CRAFTSMAN EXAMINATION, NOVEMBER 2009 PLUMBING QUESTION AND ANSWER BOOKLET. Time allowed THREE hours

Similar documents
REGISTRATION EXAMINATION, NOVEMBER 2017 TRADESMAN PLUMBER QUESTION AND ANSWER BOOKLET. Time allowed THREE hours

CRAFTSMAN EXAMINATION, JUNE 2007 PLUMBING QUESTION AND ANSWER BOOKLET. Time allowed THREE hours

REGISTRATION EXAMINATION, NOVEMBER 2014 LICENSED PLUMBER QUESTION AND ANSWER BOOKLET. Time allowed THREE hours

REGISTRATION EXAMINATION, JUNE 2015 LICENSED PLUMBER QUESTION AND ANSWER BOOKLET. Time allowed THREE hours

CRAFTSMAN EXAMINATION, NOVEMBER 2009 GASFITTING QUESTION AND ANSWER BOOKLET. Time allowed THREE hours

REGISTRATION EXAMINATION, NOVEMBER 2011 CERTIFYING PLUMBER QUESTION AND ANSWER BOOKLET. Time allowed THREE hours

CRAFTSMAN EXAMINATION, JUNE 2007 PLUMBING ANSWER SCHEDULE

REGISTRATION EXAMINATION, JUNE 2013 CERTIFYING PLUMBER QUESTION AND ANSWER BOOKLET. Time allowed THREE hours

REGISTRATION EXAMINATION, NOVEMBER 2011 CERTIFYING PLUMBER ANSWER SCHEDULE

REGISTRATION EXAMINATION, NOVEMBER 2016 LICENSED GASFITTER QUESTION AND ANSWER BOOKLET. Time allowed THREE hours

REGISTRATION EXAMINATION, NOVEMBER 2014 LICENSED PLUMBER ANSWER SCHEDULE

REGISTRATION EXAMINATION, NOVEMBER 2017 TRADESMAN PLUMBER ANSWER SCHEDULE

STUDENT NOTES Plan, size and layout sanitary pipe work and fixtures

REGISTRATION EXAMINATION, NOVEMBER 2016 CERTIFYING PLUMBER ANSWER SCHEDULE

REGISTRATION EXAMINATION, JUNE 2012 LICENSED GASFITTER QUESTION AND ANSWER BOOKLET. Time allowed THREE hours

REGISTRATION EXAMINATION, JUNE 2015 LICENSED PLUMBER ANSWER SCHEDULE

Pipe Sizing Table. Hydraulic Load Served (fixture units)

Level 1 Economics, 2016

Level 1 Physics, 2016

2. Sanitary Plumbing General Installation Requirements

Installing, modifying and maintaining domestic plumbing systems. Water Supply (Water Fittings) Regulations 1999

Level 1 Agricultural and Horticultural Science, 2011

THE CHEAPEST WAY TO HEAT YOUR WATER

Self-Containment Of Motor Caravans

PLUMBING INSTALLATIONS

NZS 4517:2010. New Zealand Standard. Fire sprinkler systems for houses. Superseding NZS 4517:2002 NZS 4517:2010

Water Supply (Water Fittings) Regulations 1999

Read Only Document Not For Distribution

Read Only Document Not For Distribution

CHAPTER VI BUILDING PLUMBING

D8) Saving water and energy on water systems. W.G. van der Schee (1) Abstract. Keywords. 1 Introduction. (1)

SUBCOURSE EDITION EN5155 US ARMY ENGINEER SCHOOL CLEAR WASTE SYSTEM STOPPAGES PLUMBING VI

Special Requirements For Health Care Facilities

House Drainage System. Building Utility & Services

BUILDING OR RENOVATING? Jonathan Smith. The Plumbers, Gasfitters and Drainlayers Board (PGDB) says: ASK TO SEE THEIR CARD

