Case Study of Underground Car Park. Team Japan

Similar documents
Case Study by Team Japan. Underground Car Park

Case Study 1 Underground Car Park

How to Use Fire Risk Assessment Tools to Evaluate Performance Based Designs

Case Study 1 Underground car park

FIRE PROTECTION AND SAFETY ANALYSIS FOR AN OFFICE HIGH RISE BUILDING. Fabio Mazza June 2016

Tunnel Fire Dynamics and Evacuation Simulations

Firefighting operations on multi-tiered vehicle stacking buildings F5-13 GD

Third Runway Project APM Depot Fire Engineering Design. Presented by Ir Wilson Sau-kit TSANG

CHOOSING A FIRE VENTILATION STRATEGY FOR AN UNDERGROUND METRO STATION

SMOKE MANAGEMENT AND EGRESS ANALYSIS OF A SPORTS ARENA USING THE PERFORMANCE-BASED DESIGN

COSTCO, SAN FRANCISCO A PRESCRIPTIVE AND PERFORMANCE BASED ANALYSIS OF FIRE PROTECTION SYSTEMS AND DESIGN

Fire Engineering in High Rise 15 November 2013

A New Zealand Case Study Building Design 11 th International Conference on Performance

OVERVIEW. Increasing Awareness of Occupant Evacuation in Tall Buildings. Traditional Focus has been on Evacuation From Fire

Virtual Compartment: An Alternative Approach to Means of Egress Design in Airport Pedestrian Tunnel

Fire Protection System and Life Safety Evaluation of Building X. Anthony W. Sublett

The Swedish National Board of Housing, Building and Planning s general recommendations on the analytical design of a building s fire protection, BBRAD

INITIAL FIRE SAFETY ASSESSMENT

SCHEDULE. Essential Safety Measures taken from Schedule 9 of the Building Regulations PART 1 BUILDING FIRE INTEGRITY

By: Russell Bainbridge March 18th, 2016 FPE 596

Sprinklers Modeling for Tunnel Road Fire Fighting

Will Clay Spring 2014

GAUTENG DEPARTMENT OF INFRUSTRUCTURE DEVELOPMENT

Statue of Liberty: A Risk Analysis

BOABC Level III Exams 7, 8, 9 and 10 Beginning April 1, 2015

INITIAL FIRE SAFETY ASSESSMENT

SAFETY. USE OF SAFETY CHECK LISTS A safety check for compliance with current regulations should be performed yearly.

The Mont Blanc tunnel project. Eric CESMAT, Sylvain DESANGHERE

INITIAL FIRE SAFETY ASSESSMENT

COMPLIANCE ALTERNATIVES

Objective based approach

COMPLIANCE ALTERNATIVES

UCL PRINCIPAL CONTRACTOR SITE FIRE SAFETY RISK REVIEW & MITIGATION MEASURES

Smoke Management in High-Rise Structures

SANTA ROSA FIRE DEPARTMENT FIRE PREVENTION BUREAU INSPECTION CHECKLIST

Culminating Project. Fire Protection and Life Safety Engineering Analysis. Cal Poly. Center for Science and Mathematics. Fire Protection Engineering

REVIEW OF TECHNICAL STANDARDS AND CALCULATION METHODS FOR DIMENSIONING OF SMOKE AND HEAT CONTROL SYSTEMS IN CASE OF FIRE IN UNDERGROUND CAR PARKS

F.R.A.M.E. EVENT NETWORKS used in "FRAME".

Element C3.5 Means of Escape

PERFORMANCE COMPLIANCE METHODS

Final Report - Volume III - Technical Manual for Planning of Fire Prevention System

Fire Safety Design when Normal Limits Don t Apply

EMERGENCY EVACUATION PLAN

and Sprinkler System in Resalat Tunnel of Tehran

Hot Issues in Fire Engineering July 2014

PERFORMANCE COMPLIANCE METHODS

Table EXIT ACCESS TRAVEL DISTANCE a OCCUPANCY SYSTEM SYSTEM. A, E, F-1, I-1, M, b,d R, S-1. B c. F-2, S-2, U c

NFPA-APSEI Fire & Security 2010

12/14/2013. Fire alarm and emergency power SPRINKLER HEAD

Simple Equations for Predicting Smoke Filling Time in Fire Rooms with Irregular Ceilings

CFD ASSESSMENT OF RAILWAY TUNNEL TRAIN FIRE SCENARIOS

SPECIAL DETAILED REQUIREMENTS BASED ON USE AND OCCUPANCY

Date: Place: Technical University of Denmark. Knowledge FOr Resilient society

PERFORMANCE COMPLIANCE METHODS

New developments in Nordic countries in fire safety engineering guidance

Case Study 2 (Production and Storage Buildings) - Spain

GAUTENG DEPARTMENT OF INFRUSTRUCTURE DEVELOPMENT

Mechanical Smoke Extract Shaft Systems

Emergency Planning and Preparedness

Date and Time of Incident. March 10, 1975

ANALYSIS OF SMOKE MOVEMENT IN A BUILDING VIA ELEVATOR SHAFTS

INITIAL FIRE ASSESSMENT REPORT (FAR)

