Commissioning of a 1 MWe Supercritical CO 2 Test Loop

Similar documents
Supercritical Carbon Dioxide Brayton Power Cycle Test Loop - Operations Review

Design of a single-shaft compressor, generator, turbine of a small scale supercritical CO 2 system for waste heat to power conversion applications

Each burner shall be equipped with a Micro-Processor Based Burner Management Flame Safeguard and Parallel Positioning Control System.

HORIZONTAL FIRE TUBE BOILERS Piping (HVAC) Pumping Equipment (HVAC).

Design and Construction Standards SECTION PLUMBING EQUIPMENT

Experience In Motion. WXH and WXM Utility-Grade Multistage Ring Section Pumps

1.1 This section applies to air handling units for HVAC Systems.

MCF 500 CENTRIFUGAL FAN FOR AIR, FOR BIOGAS, LANDFILL AND NATURAL GAS

Midea VFD Centrifugal Chiller Technology

Summary of Comments (Washington Revisions November 7, 2000) Update November 27, 2000

Geothermal ORC Systems Using Large Screw Expanders

SECTION PLUMBING EQUIPMENT

Title: YALE OFFICE OF FACILITIES PROCEDURE MANUAL Chapter: 01 - Yale Design Standard Division: HVAC Standards

Monitoring Pump Performance with Vibration. Mitchell Stansloski, PhD, PE

PLACE FOR TITLE. Continuous Control of Lube Oil Water. Contamination Never get Surprised Again. Steve Locke. The Chemours Co.

High Performance Diesel Fueled Cabin Heater. Abstract

SECTION PLUMBING EQUIPMENT

CENTRIFUGAL PUMPS. STATE the purposes of the following centrifugal pump components:

High Plume Blowers Suggested Specification Section (Master Format 1996) Suggested Specification Section (Master Format 2004)

Mud-Motor Characterization

Fans: Features and Analysis

In-Situ Roll Balancing A Revolutionary Method for Improving Dryer Section Performance

Four ways of performance improvement. 4 ways to improve perf

B. Unit construction shall comply with ASHRAE 15 Safety Code, NEC, and ASME applicable codes (U.S.A. codes).

Horizontal Split Case Pumps Type U

Introduction to Fans. The Basics of Fan Principles and Terminology

HIGH PRESSURE DOUBLE CASE PUMPS

SAMPLE SPECIFICATION FOR RIELLO ARRAY MODULATING BOILER

A 2 K Active Magnetic Regenerative Refrigeration System for Remote Cooling

DELTA-TE III. Nozzle-mix line burner

Sentry G3 Machinery Protection Monitor

Multistage Centrifugal Blowers

End-Suction Centrifugal Pump

End-Suction Centrifugal Pump

SPECIFICATION DELETED SECTION CENTRIFUGAL HVAC FANS

YST PRE START-UP CHECKLIST

DIVISION FINNED WATER-TUBE WATER HEATERS

Multistage Centrifugal Blowers

Access Energy Thermapower Organic Rankine Cycle (ORC) Systems

CASE STUDY ANALYSIS OF CENTRIFUGAL FAN HIGH AMPLITUDE VIBRATION. Ken Singleton

2017 FSRUG Thermal Performance Feedwater Heater Troubleshooting FSRUG FWH Troubleshooting 1

1. Know your process. The following guidelines will help you navigate what can be a challenging and time consuming task.

we make air move Double Inlet Centrifugal Fans (Forward Curved) FBD Series (Square Outlet Metric Size)

PhiloWilke Partnership Addendum No. 2 A/E Project No April 2016

Trinity Tft High Efficiency Gas Condensing Boiler & Water Heater

Off Design Operation of Hybrid Noncondensable Gas Removal Systems for Flash Steam Cycle Geothermal Power Plants

1.0 INTRODUCTION. Shaw Industries Group 2 SwRI Project No c

Turbo-blowers and Turbo-compressors

Sentry G3 Machinery Protection Monitor

Revitalize Building Mechanical Systems (4619)

ASH MEASUREMENT AT NRG HUNTLEY USING HIGH TEMPERATURE STRAIN GAUGES

E. Baffle Tray Column (or, Termed Shower Deck, No Holes, Caps, or Other Contact Devices)

ENERGY RECOVERY SOLUTIONS. Recover wasted energy to increase efficiency and save money immediately.