Australian/New Zealand Standard

ELECTRICAL APPLIANCE SERVICEPERSON EXAMINATION 19 November 2016 QUESTION AND ANSWER BOOKLET

AIR ADMITTANCE VALVES FOR DOMESTIC PROPERTIES Guidance Notes

Plumber Level 3 Rev. May 2011

HOME INSPECTION CHECKLIST

CERTIFYING GASFITTER

AS/NZS :2015. Plumbing and drainage AS/NZS :2015. Part 4: Heated water services. Australian/New Zealand Standard

Helping you understand your water usage

Compliance Document for New Zealand Building Code Clause G12 Water Supplies Third Edition

Helping you to understand your water use

Trade of Plumbing. Module 2: Domestic Hot and Cold Water Service Unit 11: Sanitary Appliances Phase 2

Cork Institute of Technology Higher Certificate in Engineering in Building Services Engineering Award

Read Only Document Not For Distribution

New Zip AquaFlo. Stainless steel cylinders for mains pressure hot water

PROPOSED NEW BUILDING

INSTALLATION INSTRUCTIONS OWNERS GUIDE & WARRANTY STATEMENT

Owner s Manual. Installation Details Owner s Information. 80L to 400L Electric Storage Water Heaters

Installation Instructions. Filtered Chilled drinking water for commercial kitchens and tea rooms.

CPCPWT3020A Connect and install storage tanks to a domestic water supply

ADVANCE ECB ELECTRIC COMBINATION BOILER

APPENDIX L ALTERNATE PLUMBING SYSTEMS

2012 UPC Chapter 6 Water Systems Part 2 RV

SCHOOL DISTRICT PALM BEACH COUNTY BUILDING DEPARTMENT PLAN REVIEW CHECK LIST -- PLUMBING

Sanitary Drainage Systems

CHAPTER 31. VENTS Reserved 2003 INTERNATIONAL RESIDENTIAL CODE 425R

Summary of BBS Proposed Ohio Plumbing Code Rule Changes October 2016

ELECTRICAL APPLIANCE SERVICEPERSON EXAMINATION 7 May 2016 QUESTION AND ANSWER BOOKLET

INSPECTION OF COMMERCIAL KITCHEN PLUMBING

Building Utilities 1 Plumbing and Sanitary Systems

CHAPTER 9 VENTS. run undiminished in size and as directly as possible from the building drain through to the open air above the roof.

OWNER S MANUAL WARRANTY INFORMATION AND INSTALLATION INSTRUCTIONS PROFLO AND MARATHON ELECTRIC STORAGE WATER HEATERS

CHAPTER 9 VENTS SECTION

Methods of Venting Plumbing Fixtures and Traps in the 2018 IPC

Level 1 Physics, 2014

LABOUR RATES FOR PLUMBING CONTRACTORS. A guide to the labour costs of plumbing works LABOUR RATES FOR PLUMBING CONTRACTORS

Owner s Manual. Installation Details Owner s Information Warranty. Electric Storage Water Heaters

Lecture : Introduction to building services I - Plumbing & Drainage Services 22 September 2016

CHAPTER 10 TRAPS AND INTERCEPTORS

PLEASE LEAVE THIS MANUAL WITH THE OSO UNIT AFTER INSTALLATION INSTALLATION MANUAL

2016 Plumbing Supplemental Plan Review List

MULTISAN Fully automatic sewage and waste water pump

Macerator Pumps & Lifting Station. Technical presentation Part 1

Design and size heated and cold water services and systems

WALLACE MAXIPUMP 3000, 5000, 6000 and HYDROJET 30P, 30C, 140 AND HJ400 INSTALLATION AND MAINTENANCE INSTRUCTIONS

OWNER S GUIDE. Electric and Gas Storage Water Heaters. Safety Information Owner s Information Warranty. Models

Top Tips for saving water in the home and in the garden

Design of Cold and Hot Water Systems

SINGLE LEVER CERAMIC DISC MANUAL SHOWER VALVE

HEATRAE SADIA. Installation and User Instructions for the UTC Undersink Vented Water Heater

MATERIALS Traps TRAPS. No. IPC IRC Description

City of Gainesville Inspection Permitting Fees Effective July 1, 2012

OWNER & INSTALLER MANUAL AND WARRANTY INFORMATION.

