Injection with front ends open at the ESRF

Similar documents
Minimizing radiation and beam losses at the ESRF

Radiation Safety issues for the PF-AR in KEK

Radiation Safety issues for the PF-AR in KEK

Goals Understand Responsibilities, Awareness, Communication. Beamline phases Design, Implementation, Commissioning, Operation

Vacuum Quality Assurance in Practice

SYNCHROTRON RADIATION ABSORPTION AND VACUUM ISSUES IN THE IR*

VACUUM PERFORMANCE IN THE MOST RECENT THIRD GENERATION SYNCHROTRON LIGHT SOURCES

A CONCEPT FOR CANCELLING THE LEAKAGE FIELD INSIDE THE STORED BEAM CHAMBER OF A SEPTUM MAGNET*

Dosimetry issues related to the SSRT project at the ESRF

Beam Loss Position Monitoring with Optical Fibres at DELTA

LCLS Instruments. Jerry Hastings June 20, 2008 LCLS

Table of Contents. Check the LCLS Project website to verify 2 of 12 that this is the correct version prior to use.

Performance Requirements for Monitoring Pulsed, Mixed Radiation Fields Around High-Energy Accelerators

MD456: Monitoring of abort gap population with diamond particle detectors at the BGI in IP 4

Change History Log. Rev Revision Sections Affected Description of Change /22/08 All Initial Version

Vacuum requirements and Beamline interface at the VUV-FEL User Facility

General PSS principles an introductory guide

Machine-Detector Interface

Radiation Safety for AREAL Phase 1

BESSY ventilation concept

COMMISSIONING OF THE DOSE DELIVERY SYSTEM AT MEDAUSTRON

Competency: Critically evaluate the function of the ionisation chamber in the Linear Accelerator and its importance for correct treatment delivery

How to improve air cooler vacuum steam condensers performance in the field

Active Scanning Beam 2: Controlling Delivery

Laser Damage Measurements

Applying Layer of Protection Analysis (LOPA) to Accelerator Safety Systems Design. Feng Tao

ISIS Design Division Electrical Engineering. S Birch. September 2012.

Abstract. 1 NSRRC, 101 Hsin-Ann Road, Hsinchu 300, Taiwan 2 Dept. of Biomedical Engineering & Environmental Sciences, NTHU, Hsinchu 300, Taiwan

FRIB MACHINE PROTECTION SYSTEM DESIGN AND VALIDATION STUDIES*

XFEL Collimation and Beam Switchyard Vacuum Issues

ARCON/RAMSES: Current Status and Operational Risk

Status of the PRad Experiment (E )

Experimental Particle Physics PHYS6011 Joel Goldstein, RAL

Doc. No. SP R0. CXI Reference Laser. Prepared by: Jean-Charles Castagna Signature Date Design Engineer

IE Code IE Competency Title Credit OAC Ref.

22 Radiological and Environmental Monitoring Systems Functions, Basic Configuration, and Interfaces

RAMSES: THE LHC RADIATION MONITORING SYSTEM FOR THE ENVIRONMENT AND SAFETY

Application of two hybrid control methods of expansion valves and vapor injected compression to heat pumps

FEE Diagnostics and Commissioning. June 17, 2008

SpinTron 2: 2-inch High Vacuum Magnetron Sputter Source Product Installation and Use

El63 Laser Acceleration at the NLCTA

Certification Report of the ST3000 Pressure Transmitter

Today s Outline - September 12, C. Segre (IIT) PHYS Fall 2016 September 12, / 21

The use of NEG pumps and coatings in large vacuum systems: experience and limitations

LCLS DIRECTORATE Experimental Facilities Division

Certification Report of the ST 3000 Pressure Transmitter with HART 6

IntegraTorr Sputtered Non-Evaporable Getter. We support your innovation

OVERVIEW AND FUTURE DEVELOPMENT OF THE NEUTRON SENSOR SIGNAL SELF-VALIDATION (NSV) PROJECT

Bunch Length Interferometer System

Forward-scattered radiation from the compression paddle should be considered when average (or mean) glandular dose is estimated

