OSCAR-LOWeFLOW Treatment Unit Installation Manual. January Residential

Similar documents
OSCAR-II Installation Manual, Idaho. July 2018

OSCAR-LOWeFLOW Treatment System Design Manual October 2016

OSCAR-LOWeFLOW Treatment System Design Manual January 2018

OSCAR-LOWeFLOW Treatment System Design Manual August 2017

Clean Water Made Easy. CWS Time Clock Softener Installation & Start Up Guide. Questions?

SYSTEMS for CATALYTIC FILTERS

Owner s Manual AMERICAN PERC-RITE. WASTEWATER DRIP SYSTEMS 2 ZONE or 4 ZONE SIMPLEX or DUPLEX

WM-450-PT WM-900-PT Commercial Wall Mounted Reverse Osmosis

HYDROGEN SULFIDE REMOVAL SYSTEMS

Owner s Manual. Keep with machine for reference PKC24 INSTALLATION & OPERATION REV Perlick Corporation 8300 W Good Hope Rd Milwaukee, WI 53223

Fleck 2510 SXT Catalox Installation & Start Up Guide

OPERATING MANUAL. Reverse Osmosis Equipment Model: Frame Mount Vertical FMV-1 through FMV-6. Made in U.S.A.

AccuBrine automated brine maker Technical Specifications

GLC/GW-100 MANUAL INSTALLATION SERVICE PARTS REV.1.01

J120 STEAM BOOSTER INSTALLATION, OPERATION, AND SERVICE MANUAL J120 STEAM BOOSTER. J120 Steam Booster Manual D

Mound System Pressure Distribution Worksheet

CWS Plus Sediment Filter Installation & Start Up Guide

irritec USA irritec USA THE MODULAR SAND MEDIA FILTER TM Water Tool Filters

WHITEWATER FILTER/DRIP SYSTEM MODEL 8115 / P.O. BOX 969, DENHAM SPRINGS, LA (225) Telephone (225) Fax Revised 03/01/06

EXTREME HP-1 Reverse Osmosis System

Professional Series. Chemical Feed System Model # US Patent No. 6,752,930 B2

EXTREME 1 Reverse Osmosis System

REVERSE OSMOSIS SYSTEMS

Technical Specifications & Pricing

INSTALLATION INSTRUCTIONS & HOME OWNERS MANUAL ECO 18 ECO 24 ECO 27 IMPORTANT SAFETY INFORMATION

Clean Water Made Easy

Clean Water Made Easy. Fleck 7000 Tannin Filter Installation & Startup Guide. Questions?

Fleck 5600 Carbon Filter Installation & Start Up Guide

5700-E Sediment Filter Installation & Start-Up Guide

J-PRO-22 Pump Proportional Feed Hydrogen Peroxide Installation & Start-Up Guide

FILTRATION SYSTEM MODEL: FILTER - 5 MULTI-SHIFTER, INC. P.O. BOX CHARLOTTE, N.C TEL#: FAX#:

AQUAS POOL PACKAGE INSTALLATION INSTRUCTIONS FOR MODELS: XPN AQUAS Pool Package

model NO. LSS GALLON SKID MOUNTED HIGH PRESSURE SPRAYER ASSEMBLY / OPERATION INSTRUCTIONS / PARTS

Care and Use Manual Tank Series Appliances

1. VCOM Panel Installation Instructions EIN-CP-GEN Panel Wiring Diagram EDW-WD-DAX-137

Owner s Manual GW-100 MANUAL INSTALLATION SERVICE PARTS REV.1.00

Installation Instructions AS-WH Whole House Water Filter

Sources of Graywater

IMPORTANT! ank You! Model: Twist-In 100 GPD, 3-Stage RO Unit. Installation, Operation & Maintenance Guide

J-PRO V 230V Dual Voltage Hydrogen Peroxide Pump Installation & Start-Up Guide

TM Series. Induced Draft, Counter Flow Optional Accessories

EXTREME 4 Reverse Osmosis System

Arch Feeder: Installation Manual

PolyMax H2-24 Dutch Bucket System

AUTOMATIC IN-FLOOR CLEANING & CIRCULATING SYSTEM

WS1 Greensand Installation & Start Up Guide

Whole House Descaler Installation Instructions

This material is intended only for Glass Water Systems customers. Reproduction or distribution of this material is strictly prohibited and protected.

