REGISTRATION EXAMINATION, NOVEMBER 2016 CERTIFYING PLUMBER ANSWER SCHEDULE

Similar documents
REGISTRATION EXAMINATION, NOVEMBER 2011 CERTIFYING PLUMBER ANSWER SCHEDULE

REGISTRATION EXAMINATION, JUNE 2015 LICENSED PLUMBER QUESTION AND ANSWER BOOKLET. Time allowed THREE hours

CRAFTSMAN EXAMINATION, JUNE 2007 PLUMBING ANSWER SCHEDULE

REGISTRATION EXAMINATION, NOVEMBER 2017 TRADESMAN PLUMBER ANSWER SCHEDULE

CRAFTSMAN EXAMINATION, NOVEMBER 2009 PLUMBING QUESTION AND ANSWER BOOKLET. Time allowed THREE hours

REGISTRATION EXAMINATION, NOVEMBER 2017 TRADESMAN PLUMBER QUESTION AND ANSWER BOOKLET. Time allowed THREE hours

REGISTRATION EXAMINATION, NOVEMBER 2014 LICENSED PLUMBER ANSWER SCHEDULE

CRAFTSMAN EXAMINATION, JUNE 2007 PLUMBING QUESTION AND ANSWER BOOKLET. Time allowed THREE hours

REGISTRATION EXAMINATION, JUNE 2015 LICENSED PLUMBER ANSWER SCHEDULE

REGISTRATION EXAMINATION, NOVEMBER 2014 LICENSED PLUMBER QUESTION AND ANSWER BOOKLET. Time allowed THREE hours

CERTIFYING GASFITTER

REGISTRATION EXAMINATION, NOVEMBER 2011 CERTIFYING PLUMBER QUESTION AND ANSWER BOOKLET. Time allowed THREE hours

REGISTRATION EXAMINATION, JUNE 2013 CERTIFYING PLUMBER QUESTION AND ANSWER BOOKLET. Time allowed THREE hours

REGISTRATION EXAMINATION, JUNE 2015 LICENSED GASFITTER ANSWER SCHEDULE

REGISTRATION EXAMINATION, NOVEMBER 2016 LICENSED GASFITTER QUESTION AND ANSWER BOOKLET. Time allowed THREE hours

STUDENT NOTES Plan, size and layout sanitary pipe work and fixtures

REGISTRATION EXAMINATION, JUNE 2012 LICENSED GASFITTER QUESTION AND ANSWER BOOKLET. Time allowed THREE hours

Self-Containment Of Motor Caravans

AIR ADMITTANCE VALVES FOR DOMESTIC PROPERTIES Guidance Notes

CRU-S Series Stainless Steel Condensate Recovery Unit

Building Utilities 1 Plumbing and Sanitary Systems

Read Only Document Not For Distribution

AS/NZS :2015. Plumbing and drainage AS/NZS :2015. Part 4: Heated water services. Australian/New Zealand Standard

Village of Sloan Smoke Testing September 2017

-SAMPLE- Safety Inspection Checklist: Manufacturing

Read Only Document Not For Distribution

7 Hazard assessment 8 Worker participation 9 Hazard elimination and control

Pipe Sizing Table. Hydraulic Load Served (fixture units)

CRAFTSMAN EXAMINATION, NOVEMBER 2009 GASFITTING QUESTION AND ANSWER BOOKLET. Time allowed THREE hours

University of California, Davis Laboratory Self-Inspection Checklist

Australian/New Zealand Standard

APPENDIX L ALTERNATE PLUMBING SYSTEMS

PROPOSED NEW BUILDING

HEALTH AND SAFETY INDUCTION CHECKLIST

SUBCOURSE EDITION EN5155 US ARMY ENGINEER SCHOOL CLEAR WASTE SYSTEM STOPPAGES PLUMBING VI

2. Sanitary Plumbing General Installation Requirements

Automatic Water System Pump SERIES

LABOUR RATES FOR PLUMBING CONTRACTORS. A guide to the labour costs of plumbing works LABOUR RATES FOR PLUMBING CONTRACTORS