ENGINEERING STANDARD FOR SANITARY PIPEWORK ORIGINAL EDITION JAN. 1995

Gulfport, Mississippi 21 May 2007

Union County Vocational - Technical Schools Scotch Plains, New Jersey

DESIGN AND CONSTRUCTION STANDARDS GENERAL DESIGN GUIDELINES

BACKFLOW PREVENTION GUIDE FOR COMMERCIAL, INSTITUTIONAL AND INDUSTRIAL DEVELOPMENTS

Zip Domestic ChillTap

PLEASE LEAVE THIS MANUAL WITH THE OSO UNIT AFTER INSTALLATION INSTALLATION MANUAL

O Pro electric storage water heater

PRESSURE SEWER SYSTEMS GUIDE FOR HOME OWNERS AND BUILDERS

IPC Plumbing Exam. Name: Carefully read each question and then circle the letter of the best answer.

Unit 1: Fire Engineering Science (A/505/6005)

HANDHELD SHOWER. Installation and Maintenance Instructions. SP272 Series. SP273 Series. SGR027 Series SGR028 Series SGR029 Series.

Owners Manual for the Rainmaster Water Recycling System

Transcription:

Affix label with Candidate Code Number here. If no label, enter candidate Number if known No. 9195 CRAFTSMAN EXAMINATION, NOVEMBER 2009 PLUMBING INSTRUCTIONS QUESTION AND ANSWER BOOKLET Time allowed THREE hours Check that the Candidate Code Number on your admission slip is the same as the number on the label at the top of this page. Do not start writing until you are told to do so by the Supervisor. Total marks for this examination: 100. The pass mark for this examination is 60 marks. Write your answers and draw your sketches in this booklet. If you need more paper, use pages 21 25 at the back of this booklet. Clearly write the question number(s) if any of these pages are used. All working in calculations must be shown. Candidates are permitted to use the following in this examination: Drawing instruments, approved calculators The following are NOT permitted in the examination room: Any publications, Acts, Regulations, Codes of Practice, or Standards Check that this booklet has all of 25 pages in the correct order and that none of these pages is blank. YOU MUST HAND THIS BOOKLET TO THE SUPERVISOR AT THE END OF THE EXAMINATION Plumbers, Gasfitters and Drainlayers Board, 2009. All rights reserved. No part of this publication may be reproduced by any means without the prior permission of the Plumbers, Gasfitters and Drainlayers Board.

QUESTION 1 Give TWO reasons why plumbers need to have knowledge of NZS 3604: Timber Framed Buildings when designing plumbing systems. 1 2 Total 2 marks Craftsman Plumbing 9195, November 2009 1

QUESTION 2 (a) AS/NZS 3500 Part 1: Water services requires that supply tanks be fitted with an overflow. State THREE requirements of the standard that must be met in relation to the discharge point of the overflow. 1 2 3 (3 marks) Craftsman Plumbing 9195, November 2009 2

QUESTION 2 (cont d) (b) A storage tank is to be installed to supply wash-down water to a dairy shed complex. The volume of the tank is 25 000 litres. The inflow pressure is 500 kpa. The tank must fill from empty in 1.25 hours. With the aid of the following table, determine the diameter of the float-valve inlet orifice. Show the calculation required. Rate of inflow to storage tanks Diameter of float valve inlet orifice (mm) Inflow at 500 kpa (L/s) 6 0.54 8 0.95 10 1.49 15 3.40 20 6.00 25 9.30 32 15.30 40 23.80 (3 marks) Total 6 marks Craftsman Plumbing 9195, November 2009 3