THEORY OR OPERATION 2 SENSOR UNIT - MECHANICAL 6 SENSOR UNIT - ELECTRICAL 8 CONTROL UNIT - MECHANICAL 9 CONTROL UNIT - ELECTRICAL 9 OPTIONS 11

Model Predictive Control of Pilot Spray Dryer Unit Designed and implemented for an Educational Institute

Application of a hybrid control of expansion valves to a 3-ton large room cooling system

arxiv: v1 [physics.ins-det] 27 Jan 2012

DEVELOPMENT OF THE TANGO ALARM SYSTEM

Induction heating with the ring effect for injection molding plates

THE NEXT GENERATION IN VISIBILITY SENSORS OUTPERFORM BOTH TRADITIONAL TRANSMISSOMETERS AND FORWARD SCATTER SENSORS

Ionisation Chambers Containing Boron as Neutron Detectors in Mixed Radiation Fields

NON-DESTRUCTIVE 2-D BEAM PROFILE MONITOR USING GAS SHEET IN J-PARC LINAC -overview & hardware construction-

Using Smoke Obscuration to Warn of Pre-Ignition Conditions of Unattended Cooking Fires

Remote Helium Cooling Loops for Laboratory Applications

FOF INDUSTRIAL SATURATED STEAM STERILIZERS

Application Note. Application Note for BAYEX

Can one cool the MICE magnets and the Hydrogen Absorbers with Small Coolers? Michael A Green Oxford University Physics Oxford OX1 3RH, UK

Victoreen & 660-8

The Shortwave Reflectance of the Yankee Environmental Systems Hotplate

Monitoring of Radiation Exposure Adjacent to a Linear Accelerator Treatment Bunker with a Highlight Window

Engineered and Administrative Safety Systems for the Control of Prompt Radiation Hazards at Accelerator Facilities

Ion Pump Evolution. VacIon Plus. Titanium Sublimation Combination Pumps (TSP)

Development of a Novel Contamination Resistant Ionchamber for Process Tritium Measurement and use in the JET First Trace Tritium Experiment

TSI AEROTRAK PORTABLE PARTICLE COUNTER MODEL 9110

EFFECT OF CENTRAL PILE IN INCREASING THE BEARING CAPACITY OF BORED PILE GROUPS

Failure Modes, Effects and Diagnostic Analysis

SYSTEM DESIGN REQUIREMENTS

STUDY ON THE REACTION TO FIRE OF MEDIUM VOLTAGE CABLES SYSTEMS

Thick-Film Heater achieves Superior Performance in Thermal Response, Uniformity and Efficiency.

Use of control and analytical X-ray apparatus

Turnkey Solutions for Radiation Protection in PET Laboratories R A D I A T I O N P R O T E C T I O N

Conceptual Design of a Better Heat Pump Compressor for Northern Climates

Special Aspects in Designing High - Frequency Betatron

NOTE: The color of the actual product may differ from the color pictured in this catalog due to printing limitation.

United Electric Controls One Series Safety Transmitter Safety Manual

Investigation report. Radiation resistance of fire detectors under the influence of radioactive gamma radiation

Design Considerations of LED based Visible Notification Appliances. Johnny K. W. Siu, Ph.D. - Light Engine Limited I. INTRODUCTION

Rutgers Environmental Health and Safety (REHS)

VAC PLC. System Description

Dosimetric verification of intensity modulated radiation therapy

Mechanical Concept of the TESLA Detector

Radiation Safety Systems

Temperature Distribution of Rotary Heat Recovery Units

CHAPTER 2 EXPERIMENTAL APPARATUS AND PROCEDURES

SR-5/2D Solar-Power-Regulator

PoS(ICHEP2012)516. The status of the CMS pixel upgrade detector

Session Four Functional safety: the next edition of IEC Mirek Generowicz Engineering Manager, I&E Systems Pty Ltd