Special Requirements For Health Care Facilities

2009 IRC. and Fuel gas Provisions

Lecture : Introduction to building services I - Plumbing & Drainage Services 22 September 2016

HOME INSPECTION CHECKLIST

USER MANUAL INSTALLATION INSTRUCTIONS WARRANTY REGISTER

1 Exam Prep Plumber s Handbook Tabs and Highlights

CHAPTER VI BUILDING PLUMBING

Machine Guarding BLR B L B R usi ne B s u s si & n e L s e s g a & l L R e e g s a o l u r R c e e s s o(u 1rc 7 e 1 s 0) 1

BUILDING OR RENOVATING? Jonathan Smith. The Plumbers, Gasfitters and Drainlayers Board (PGDB) says: ASK TO SEE THEIR CARD

General Workplace Safety Checklist

The Plumbing Regulations 2008

Plumbing Lesson Four: Plumbing System Plan. Student Handouts

Roof Mount Solar Hot Water System USER MANUAL

ARCHIVED. Compliance Document for New Zealand Building Code Clause G4 Ventilation Second Edition. Prepared by the Department of Building and Housing

Chapter 12 HOT WORK OPERATIONS. Purpose:

Plumber Level 3 Rev. May 2011

installation INSTRUCTIONS

Patrick County Horizons Jeb Stuart Hwy. Stuart, Va

ENERSTORE. Vented Hot Water Storage System INSTRUCTIONS PLEASE LEAVE WITH HOUSEHOLDER

7 Hazard assessment 8 Worker participation 9 Hazard elimination and control

2009 IPC ,IMC Q &A ANDIFGC

Employee Health Protection

The following test is Continuing Education for: Master Plumbers, Journeyman Plumbers, UDC Plumbing Inspectors, and Commercial Plumbing Inspectors.

Level I Chapter 1 Worksheet

Inverted Bucket Steam Traps

1 Exam Prep Plumbing State Contractors Practice Exam 2

St. Vincent s Health System Page 1 of 6

Owner s Guide and Installation Instructions

Standard Assessment Procedure Instantaneous Waste Water Heat Recovery Systems Design Checklist for 'System A' Installation Configuration

ENGINEERING STANDARD FOR SANITARY PIPEWORK ORIGINAL EDITION JAN. 1995

SOLARGAIN HOT WATER User Manual

INSTALLATION OPERATION MAINTENANCE

Sanitary Drainage Systems

Owner s Guide and Installation Instructions

DOMESTIC & COMMERCIAL PLUMBING SYSTEMS FURTHER INFOMATION

HUDSON VALLEY COMMUNITY COLLEGE BUILDING EMERGENCY ACTION PLAN FOR OUTSIDE EMERGENCY ASSISTANCE: DIAL 911 TO REACH THE SARATOGA CTY POLICE & FIRE

Sample Safety Inspection Checklist

Clean Up Safely After a Disaster

Crisis Response Plan Greenwood Center 207 West Park Avenue Greenwood, MS

EMERGENCY RESPONSE PLAN FOR

Plumbing, Electrical, Air Conditioning and Gas Fitting Report

Handling or using the product improperly and in disregard of the instructions with this mark might result in serious bodily injury or death.

INSTALLATION MANUAL Roof Mount Solar Hot Water System

Is Sewer Gas Giving Your Customers the Wrong Impression?

