow feedback cards, will be utilized to supply 100% outdoor makeup air to the laboratory, and will be positioned to maintain airflow based on total exhaust flow minus the room offset airflow. The supply valves will be overridden to open further upon a need for more cooling. Phoenix Controls VAV general exhaust valves can also be overridden in case of an emergency. Schematics (Chilled Water Side) Schematic 2 (Campus Chilled Water Loop) 11

Christopher Kelly Technical Report Three 2010 Schematic 3 (Process Chilled Water Loop) Schematic 2 and Schematic 3 describee the chilled water loops between the penthouse level and the mechanical room on the first floor. The campus chilled water supply, which enters through 6 underground pipes, will be at a temperature of 42 F and at a return temperature of 58 F. The loop shown in schematic 2 serves the fan coil units in each linear equipment corridor as well as the cooling coils in the air handling units. The main supply and return risers, whose chilled water is supplied by the campus loop, are on the west side of the diagram. The process chilled water loop shown in Schematic 3 serves miscellaneous laboratory equipment on floors two through five. The designed condenser water supply temperature will be at 85 F and a return temperaturee of 95 F. The processs chilled water system will be isolated from the campus system via a plate and frame heat exchanger. The system will have the capacity of supplying and returning temperatures between 55 degrees and 65 degrees Fahrenheit. Operational temperatures may be as high as 85 to 95 degrees Fahrenheit. 12

Chilled Water Control Strategies For multi bank coil arrangements, each coil will be furnished with an isolation valve, a P/T plug on the supply side of each coil, a balancing valve, and a P/T plug and isolation valve on the return side of each coil. The supply side of the coil bank will have an isolation valve, strainer with differential pressure gage, thermometer, pressure gage, vents, and drains. The return side of the coil bank will have a pressure gage, thermometer, modulating two way control valve, isolation valve, vents and drains. Two way control valves will modulate flow of chilled water through the cooling coils to maintain leaving air temperature set points. Separate leaving air temperature transmitters, in the air handling unit discharges, will be provided for controlling the pre heat and chilled water coils. A low limit temperature sensor across the upstream face of the chilled water coil will be provided to de energize the supply fan in the event of frigid air temperatures, in order to minimize the probability of the chilled water coil freezing. When the low limit temperature sensor alarms and alerts the Building Automation System, the chilled water coil control valve will be driven open. Schematics & Control Strategy (Hot Water Side) The hot water heating system will consist of two shell and tube LPS to hot water heat exchangers. Each heat exchanger will be sized for 100% of the load. Two primary system pumps will be provided, each with a variable frequency drive and each sized for 100% of load. VFDs will maintain the differential pressure set point in the system. One or both pumps may operate to meet capacity for optimum energy use. Multiple secondary loops will be provided for the perimeter radiation. Each loop will consist of a 3 way mixing valve and hot water circulator pumps. This system will be constant volume. Reheat coils and other heating equipment will be provided with modulating twoway control valves located on the return side of each coil. Terminal reheat valves will modulate to maintain the room temperature set point. 13

Christopher Kelly Technical Report Three 2010 Schematic 4 (Steam Pressure Reducing Stations) Schematic 4 details the process in which high pressure steam, delivered from the 6 campus line, is reduced into medium and low pressure steam. Medium and low pressure condensates are also produced. The mediumm pressure stream is distributed to the sterilizers and glass cleaning equipment in the laboratories and their support spaces. The low pressuree condensate is delivered to the heating coils and humidifiers. Low pressure steam is deliveredd to the laboratory hot water heaters, domestic hot water heater, and the shell and tube heat exchangers located in the first floor mechanical space. 14

Data Found in Previous Technical Reports Previous Technical Reports covered the information required for this report. The repeat areas include ASHRAE Standard 62.1, ASHRAE Standard 90.1, and TRANE Trace simulation data. Ventilation Requirements Within the Salk Hall Addition, three air handling units supply the building with 87,000 CFM with the entire volume being outdoor air. The building was assessed per the Ventilation Rate Procedure according to ASHRAE Standard 62.1 and was determined to be within compliance. AHU-1 AHU-2 AHU-3 Air Handling Units and Total Airflow Rates (CFM) 29,000 (100% OA) 29,000 (100% OA) 29,000 (100% OA) The Salk Hall Addition only distributes supply air from the ceiling and therefore the zone air distribution effectiveness (Ez) was found to be 1.0 for both cool and warm supply air. The ventilation system has been designed to be capable of providing the required ventilation rates in the breathing zone whenever the zones served by the system are occupied, including full and part load conditions. One or more motion/infrared occupancy sensors will be installed to serve individual temperature controlled zones. When a zone is determined by the sensors to be occupied, the lights of the zone will be switched on and the air system will be indexed to occupied set points. When the zone is determined to be unoccupied, the lights of the zone will be switched off and the air system will be indexed to unoccupied set points. Sensors will incorporate an adjustable delay to prevent too frequent setting changes. This adjustment to supply air is in direct correlation to the ventilation air since the HVAC system is 100% outdoor air. 15