Trinity Lx400 High Efficiency Gas Condensing Boiler & Water Heater

Union County Vocational - Technical Schools Scotch Plains, New Jersey

Trinity Lx200 High Efficiency Gas Condensing Boiler & Water Heater

SECTION CHILLERS

199,000 to 4,000,000 Btu/h 150 to 4500 Gallons Storage

Project Name: Project Address: Installer Name: Installer Address: Date of Inspection:

AFUE up to 85.2% Heating Input 105,000 to 245,000 Btuh

ECO-ANT21 Corporation

Condensate Pumps Jones Boulevard Limerick Airport Business Center Pottstown PA Tel:

SB Series Brazed Plate Heat Exchanger Installation Manual

Goulds 3600 Between-Bearing, Axially-Split, Multi-Stage Pumps. Goulds Pumps

Project Name: Location: Engineer: Contractor: I. GENERAL

THERMODYNAMICS STEAM P7690 AND STEAM BENCHES CUSSONS TECHNOLOGY LABORATORY RECOMMENDATION

Submersible A Series Wastewater Pumps AMX, AV and AK Hydraulic Ranges

UNIVERSITY SERVICES ANNEX James Madison University Harrisonburg, Virginia State Project Code: Architect s Project Number:

Energy Conservation with PARAG Energy Efficient Axial Flow FRP Fans

Model UDAP. Power Vented, Low Static Axial Fan Commercial/Industrial Unit Heaters DESCRIPTION STANDARD FEATURES OPTIONAL FEATURES - FACTORY INSTALLED

Hubbell NX500 High Efficiency Gas Condensing Water Heater

Case Study: Preventing Reactor Feed-water 1X Vibration by the Addition of Axial Clearance in the Rotating Assembly

C. ASME Compliance: Fabricate and label water chiller heat exchangers to comply with ASME Boiler and Pressure Vessel Code: Section VIII, Division 1.

470 Series Stamped Stainless Steel Pumps

GUIDE SPECIFICATION ADVANCED RADIANT SYSTEMS SL/SLV SIRIUS LINEAR RANGE HIGH EFFICIENCY CONTINUOUS INFRARED SYSTEMS

Water engineers and utilities are often

Annex A-8 CONCENTRATED SOLAR POWER UNITS INDEX TO SYSTEM/COMPONENT CAUSE CODES

Silhouette. Feedwater Heater. Boiler Feedwater

FXLF-9. High Efficiency Water Heaters and Boilers

COILS / INDUSTRIAL HEAT EXCHANGERS / NUCLEAR PRODUCTS / AIR COOLERS

KINGS COUNTY JAIL EXPANSION PHASE III COUNTY OF KINGS SECTION

D. NEMA Compliance: Provide electric motors and components which comply with NEMA standards.

ENGINEERING LETTER 4

Bryan Flexible Water Tube. Ultra-High Efficiency Condensing Hot Water Boilers. 3,000,000 BTUH Natural Gas Fired

SECTION (15486) - FUEL-FIRED, DOMESTIC WATER HEATERS

Performance test of a helium refrigerator for the cryogenic hydrogen system in J-PARC

FOR SERVICE TECHNICIAN ONLY DO NOT REMOVE OR DESTROY WARNING

Goulds 3600 Between-Bearing, Axially-Split, Multistage Pumps

96.2% Thermal Efficiency HIGH EFFICIENCY COMMERCIAL BOILERS CON X US REMOTE CONNECT. MODBUS AND BACnet MSTP PROTOCOL

Williams & Davis Boilers

LN series STERLING PUMPS. Horizontal Split Case Pumps. Double Volute. Single Stage.