Induction Billet Heaters with Enthalpy Controlled Zone Heating

Understanding Process Vacuum for Process Improvement

FIRE DYNAMICS IN FAÇADE FIRE TESTS: Measurement, modeling and repeatability

The development of a plastic scintillator for radiotherapy dosimetry

WG Container & Cargo X-Ray Scanning Portal

the production region, magnet and 1st range region, and the 2nd range region. These were added to arrive at a totgl number of V

Transcription:

Injection with front ends open at the ESRF P. Berkvens, P. Colomp and F. Bidault European Synchrotron Radiation Facility Abstract The ESRF is planning to introduce, beginning of 23, a new mode of operation consisting of injection with front ends open. Although it is not foreseen to run a continuous top-up mode - we will continue with our standard operation schemes, with typically two 5 ma top-ups per day in multi-bunch mode - this mode will already drastically reduce the heat load changes on the first optical components of the beamlines during injection. A number of radiation measurements have been carried out to assess the feasibility of this mode in terms of radiation protection. Indeed, the ESRF has adopted a radiation protection policy where all people working in the experimental hall are considered as non-exposed workers. With the present European legislation this means that we must respect the dose limit of 1 msv.y -1 (.5.h -1 ). Because users normally stay for a relatively short period at the ESRF, we have translated this annual dose limit in a dose constraint of.5 4 = 2 per 4-hour period. The results of the radiation measurements showed that while injection with front end open will be feasible within the present radiation policy of the ESRF, it is potentially possible to exceed the 4-hour dose limit in a single 5 ma top-up, in case of degraded injection efficiencies. It has therefore been decided to install an interlocked radiation monitoring system associated with this mode of operation. The paper summarizes the results of the radiation measurements and describes the interlocked radiation monitoring system. 1. Introduction A number of 3 rd generation light sources are using or planning to use continuous topup to compensate for short beam lifetimes, essentially due to reduced vertical apertures to allow for small gap insertion devices. The lifetime at the ESRF is excellent (e.g. better than 6 hours at 2 ma) and continuous top-up is therefore not envisaged. However, the possibility to keep the front ends open during injection presents the obvious advantage of reducing the fluctuations of the thermal power on the beamline s optical elements. All people working at the ESRF (staff members, users, external companies) are considered as non-exposed workers. From the annual dose limit of 1 msv a derived 4-hour dose limit of 4.5 = 2 is obtained. Interlocked radiation monitors integrated in the accelerator personal safety system guarantee this 4-hours dose limit everywhere around the storage ring. Injection with front end open could only be envisaged if it is shown to be feasible with this 4-hour dose constraint. A number of radiation measurements have therefore been carried out in the last 18 months. These measurements, described in detail in the following sections, showed that while injection with front ends open should be possible, the development of a dedicated interlocked radiation monitoring system will be necessary. The latter system will be completed during the 22-23 winter shutdown and injection with front ends open will start at the ESRF during the first weeks of operation in 23.

2. Experimental set-up for the radiation measurements A number of radiation measurements have been carried out to assess the feasibility within the present ESRF radiation protection policy of topping up the storage ring with front ends open. Figure 1 shows schematically the experimental set-up used for these measurements. A lead block was placed behind the front-end pre-pumping vessel to scatter the incident bremsstrahlung. The dimensions of this block were such that the dose rates from scattered bremsstrahlung, as well as the neutron dose rates, are representative for what can be expected from a typical beamline layout. Radiation monitors outside the optics hutch were used to measure the dose integrated during an injection with frontend open. Photon doses were measured using a PTW 5 litre ionisation chamber; while neutron doses were measured using Apfel REMbrandt superheated drop monitors. Inside the optics hutch a small.6 cm 3 farmer-type ionisation chamber was placed in front of the lead block to measure the on-axis bremsstrahlung dose rates this chamber was shielded with 3 mm of lead to stop the dipole synchrotron radiation. 1.5 m 6 o PTW 5 l ionisation chamber Apfel REMbrandt monitors 5 mm Pb 1 mm Pb 1 mm Cu 5 mm Pb 15 mm 4 cm.6 cm 3 ionisation chamber 85 cm 7 cm Be window Figure 1: Experimental set-up used for the radiation measurements A number of measurements were carried out, each measurement consisting in a dose integration for a zero to 2 ma injection with front end open. Different machine