EXTREME HC-2 Reverse Osmosis System

American Dish Service

Fleck 2510 Sediment Filter Installation & Start-Up Guide

EXTREME 2 Reverse Osmosis System

1-866-PENNERS

High Capacity Instantaneous Steam Fired Water Heater

Fleck 7000 Sediment Filter Installation & Start-Up Guide

Clean Water Made Easy

Kinetico 2060f OD Sulfur Guard Installation Instructions

C. ASSE 1013: Performance Requirements for Reduced Pressure Principle Backflow Preventers.

EXTREME HC-8 Reverse Osmosis System

IH091: Home Wastewater Disposal System Installation Instructions & Warranty Information

OWNER S MANUAL. How to install, operate and maintain your. EcoWater Systems Automatic Sediment Filter. EcoWater Systems Poland

1. Read all instructions before proceeding with the installation. Improper installation may void warranties.

7800 Neutralizer Installation & Start-Up Guide

Iron Air Charge MangOx 2510 SXT Installation & Start Up Guide

SPECIFICATION SECTION:

ABBREVIATIONS: TABLE OF CONTENTS: REFERENCE MATERIALS: CITY OF SEATTLE COMBINED SEWER OVERFLOW GALLONS PER MINUTE POLYVINYL CHLORIDE SQUARE FEET

PHYSICAL FACILITIES Consultant s Handbook Specifications Division 21 Fire Suppression 3000 Fire Pumps

Paragon. Induced Draft, Counter Flow Optional Accessories

OPERATING AND MAINTENANCE MANUAL FOR PLATE HEAT EXCHANGER INDIRECT FIRED WATER HEATER. Electric Heater Company Base Model "BWXP"

Owner s Manual GLC MANUAL INSTALLATION SERVICE PARTS REV.1.00

OPERATING AND MAINTENANCE MANUAL FOR INSTANTANEOUS STEAM FIRED WATER HEATER ELECTRIC HEATER COMPANY BASE MODEL F

4. TECHNOLOGY AND DESIGN CRITERIA

Clean Water Made Easy

Clear Comfort Residential Pool & Spa Sanitization System Installation, Operations & Maintenance Manual

NBSeries Installation Operation & Maintenance

4-1 1 / 2 " Tees / 2 " hole saw w/ 1/4" drill bit / 2 " Male slip plugs

IRRIGATION FOR CONSERVATION

One Less Thing to Forget...

Media Service Instructions 1500 Series BAT Media Plants

INSTALLATION, OPERATION AND SERVICE MANUAL AERATION SYSTEMS FEATURING AIR COMPRESSOR AND AIR ELIMINATOR TANK

AllClear G2 Series Pressurized Filters Product Manual

EcoSmart Troubleshooting Guide

Models Series Series

Equipment Alert. P-Trap Must Be Installed to Exhaust or Warranty will be Voided. Refer to this Manual for installation Instructions

HOMEADVANTAGE II IMPORTANT SAFETY INFORMATION

FilterWeir OPERATING MANUAL F060. Read entire instructions prior to installing unit. Great Equipment Is Just Part Of The SAViO Excellence Line.