The ventilation system designed for the Salk Hall Addition is also in compliance with the University of Pittsburgh s laboratory design standard of 6 air changes per hour in laboratories and their associated spaces. Thermal Loads and Energy Use Per TRACE 700 The TRACE 700 outputs state that Salk Hall will demand 4,260,888 [kwh] at a cost of $357,915 per year. The largest demand on the electrical system, relative to the mechanical systems, is the energy required for fan operation. The ventilation requirement of Salk Hall s laboratories and their support spaces is the key factor which influences the high fan power demand. In the model, the supply fan delivers 86,000 [CFM] while the exhaust fans pull 91,754 CFM. The design for the Salk Hall Addition allows for 87,000 [CFM] of outdoor supply air. The following table describes the peak cooling load of the Salk Hall Addition. Calculated Cooling Load Type Total Load [Btu/hr] Calculated Cooling Load Type Total Load [Btu/hr] Skylite Solar 24,767 Infiltration 195,538 Skylite Cond 969 Lights 267,794 Roof Cond 9,837 People 251,201 Glass Solar 226,056 Misc 781,820 Glass/Door Cond 57,506 Exh. Fan Heat 287 Wall Cond 44,343 Ventilation Load 1,044,449 Partition/Door 36,838 Ov/Undr Sizing 18,300 Floor 175 Sup. Fan Heat 447,067 Adjacent Floor 0 Duct Heat Pkup 91,506 Totals 3,497,528 [BTU/hr] The two largest loads are from the ventilation airflow rates and the internal equipment loads. These results are comparable to the energy model that Ballinger created within an acceptable range. 16

The following table is a breakdown of energy consumption by each respective piece of heating or cooling equipment. The heating energy requirement is much less than the cooling requirement. This is due to the high internal loads. System Elect Cons. (kwh) PCldW Cons. (kbtu) P.Stm Cons. (kbtu) Total Building Energy (kbtu/yr) Primary heating Primary heating 70,055 70,055 Other Htg Accessories 691 2,360 Primary cooling Cooling Compressor 128,897 128,897 Auxiliary Lighting Supply Fans 2,126,627 7,258,176 Pumps 14,400 49,147 Lighting 514,005 1,754,300 Receptacle Receptacles 1,604,740 5,476,976 Totals 4,260,463 128,897 70,055 14,739,912 Purchased chilled water for the Salk Hall Addition is estimated to cost the University under $1000 dollars per year. The amount of purchased steam required is under $1200 per year. These two values are relatively low due to the fact that both utilities are delivered from central plants on campus. It is important to keep in mind that the building is under construction, therefore no actual demand values can be referenced, and the actual cooling demand may vary from the TRACE simulation outputs. The ASHRAE RSTM spreadsheet was used to model the northwest laboratory after Ballinger found discrepancies in the TRACE 700 results. The results were as follows: 17

Loads TRACE OUTPUT RSTM OUTPUT % Difference (Trace to RSTM) Glass Solar 13,505 Btu/h 9,358 Btu/h 44 % Larger Wall/Window 5,374 Btu/h 3,555.6 Btu/h 51 % Larger Conduction Infiltration 8,771 Btu/h 7,689.4 Btu/h 14 % Larger Lights 14,786 Btu/h 15,192.9 Btu/h 3 % Smaller People 9,468 Btu/h 4853.7 Btu/h 95% Larger Misc 63,509 Btu/h 61,670 Btu/h 2.9 % Larger The RSTM outputs are significantly lower than the TRACE 700 outputs and this example can be used to show that the energy demand on any given building will most likely fall between a range of values. 18

