Jill Stachura STORMWATER BMP AND STREAM RESTORATION IN A CITY PARK. October 2013 Southeast Stormwater Association Annual Conference, Charlotte, NC

Similar documents
Lilburn, GA STORMWATER BMP AND STREAM RESTORATION IN A CITY PARK. July 2013 Jill Stachura

Stormwater BMP and Stream Restoration in a City Park. Jeff Herr P.E., D.WRE Jill Stachura

The use of low head weirs to. perennial streams with their floodplains:

Stormwater Regulations & Considerations Morse Study Area. Pam Fortun, P.E. CFM Senior Stormwater Treatment Engineer Engineering Services Division

Stream Restoration: Working with Nature?

Stream Restoration: Working with Nature? Greg Jennings, PhD, PE

Tentatively Selected Plan within Harlem River, East River and Western Long Island Sound Planning Region. First Level Costs. Federal Non-Federal Total

Guiding Landowners in Stream Restoration. The Science, Practice & Art of Restoring Native Ecosystems 2015

Retrofit of the Gwinnett County DWR Facility Using Low Impact Development Practices SESWA 2012 Annual Conference October 19, 2012

Craven Street Stormwater Improvement Projects

URBANIZED STREAM CORRIDOR: COMMUNITY APPROACH TO ADDRESS EROSION

Do you know there your MS4 is?

Swan Creek Urban BMP Inventory and Assessment. Jeff Grabarkiewicz, Kari Gerwin, Ann-Drea Hensley TMACOG, Lucas SWCD/Engineers, and Partners

COMMUNITY DEVELOPMENT DEPARTMENT POLICY DRAINAGE FOR RESIDENTIAL PROJECTS WITH ONE OR TWO UNITS REVISED JANUARY 4, 2018

SOP 6: Erosion and Sedimentation Control SOP 6: EROSION AND SEDIMENTATION CONTROL

6.5 Lakewood Gulch. Basin Snapshot

Old Mill Community Association Bioretention Facility

3/7/2013. Compliance & Sustainability

KENT COUNTY STORMWATER MAINTENANCE DISTRICT STORMWATER BMPs MAINTENANCE TASKS AND RESPONSIBILITIES GUIDANCE DOCUMENT BIO-RETENTION FACILITIES

The Benefits and Challenges Associated with Green Infrastructure Practices

Working Group Meeting

STREAM BANK STABILIZATION THORPS MORTIMER RECREATION AREA Grandfather Ranger District SITE LOCATION & DRAINAGE AREA

Action Plan for Retrofitting Structural BMPs

Low Impact Development in the Transportation Environment: Lessons Learned in North Carolina

North Branch of Cypress Creek Ecological Restoration: A Comprehensive Approach to Stream Restoration

Evaluating Low Impact Development Practices for Stormwater Management on an Industrial Site in Mississippi

Monica Smith, PE President Robinson Engineering Company

Can Urban Redevelopment Restore Aquatic Resources

Stormwater Retrofitting: The Art of Opportunity. Presented by the Center for Watershed Protection

Evaluating Urban Stormwater Retrofits in the SE US Coastal Plain

Severn River Sub-Watershed: BMP 09-Retrofit

Chapter 3 Site Planning and Low Impact Development

City of Fort Worth. December 1, 2004

STREAM BUFFERS

Bioretention cell schematic key

A Review of Green Infrastructure Projects Implemented in the Grand Traverse Region

BE WATER WISE. Managing Your Onlot Stormwater. Sept. 23, 2006 Watershed Weekend

Building Green: An Update on Atlanta's Green Infrastructure Approach

PROJECT SCOPE OF WORK CITY OF TOWN AND COUNTRY STORMWATER PROGRAM

SUPPORTING DOCUMENT STORMWATER POLLUTION PREVENTION PLAN (SWPPP) NARRATIVE

Managing Stormwater within the Road Right-of-Way: An Urban NAI Approach

Construction Progress Report

Green Infrastructure Modeling in Cincinnati Ohio. Small Scale Green Infrastructure Design Using Computer Modeling

Melissa Bernardo Hess, PE, CFM February 18, 2016

Outfall Retrofit Feasibility Study

SECTION 6. Routine Maintenance Activity Details

Part 4: CRS Stormwater Management Activity (450) and Urban Flooding Best Practices

Urban Stormwater Retrofit Program Highlights

LOUISIANA STATE UNIVERSITY COMPREHENSIVE & STRATEGIC CAMPUS MASTER PLAN. APPENDIX G - Stormwater Study Findings & Stormwater Solutions

PICTURE CANYON Planning Riparian-Wetland Refugia in an Urban Setting

Problem Understanding

2014 HDR 2014 Architecture, HDR, Inc., all all rights reserved. reserved.

Erosion Control for Home Builders in the. City of Jacksonville

2.1.4 Roof Downspout Rain Gardens

Urban Stormwater Management. Rebecca Leonardson Rui Teles Brooke Ray Smith

WEFTEC.06. ** City of Caldwell, Idaho

FirstLight Power Shoreline Management Manual Sustainable Shoreline Designs: From Long Island to Lake Erie Webinar Series

Funding Assistance to Stormwater Utility Fee Payers for Stormwater Solutions and Incentives. Danny Bowden City of Raleigh Stormwater Utility

Tips for Maintaining and Enhancing Stormwater Management Areas

Structural Storm Water Best Management Practices (BMPs)

Urban Water Management (ESRM 311 & SEFS 507) Cougar Mtn Regional Wildland Park & Lakemont Blvd, Bellevue WA

Stormwater Management at The University of New Orleans

When planning stormwater management facilities, the following principles shall be applied where possible.