Building Description Applicable Codes & Standards Prescriptive Requirements. Performance Based Design

CFD STUDY OF FIRE PROTECTION SYSTEMS IN TUNNEL FIRES

CHAPTER 7 ALTERATIONS LEVEL

Steven Craft, PhD, P.Eng. FIRE SAFETY DURING THE COURSE OF CONSTRUCTION

Applying the New Zealand Performance Based Design Fire Framework to Buildings Designed in Accordance with NFPA5000

Life Safety - Means of Egress/Exits NFPA 101

22 BISHOPSGATE Lift Evacuation Strategy

INITIAL FIRE SAFETY ASSESSMENT - EXPANSION

2012 B.C. Building Code Compliance Review (Division B Part 3)

FIRE DEPARTMENT - RULES FOR FIRE PROTECTION IN AUSTRIA

Construction Innovation Center Building 186

Practicalities and Limitations of Coupling FDS with Evacuation Software

The Situation. Modeling Storage Occupancies Under Sloped Ceilings. Concerns (Elevation View) The Concerns 4/29/ NFPA Conference & Expo

PREMISES FIRE SAFETY HANDBOOK

FINDINGS FROM FIRE TESTS IN TUNNEL CONSTRUCTIONS WITH VENTILATION SYSTEMS AND FIXED FIRE SUPPRESSION SYSTEMS

ECONOMIC JUSTIFICATION FOR SPRINKLER SYSTEMS

SPECIAL DETAILED REQUIREMENTS BASED ON USE AND OCCUPANCY

Emergency Evacuation Plan. Tiffany Tower Plot W2 Jumeirah Lakes Towers

Case Study 2 Production and Storage. SFPE Polish Chapter Wojciech Węgrzyński, Grzegorz Krajewski Building Research Institute (ITB)

The Physical Environment Portal: Module 5, LS Leadership

Franz Evegren. Robust brandriskbedömning ur ett IMO-perspektiv

Is There A Need to ENCLOSE ELEVATOR LOBBIES IN TALL BUILDINGS?

ISO/TR TECHNICAL REPORT. Fire-safety engineering Technical information on methods for evaluating behaviour and movement of people

Study of Numerical Analysis on Smoke Exhaust Performance of Portable Smoke Exhaust Fan

THE REPUBLIC OF LIBERIA LIBERIA MARITIME AUTHORITY

California Fire Code (CFC) Part III contains requirements. Building and Equipment Design Features PART. Chapters 5 through 19

FIRE SAFETY INSPECTION REPORT

C/VM2 Verification Method: Framework for Fire Safety Design For New Zealand Building Code Clauses C1-C6 Protection from Fire

Guidance for writing a Personal Emergency Evacuation Plan (PEEP)

EVACUATION PROCEDURES IN EDUCATION PREMISES

PACDA Application Forms. 5/15/2018 Aman Fire Protection Consultants 1

Fire and smoke management in a uni-directional road tunnel for a congested traffic condition

Design of Fire safety in Multi Occupancy Residential Accommodation

Unit 2 Fire Safety (Zone 2)

Fire Hazard Analysis of Technical Area 53 Building 1

Human Factors - Egress Analysis for High Hazard Occupancies. Presented by: Michael J. Klemenz, PE, SFPE

Quantitative risk assessment for a fire suppression system in the New Tyne Crossing. Dr Fathi Tarada

NUMERICAL SIMULATION OF FIRE SPREAD IN TERMINAL 2 OF BELGRADE AIRPORT. PO Box 522, Belgrade, Serbia and Montenegro

Transcription:

11th Conference on Performance Based Codes and Fire Safety Design Methods Case Study of Underground Car Park Team Japan

We focused on the characteristics of the fire behavior of car fire. Car fire is not so powerful and unlikely to spread. We installed minimum fire safety items such as compartmentation with openings and smoke exhaust system utilizing ramp and smoke shaft. Evacuation safety was verified except the occupants in the dead-end of parking space. Dense smoke and soot affected firefighting activity. Executive Summary