American Dish Service

OPERATING MANUAL MODEL AIR 1500TM AIR DRYER

Home Inspection Report

Installation S19-324D1. Class I, Division 1, Groups C & D Explosion Proof. Emergency Signaling System

SEISCO SUPERCHARGER EXTENDER/BOOSTER INSTALLATION GUIDE & OWNERS MANUAL

PRO SERIES IMPORTANT SAFETY INFORMATION

Casper Hoop House Workshop 12 Ft. x 36 Ft. Del Jimenez. 12ft x 36ft Hoop House 2

Retro-DWS Other Methods Internal Heating Cable System for Sewer Pipe and Waste Drain Applications

Standard and CELDEK Evaporative Cooler Modules Installation, Operation, and Maintenance Manual

TCPSeries Installation Operation & Maintenance

Water Softener & Single Tank Triple Treat System Installation Overview. Using 1850 Metered Valves

/99 USA. Installation Manual SU Save These Instructions!

J-PRO-22 Pump Proportional Feed Chlorinator Installation & Start-Up Guide

IJ3000 IJ3000 Flushing System N Revision B Installation Instructions Page 1 of 10

Transcription:

OSCAR-LOWeFLOW Treatment Unit Installation Manual January 2016 Residential US Patent # 8,889,007 Manufactured by: Lowridge Onsite Technologies, LLC PO Box 1179 Lake Stevens, WA 98258 877-476-8823 info@lowridgetech.com www.lowridgetech.com 1

Table of Contents System Overview Prior to Installing a LOWeFLOW unit List of Components Loading and Unloading Instructions Installation Steps: 1. Determine the orientation and position of the tanks and LOWeFLOW filter. 2. Excavate the holes for tanks and LOWeFLOW filter. 3. Setting tanks and LOWeFLOW filter. 4. Plumbing and filling the LOWeFLOW filter. 5. Install splitter tee and splitter valve. 6. Install dosing pump. 7. Install LOWeFLOW headworks. 8. Plumbing connections 9. Wire control panel, floats, and pumps. 10. Pumps, floats, and splitter valve settings 11. Back fill and water test. 12. OSCAR installation 13. Panel Operation and Start-up procedures. Replacement Instructions: 1. Solenoid valves 2. Coils 3. Dose/Flush pump 4. Discharge pump Material Specifications: 1. Media 2. Containment Vessels a. Septic Tanks b. Recirculation Tanks c. Septic/Recirculation combination d. LOWeFLOW Filter containment vessel 3. Plumbing 4. Assembled Components a. Headworks b. Splitter tee c. Splitter valve d. Coil 5. Recirculation Pump 2

System Description: The LOWeFLOW treatment unit is comprised of the LOWeFLOW recirculation filter, a septic tank, recirculation tank, discharge/clarifier tank, headworks, and control equipment. Wastewater is collected in a standard septic tank where gross solids are settled out and primary treatment occurs. Septic tank effluent flows from the septic tank into the recirculation tank. Liquid in the recirculation tank is mixed with treated filtrate from the LOWeFLOW filter. The mixed liquid is dosed to a drip tubing network called a Coil in the top of the LOWeFLOW filter. Treated filtrate from the LOWeFLOW filter flows back to the recirculation tank through the split flow tee. The position of the splitter valve determines the flow path of the filtrate. When the liquid level in the recirculation tank is high enough to seat the splitter 3