CHAPTER 102 REQUIREMENTS CRITCAL STAGES DURING CONSTRUCTION ACTIVITIES

12/7/2007. Christopher B. Burke Engineering West, Ltd Aux Sable Creek Watershed Plan Update 1

Checklists. Project Name: Location: File Number: Date of Submittal: Reviewer: Date: Applicant: Contact Name: Phone Number:

Sustainable Storm Water Management

Two Sides of the Green Infrastructure Coin. Jaren Hiller, PE, LEED AP Nathan Guequierre

Storm Water Quality and Shoreline Restoration Improvements - Grant Funding Request City of Mound Carlson Park Bolton & Menk Project No.

Example Stormwater Control Plan For a Residential Subdivision Project. Whispering Pines Lane Anytown, USA. February 21, 2018

Types and Basic Design of Post-Construction BMPs

The Art and Science of Stormwater Retrofitting

Chesapeake Bay Pollution Reduction Plan

Inventory and Assessment of Stormwater Infrastructure

RECONNECTING A COMMUNITY TO THE CREEK

Banking on Natural Fibers Products made from coir and jute play a key role in stabilizing a restored stream for a commercial stream mitigation bank.

ENVIRONMENTAL STEWARDSHIP, COMMITMENTS, AND COMPLIANCE

Beyond Rain Gardens Advancing the Use of Compost for Green Infrastructure, Low Impact Development, & Stormwater Management

continues in the watershed, additional flood control and water quality / natural system improvements may be required in the future.

Riparian Buffer on the Bushkill Creek. Policies

Fixer Upper. MS4 Post-Construction and Redevelopment. Anthony Betters, CSI City of Waco Environmental Storm Water Compliance

Kickapoo Woods Restoration Plan

STORMWATER MANAGEMENT CODES ANALYSIS RICHLAND COUNTY, SC SITE PLANNING ROUNDTABLE

WET PONDS INSPECTION & MAINTENANCE CHECKLIST

FURNEAUX CREEK 5 CHANNEL

WETLAND SOD u Bare Root Wetland Plants u Deep Rooted Willows u Coir Logs u Native Trees & Shrubs u Habitat Islands u Custom Growing

City of Columbia BMP Manual. Volume Calculation Tool and Examples

319 Grant: Baker Creek & Centenary Creek Restoration Initiative

Stormwater Management Techniques WMPF LAND USE TRAINING INSTITUTE MARCH 14, 2018

WQ-23 MOUNTAINOUS AND STEEP SLOPE SITES

Erosion & Sediment Control Plan Application Form & Checklist

One County s Success in Linking Watershed Protection and Land Use Planning

Operations and Maintenance Plan

Inventory and Assessment of Stormwater Infrastructure

Use of Best Management Practices

An Update on the Mandated Stormwater Initiative Chesapeake Bay TMDL

KYTC and NFIP: Bridging Floodplain Management and Design KAMM CONFERENCE AUGUST 25, 2015

Homeowners Guide to Stormwater BMP Maintenance

POLE BRIDGE ROAD NEAR FIVE LOT FARM

ADOPTED CAPITAL IMPROVEMENT PROGRAM BUDGET ARROYO PROJECTS

Transcription:

Jill Stachura STORMWATER BMP AND STREAM RESTORATION IN A CITY PARK October 2013 Southeast Stormwater Association Annual Conference, Charlotte, NC

Project Location Gwinnett County, GA: Population: 825,000 Area: 437 sq. miles 1,300 miles storm drainage system 80,000 structures maintained Stormwater Utility income $32M/yr Brown and Caldwell 2

Watershed Improvement Program Watershed Assessment - 1999 Watershed Protection Plan - 2000 Watershed Improvement Plans (WIPs) 2001- present Project Implementation 2005 - present Brown and Caldwell 3

Gwinnett County Watershed Improvement Program Goals Meet Permit Requirements (NPDES, MS4, MNGWPD, TMDLs) Improve and Protect Water Quality Improve Aquatic Habitat Meet Water Quality Standards/ Designated Use [303(d) listed] Improve Natural and Urban Environment for the public s use Brown and Caldwell 4

Gwinnett County: Watershed Improvement Plans 2001 2010 Stream Walks BMP Inventory GIS WQ Modeling CIP Development BC completed WIPs for 60% of County ~ 300 sq. miles. Brown and Caldwell 5