1. Fire Spread 2. Smoke Control 3. Evacuation 4. Fire-Fighting Strategy of Fire Safety

1. Fire Spread 2. Smoke Control 3. Evacuation 4. Fire-fighting

Fire Does Not Spread Beyond Lanes

number of data 40 20 35 18 30 16 14 25 12 20 10 158 106 4 5 2 0 average = 0.0362 Probability of Non-Exceedance =95% Fire Growth Rate [kw/s 2 ] 0 0.05 0.1 0.15 0.2 0.25 0-0.01 0.01-0.02 0.02-0.03 0.03-0.04 0.04-0.05 0.05-0.06 0.06-0.07 0.07-0.08 0.08-0.09 0.09-0.1 0.1-0.11 0.11-0.12 0.12-0.13 0.13-0.14 0.14-0.15 0.15-0.16 0.16-0.17 0.17-0.18 0.18-0.19 0.19-0.2 0.2-0.21 0.21-0.22 0.22-0.23 0.23-0.24 0.24-0.25 fire growth rate α [kw/s 2 ] Design design value = 0.112 value =0.112 lognormal (0.0362, 0.0574) 0.00025 6 0.0002 5 number of data 4 0.00015 3 0.0001 2 0.00005 1 Ref: MZM. Tohir, M. Spearpoint, Distribution analysis of the fire severity characteristics of single passenger road vehicles using heat release rate data, Fire Science Reviews, Vol. 2, No. 5, 2013 0 Maximum HRR [kw] average=4260 design value =8900 Design value lognormal (4260, 2449) =8,900 Lognormal (4260, 2449) 0 2000 4000 6000 8000 10000 0-400 400-800 800-1200 1200-1600 1600-2000 2000-2400 2400-2800 2800-3200 3200-3600 3600-4000 4000-4400 4400-4800 4800-5200 5200-5600 5600-6000 6000-6400 6400-6800 6800-7200 7200-7600 7600-8000 8000-8400 8400-8800 8800-9200 9200-9600 9600-10000 maximum heat release rate Q max [kw] Statistically Process: a, Q max

Three Kinds of HRR Curves HRR 6Qmax Fail to control by sprinkler in a stacked zone 2Qmax Fire spread to adjacent cars 3Qmax Fail to control by sprinkler in a non-stacked zone Qmax Q=αt 2 Qsp Fire spread to adjacent cars Succeed to control by sprinkler time Design Fire

1. Fire Spread 2. Smoke Control 3. Evacuation 4. Fire-Fighting

Prevent Horizontal Smoke Spread by Natural Smoke Ventilation smoke shaft Active smoke compartment Induction of fresh air GF ramp ramp B1F B2F Smoke Control

Fresh Air Zone B Zone A Fresh Air z Dividing the car park into 3 smoke zones Smoke is exhausted through smoke shaft or a ramp Zone C Smoke Exhaust Vestibule Pressurization Fresh air is supplied through other ramps Installing vestibule pressurization system Strategy of Fire Safety

Scenario-s1 Scenario-f1 Zone C Scenario-s3 Scenario-f3 Scenario-s2 Scenario-f2 Settings of Each Scenario Scenario Sprinkler Fire Growth rate α Qmax [MW] HRR [kw/m 2 ] Scenario-s1 Success 0.122 1.0 125.0 Scenario-f1 Fail 0.122 17.8 2225.0 Scenario-s2 Success 0.122 1.0 125.0 Scenario-f2 Fail 0.122 8.9 1112.5 Scenario-s3 Success 0.122 1.0 125.0 Scenario-f3 Fail 0.122 8.9 1112.5 Fire Scenarios

Temperature Distribution at Z=1.8m Time 120s 300s 420s Scenario-f1 Sprinkler failed case Scenario-s1 Sprinkler succeeded case 20 40 60 80 100 120 140 160 180 200 220[ C] Simulation Results

1. Fire Spread 2. Smoke Control 3. Evacuation 4. Fire-Fighting

Huge space - Requires long time for evacuation - Exposes occupants to smoke before noticing emergency Limited illumination - Reduces evacuation speed - Impairs sight of direction Closed space - Rises smoke temperature - Causes F.O. Characteristics of This Car Park

Evacuation Strategy - Compartment - Emergency light and Exit sign - Smoke shaft - Temporary refuge area ZoneB ZoneA stair Temporary refuge area Smoke Shaft Exit Exit sign Compatment Emergency light ZoneC ELV Horizontal evacuation Evacuation Planning

Hs [m] 1.8 [m] Hs [m] < 1.8 [m] Toxic More than 1.8m Exit Less than 1.8m Loss of Visibility Exit SAFE Yes UNSAFE No [Toxic] Cs [1/m] 0.5 [1/m] CO 2 [%] 0.5 [%] Ts [deg C] 44.8 [deg C] [Visibility] V [m] L (20m) [m] Ts [deg C] 140 [deg C] 30 [min] t escape [min] Tenability Criteria

Occupants are supposed to start evacuation when smoke descends in an adjacent grid Grid size: 24mx24m Smoke Level [m] 3 2.5 2 1.5 1 0.5 0 0 100 200 300 400 Time[sec] An adjacent grid! Smoke Level [m] 3 2.5 2 1.5 1 0.5 0 0 100 200 300 400 Time[sec] An adjacent grid! Evacuation Start Time