valve, all of the filtrate passes to a clarification/discharge tank, otherwise, all or a portion of the returning filtrate returns to the recirculation tank. Prior to Installing an OSCAR-LOWeFLOW Unit: Before installing a LOWeFLOW unit, the installer must complete in-class and in- field training by representatives of Lowridge Onsite Technologies, LLC. The Installer must insure that no water softener discharge is plumbed into any of the drains that feed the system. The residential LOWeFLOW unit is intended to treat only wastewater generated by normal activities from laundry machines, toilets, showers, and kitchen and bathroom sinks. No special chemical additives are needed for the normal functioning of the LOWeFLOW unit. List of components: 1. Control panel: LF2P-RF-OS 2. LOWeFLOW Headworks: three (3) oil filter 0-100 psi pressure gauges, one (1) 3/4-120 mesh, 130 micron Arkal disc filter, five (5) Netafim 1 normally closed solenoid valves and container. 3. LOWeFLOW treatment unit: containment vessel and drip tubing Coil. 4. Splitter tee 5. Splitter valve 6. Recirculation pump, 1/2 hp 7. Float switches 8. Discharge pump, ½ hp 9. OSCAR coils 10. OSCAR Headworks: three (3) oil filter 0-100 psi pressure gauges, one (1) 3/4-120 mesh, 130 micron Arkal disc filter, one ball valve, and container. Unloading and un-packaging instructions: Lowridge Onsite Technologies, LLC takes great care to manufacture and package the LOWeFLOW unit to prevent damage during shipping and handling. It is expected that everyone from the manufacturing personal to the installation crew take reasonable steps not to drop, throw, or damage the product. Do not handle the Coil by the tubing. Handle the Coil by the 2 PVC bracket. The polyethylene LOWeFLOW filter containment basin is light enough that two people can easily lift and carry the unit. 4

If there are defects in any of the LOWeFLOW parts, call Lowridge. Installation steps: Step 1: Determine the orientation and position of the tanks and LOWeFLOW filter. Some designs will have specific locations for the system components based on required set - backs, elevation, logistical issues, or aesthetic concerns. Before excavating begins, verify that the proposed locations of the LOWeFLOW filter, headworks, septic/recirculation tank, and discharge tanks are laid out in a manner that will allow for efficient pipe connections. Step 2: Excavate the holes for tanks and LOWeFLOW filter. Excavate the tank holes as per the tank manufacturer s recommendations. Take appropriate steps to insure the tanks will not settle after backfill. Determine the desired depth of the LOWeFLOW filter. The key concern is to insure that the underdrain of the LOWeFLOW filter is above the elevation of the flow splitter. Maintain at least a 2% fall between the underdrain and splitter tee, minimum 2 of fall. The depth of the recirculation tank will determine the depth of the LOWeFLOW filter, or vice-versa. Under drain Split flow tee Step 3: Setting tanks and LOWeFLOW filter. Tanks: Set tanks according to tank manufacturer s recommendations. LOWeFLOW Filter Containment Vessel: 5

Excavate a hole for the basin that incorporates a 3 layer of pea gravel. Place about 6 cu. ft. of pea gravel in the center of the excavation in the shape of a mound. This additional gravel will support the bottom of the basin making a domed shape. See below. If need be, the LOWeFLOW basin can be set at surface grade with a mound of pea gravel for support. Step 4: Plumbing and filling the LOWeFLOW filter. Install the underdrain, supply and flush lines. Place underdrain (3 corrugated) ABS pipe. There are 4 glue connections and 2 threaded to complete. First, thread the insert connectors as shown below. First insert the two basin adapters into the 1 1/2 threaded connectors. Use teflon tape or paste on threads. Install the basin adapters from the outside of basin. 6

3 Corrugated ABS Glue in internal piping and then support with a small amount of pea gravel. Horizontal portions must be level. Fill basin with pea gravel to the bottom of top rib. Place Coil on gravel media. Note orientation of fittings on manifold. Remove caps and glue connections. Handle the Coil by the 2 PVC frame. Do not lift or handle the Coil by the drip tubing. Cover coil with child proof mesh. 7

Cover Coil with pea gravel. Slightly mound some excess gravel on top of basin. Step 5: Install splitter tee and splitter valve. Install tank adapter into tank boot. The splitter tee is installed just outside the recirculation tank. Orient the third tee opening to the 2 or 10 o clock position. Install second tank adapter into the discharge tank. Connect the splitter tee to the discharge tank plumbing. 8

I Glue the U fitting to the splitter tee end. Assemble the splitter valve. Remove the tape from the splitter valve housing. Remove set screw from housing. Place splitter valve seat on housing and secure with set screw. Glue handle as shown. 9

