SUNBRIDGE PARKWAY PRELIMINARY DESIGN STUDY. November 30, 2017

Similar documents
SUNBRIDGE PARKWAY PRELIMINARY DESIGN STUDY. Board of County Commissioners Public Hearing

Agenda. Introductions and Overview Study Purpose Study Approach Key Analysis Components Study Context Development Activity ( )

Frequently Asked Questions. What is Sunbridge?

East Central Florida Corridor Task Force Study Area

SH 199 Corridor Master Plan. Community Meeting No. 2 May 31, 2017

I-4 Poinciana Parkway Connector Project Development and Environment (PD&E) Study. OCX Board Meeting

AASHTO SUBCOMMITTEE ON DESIGN. June 15, 2006 MARK ROBINSON, P.E. DISTRICT 5 INTERSTATE PROGRAM MANAGER FLORIDA DEPARTMENT OF TRANSPORTATION

Figure 5. Previously Identified Viable Corridors

Gadsden County Planning Commission Agenda Request

FDOT/FTBA Construction Conference Work Plan

open public hearing and allow public comment request to continue LPA public hearing to January 16, 2014 at 10:30 am

ORANGE COUNTY IMPLEMENTING THE FOUR C s

I-4 Beyond the Ultimate. Florida Transportation Builders Association February 9, 2018

Pond Siting Report Update

Osceola County Board of County Commissioners 1 Courthouse Square, Suite 1100 Kissimmee, FL

Old Brick Township DRI Recommendation Report

Leduc Industrial Outline Plan SE W4

Pine Island Road Corridor Master Plan

FEGN Update Goals and Objectives

DOMINION BOULEVARD CORRIDOR STUDY AND ECONOMIC DEVELOPMENT STRATEGIC PLAN A MODEL FOR CHESAPEAKE S FUTURE

ARGENTA TRAIL (CSAH 28/63) REALIGNMENT SOUTH PROJECT (CP 63-25)

Northeast Connector Expressway Extension Concept, Feasibility and Mobility Study Environmental Advisory Group Meeting #1 June 26, 2018

Public Hearing. Charlotte County-Punta Gorda MPO - Meeting Rooms A and B March 14, open house at 4 p.m., formal presentation at 5 p.m.

PD&E STUDY SR 9/I-95 FROM SOUTH OF SR 870/COMMERCIAL BOULEVARD TO NORTH OF CYPRESS CREEK ROAD FM # ETDM 14222

PUBLIC HEARING. Thursday, December 14, 2017 FDOT Urban Office 2198 Edison Avenue Jacksonville, FL 32204

Scope of Services. River Oaks Boulevard (SH 183) Corridor Master Plan

Iowa 100 Extension Project Visualizations for Design and Public Involvement ASCE Transportation Conference November 6, 2013 Ames, Iowa

WELCOME TO OPEN HOUSE TWO November 28, 2018

Photo by Carlton Ward Jr. Executive Summary

Better Cycling. The City will update the cycling master plan (London ON Bikes) based on the approved BRT network.

Project Overview. Get Involved. Public Information Meeting. Contact Information

WELCOME CPT CORRIDOR AREA PROJECT BACKGROUND BROOKSIDE BLVD. The objectives of the CPT Functional Design Study included:

DRAFT MAP AMENDMENT FLU 04-4

Gold Line Bus Rapid Transit Transit Oriented Development (BRTOD) Helmo Station Area Plan

WELCOME! 8 8:30 6: TH STREET IMPROVEMENTS. Open House. Presentation & Q&A

Poinciana Parkway Extension Project Development & Environment Study

Municipal Class EA Study Public Information Centre No. 1 December 13, :00 pm 7:00 pm. Please sign in so we can keep you updated on this study

ORANGE COUNTY AT A GLANCE

We d like to thank you for attending this Wekiva Parkway Section 8 Preliminary Design Update hosted by the Florida Department of Transportation.