B. Use UT Austin specifications and equipment schedule format for HVAC equipment where available.

ISOLATED DIRECT DRIVE PLENUM FAN (IDDP)

ANNEX A-1 GEOTHERMAL UNITS INDEX TO SYSTEM/COMPONENT CAUSE CODES BOILER BALANCE OF PLANT STEAM TURBINE GENERATOR MISCELLANEOUS - GEOTHERMAL EXTERNAL

Tankless On Demand Electric Water Heater

Medupi Unit 6 ACC hot cleaning: Method and results

IN THE MARINE INDUSTRY

JFT Flight Machine. JFT Flight Machine. Models. Options. Standard Features. JFT Flight Machine

GH Series End Suction Centrifugal Pumps For Flows to 2,500 GPM

Forced Draft Boiler Flue Gas Venting: Problems & Solutions. Presented by Steve Connor and Patrice Gouin January 27, 2016

Transcription:

Commissioning of a 1 MWe Supercritical CO 2 Test Loop J. Jeffrey Moore, Ph.D. Doug Hofer, Ph.D. Stefan Cich Jason Mortzheim Meera Towler General Electric Tim Allison, Ph.D. John Wade Southwest Research Institute (SwRI) energy.gov/sunshot 1

Project Objectives To develop a novel, high-efficiency supercritical CO 2 (sco 2 ) hot-gas turbo-expander optimized for the highly transient solar power plant duty cycle profile This sco 2 turbo-expander design advances the state-of-the-art from a current Technology Readiness Level (TRL) 3 to TRL 6 To optimize novel recuperator technology for sco 2 applications to reduce their manufacturing costs The sco 2 turbo-expander and heat exchanger will be tested in a 1- MWe sco 2 test loop, fabricated to demonstrate the performance of components along with the overall optimized sco 2 Brayton cycle The scalable sco 2 turbo-expander and improved heat exchanger address and close two critical technology gaps required for an optimized concentrating solar power (CSP) sco 2 plant and provide a major stepping stone on the pathway to achieving CSP at $0.06/kWhr levelized cost of electricity, increasing energy conversion efficiency to greater than 50%, and reducing total power block cost to below $1200/kW installed 2

Sunshot Program Overview Team: SwRI, GE, KAPL, and Thar Energy Project: 5-year, $10 million program to develop & test an expander & recuperator for sco 2 power generation from CSP Schedule: Expander, recuperator, and test loop design complete System targets: 10 MWe net module size 50% net thermal efficiency Expander targets: ~14 MW shaft power >700 C inlet temp >85% aero efficiency Multi-stage axial 3 3

Motivation for sco 2 Cycles over Steam 20 MW steam turbine 14 MW sco 2 turbine 150 lb rotor 7 rotor tip diameter 27,000 rpm 1000 100 10 Vapor properties at 25 C (77 F) condenser 1 0.1 2,000x 10,000x CO2 H2O 4 0.01 Vapor Pressure (bar) Vapor Density (kg/m3) 4

Recompression sco 2 Cycle 5 5

Simple sco 2 Recuperated Cycle for Test Loop Pump Load Dyno 6 6

Loop Operating Conditions Component T out, C ( F) P out, bar (psi) Flow, kg/s (lb/s) Pump 29.22 (84.60) 255.0 (3698) 9.910 (21.85) Recuperator- Heat 470.0 (878.0) 252.3 (3659) Heater 715.0 (1319) 250.9 (3639) Expander 685.7 (1266) 86 (1247) Recuperator- Cool 79.58 (175.2) 84 (1218) PreCooler 10.00 (50.00) 83 (1204) 8.410 (18.54) 9.910 (21.85) 7 7

Project Schedule Work has been divided into three phases that emulate development process from TRL3 to TRL6 Phase I Turbomachinery, heat exchanger, and flow loop design (24 months) Phase II Component fabrication and test loop commissioning (33 months) Phase III Performance and endurance testing (6 months) 8 8

Nozzle Casing Rough Machine Machining, welding, and heat treat complete 9 9

Turbine Inlet - Welding and Heat Treat Complete Welding and heat treat completed Final machining completed 10 10