tunings were used to simulate different injection efficiencies, as explained below. Measurements were carried out on a dipole beamline (BM25) and an insertion device beamline (ID31). The straight section of this beamline was equipped with a 5-meter long 8 mm internal height vacuum vessel. All ID gaps were fully opened. The optics hutch on ID31 has a 3 mm thick lead sidewall, the BM25 hutch has an 8 mm thick lead sidewall. Two sets of measurements have been carried out on ID31. In between the first and the second series of measurements the front end was equipped with a 4.5 mm diameter copper aperture. The second set of measurements was therefore representative for undulator beamlines, whereas the first set was representative for wiggler beamlines. 2 o 2 mm 4.5 mm 4 (2) mm 8 mm 1 mm 2 mm Figure 2: 4.5 mm diameter copper aperture in undulator beamlines (left). In the new high power front ends, a similar rectangular 4 4 mm2 (or 4 2 mm2) copper aperture is installed (right). 3. Results and discussion without 4.5 mm copper aperture with 4.5 mm copper aperture integrated dose (2 ma fill) ID31 injection losses (% of 2 ma stored beam) integrated dose (2 ma fill) ID31 injection losses (% of 2 ma stored beam) nominal n: 1.44 γ:.48 total: 1.93 scraper closed n:.38 γ:.11 total:.49 scrapers open n: 4.5 γ: 1.4 total: 5.45 coupling correction off n: 4.9 γ: 14.9 total: 55.8.16 %.33 %.36 % 6.3 % n:.1 γ:.4 total:.14 n: γ: total: n:.6 γ:.1 total:.7 n: 2.1 γ:.44 total: 2.54 2.8 % % 4.7 % 11.4 % Table 1: Results of ID31 measurements. Table 1 shows the results of the measurements on ID31. As explained above a number of 2 ma injections were carried out, and the integrated photon and neutron doses

were recorded. Four different injection conditions were used. Under the nominal conditions an overall injection efficiency of 75 % was obtained. By closing the scrapers in the injection area, the overall injection efficiency was degraded, but the local losses in the cell 31 straight section were reduced. By opening these scrapers the local losses in cell 31 were increased. Finally by switching off the coupling correction these local injection losses were further increased. The injection losses in cell 31 were roughly quantified by using the integrated dose measured with Apfel neutron monitors placed on the roof of the storage ring. Earlier measurements resulted in a conversion factor between electron loss power and dose rate of 2.5.kJ -1 (see reference [1]). The estimated local losses are given in table 1, expressed as % of a 2 ma stored beam ( e.g. 4.7 % means.47 5.6 1-7 C = 26 nc or 158 J) All measurements were carried out with an injection repetition rate of 1 Hz. Whereas the PTW ionisation chambers have a 1% collection efficiency under these conditions, the results from the Apfel monitors were corrected using an efficiency curve that we obtained earlier, from radiation measurements using different values of the current extracted from the booster. This efficiency curve is shown in figure 3. detection efficiency (%) 1 95 9 85 8 75 7 65 6.1.2.3.4.5.6 measured dose (/pulse) Figure 3: Experimentally determined efficiency curve for measuring pulsed radiation with the Apfel REMbrandt neutron monitor. Finally, it was observed that the integrated dose measured with the on-axis thimble ionisation chamber was proportional, under all conditions, with the bremsstrahlung dose measured outside the hutch. This result was used to further quantify injection with front-end open for non-standard filling patterns (see hereafter). The results shown in table 1 should be interpreted in the following way. The typical operation of the ESRF in the standard 2/3 or uniform filling mode consists in a top-up every twelve hours. With lifetimes in these standard filling patterns above 6 hours, roughly 5 ma are injected during these top-ups. As explained above, the radiation protection policy at the ESRF consists in guaranteeing the derived dose-limits for non-exposed workers during 4-hour periods (2 ). Injection with front-ends open