QUESTION 3 (a) In a multi-storey building, water for sanitary fittings and fixtures is supplied from a header tank on the roof. Pressure ratio valves can be installed at various levels to lower the supply pressure to the rated working pressure of the fittings and fixtures. In order to comply with AS/NZS 3500 Part 1: Water services, the installation of these valves must meet specific installation requirements. Give these requirements. 1 2 3 4 5 (5 marks) Craftsman Plumbing 9195, November 2009 4

QUESTION 3 (cont d) (b) A supply tank and pipework tank have been installed to supply drinking (potable) water. Following are the specifications for the installation. Tank A, 3500mm in diameter, with the overflow level 2500mm above the base. Tank B, 2800mm in diameter, with the overflow level 2200mm above the base, on a 300mm high stand. The tanks are manifolded together by 2.5m of 80mm NB pipe. There is a total length of 24m of 50mm NB pipe from the tanks to the outlet. The supply tank and pipework must be chlorinated before being put into service. 400ml of 12.5% sodium hypochlorite solution must be used for each 1000 litres of water capacity in the installation. Calculate the amount of sodium hypochlorite solution required to chlorinate the complete installation. Give your answer in litres. (4 marks) Craftsman Plumbing 9195, November 2009 5

QUESTION 3 (cont d) (c) A water reticulation system is to be installed. The pipes and fittings must be selected to ensure compliance with AS/NZS 3500 Part 1: Water Services. Give FOUR factors to be taken into account when selecting the material for the pipes and fittings. 1 2 3 4 (4 marks) Total 13 marks Craftsman Plumbing 9195, November 2009 6

QUESTION 4 (a) Give THREE aspects of the way in which a craftsman plumber must provide direction as determined by the Plumbers, Gasfitters and Drainlayers Board. 1 2 3 (3 marks) (b) Give THREE aspects of the way in which a craftsman or registered plumber must provide supervision as determined by the Plumbers, Gasfitters and Drainlayers Board. 1 2 3 (3 marks) (c) A non-apprentice working at plumbing has held a limited certificate for less than two years. Give the supervision requirements for this class of worker. (2 marks) Total 8 marks Craftsman Plumbing 9195, November 2009 7

QUESTION 5 The drawing opposite is a schematic plan of an undertaker s premises. The water pipe layout and the usage of the various areas are shown. Backflow protection is to be provided to comply with the minimum requirements of the New Zealand Building Code Clause G12 Water Supplies. Mechanical backflow prevention devices are to be used for all containment, zone and individual backflow prevention. (a) (b) (c) (d) For each area where an actual or potential cross-connection hazard exists, label on the plan the hazard rating. On the plan, show the position of each mechanical backflow prevention device required. Label each backflow prevention device to show whether it is for individual, zone or containment purposes. Label each pipeline either drinking (potable) water or non-drinking (non-potable) water. Craftsman Plumbing 9195, November 2009 8

QUESTION 5 (cont d) Boiler room Car wash area Mortuary Embalming room Boundary Non-carbonated drink dispenser Staff cafeteria Water supply Fire hose reel Hose tap Territorial Authority Water Main Manager s residence Public reception area Kitchen Irrigation system with chemical injection Total 11 marks Craftsman Plumbing 9195, November 2009 9

QUESTION 6 The graph below relates to the discharge rates for the relief valves of reduced pressure zone backflow prevention devices. 1205 RELIEF VALVE DISCHARGE RATES for Reduced Pressure Zone Devices Zone Pressure (kpa) 1035 860 690 520 345 172 20mm, 25mm, 32mm 40mm, 50mm 65m 80m 100m, 150mm 200m, 250mm Typical flow rates for floor drains 50mm 80mm 100mm 125mm 150mm 200mm 208L/min 423L/min 643L/min 964L/min 1703L/min 2876L/min 0 0 378 757 1135 1514 1892 2271 2649 3028 3406 Flow Rate (L/min) From the graph, establish the rate of discharge and the size of the drain required for the following diameter backflow prevention device installations. (a) A DN 25mm device operating at 1035kPa. (i) The discharge rate. (ii) The diameter of the drain. (1 mark) Craftsman Plumbing 9195, November 2009 10