Turbine Key Achievements Largest scale, highest temperature SCO2 expander developed to date Employs industrial bearings and seals which can be scaled to utility scale One-piece rotor manufacturing developed to eliminate blade to rotor attachment Shrouded blades maintain highest efficiency Rotordynamic design to accommodate high density gas and high speed Casting issues overcome with a fabricated case design 11 11

Task 2.3: Test Loop Hardware Acquisition and Installation Overview of Burner/Blower, Heat Exchanger, and Exhaust Ducting in Relationship to the SunShot Turbine and Recuperator Close-up of the Heat Exchanger with the Associated Support Structure, Spring Can Supports, Expansion Joints, etc. 12 12

40 MMBtu/hr (11.7 MW) Heater Recuperator Outlet/ Heater Inlet Heater Outlet/ Turbine Inlet Temperature 470 C 715 C Pressure 251.9 bar 250.9 bar Mass flow rate of CO 2 8.410 kg/s 8.410 kg/s 13 13

Heater HX Staggered tube configuration Designed by SwRI Manufactured by Thar First Inconel 740H heat exchanger 14 14

Primary Heater Overview of Burner/Blower, Heat Exchanger, and Exhaust Ducting in Relationship to the SunShot Turbine and Recuperator Dayco Heater Heater exhaust system installed. Heat Exchanger with the Associated Support Structure, Spring Can Supports, Expansion Joints, etc. 15 15

Firing of Gas Heater Heater was test fired to 1000F Heater temperature control system tuned 16 16

Thar Recuperator Development Milestone: Delivery of 5-MWt compact recuperator and performance qualification testing to demonstrate that performance specifications are met. Completion Target Metrics: Test unit size 50-kW scale up 100:1 for Phase 3. Capacity (% of design) = Design goal is minimum of 80% of 35 MW/m 3 (i.e., 27 MW/m 3 ). Pressure drop (% of design) < 1.5 times of bench-scale performance Cost (% of design) < Goal is not more than 1.5 times $50/kW (i.e., no more than $75/kW) 17 17

18 18

Thar Recuperator Development The delta pressure across the HX was designed to meet the milestone of being less than 1.5 times the bench-scale performance. The capacity of the 20,000 micro-tube tube bundle is calculated at 89 MW/m3, exceeding the design goal of 35 MW/m3. The pressure vessel fabrication and tube bundle was completed and passed the hydro test and received an ASME stamp. 19 QA/QC of the tube bundle indicated that there was to be a delay in the delivery of the recuperator. This lead to a decision point to install a backup recuperator that had been ordered. Thar continues reviewing all stages in micro-tube recuperator fabrication in light of lessons learned from the fabrication of the first generation SunShot microtube bundle. 19

Recuperator Contingency Plan Issued PO to Vacuum Process Engineering (VPE) for Alternative Recuperator Printed Circuit Heat Exchanger (PCHE) Delivered in April, 2017 Required piping rework 20 20

VPE Recuperator on Stand 21 21

Pump Commissioning Test Loop pressure checked Pump commissioning complete Pump spun at low speed 22 22

Final Turbine Design 10 MW Gen 4MW Comp 23 23

Turbine Assembly Assembly completed with no major issues All fits and seal clearances verified Rotor runout met specifications Axial end-play adjusted with shim packs Radial bearing clearances verified Thermal seal instrumentation added 24 24

Turbine Assembly Completed Turbine assembled and installed on test stand Connections made to turbine in this order: Large piping Small piping Lube oil supply and drain Instrumentation Dynamometer not installed for initial commissioning tests 25 25

Task 2.2: Turbo-Machinery Fabrication Turbine Case Assembly Inlet Plenum Nozzle Casing Exit Plenum Dyno Volute DGS Housing Bearing Housing 26 26

27 10 MW Frame Size SCO2 Turbine

Test Loop Components Dry Gas Seal Panel IN625 Piping IN740H Piping Heater Recuperator Lube Oil Supply Lube Oil Drain 28 28