Place splitter valve on U fitting. DO NOT GLUE SPLITTER VALVE ASSEMBLY TO THE U FITTING! Step 6: Install dosing pump. Place the pump into the recirculation tank. Attach a 1 union on the horizontal supply line and exit the tank through the riser wall. Make sure to use an appropriate grommet or other method to insure the protrusion is water tight. Step 7: Install LOWeFLOW headworks. The best installation location of the headworks is on top of one of the tanks. The tank top provides a solid base of support and acts as a barrier against mole and gopher infestation. Step 8: Plumbing connections The headworks has four (4) plumbing connections: pump line from dosing pump, Coil supply line, Coil flush line, and flush vent line to septic tank inlet. Plumb the connections to the headworks so that the pipes are supported by the top of the tank or hand bed the pipes before backfhilling the system. 10

Underdrain Connect the LOWeFLOW filter underdrain to the flow splitting tee using 2 sch 40 PVC pipe. Connect the outlet position of the splitter tee to the clarifier/discharge tank. 11

Step 9: Wire control panel, floats, and pumps. Mount the LOWeFLOW control panel on a post or a non bedroom wall chest to eye level. Always use PVC electrical conduit between the splice boxes and the control panel and follow all applicable electrical codes. Do not use direct burial wire on LOWeFLOW systems. Follow the wiring directions provided inside the control panel. Power requirements for the LOWeFLOW system are as follows: Recirculation pump, 110 volts, up to 18 amps start and 10.5 amps running (20 amp breaker) Discharge pump, 110 volt, up to 18 amps start and 11 amps running Headworks 24 volts, 0.4 to 0.6 amps Step 10: Floats, Pumps, and Splitter Valves Settings Minimum liquid level (MLL) = 80% of daily design flow. MLL will approximately 6 below the top of the splitter valve shroud. Redundant off float = MLL- 2 High level alarm float = MLL + 4 Step 11: Back fill and water test. Prior to backfilling, all tanks should be water tested and all start-up procedures must be completed. Fill tanks to 2 above riser connections and mark water level. There should be no measurable water loss for 2 hours. Backfill tanks with appropriate material. At all times follow tank manufacturer s instructions. Hand-bed all pipes. Step 12: OSCAR installation. Installation: Before preparing the basal area for the sand layer the soil moisture content must be checked to prevent smearing the soil interface. Dig a small excavation in the basal area with a hand shovel. The excavation need only be 12 wide and 12 deep. If the exposed sides of 12

the excavation are shinny without any cracks or crumbled edges, the soil is too moist. If the exposed soil surface crumbles and cracks, the soil is dry enough for preparation. To prepare the soil interface, stake the basal area and remove any forest duff and forest under growth, if present. Trees and stumps should be left in place. In pasture or lawn areas, mow the grass as short as possible. After removing as much loose organic material as possible, rake the soil surface 2-3 deep parallel to the contour throughout staked basal area. The teeth of a backhoe bucket can be used. Do not remove sod. Apply the base layer of sand media as per the design. The top of sand layer under the coil must be level. Place the coils and connect the supply and flush manifolds as prescribed in the design. It is recommended to place the manual headworks near the OSCAR at the same elevation or higher than the coils. The flush line for the OSCAR shall terminate in the discharge tank. Two inspection ports must be installed: one in the coil area and the other in the basal area. Place the final 6 of sand media for final cover. It is recommended to immediately broadcast grass seed or plant a ground cover, preferably periwinkle (vinca-minor). A layer of natural mineral soil can be added to cover the sand, but is not needed to establish plant growth. Do not use a manufactured top soil mix. Also, avoid soil that is high in organic matter. A couple of inches of beauty bark could be used to top dress the sand. 13