QUESTION 6 (cont d) (b) A DN 20mm device operating at 690kPa. (i) The discharge rate. (ii) The diameter of the drain. (1 mark) (c) A DN 80mm device operating at 520kPa. (i) The discharge rate. (ii) The diameter of the drain. (1 mark) (d) A DN 40mm device operating at 860kPa. (i) The discharge rate. (ii) The diameter of the drain. (1 mark) Total 4 marks Craftsman Plumbing 9195, November 2009 11

QUESTION 7 A residential apartment is to be supplied with hot water from a storage hot water heater. The heater has a capacity of 200 litres and a 3.5kW electric element. The water is to be heated to 70ºC. The temperature of the water entering the storage hot water heater is 7ºC. The apartment has: one shower one handbasin one kitchen sink one dishwasher one clothes washer. (a) Complete the table below to calculate the possible maximum simultaneous hot water demand for the apartment. Typical flow rates of hot water demand at the outlet of fittings Fitting Flow rate Shower 0.1 L/s Handbasin 0.1 L/s Kitchen sink 0.2 L/s Clothes washer 0.2 L/s Dishwasher 0.2 L/s TOTAL (2 marks) (b) When the shower, sink and dishwasher are operating simultaneously, the delivery flow rate of mixed water is 0.9 litres/s. Calculate the delivery temperature of the water in this situation. Formula: Litres hot water temp. rise cold to hot = litres mixed water temp. rise cold to mixed (3 marks) Craftsman Plumbing 9195, November 2009 12

QUESTION 7 (cont d) (c) Calculate, in hours and minutes, the recovery time of the water heater if 2.5% of the energy input is lost during the heating process. The specific heat of water is 4.2 kj/kg/ºc Formula: Energy input = mass of water (kg) specific heat of water temperature difference 1000 3.6 time (h) (5 marks) Total 10 marks Craftsman Plumbing 9195, November 2009 13

QUESTION 8 The drawing below shows individual valve vented storage hot water heaters installed above each other in an apartment building. All valves discharge to a common stack, which then discharges into the branch to the soil stack. Complete the drawing to show the following so that the system complies with AS/NZS 3500 Part 4: Heated water services. (a) (b) (c) the method of discharge from the individual valves the common stack the method of discharge to the soil stack. HWC HWC HWC HWC HWC Branch to soil stack Total 4 marks Craftsman Plumbing 9195, November 2009 14

QUESTION 9 (a) A hot water supply reticulation system is to be designed. Give the FIVE design requirements that must be met for the piping system to comply with AS/NZS 3500 Part 4: Heated water services. 1 2 3 4 5 (5 marks) (b) Give THREE advantages of multiple valve vented storage heaters being installed in parallel. 1 2 3 (3 marks) (c) Give THREE disadvantages of multiple valve vented storage heaters being installed in series. 1 2 3 (3 marks) Total 11 marks Craftsman Plumbing 9195, November 2009 15