Project Location Camp Creek 7 sq. mile drainage area at project site Within 100 yr FEMA floodplain (Zone AE) City owned property Greenway 303(d) listed for fecal coliform bacteria (urban runoff) Brown and Caldwell 6

Site Information Pre-Restoration 900 linear feet 30 foot wide channel with 8 to 12 foot vertical banks Railroad overpass just upstream Brown and Caldwell 7

Lilburn City Park Camp Creek Restoration Incised channel, no connection to floodplain (Rosgen F-5) Poor habitat Stream eroding into left bank and encroaching historic inert waste landfill and park facilities Steep, vertical banks - safety hazard to park patrons Debris jams throughout Brown and Caldwell 8

Pre-Construction Conditions Municipal complex (courts, police, etc.) On downtown square, high visibility Park has large greenspace, amphitheater, walking trails, playground, etc. Camp Creek flows along eastern border of parcel Camp Creek fenced off from park Five pipe outfalls; direct stormwater discharges to creek from 30 developed acres, no treatment Flooding problems in park Brown and Caldwell 9

Pre-Construction Monitoring Water Quality Sampling High bacteria, high TSS during storms, high nitrogen, high organic content Habitat Assessment Suboptimal Benthic macro-invertebrate assessment Poor Geomorphic measurements F-5, Incised, aggraded in places Debris jams Brown and Caldwell 10

Alternative 1 Priority 3 Stream Restoration Stabilize banks in place Create floodplain benches and reconnect to floodplain where feasible Remove concrete debris Revegetate Brown and Caldwell 11

Alternative 2 Priority 1 Stream Restoration Relocate stream into right floodplain Utilize old channel for bioretention treatment of 30 acres Remove invasives and revegetate Brown and Caldwell 12

Project Benefits Improved stream access to floodplain for water quality benefit Moved stream away from park facilities and landfill Enlarged park area and provides new amenity for patrons Combined several storm sewer outfalls Bioretention stormwater treatment (3 cascading cells, fieldstone outfall) for 30 acres Brown and Caldwell 13

Construction 150 days Substantial Completion (March July 2012) First built new channel, Camp Creek isolated from construction Removed plug and activated new channel Combined outfalls and built 3 cascading bioretention cells Plantings three phases Brown and Caldwell 14

Design & Construction - Stream C-5 Type Channel 975 linear feet 0.2% slope 2 stone cross vanes 5 stone J-hooks 2 log J- hooks 3 double stone J- hooks Toe wood/brush mattresses Brown and Caldwell 15

Stream Construction Cleared and flagged for new channel Roughed in new channel Brown and Caldwell 16

Stream Construction New Channel Existing Channel Brown and Caldwell 17

Stream Construction Log vane Scour log and toe wood/brush mattress Brown and Caldwell 18

Stream Construction Stone J-hook Completed Stone J-hook Brown and Caldwell 19

Completed Project New Channel Old Channel, Now Bio- Retention Brown and Caldwell 20

Completed Project Brown and Caldwell 21

Completed Project Old Channel, Now Bio- Retention New Channel Brown and Caldwell 22

Completed Project Brown and Caldwell 23

Design & Construction Bioretention BMP 5 outfalls total drainage area 30 acres Designed system of 3 cascading bioretention cells in old channel Underdrain system with valve (only to be used if needed) Engineered soil Outfall connection to stream Plantings Brown and Caldwell 24

Bioretention BMP Underdrain Installation Installing Engineered Soil Brown and Caldwell 25

Bioretention BMP Engineered soil Installed in 1-ft lifts, water in, no compaction Type 3 Rip-rap at outfalls Brown and Caldwell 26

Bioretention BMP Cobble and mulch installed Sod and Irrigation System Brown and Caldwell 27

Bioretention BMP Brown and Caldwell 28

Bioretention BMP Brown and Caldwell 29

Bioretention BMP Complete, planted BMP Fieldstone Outfall Structure Connection to creek Brown and Caldwell 30

Bioretention BMP during rain event Brown and Caldwell 31

End of Project Reach, looking downstream Brown and Caldwell 32

Post-Construction Plantings Maintenance LOMR Water Quality and Geomorphic Monitoring Construction Cost - $772k Brown and Caldwell 33

Flood of September 2009 Railroad Crossing Brown and Caldwell 34

Post Flood Repairs by City Railroad Crossing Brown and Caldwell 35

February 2011 - Preconstruction Railroad Crossing Brown and Caldwell 36

During Construction Installing Fieldstone Cross Vanes, Structures 1 and 2 Railroad Crossing Railroad Crossing Brown and Caldwell 37

April 2012 Construction Railroad Crossing Brown and Caldwell 38

June 2012 End of Construction Railroad Crossing Brown and Caldwell 39

January 2013 Near Bankfull Event Railroad Crossing Brown and Caldwell 40

Acknowledgements Gwinnett County Department of Water Resources City of Lilburn Georgia Development Partners Meanders River Restoration, Inc. Brown and Caldwell 41