Community Meeting US 101/Peninsula Avenue Interchange Project JUNE 25, 2015

Similar documents
FREEWAY MAINLINE FAIR SHARE WEEKDAY PM PEAK HOUR

SR-2 Freeway Terminus Improvement Project

NORTH, NORTH REDWOOD BOULEVARD CORRIDOR STUDY

4.1 Build Alternative 1 Construction Phasing

4/8/2015 Item #10D Page 1

PROPOSED IMPROVEMENTS

WHAT IS THE PURPOSE OF THE OPEN HOUSE?

Route 7/15 Norwalk. Route 7/15 Norwalk Project Project Advisory Committee Meeting #5. Wednesday, November 14 th, Norwalk City Hall

ARGENTA TRAIL (CSAH 28/63) REALIGNMENT SOUTH PROJECT (CP 63-25)

Boster, Kobayashi & Associates 59 Rickenbacker Circle Office: (925) P.O. Box 2049 Fax: (925) Livermore, CA

ECR. el camino real master plan. settings and opportunities. The City of San Mateo SMWM. Adopted by the San Mateo City Council September 18, 2001

Municipality of Anchorage. Community Council Survey Capital Projects Needs Ranking Survey (ALPHABETICAL) Airport Heights

US 95 Phase 2B/5 Open House

BURLINGAME BAYFRONT SPECIFIC PLAN

HILLSDALE STATION AREA PLAN COMMUNITY WORKSHOP 2 City of San Mateo

Iowa 100 Extension Project Visualizations for Design and Public Involvement ASCE Transportation Conference November 6, 2013 Ames, Iowa

Interstate 229 Major Investment Study Exit 9 Benson Rd Sub-Study

SOUTH SAN FRANCISCO GATEWAY STUDY

Project Overview. Fairfax County Parkway Widening Fairfax County. Get Involved. Public Information Meeting. Contact Information

DETROIT RIVER INTERNATIONAL CROSSING STUDY. County of Essex. June 4, 2008

The Border Transportation Partnership

Rt. 29 Solutions Project Delivery Advisory Panel. January 7, 2016

2040 Long Range Transportation Plan

Proposed Capital Improvement Program and Capital Budget FY & FY

PREPARED FOR: PLATTEVIEW ROAD CORRIDOR STUDY EXECUTIVE SUMMARY

SUBJECT: Program Manager s Report for January - February 2018

EXECUTIVE SUMMARY. Introduction

2017 Investment in Infrastructure Expo February 28, 2017 Jason Jonas, P.E. Public Works Director

Kurt G. Larson, PE, PTOE

ALTERNATIVES. NCDOT made an early decision to first determine how to build the project (construction method) followed by what to build (alternatives).

Green Streets and Green Infrastructure Planning A Tale of Two Cities: San Mateo and Emeryville

Fifth and Detroit Street Design May 2017 Capital Improvements Committee. DOWNTOWN Street Design

Debra Larson and Director Malcolm Dougherty

City of Waukee, Iowa Capital Plan PROJECTS BY DEPARTMENT

Note: Red text denotes additions/ changes from Dec 23, 2009 draft Page 1 of 12

4 LAND USE DESIGNATIONS

Puget Sound Gateway Program Team. Phase 1, SR 509 Completion Project NEPA Re-evaluation

'EX~hnib;ritrA~~o r

International Blvd. TOD Plan Public Workshop #1

510 Highways, Streets & Roads Comprehensive Plan Section 510

New Stanton Project Update July 3, 2012

The Lincoln Neighborhood Corridor Plan. The LiNC

I-4 Beyond the Ultimate. Florida Transportation Builders Association February 9, 2018

I. DESCRIPTION OF PROPOSED ACTION... 1 A. General Description... 1 B. Historical Resume and Project Status... 2 C. Cost Estimates...