Richmond Road Complete Street Meeting #1, April 25, 2016

North Ranch Master Plan

Rapid Transit Implementation Working Group

Mitchell Ranch South MPUD Application for Master Planned Unit Development Approval Project Narrative. Introduction

9 th Street Sub Area Plan

Selected Area Study. Vision Plan Draft

BOISE, IDAHO COUNCIL WORK SESSION AGENDA September 19, :00 PM City Hall - Council Chambers

TRANSPORTATION ELEMENT GOALS, OBJECTIVES, AND POLICIES

South Dakota 100 Corridor Preservation

Boeckman Road Extension

DRAFT SECTION 4(f) EVALUATION INTERSTATE 73 FEIS: I-95 to I-73/I-74 in North Carolina

Section4 Design Vision & Implementation Plan

Fairfax County Parkway (Route 286) Widening Project

Bostwick Road. Municipal Class Environmental Assessment. October 13, City of London. Bostwick Road Municipal Class Environmental Assessment

March 21, 2018 ALCA Meeting. March 21, 2018

Northeast Anthony Henday Drive Manning Freeway to Whitemud Drive Welcome to this Construction Information Session

Tennessee Stormwater Management Program. Stormwater Management Site Assessment and Inventory Checklist. Quick Check o Vicinity Map within Watershed

COLLIER BOULEVARD (CR 951) CORRIDOR

Welcome. Northern Segment of Hwy 100 I-90 to South of Madison Street Meeting Goals:

Potential Green Infrastructure Strategies May 6, 2015 Workshop

Cobb County Design Guidelines Mableton Parkway & Veterans Memorial Highway Community Design Workshop January 12, 2017

St. Clair Avenue West Area Transportation Master Plan

5-E ====================================================== -==-= ====================================================

Poinciana Parkway Southport Connector Project Development and Environment (PD&E) Study

Bostwick Road. Municipal Class Environmental Assessment. Public Information Centre #2 June 14, City of London

Public Information Centre #1

This page left intentionally blank.

ROAD CONSTRUCTION. 36 June 2014 ROADS&BRIDGES

Purpose of Tonight s Meeting

Boca Raton II Tri-Rail Station PD&E Study and 30% Documents Public Kick-Off Meeting. August 29, 2017 Spanish River Library

Designing for Sustainability: A Consultant s Perspective

Gratigny Parkway East Extension Project Development & Environment (PD&E) Study

Master Environmental Servicing Plan & Secondary Plan

Northern Branch Corridor SDEIS March 2017

At first Work Session on October 22, At second Work Session on November 19, At third Work Session on December 3, 2015

I-494 Rehabilitation Project SP (I-394 to Fish Lake Interchange) June 2014 Section 4(f) De Minimis Determination

Narcoossee Roadway Corridor

EXECUTIVE SUMMARY. Introduction

Route 347. New York State Department of Transportation Region 10, Long Island. THE GREENING of ROUTE 347

2.0 AREA PLANS. Lakeside Business District. Lakeside Business District Land Use Categories:

OP Council Resolution June 16, Planning and Development Services

M E M O R A N D U M July 27, 2018

Northwest Corridor LRT Line to Irving/DFW Public Meeting No. 1 Project Overview

NORTHEAST RIVER CROSSING FUNCTIONAL PLANNING STUDY

PRELIMINARY DRAINAGE REPORT LATHAM 200 MMSCFD GAS PROCESSING PLANT

Present. and. Future

Highway 427 Industrial Secondary Plan Area 47 Schedule C Class Environmental Assessment For Arterial Roadways

INTEGRATING PROTECTION OF ECOSYSTEM SERVICES INTO THE PLANNING PROCESS IN FLORIDA

O l so n M e morial Highway, S t e , G o l d e n V a l l e y, MN Delano Laketown Homes Concept Plan

Mavis Road Class Environmental Assessment

McKay Road Interchange and Salem / Lockhart Crossing

STORMWATER REPORT FOR WALMART SUPERCENTER STORE # SIOUX FALLS, LINCOLN COUNTY, SOUTH DAKOTA BFA PROJECT NO

Introductions Project overview Scope of work Schedule. Agenda. Community/Stakeholder Input Process Discussion Summary/Next Steps

Community Engagement Committee Meeting #1 December 10, :30pm-8:30pm

MALLETTS BAY INITIATIVE

1.0 INTRODUCTION 1.1 TH 14 WEST STUDY AREA Project Description Functional Classification Purpose of the Project

2 STATUTORY PUBLIC MEETING AND INFORMATION REPORT FOR PUBLIC MEETING ON AMENDMENT NO. 62 TO THE YORK REGION OFFICIAL PLAN

Waverley West B Secondary Planning Process. Open House South Pointe School April 25, 2018

Hurontario/Main Street Corridor Master Plan Mississauga and Brampton Building a new and integrated vision for the corridor

Queensborough Eastern Neighbourhood Node. Community Open House

PREPARED FOR: PLATTEVIEW ROAD CORRIDOR STUDY EXECUTIVE SUMMARY

Transcription:

SUNBRIDGE PARKWAY PRELIMINARY DESIGN STUDY November 30, 2017

Agenda Introductions and Overview Study Purpose Study Approach Key Analysis Components Study Context Existing Conditions Corridor Constraints Recommended Improvement Concept Public Engagement & Schedule Discussion

Study Purpose Identify Context Sensitive & Cost Feasible Improvements Document Project Need Balance Needs of All Users Safety Mobility Comfort Automobiles Pedestrians Cyclists Freight Transit

Study Approach and Key Analysis Components

Study Context Sunbridge Parkway Preliminary Design Study Aerospace Parkway/Dowden Road to the Orange/Osceola County Line Associated Projects New Interchange on State Road 528 Segment 1 Sunbridge Parkway Future Connection to Cyrils Drive Extension in Osceola County

Development Activity Existing and Proposed Developments Sunbridge Planned Development Camino Reale Starwood Northeast District Lake Mary Jane Rural Settlement Narcoossee Community Developments

Existing Conditions Deseret Ranch 60 year old cattle ranch/agricultural operation One of the largest calf-cow operations in the U.S. 45,000 calf producing beef cattle Predominately pasture lands or undeveloped City of Cocoa Existing water supply wells UTILITIES

Existing Drainage Two Water Management Districts South Florida Water Management District St. Johns River Water Management District Two Primary Receiving Water Bodies Econlockhatchee River Lake Okeechobee via Wetlands and the Kissimmee River

Environmental Considerations Environmental Lands Stewardship Program Compliance Avoid/Minimize Wetland Impacts Maximize Use of Least Valuable Environmental Lands Protect Critical Wildlife Links

Corridor Has Undergone Pre-Permitting Data Collection and Analysis Hydrologic and Natural Features

Existing Environmental Analysis Details Potential for Three Wildlife Crossings Containing One Wet and Two Dry Crossing Structures Each (Segments 1, 3b &4) Species of Special Concern American Alligator Eastern Indigo Snake Florida pine snake Gopher Tortoise Florida Burrowing Owls Florida Sandhill Crane Southeastern American Kestrels Wood Storks Sherman s Fox Squirrels Strategic Habitat

Traffic Analysis Average Annual Daily Traffic (AADT) 2025 - Opening Year Traffic Volume Northern Project Limit to Innovation Way South - 16,800 Innovation Way South to County Line 24,300 RR Crossing 2040 - Design Year Traffic Volume Northern Project Limit to Innovation Way South 39,700 Innovation Way to County Line 36,500

Drainage Urban Sections Curb and Gutter Stormwater conveyed to ponds Stormwater treatment takes place in the ponds RURAL SEGMENTS Rural Sections Roadside Swales Stormwater treatment takes place in the swale

Rural Roadway Section Segments 2, 3a and Part of 3b 133 ROW Phase 1 Initial 2-Lane Rural

Urban Roadway Sections Segments 2, 3a and Part of 3b 133 ROW Phase 2 Interim 2-Lane Urban Conversion 133 ROW Ultimate 4-Lane Urban Expansion

Rural Roadway Sections Segment 4 and Part of 3b 160 ROW Phase 1 Initial 2-Lane Rural 160 ROW Ultimate 4-Lane Rural Expansion

Estimated Cost Estimated Constructed Roadway Cost Aerospace Parkway/Dowden Road to Orange/Osceola County Line Four Lane Ultimate Configuration Does Not Include the Cost of Mitigation Total Project Cost: $49,024,550.52

Public Engagement Newsletters Website Community Meeting LPA/BCC Public Hearings www.orangecountyfl.net/traffictransportation/sunbridgeparkway

Public Engagement Schedule Public Involvement Activity Local Planning Agency Work Session Local Planning Agency Public Hearing Board of County Commissioners Public Hearing Target Dates December January March www.orangecountyfl.net/traffictransportation/sunbridgeparkway

Contact Information Blanche Hardy, P.G. Jeffrey J. Newton, P.E. Orange County Project Manager Consultant Project Manager Community, Environmental & Donald W. McIntosh Development Services Associates, Inc. Transportation Planning Division 2200 Park Avenue North 4200 South John Young Parkway Winter Park, Florida 32789 Orlando, Florida 32839 jjnewton@dwma.com blanche.hardy@ocfl.net (407) 644-4086 (407) 836-0257 www.orangecountyfl.net/traffictransportation/sunbridgeparkway

SUNBRIDGE PARKWAY PRELIMINARY DESIGN STUDY www.orangecountyfl.net/traffictransportation/sunbridgeparkway