will therefore be compatible with the present radiation protection policy if the added dose due to a 5 ma top-up would not exceed this 2 dose-limit. This comparison is made in table 2. nominal scraper closed scrapers open coupling correction off without aperture.48.12 1.36 13.9 with aperture.4.18.64 Table 2: Total dose integrated during a 5 ma top-up. Fro m table 2 we can conclude that, within the present ESRF radiation protection policy, only extremely detuned beam conditions could lead to unacceptable high doses on wiggler beamlines. On the other hand the results also show that a significant dose increase can be expected from less extreme storage ring conditions, on both wiggler and undulator beamlines. Although the front-end mask drastically reduces the doses outside undulator beamlines compared to wiggler beamlines, these undulator beamlines are expected to have higher local beam losses due to the presence of small gap insertion device vacuum vessels. The general conclusion from our radiation measurements is therefore that under normal operational conditions, injection with front end open is absolutely compatible with our present radiation policy. However the results of these radiation measurements also show that under certain degraded storage ring optics, doses outside the optics hutches could exceed the derived 4-hour dose limits. It was therefore decided to (a) go for this new mode of operation and (b) develop a dedicated interlocked radiation monitoring system for it. The results of the radiation measurements on the bending magnet beamline BM25 did not reveal any significant dose increase due to injection with front-end open. However, as a conservative safety measure it was decided to equally equip the bending magnet beamlines with an interlocked radiation monitor. 4. Non-standard filling patterns A number of non-standard filling patterns are used at the ESRF: single-bunch, 16 bunch and hybrid filling mode. Although the injected charge per top-up in these modes is smaller (typically 35 ma every 6 hours in 16-bunch and 9 ma every 4 hours in single bunch) or only slightly higher (typically 7 ma every 12 hours in hybrid mode), a potential problem with injection with front-end open may come from the cleaning of the individual bunches. A number of measurements have therefore been carried out to assess the feasibility of injection with front ends open in these nonstandard filling modes. These measurements were carried out on the ID6 Machine/Safety diagnostics beamline. This undulator beamline is installed on a straight section equipped with an 8 mm ID vessel, which shows one of the highest local beam losses. We have used the dose readings from a.6 cm 3 ionisation chamber

placed on-axis in the optics hutch it was shown before that the dose from such a chamber is proportional to the dose measured outside the optics hutch. We show hereafter the results obtained in hybrid mode, the conclusions for the other modes being similar. Note that hybrid mode is a mode consisting of a ( 6 ma) single bunch and a ( 195 ma) 1/3 rd fill bunch train. After top-up, the single bunch is cleaned. Figure 4 shows the measured dose-rates on-axis inside the optics hutch during 8 days of hybrid mode operation. 1. 2 on-axis dose rate (Gy.h -1 ).1 15 1 5 stored beam (ma).1 1 2 3 4 5 6 7 8 days Figure 4: Measured on-axis dose-rates inside the ID6 optics hutch during 8 days of hybrid mode operation. 2.4 2 integrated dose (Gy) 2.2 2. 1.8 15 1 5 stored beam (ma) 1.6 4 5 6 days Figure 5: Integrated on-axis dose inside the ID6 optics hutch during 2 days of hybrid mode operation.

One sees the gas-bremsstrahlung contribution during beam decay, and the momentary increased dose rates during injection or following a beam trip. Figure 5 shows the integrated dose over two days during this period, clearly indicating that the contribution of the dose during injection to the total integrated dose is completely negligible. Details of the dose contributions during a typical top-up are shown in figure 6. We see that the dose due to the cleaning of the single bunch is extremely small. The cleaning uses a scraper located in cell 22. From the beam loss monitors we know that maximum beam losses during cleaning occur in cell 23 (ID23 is an undulator beamline with a front end similar to ID6). These losses are about 1 times higher than the losses during cleaning occurring in cell 6. This means that in 16- bunch dose rates during cleaning outside ID23 could be more than 1 times higher than those recorded for ID6 during hybrid mode cleaning. But even then, the integrated dose due to cleaning will be small. Injection with front ends open will therefore also be allowed during the non standard beam modes..15 25 2 on-axis dose rate (Gy.h -1 ).1.5 total current single bunch ( 4) 15 1 5 ma..76.77.78.79 days single bunch top-up 1/3rd top-up Figure 6: Dose-rate pattern during hybrid mode top-up. 5. Interlocked radiation monitors cleaning We have chosen for the interlocked radiation monitors 5 litre ionisation chambers combined with Unidos electrometers from the company PTW. These monitors were selected because of their reliability, high sensitivity, large dynamical range and compatibility for pulsed radiation. The otherwise standard Unidos electrometers are equipped with an interlock relay, providing interlock contacts that open when the integrated dose exceeds a programmable set point. These interlocked contacts are