29 Loop Pressurization

Commissioning Procedure # Test Name Test Description Dyno Heater Speed TIT TEP Exit Criteria S1 Slow roll, init. seal break in, and rotordyn. instrum. check Impeller removed. Off 5,000 rpm 47 C (or max pump discharge) S2 S3 ESD and overspeed trip check Seal break in, trim balance Spin turbine up to 2,000 rpm and immediately shut down. Confirm that tachometer was triggering and proximity probes were functioning properly. Repeat spin up and shut down procedure with increasing target speeds in approximately 1,000 2,000 rpm increments up to 5,000 rpm. This will allow abradable seals to safely cut in during transients in case there is rubbing. Spin turbine up to 5,000 rpm and activate the ESD switch to confirm its function. Set overspeed trip value to 4,000 rpm. Attempt to spin turbine up to 5,000 rpm and confirm that the overspeed trip functions properly. Spin turbine up to target speed and immediately shut down. This will allow abradable seals to safely cut in during transients in case there is rubbing. Execute trim balancing as necessary to reduce vibration levels below limit. Increase target speed from 5,000 rpm in approximately 1,000 3,000 rpm increments up to 18,000 rpm. Capture coast down Bode plot from maximum speed. Impeller removed. Off 5,000 rpm 47 C (or max pump discharge) Impeller removed. Off 18,000 rpm 47 C (or max pump discharge) 80 bar Observe all rotordynamics instrumentation functioning properly. 80 bar Observe ESD and overspeed trip sequences are functioning properly. 80 bar Observe normal vibration within amplitude limits and without signs of rubbing across speed range. Confirm bearing and SFD performance. Confirm rotordynamics model prediction of unbalance response without dyno impeller ; tune model if necessary. S4 S5 Cold test, limited speed Dyno impeller breakin Operate up to 21,000 rpm. Achieve steady state conditions. Capture coast down Bode plot from maximum speed. Spin turbine up to target speed and immediately shut down. Execute trim balancing as necessary to reduce vibration levels below limit. Increase target speed in approximately 1,000 3,000 rpm increments up to maximum speed (power limited without heating turbine flow). Capture coast down Bode plot from maximum speed. Impeller removed. Off 21,000 rpm 47 C (or max pump discharge) Impeller attached; adjust flow control valves for min power (within safe operating range). Off 12,000 rpm (or maximum power limited speed) 47 C (or max pump discharge) 80 bar Successfully operate at 1 steady state condition. 80 bar Observe normal vibration within amplitude limits and without signs of rubbing across speed range. Confirm rotordynamics model prediction of unbalance response with dyno impeller ; tune model if necessary. 30

Commissioning Procedure S6 S7 Warm test, limited speed Warm test, full speed plot from maximum speed. Operate up to 21,000 rpm (or maximum powerlimited speed) with heater off. Fire heater to adjust dyno flow from Impeller attached; increase TIT to 150 C (rate < 5 C/min), verify min to max (or within thermal seal performance, and make appropriate safe operating range) adjustments to DGS cooling flow. Slowly increase for 5 steady state TIT to 550 C (rate < 5 C/min), modify cooling flow as points. necessary. Obtain 5 steady state operating points from min to max dyno flow; adjust TIP to maintain speed, TIT, and TEP. This test may be a continuation of a successful limited speed warm test without shutdown (if not, refer to previous procedures). Increase speed to 27,000 rpm. Achieve steady state conditions. Obtain 5 steady state operating points from min to max dyno flow; adjust TIP to maintain speed, TIT, and TEP. S8 Hot test, full speed This test may be a continuation of a successful full speed warm test without shutdown (if not, refer to previous procedures). Slowly increase TIT to 715 C (rate < 5 C/min). Achieve steady state conditions. Obtain 5 steady state operating points from min to max dyno flow; adjust TIP to maintain speed, TIT, and TEP. Impeller attached; adjust dyno flow from min to max (or within safe operating range) for 5 steady state points. Impeller attached; adjust dyno flow from min to max (or within safe operating range) for 5 steady state points. Fired 21,000 rpm 550 C 80 bar Successfully operate at 5 steady state conditions. Document transient and steady state performance for all components in the loop. Document required DGS flow rates. Fired 21,000 rpm (or maximum power limited speed) 550 C 80 bar Successfully operate at 5 steady state conditions. Document transient and steady state performance for all components in the loop. Fired 27,000 rpm 715 C 80 bar Successfully operate at 5 steady state conditions. Document transient and steady state performance for all components in the loop. S9 Normal shutdown from max TIT TIT = Turbine inlet temperature TIP = Turbine inlet pressure TEP = Turbine exhaust pressure DGS = Dry gas seal SFD = Squeeze film damper ESD = Emergency shut down This test may be a continuation of a successful full speed hot test without shutdown (if not, refer to previous procedures). Slowly decrease TIT to 200 C (rate < 5 C/min). Turn off burner, but maintain air blower flow. Reduce speed to 5,000 rpm. After heater air exit temperature reaches 150 C, stop turbine and pump. Impeller attached. Fired 27,000 rpm 715 C 80 bar Successfully shut down. Document transient performance for all components in the loop. 31