QUESTION 10 The drawing opposite shows a cross-sectional view of a residential building. The drawing is not to scale. Sanitary fixtures and the drain below the floor slab are shown. The grade of the drain is 1.65%. The foul water pipework is to be installed to comply with the minimum requirements of AS/NZS 3500 Part 2: Sanitary plumbing and drainage. (a) Using the tables below, complete the drawing to show: (i) connections to the drain (ii) venting requirements (iii) overflow relief (iv) diameters of foul water pipes and vent(s) (v) traps. Fixture unit ratings Fixture Min. discharge pipe size Fixture unit rating Basin 40 1 Bath 40 4 Sink 50 3 Shower 40 2 Water closet pan with flush valve 100 6 Maximum Fixture Unit Loading For Vented Drains Nominal size of drain, DN Grade % 65 80 100 2.50 25 100 255 2.00 76 205 1.65 61 165 1.45 50 140 1.25 42 120 Size of vents Size of vent pipe Fixture units discharging to drain 40 >1 < 10 50 >10 <30 65 >30 < 175 80 >175 < 400 100 > 400 Craftsman Plumbing 9195, November 2009 16

QUESTION 10 (cont d) 12000mm Sink Shower Bath 900 mm 1000 mm Basin WC 1600 mm Basin GL FWG GL Drain Grade 1.65% Demarcation point (10 marks) (b) The drain below the floor slab is laid with a grade of 1.65%. The distance from the top of the pipe at the head of the drain to the floor level is 450mm. Calculate the level of the drain invert below the floor at the demarcation point with the drainage contractor. (2 marks) Total 12 marks Craftsman Plumbing 9195, November 2009 17

QUESTION 11 The diagram opposite shows a foul water installation consisting of four discharge stacks. All the stacks are to have relief vents fitted. All the relief vents are to discharge through a header vent. The header vent is to discharge to the stack vent from the 100mm foul water stack. The developed length of each relief vent is 16 metres. The system is to comply with the minimum requirements of AS/NZS 3500 Part 2: Sanitary plumbing and drainage. (a) Complete the drawing to show the relief vents, header vents and stack vent. (4 marks) (b) Using the fixture unit ratings and stack diameters shown on the diagram and the tables below, size all the vents. Show your answers on the diagram. (7 marks) Size of relief vents and stacks Vent size (dn) 32 40 50 65 80 100 Stack size (DN) Fixture unit load Length of vent in metres 40 16 6 15 50 20 8 15 46 50 36 6 10 30 65 20 12 40 110 65 56 7 24 80 170 80 20 8 27 70 110 80 80 12 20 100 150 9 25 70 280 100 300 8 22 60 216 100 500 6 19 50 197 Size of header vents Size of stack vent or relief vent DN Equivalent number of DN 50 vents 50 1 50 65 2 65 80 3 80 100 6 100 Size of header vent DN Craftsman Plumbing 9195, November 2009 18

QUESTION 11 (cont d) Roof line Ceiling line 65mm Stack 24 FU 50mm Stack 34 FU 80mm Stack 79 FU 100mm Stack 185 FU Total 11 marks Craftsman Plumbing 9195, November 2009 19

QUESTION 12 (a) List FOUR performance outcomes that a building s foul water system must meet to comply with the New Zealand Building Code. 1 2 3 4 (2 marks) (b) List TWO factors used when calculating the size of roof gutters as specified in the New Zealand Building Code Clause E1/AS1 Surface Water. 1 2 (2 marks) (c) State when it is necessary to provide overflow outlets to roof gutters in order to comply with the New Zealand Building Code Clause E1/AS1 Surface Water. (1 mark) (d) Give THREE requirements of the New Zealand Building Code Clause E1/AS1 Surface Water that must be met when overflow outlets are being installed in internal roof gutters. 1 2 3 (3 marks) Total 8 marks Craftsman Plumbing 9195, November 2009 20

This page is available for additional working or answers Question number Craftsman Plumbing 9195, November 2009 21

This page is available for additional working or answers Question number Craftsman Plumbing 9195, November 2009 22

This page is available for additional working or answers Question number Craftsman Plumbing 9195, November 2009 23

This page is available for additional working or answers Question number Craftsman Plumbing 9195, November 2009 24

This page is available for additional working or answers Question number Craftsman Plumbing 9195, November 2009 25

For Examiner s use only Question number Marks Marks 1 2 3 4 5 6 7 8 9 10 11 12 Total