LEED Analysis for Mechanical Systems The Salk Hall addition plans to apply for LEED certification after the construction process is significantly underway. There are two main categories under LEED for assessing the building s mechanical systems. They are Energy and Atmosphere and Indoor Environmental Quality. The Salk Hall addition will have to submit to the criteria established by LEED 3.0, in which there are 3 prerequisites for Energy and Atmosphere and 2 prerequisites for Indoor Environmental Quality. These prerequisites are mandatory benchmarks for sustainable design. Energy and Atmosphere EA Prerequisite 1 is to have fundamental commissioning of the building systems after construction has been completed. Since construction is in its early phases, the Salk Hall Addition cannot fulfill this requirement yet. EA Prerequisite 2 is a design phase prerequisite that states the building has to meet the minimum energy performance which is outlined in EA Credit 1. EA Prerequisite 3 is also a design phase prerequisite in which no CFC based refrigerants are to be used in the designed cooling equipment. EA Credit 1 evaluates energy performance. This credit cannot be evaluated until a suitable baseline energy model is created for a comparison to the proposed design. EA Credit 2 requires on site renewable energy. The Salk Hall Addition does not utilize renewable energy and therefore cannot receive any points for this credit. EA Credit 3 deals with enhanced commissioning and is worth 2 points. Again, the Salk Hall Addition is in its early construction phases. EA Credit 4 is enhanced refrigeration managements. The total refrigerant impact per ton must be less than 100. 19

EA Credit 5 is measurement and verification. If points are needed after construction is completed, measurement and verification of energy consumption can be done for an extra three points. EA Credit 6 deals with buying green power from a utilities provider. The Salk Hall addition receives its utilities from the University of Pittsburgh s central plants and therefore will not receive points for this credit. Indoor Environmental Quality EQ Prerequisite 1 requires ASHRAE Standard 62.1 to be met for indoor air quality. Based on the calculations of Technical Report 2, the Salk Hall Addition will meet these criteria. It is important to keep in mind that the University of Pittsburgh has its own standard for acceptable air quality in laboratories and their support spaces. The rate of 6 air changes per hour in these respective spaces has also been met. EQ Prerequisite 2 deals with environmental tobacco smoke control. The Salk Hall Addition is a non smoking building. EQ Credit 1 deals with the monitoring of outdoor air delivered to the conditioned spaces. The credit requires that C0 2 monitoring must be done in every densely occupied space. This credit will not be met by the current design of the Salk Hall Addition. EQ Credit 2 is increased ventilation. The Salk Hall addition will most likely meet this requirement due to the high air change rates established by the University standard. While the addition will gain points in this category, the increased fan power will hurt the proposed case when it is compared to the baseline model required for EA Credit 1. EQ Credit 6.2 requires individual comfort control for 50% of the buildings occupants including multi occupant spaces. This credit is met because each thermal zone is controlled by a thermostat and its own terminal VAV unit. 20

EQ Credit 7.1 deals with the thermal comfort of the occupants. ASHRAE Standard 55 2004 is satisfied within the Salk Hall design. EQ Credit 7.2 is the verification of thermal comfort. This credit cannot be gained until a post occupancy study is performed. Overall Evaluation Overall the mechanical system of the Salk Hall addition is well designed. Laboratories often pose a greater design challenge than other buildings due to the large variation in internal loads as well as their high ventilation requirements. In order to maximize efficiency, a variable air volume system has been implemented. This system is capable of supplying the required ventilation air under full and part load conditions, as well to provide make up ventilation air when fume hoods or biological safety cabinets are active. The estimated construction cost of the mechanical system is around 11% of the total cost. This is within an appropriate range since laboratories often require a large amount of lab equipment and its associated architectural casework. Since the Salk Hall Addition receives its utilities from campus plants, the most expensive pieces of mechanical equipment are the air handling units. Variable air volume systems are conventional and easy to install and operate. The operating cost of the building is dominated by the ventilation requirement of the laboratories. Due to the fact that the laboratories require 6 air changes per hour, the supply fans have a high electrical demand. Lab equipment also drives the building s operation costs up. The myriad of lab equipment associated with the respective spaces can often demand up to 6 8 watts per square foot per hour. In total, the associated cost of operating the building is roughly $4.30 per square foot. This is within an acceptable range, based on the operation cost rates of other buildings on campus, of the $4.40 per square foot value. 21

The Salk Hall Addition demands a large amount of hot water for the reheat coils in the terminal supply units. If the mechanical system utilized waste hot water, it could be distributed to the terminal reheat coils which would ultimate yield an increase in energy savings. One design issue that the Salk Hall Addition may run across is a lack of added capacity in case of future expansion or a change in the building program. The system currently provides an added 1000 [CFM] to the peak simulated demand. This simulated demand does not include duct losses and this fact could become problematic if extra fume hoods or biological safety cabinets are added to the building s program. 22