Start-up Instructions: Before powering up the control panel, inspect the wiring to insure the connections were done correctly. Fill the discharge tank with enough water to completely submerge the pump plus 5-6 of addition water. Manually turn on the discharge pump and open the flush valve in the LOT-HWN-.7 headworks. Flush for 3-4 minutes. Turn off pump and remove and clean the disc filter. Replace the disc filter and activate the pump again. Repeat this step until no more debris is caught by the disc filter. Close the flush valve completely and activate pump. Wait for the pressure to stabilize and then record the flow for one minute. The flow rate for each coil is 0.35 gpm. Verify the flow rate is consistent with the number of OSCAR coils installed. (See Table XY for dosing flow rate). Open flush valve completely and turn on pump. Record the flush flow rate. The flush flow rate should be at least what is listed in table XY for Flush GPM. Leave the HOA toggle switch in the AUTO position. The timer settings are factory set. TABLE XY Design flow Total coils # of lats. Coils per lat. Dose GPM Flush GPM Excess TDH 240 5 5 1 1.75 9.75 105 360 8 4 2 2.8 9.2 105 480* 10 2 5 3.5 6.7 70 480* 10 5 2 3.5 11.5 100 600 12 3 4 4.2 9 80 *There are two options with the 480 gpd flow rate: 2 laterals with 5 coils per lateral or 5 laterals with 2 coils. All coils must be in a single line. Step 13: Panel Operation and Start-up procedures. Panel Operation: The LF2P-RF-OS control panel is a 110 volt universal panel for most single family OSCAR-LOWeFLOW systems. It has the capacity to operate three major outputs: recirculation pump, discharge pump, and the Reverse Flush headworks. All logic is controlled by a Siemens Logo. The pump operation options are as follows: Recirc. Pump (Pump #1): is operated in a time-dose mode. Pump #1 pressurizes the Coil and back-flushes the disc filter and forward flushes the Coil(s). The control panel allows the operator to determine the number of dose cycles before the disc filter flush and Coil flush cycles. This pump has a redundant off 14

float switch that will shut off Pump #1 if the liquid level falls below the minimum liquid level. Discharge Pump (Pump #3): Verify the pump runs. The discharge pump is timedosed. The bottom float switch operates as the Timer On float switch. The high level alarm float will override Pump #1 off. The timers have the following factory default settings (see timer setting chart in Timer Settings Chart below: Recirculation-pump dosing: 3.5 minutes off, 30 seconds on. (V1_OFF, V1_ON) Disc filter flush: after pre-set number of dose cycles have completed (90 doses), the disc filter flush ON cycle runs for 15 seconds. (V2_ON). Coil flush: after Disc filter flush is completed, the Coil flushes for 2 minutes (V1V3_ON). Discharge pump settings: proprietary. Call Lowridge for assistance if discharge settings need to be changed. Start Up Procedures: Prior to conducting any of the following procedures, inspect the wiring to insure the system is correctly wired. Pull all the float trees from the tanks and place across the tank openings so all the floats hang down. Now power up the system and turn all the breakers to the ON position. Ensure there is enough water in tanks to conduct pump tests. Follow all the steps in order as outlined in this manual. a. Test pumps: Recirculation/Flush pump: To energize the recirculation pump position pump #1 (recirc pump) toggle switch and V1 toggle switch to Hand. Pressures in headworks should rise and stabilize in a few seconds. Position toggle switches to AUTO. Discharge pump: Energize the discharge pump by switching the Pump #3 toggle switch to HAND. Verify pump runs. Then switch toggle to AUTO. b. Test floats: Test recirculation floats: Lift top float. The alarm should sound and the beacon should illuminate. Test the discharge floats: Lift the top float, the alarm should sound, the beacon light illuminate, and recirculation pump should stop. Replace floats in the 15