SPEAKMAN GRAVITYFLO PORTABLE EYEWASH SE-4000

THE SEVERN. Installation Instructions for Freestanding Severn Stove with Boiler PERFORMANCE RATING

Australian/New Zealand Standard

SPEAKMAN GRAVITYFLO PORTABLE EYEWASH SE-4000

Commercial Processing Checklist Environmental Health Food Premises

Hot water safety in bathrooms

AS/NZS 4234:2008 AS/NZS

6.0 Emergency preparation

Medical Gas and Vacuum Systems

OPERATING AND MAINTENANCE MANUAL FOR PLATE HEAT EXCHANGER INDIRECT FIRED WATER HEATER. Electric Heater Company Base Model "BWXP"

Australian/New Zealand Standard

COMMERCIAL SOLAR SOLUTIONS

For further assistance or information contact our service desk. Congratulations for choosing a Solahart GreenGlo water heater

Fire Prevention in Healthcare Facilities. Leaders Guide and Quiz

El Segundo Fire Department. Unified Program (UP) Form CONSOLIDATED CONTINGENCY PLAN I. FACILITY IDENTIFICATION

CUSTOMIZED TEACHER ASSESSMENT BLUEPRINT PLUMBING. Test Code: 5924 Version: 01

Read Only Document Not For Distribution

Jennings Street School

Transcription:

No. 9195 REGISTRATION EXAMINATION, NOVEMBER 2016 CERTIFYING PLUMBER ANSWER SCHEDULE Plumbers, Gasfitters and Drainlayers Board, 2016. All rights reserved. No part of this publication may be reproduced by any means without the prior permission of the Plumbers, Gasfitters and Drainlayers Board.

ANSWER 1 Location Fire Collar required A 240.240.240 B 180.180.180 C 120.120.120 D 240.240.240 ANSWER 2 Total 4 marks Fixtures discharging to ORG Ensuite basin to ORG 40 mm needs vent. Ensuite basin to ORG 65 mm no vent req. Laundry to ORG 40 mm needs vent. Laundry to ORG 65 mm no vent req. Venting Main vent 50 mm diameter. Main vent location. Correct number of vents. Fixtures to FWG if used FWG receiving fixtures from another room. FWG receiving waste from kitchen sink/toilet. Fixture discharge pipes to FWG incorrect size. Main and branches Main drain not 100 mm. Branch drains not 65 mm. Ensuite toilet to outside no vent. Ensuite toilet to main line over 10 m needs vent (50 mm). Drainage plan altered Missed fixtures Total 9 marks Certifying Plumber 9195 Answers, November 2016 1

ANSWER 3 (a) When the developed length of the waste pipe from the crown of the water trap to the gully trap is greater than 3.5 m. When the waste pipe discharges to a combined waste pipe. Where any 32 mm discharge pipe to a gully trap has a vertical drop of greater than 1.5 m. All fixtures connected to a stack, except the highest connection (for lengths refer to table). (4 marks) (b) (i) When the stack receives discharge from three levels. (ii) 40 mm. (iii) Connect to the bottom of the discharge stack at no less than 300 mm below the lowest discharge pipe served. Connect at an angle of 45º. (2 marks) (iv) A relief vent is fitted to a waste stack to balance the air pressure in the stack, which prevents water trap seal loss. To allow an increase in the number of discharge units. (2 marks) (c) (i) 1:80 or 1.25% (ii) Ensures that any condensation or liquids will drain back into the sanitary plumbing and drainage system. Ensures that foul gases will travel upwards. (2 marks) Total 13 marks ANSWER 4 The vent from basin discharging to the gully is inter-connected with a vent from the drain. Foul gases from the drain could travel through the vent system and discharge at low level through the outfall of the basin waste pipe, causing a nuisance. Total 2 marks Certifying Plumber 9195 Answers, November 2016 2