Summary of Turbine Operating Limits 32 Measured Quantity Limit Action if Limit Exceeded Synchronous (1x) vibration factory acceptance with proximity probes 0.7 mil p-p (ISO 7919 Zone A) Reduce speed or change load condition to try to eliminate high vibration, or shut down. Evaluate possible causes for high vibrations and correct (e.g. trim balance) Subsynchronous (nx, n<1) vibrations measured with proximity probes Overall vibration Amplitude measured with proximity probes Housing acceleration measured with accelerometers Oil supply temperature Oil drain temperature 0.18 mil p-p Reduce speed or change load condition to try to eliminate subsynchronous vibration presence, or shut down. Evaluate possible causes for subsynchronous vibrations and correct, if possible, or justify setting higher limit. 1.5 Alarm Reduce speed or change load condition to try to eliminate high vibration, or shut down. Evaluate possible causes for high vibrations and correct, if possible, or justify setting higher limit. 1.8 mil p-p Note: Based on experience chart. 0.25 in/s RMS velocity (factory acceptance). Shut down determine the cause for the high vibration and correct it or justify setting a higher limit. Reduce speed or change load condition to try to reduce acceleration amplitude, or shut down. Evaluate possible causes for high acceleration amplitude and correct, if possible, or justify setting higher limit. 130 F Evaluate lube oil cooler and reduce supply temperature 50 F above oil inlet temperature. Shut down and determine the cause for the high oil temperature rise and correct it or justify setting a higher limit. 350 F Decrease turbine TIT or increase seal gas flow rate. DGS Casing temperature DGS pressure 1500 psi Decrease loop pressure. Casing temperature? 1320 F (715 C) Reduce burner temperature Casing temperature 670 C/hr, increasing Turn down heater temperature or flow. rate 670 C/hr, decreasing Turn up heater temperature or flow. Heater air 1700 F Reduce fuel flow rate.?

Summary of Loop Operating Limits Measured Quantity Limit Action if Limit Exceeded Loop low pressure 1600 psi (PSV set point) Vent loop limit Loop high pressure 3950 psi (turbine case rating) Vent loop limit Turbine inlet 1320 F Reduce heater fuel flow temperature limit Turbine exhaust 1270 F Reduce heater fuel flow temperature limit Carbon steel pipe 600 F (900# ANSI Flange Limit) Reduce heater fuel flow temperature limit Precooler inlet temperature limit 500 F Reduce heater fuel flow 33

34 Turbine Commissioning

Summary of Commissioning Activities Turbine assembly complete and installed in loop Recuperator installed including piping rework Piping cleanout and leak test Dry gas seal supply commissioning Lube oil commissioning Final instrumentation installation Control system checks Turbine was first spun Dec. 21, 2017 Break-in complete Speed increased to 13,000 rpm traversing first critical speed Vibrations very low (<0.25 mils p-p) Testing has continued through March, 2018. To date, turbine inlet conditions of 550C, 200 bar at 24,000 rpm have been achieved. 35 35

Discussion Questions??? energy.gov/sunshot 36