discharge tank insuring the bottom float is inverted. The discharge pump will cycle in a few minutes. c. Test Headworks valves: While the recirculation pump is running, all three pressure gauges should be reading approximately 30-35 psi and no water should be flowing into the inlet of the septic tank. To test the disc filter flush sequence, go to the control panel and set the timers for the following: V1_OFF= 30 seconds, V1_ON= 30 seconds. V1_COUNT for 2 cycles (ON=2) V2_OFF: 30 seconds, V2-ON: 15 seconds V2_COUNT for 1 cycle (ON=1) V1V3_OFF; 30 seconds, V1V3_ON: 2 minutes V1V3_CNT for 1 cycle (ON=1) These parameter settings will enable the dose sequence to activate on and off every 30 seconds for two cycles. Pressures on all gauges will read about 30-35 psi. After two (2) dose cycles the system will flush the filter for 15 seconds, then flush the Coil for 2 minutes and then the dose sequence will start again. During the flush cycle the pressure readings will fluctuate much lower than during dosing. During the flush sequence liquid will be flowing into the inlet of the septic tank. Allow the system to cycle multiple times. Check for leaks and proper valve function. Clean disc filter: Turn power off to the recirculation pump, loosen backing nut on the filter housing, remove disc filter housing, and remove disc filter cartridge. Rinse filter cartridge into tank and re-assemble the disc filter. Turn power on to the recirculation pump. d. Test splitter valve Fill the recirculation tank to the minimum liquid level or slightly higher. The minimum liquid level is approximately 6 below the top of the 4 shroud. Liquid flowing from the bottom of the LOWeFLOW filter into the splitter valve will start to fill up the stand pipe of the splitter valve. Within a couple of minutes, liquid should be flowing into the discharge basin or tank. Allow the recirculation pump to run until the liquid level in the recirculation tank drops low enough for the splitter valve to unseat. At this point no liquid should be 16

flowing into the discharge basin and all returning liquid from the LOWeFLOW filter will drop into the recirculation tank. e. Verify recirculation flow and pressure. While the recirculation pump is running, remove the splitter valve. Capture and measure the amount of water that falls through the splitter Tee in 30 seconds. The average flow rate for a single 500 gpd Coil dosed 30 seconds on and 30 seconds off should be between 2 to 2.5 gpm. Reset the timer settings to the following: V1_OFF: 3.5 min, V1_ON: 30 seconds V1_COUNT, ON=90 Leave the remainder of the settings the same. Timer Settings for Recirculation Pump The goal is to achieve a recirculation ratio of 4:1 of the average daily flow. The table below gives the timer settings for a variety of average daily flows. Note that the ON time is always 30 seconds. The standard 500 gpd Coil has an estimated dose volume of approximately 2.5 gal/dose. Actual flow may vary. Ave. Daily Flow Recirc. Flow rate ON Time OFF Time 100 gpd 400 gpd 30 seconds 9.5 min 150 600 6.0 200 800 4.5 250 1000 3.5 300 1200 3.0 350 1400 2.5 400 1600 2.0 500 2000 30 seconds 1.5 min Replacement Instructions: There are several components that are critical to process performance: solenoid valves in the headworks, drip tubing in the Coil, and the dosing/flush pump. 17

Solenoid Valves, 2-way throttling valve, Netafim part number, 61ET1PBI-BC: To replace remove six screws, remove bonnet, remove and replace diaphragm, replace bonnet and tighten screws. Valves can be purchased from Lowridge Onsite Technologies. Coil, 4-100 laterals of Netafim Bioline, 08WRAM.4-06V500: To replace the Coil remove gravel media from top of Coil, cut each of the 1 PVC feed lines adjacent to the manifolds, fold the feed lines up, and removed Coil. Place the new Coil in the basin, fold down the feed lines and glue the manifold to the feed lines, and cover Coil with pea gravel. Coils can be obtained from any LOWeFLOW dealer or Lowridge Onsite Technologies, LLC. Dose/Flush Pump, Flint and Walling FWF 5031-0005: Cut power to pump, disconnect wire connections in splice box, remove pump from tank, and disconnect pump from piping. Connect new pump piping, connect wiring in splice box, place pump into tank, and re-energize power to pump circuit. Material Specifications: Media: LOWeFLOW ASTM C-33, #8, nominal size 9.5mm to 2.36mm Size 12.5mm 9.5mm 4.75mm 2.36mm 1.18mm %passing 100 85-100 10-30 0-10 0-5 OSCAR ASTM C-33 concrete sand as per WADOH Recommended Standard & Guidance for Intermittent Sand Filter. Containment Vessels: All containment vessels must on the WA DOH approved list of containment vessels. Man-hole openings must be 24 nominal size to surface grade with a locking lid to preclude un-authorized access. All tanks must be water tight to the riser lid opening. All Protrusion through the riser wall for electrical conduits and other piping must be sealed to preclude any water infiltration. Septic tanks: Septic tanks must conform to local or State codes. At a minimum, septic tanks must be single compartment with a retention time of 1.6 times the daily design flow. Minimum design flow is 500 gpd. Larger tanks sizes and multiple compartment septic tanks are acceptable. Inlet and outlet connections must have a Fernco type boot with a stainless 18