North Loop Paving. December 18th, Street Reconstruction Project. Forrest Hardy, Transportation Planner Minneapolis Public Works

Physical Connectivity Do not have structures that physically divide the community more than it is divided today

UPDATE ON: Water Quality Enhanced BMPs / Landscaping. January 2017

MassDOT Highway ACEC State Markets Conference April 4, Jonathan Gulliver, Highway Administrator

Meeting Purpose: Date and Time: Location: Attendance: Handouts:

Memorandum CITY OF DALLAS. Riverfront Boulevard Design From Continental Avenue to Cadiz Street

I-75/I-475 Interchange Upgrade Project Informational Meeting Tuesday, July 27, 2010

Index to Projects by Project Name

Dumbarton Transportation Corridor Study. Stakeholder/Public Meetings August 16, 2017

Index to Projects by Project Name

Getting Started On Your Green Infrastructure (GI) Plan

North Carolina Department of Transportation Project Development and Environmental Analysis Branch

DRAFT Civic Center Station Area Plan. Executive Summary

112th Avenue Light Rail Options Concept Design Report JUNE 2010 PREPARED FOR PREPARED BY TBG PGH

Isabel Neighborhood Plan: Alternatives

Welcome. Tina Fischer. East Tampa Area Community Working Group September 25, Collaborative Labs, St. Petersburg College

Exhibit A. SH 161 RTC Work Program of New Projects. Collin County

SH 199 Corridor Master Plan. Community Meeting No. 2 May 31, 2017

Dumbarton Transportation Corridor Study

BURTON STATION STRATEGIC GROWTH AREA PLAN UPDATE JANUARY 25, 2018 PUBLIC MEETING

DETROIT RIVER INTERNATIONAL CROSSING STUDY. Walpole Island First Nations Meeting December 13, 2007

Lake Hazel/Gowen Relocation Alignment Study Report

Reconfiguration of The Six Points Interchange. Community Update #2 June 18, 2014

Innovative Worldwide VE Case Studies & How Cultural Values Impact Creativity

September 28, 2017 Wentworth Avenue (CR 8) Sidewalk Improvements Open House

Project Overview & Summary of Existing Conditions

FDOT/FTBA Construction Conference Work Plan

Case Study: City of San Mateo

METRO Gold Line BRT CMC Meeting

Welcome. South Seminole Heights Civic Association, Inc. Tampa Interstate Study Supplemental Environmental Impact Statement.

Section 4.11 Traffic and Transportation 4.11 TRAFFIC AND TRANSPORTATION

Capital Projects in and near Odenton Town Center

3.0 Existing Corridor Infrastructure

PROJECT UPDATE BON AIR ROAD BRIDGE REPLACEMENT AND MAGNOLIA AVENUE WATER QUALITY FACILITIES

Update on the Bayfront Canal Bypass Project. Recommendation This an informational item only. No City Council action is required at this time.

2900 Steeles Avenue East at Don Mills Road in the Town of Markham

2014 PSPE Philadelphia Chapter Outstanding Engineering Achievement Award Nomination

Places29: List of Implementation Projects

Optimize. Innovate. Deliver. Engineering the Future of Bus Rapid Transit

Dumbarton Transportation Corridor Study. JPB Board of Directors September 7, 2017

Princess Anne Road. Phase VII (CIP 2-195) Citizens Information Meeting

MEMORANDUM. I2 District Downtown Parking Overlay District 24,000 square feet /.55 acres. Industrial Employment District North Loop Small Area Plan

PUBLIC HEARING. Thursday, December 14, 2017 FDOT Urban Office 2198 Edison Avenue Jacksonville, FL 32204

Attachment A PROJECT STATUS REPORT Page 2 TABLE OF CONTENTS 1. Active Projects... 5 SOUTHWEST COUNTY... 5 a. Caldecott Fourth Bore Project (1001/1698)

Public Information Centre #1

Whitehurst Freeway Deconstruction Feasibility Study

Rt. 29 Solutions Project Delivery Advisory Panel. December 3, 2015

Hunt Highway CELESTE PEMBERTON, CFM, CPM PINAL COUNTY CARLOS SANCHEZ SORIA, PE T.Y. LIN INTERNATIONAL

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Projects

Welcome. Northern Segment of Hwy 100 I-90 to South of Madison Street Meeting Goals:

124 Subarea Visions. Vision Plan. A. Nelessen Associates, INC I Visioning I Planning I Urban Design

AGENDA ACTION ITEMS INFORMATION ITEMS

5.0 WAYFINDING STREETSCAPE DESIGN MASTER PLAN 55

Capital Projects impacting Odenton Town Center

NORTH-SOUTH CORRIDOR STUDY EXECUTIVE SUMMARY. Executive Summary

Project Study Report (Project Development Support) for Placer Parkway

Transcription:

Community Meeting US 101/Peninsula Avenue Interchange Project JUNE 25, 2015

Project Team Gary Heap, Engineering Division Manager Tracy Scramaglia, Senior Engineer Ramesh Sathiamurthy, AECOM Peter DeStefano, AECOM Support Staff Ken Chin, Project Manager II Trieu Tran, Assistant Engineer

2004-2007 Initiation of US 101 Poplar/Amphlett Corridor Study Identified need for safety improvements, but no support for ramps at Peninsula Avenue 2009-2012 City retained traffic consultant Short term solution: Poplar Corridor Safety Improvement Project Long term solution: Southbound freeway ramps at Peninsula Avenue 2014-2015 SMCTA retained engineering consultant (AECOM) Caltrans approved the PSR-PDS in May 2015 to advance the project into the PA&ED Phase

Poplar Corridor Safety Improvement Project Status Update Present: Future: Final Design Completed Begin Construction Spring 2016 End Construction Summer 2016

Peninsula Avenue Interchange Project Identified as a long term solution for the interchange ramps Project will add ramps for southbound US 101 at Peninsula and close ramps at Poplar Present: Future: Project Study Report- Project Development Support (PSR-PDS) approved by Caltrans PA&ED Approval - 2017 Begin Design - 2018 Begin Construction 2022 End Construction - 2024

Peninsula Ave Why a Long Term Solution at Peninsula? Project Need: Safety: Non-standard ramp geometry at Poplar Avenue Provide Standard Interchange Configuration: Consolidate NB & SB ramps at Airport & Peninsula Peninsula is designed to handle future traffic from/to the freeway 5-foot shoulders & no street parking No driveways Two lanes in each direction

Peninsula Ave Peninsula Avenue Interchange Alternative 1 Tight Diamond Configuration Poplar Creek Golf Course N Bayshore Blvd To San Jose Off-Ramp On-Ramp N Idaho St Remove Ramps City of San Mateo N Humboldt St City of Burlingame San Mateo High School

Peninsula Avenue Interchange Alternative 1 Tight Diamond Configuration Off-Ramp to Peninsula Ave Typical Cross Section Local Street

Peninsula Ave Peninsula Avenue Interchange Alternative 2 Partially Spread Diamond Configuration Poplar Creek Golf Course N Bayshore Blvd To San Jose Off-Ramp On-Ramp N Idaho St Remove Ramps City of San Mateo N Humboldt St City of Burlingame San Mateo High School

Peninsula Avenue Interchange Alternative 2 Partially Spread Diamond Configuration Off-Ramp to Peninsula Ave Typical Cross Section Local Street

Peninsula Avenue Interchange Peninsula Avenue Typical Sections Existing Typical Section Proposed Typical Section

Alternatives Summary Alternative 1 has a smaller footprint and potentially, less impacts Alternative 2 provides better intersection spacing between the ramps and North Bayshore Blvd Preliminary Capital* Cost for Alt 1: $47M Preliminary Capital* Cost for Alt 2: $61M * Construction + Right-of-Way + Utilities (2015 Dollars)

Caltrans Process Project Initiation Document (PID) Phase (Completed) Project Approval & Environmental Document Phase (PA&ED) Final Design (PS&E) Bid Advertisement Begin Construction

Schedule Jan 2016 Jan 2018 2 years Jun 2018 Dec 2021 Jun 2022 Jun 2024 3.5 years 2 years Environmental (PA&ED) Design & ROW (PS&E) Construction

Next Steps Obtain Funding for the PA&ED Phase Begin PA&ED Traffic Forecasting and Operational Analysis Evaluate Design Alternatives Environmental Studies Public Outreach Project Approval Begin Final Design

Questions and Updates Tracy Scramaglia Senior Engineer (650) 522-7316 tscramaglia@cityofsanmateo.org www.cityofsanmateo.org/peninsula