ANSWER 5 Vent terminates outside the building Storage tank vented Vent 50 mm Max height 100 mm below WHB inlet to tank Pump inlet located in lowest point in tank Pump outlet min 25 mm diameter Valve train and pump correct Outlet connected to stack or drain at correct location Total 8 marks ANSWER 6 (a) Volume = R 2 L Section A: Volume = 0.016 2 3 = 0.00242 m 3 (½ mark) Section B: Volume = 0.0125 2 4 = 0.00196 m 3 (½ mark) Section C: Volume = 0.010 2 4 = 0.00126 m 3 (½ mark) Section D: Volume = 0.0075 2 3 = 0.000530 m 3 (½ mark) Section E: Volume = 0.0075 2 7 = 0.00124 m 3 (½ mark) Total volume = 0.00741 m 3 or 7.41 litres (1 ½ mark) (4 marks) (b) No. of grams = 1500 0.05 = 75 grams (2 marks) (c) The water contains organic matter or has a chemical composition that requires a greater dosage. Total 7 marks ANSWER 7 (a) Any ONE Replacing an open-vented water storage heater with a valve-vented water storage heater The cylinder is being relocated (b) Any ONE The replacement cylinder is a comparable open-vented water storage heater and is fixed in the same position, and uses the same pipework, as the replaced water storage heater The cylinder is being replaced with a gas-fired continuous flow water heater (and the wetback is to be disconnected) (c) 12 months. Total 3 marks Certifying Plumber 9195 Answers, November 2016 3

ANSWER 8 (a) Any THREE (1 mark each) Oxygen level. Presence of toxic or flammable gases. Temperature. Presence of dust. (3 marks) (b) Any FOUR (1 mark each) Two-way radio. Tripod and harness. Length of rope. Phone for contacting emergency services. Gas monitoring equipment. Timer. Record of entry and exit. Total 7 marks ANSWER 9 Location number Hazard rating Device type 3 M DCVA 12 H RPZ 14 H RPZ 15 H RPZ 16 M DCVA Total 15 marks ANSWER 10 (a) Action Minimise Eliminate Wearing safety glasses 3 Replacing a noisy machine 3 Completing work usually performed at heights on ground level 3 Providing screens around an area where welding is taking place 3 Using earmuffs or ear plugs 3 Fitting safety guards to machinery 3 Train staff in correct use of equipment 3 Using edge protection when working at heights 3 (4 marks) Certifying Plumber 9195 Answers, November 2016 4

(b) Any SIX (½ mark each) (i) Any of the following injuries or illnesses that require the person to have immediate treatment (other than first aid). The amputation of any part of his or her body. A serious head injury. A serious eye injury. A serious burn. The separation of his or her skin from an underlying tissue (such as degloving or scalping). A spinal injury. The loss of a bodily function. Serious lacerations. An injury or illness that requires, or would usually require, the person to be admitted to a hospital for immediate treatment. An injury or illness that requires, or would usually require, the person to have medical treatment within 48 hours of exposure to a substance. Any serious infection. (3 marks) (ii) WorkSafe New Zealand. (iii) Must be given by the fastest possible means in the circumstances. (iv) Any THREE (1 mark each) To assist an injured person. To remove a deceased person. It is essential to make the site safe or to minimise the risk of a further notifiable event. An action that is done by, or under the direction of, a constable acting in execution of his or her duties. An action for which an inspector or the regulator has given permission. (3 marks) Total 12 marks ANSWER 11 Valve train on cold inlet. Cold feed into bottom of HWC. Feed from HWC to CFWH from low level. Pump included in installation. Pump located correctly. Hot return to HWC at higher level. Tempering valve installed with mixed feed to outlets. TPR valve installed on HWC. System must operate. Total 8 marks Certifying Plumber 9195 Answers, November 2016 5

SECTION B 1. C 45 C. 2. D 1500 kpa. 3. B The latitude of the installation. 4. D The solar panel. 5. C An electric element that raises the water temperature slightly to start a thermo-syphon current. 6. C One heat source can be used for both potable and non-potable hot water supplies. 7. B A pump. 8. A When the bypass has the identical rating as the device being bypassed. 9. E When installed in a toxic environment. 10. D The building owner. 11. D 15 years. 12. E 50 years. Total 12 marks Certifying Plumber 9195 Answers, November 2016 6