steel clamp. Other sealing mechanisms can be used with prior written approval from Lowridge Onsite Technologies, LLC. Concrete: Where ever possible, concrete tank bodies should be single piece construction. Man-hole risers should be cast in-place. Recirculation Tanks: Recirculation tanks must have a minimum volume to accommodate the minimum liquid level, working volume, and emergency storage criteria. Local or State code may dictate differing emergency storage volumes. Septic/Recirculation combination: A second option for the septic tank and recirculation tank is to use a double compartment tank with a flow through port between the two compartments. At a minimum, a 1500 gallon tank with a 2/3, 1/3 volume split between the first and second compartment is required. The first compartment is the primary of settling vessel and the second compartment is the recirculating tank. A minimum 4 diameter flow through port must be installed at 24-29 above the tank floor. The minimum liquid level for this option is 39-40 for a 500 gpd design flow. LOWeFLOW Filter Containment Vessel: Regardless of the material used, all containment basins must have the structural strength to be self supporting filled with media or buried to surface grade. Polyethylene: the poly basin is made from medium to low density polyethylene with a wall thickness of 0.150, and resistant to UV light degradation. The inside diameter of basin is 61 and is 36 tall. The 5 foot nominal size diameter provides 20 sq. ft. of surface area. The underdrain, supply and flush lines enter the vessel through the sidewall near the bottom. The supply and flush lines are plumbed horizontally to the center of the basin and then vertically to connect to the Coil manifolds. PVC line wood box: Minimum lined box dimensions are 5 x 5 wide by 36 deep. The box is made of 1/2 marine plywood with three outer supportive bands of pressure treated 2 x 4 s. The box is lined with a 30 ml PVC liner with a boot underdrain. The supply and flush lines are routed to the bottom corners of the box and then vertical between the interior of the box and the PVC liner. The supply and flush lines are connected to the Coil manifolds just below the top of the container. Plumbing: All piping must be PVC. The 2 underdrain and 1 supply and flush lines must be sch40. Assembled components: Lowridge assembles the following components: headworks, splitter tee, splitter valve, Coil, and Coil manifolds. Headworks: the headworks for the LF-500 is made of all 1 sch PVC pipe and fittings, 1 NC Dorot solenoid valves, 3/4 Arkal disc filter (120 mesh, 130 micron), Three oil filled pressure gauges, and a polyethylene valve box with lid. Splitter tee: Splitter tee is made from 2 sch40 PVC pipe, a 2 x 2 x 1 tee with a 2 x 1 bushing. 19

Splitter valve: The splitter valve is made of a combination of 2 sch 40 pipe and fittings and 4 ASTM 3034 pipe. Coil: The Coil is constructed of Netafim Bioline (0.42 gph emitter at 6 spacing) attached to a 2 PVC bracket. Recirculation Pump: The recirculation pump is a ½ hp, 115 volt, 19 or 30 gpm rated turbine pump. 20