Sprinkler: Failure ASET: 197 [sec] RSET: 310 [sec] Hs : 1.3 [m] CO 2 : 0.6 [%] Cs : 1.9 [1/m] V : 4.2 [m] Ts : 45.1 [deg C] OK! ASET: 90 [sec] RSET: 116 [sec] Hs : 1.6 [m] CO 2 : 0.17 [%] Cs : 0.28 [1/m] V : 25.0 [m] Ts : 27.8 [deg C] ASET: 166 [sec] RSET: 274 [sec] Hs : 1.1 [m] CO 2 : 0.45 [%] Cs : 1.55 [1/m] V : 6.2 [m] Ts : 39.0 [deg C] Exit(3) NG Scenario-f1 Scenario-f2 Scenario-f3 Exit(3) NG Sprinkler: Success ASET: 207 [sec] RSET: 375 [sec] Hs : 1.4 [m] CO 2 : 0.21 [%] Cs : 0.53 [1/m] V : 16.1 [m] Ts : 26.1 [deg C] OK! ASET: 91 [sec] RSET: 116 [sec] Hs : 1.6 [m] CO 2 : 0.16 [%] Cs : 0.29 [1/m] V : 25.0 [m] Ts : 27.6 [deg C] OK! Exit(3) NG Scenario-s1 Scenario-s2 Scenario-s3 ASET: 175 [sec] RSET: 326 [sec] Hs : 1.3 [m] CO 2 : 0.21 [%] Cs : 0.48[1/m] V : 20.0 [m] Ts : 26.7 [deg C] Verification Result of Evacuation Safety

Fire Control Sprinklers can improve evacuation conditions such as smoke layer and visibility. Evacuation Starting Time Prompt activation of emergency alarm/voice system and facility management are necessary. Remediation of Dead Ends Means of egress should be arranged to the dead end to prepare an evacuation route getting away from fire origin. Verification Result of Evacuation Safety

1. Fire Spread 2. Smoke Control 3. Evacuation 4. Fire-Fighting

Entrance-B1 Stairwell-B1 Stairwe11-A1 Entrance-A1 The firefighters would arrive at the fire site 11 minutes after the fire has occurred. Entrance-B2 Entrance-C1 Stairwell-B2 Stairwell-C1 Ground floor of the Car Park Stairwell-A2 Entrance-C2 Entrance-A2 Three out of six fire crews approach the entrances located on the ground floor of the building. Stairwell-C2 Access of Fire-Fighters

Stairwe-B1 Zone B Stairwe-A1 Zone A The firefighters would reach the vestibules on the floor of fire origin 20 minutes after the fire has occurred. Stairwe-B2 Stairwe-C1 Zone C Stairwe-C2 Stairwe-A2 The maximum value of extinction coefficient of smoke in the compartment of fire origin would become 2.0 L/m at that time. Rescue

Fire Engine Fire stand pipe Hose Wat er Tank Firefighters should spray water in a rough direction toward the fire origin through the opened door from the vestibules. Car Park Spr i nkl er Head Room of Fire Origin Wat er Tank z Al ar m Firefighters Val ve Spr i nkl er Pump Stairwell Water will be continuously sent to the sprinkler system from a fire engine. Firefighters will spray water to the fire origin until extinguishment. Suppression

Installed the least fire safety items Compartment : Fire resistant walls and active smoke barriers Smoke exhaust : Ramps and smoke shaft Smoke density and visibility are critical For evacuation Only evacuation from dead end is not secured, even with sprinkler. For fire-fighting Sprinklers and interconnection of fire engine to sprinklers are necessary. Conclusion

Questions? Thank You for Your Attention

Appendix

Sprinkler Activation Qsp : HRR of SP system activated HRR Qsp=861kW 1.0MW time Near the thermal point temperature Tg [deg] 200 180 160 140 120 100 80 60 40 20 0 Activation time of SP α=0.122 RTI=32 Nominal Activation Temperature of SP Head = 72 [deg.] 84sec(HRR=861kW) 0 30 60 90 120 150 180 210 240 Time[sec] HRR of SP Activated Case

Whole Model For the Simulation of Fire Fighting (0-20minutes) Partial Model For the Simulation of Evacuation (0-10minutes) *Only Zone C *The cell size of Z direction is more detailed Simulation Models

Car Park Rescue Crew Entrance Firefighters will use entrances on the ground floor as staging areas to allocate firefighting equipment and extend water hose. B1 B2 Room of Fire Origin Vestibule Firefighters Stairwell These groups of firefighters will search evacuees who failed to escape, in order to rescue or lead them to the outdoor. Rescue