1 4 1 2 1 8 6 4 2 integrated into the corresponding beamline personal safety system as explained later in this section. Figure 7 shows a typical dose rate pattern that will be measured with these monitors. The measured dose rate is the sum of the background H and the scattered bremsstrahlung contribution back H γ. As a conservative measure we will include the background contribution in our dose constraint. We also have to take into account the neutron contribution. From reference (2) we know that the neutron dose rate will be typically twice as high as the scattered bremsstrahlung contribution the fact that the results in table 1 show a neutron dose 3 times higher than the photon dose is due to the fact that there is substantial photon attenuation in the lead block, more than in typical optical elements. The dose limit on the measured integrated dose for the interlock relays is therefore obtained in the following way. front end closed, or no beam in SR increased dose rate during injection dose rate. H γ. H back. H meas 5 1 15 2 beam decay Figure 7: Typical measured dose rate pattern. time (hours) beam decay Our dose constraint limits the total integrated dose over 4 hours to 2, the derived dose limit for non-exposed workers: with Thus: or t H total total H = dt < 2 µ Sv, t 4 hours H back H n = 2 H γ t H back + 3 H γ n + H + H γ dt < 2 µ Sv, t 4 hours

t or finally t 3 H meas H back dt < 2 H back 2 + 2 3 dt < 2 µ Sv, t 4 hours 4h H back dt µ Sv, t 4 hours A typical value for H back is.8.h -1, which then gives a dose limit of.88 for the measured photon dose. The integration of these new radiation monitors in the personal safety systems (PSS) is done in the following way. Figure 8 shows schematically the logic used until now in the machine and beamline personal safety systems associated with the storage ring injection. 24 V 24 V position: injection position: stored beam all front ends closed SR beam permit permit to open front end position: injection booster extraction permit accelerator PSS beamline PSS Figure 8: Logic used until now in the machine and beamline personal safety systems associated with the storage ring injection.

24 V 24 V position: injection SR beam permit by-pass key position: stored beam radiation monitor interlock permit to open front end position: injection minimum 5 ma stored all front ends closed booster extraction permit beamline PSS accelerator PSS Figure 9: Logic used to implement injection with front ends open in the machine and beamline personal safety systems. A PSS key located in the central accelerator control room is used to differentiate between injection mode and stored beam mode. When this key is in the position stored beam the front ends can be opened, while the booster extraction is blocked. When it is put in the position injection to allow the booster extraction all front ends are closed. The logic of the SR beam permit which raises the permits for the storage ring RF and for the linac equally guarantee that no injection is possible if not all front ends are closed. The new corresponding PSS logic is shown in figure 9. The condition concerning the closing of the front ends is removed from the SR beam permit. Booster extraction is still conditioned with the, and injection with front ends open is allowed if minimum 5 ma are stored (via the interlock from the dedicated current monitors). The latter conditions guarantees that no injected beam could be accidentally directed into a beamline, due to an error in the storage ring beam optics. In the beamline PSS, the permit to open the front end during injection is given by the dose limit interlock from the dedicated radiation monitor. During stored beam conditions (booster extraction blocked) the active radiation monitor interlock is bypassed. In this case an alarm in the central control room will be generated if any of the interlocked monitors exceeds 75 % of the corresponding dose limit. This alarm will trigger an intervention of the Radiation Protection Group, and the necessary action will be decided after verification. The distinction between injection and stored beam conditions avoids unnecessary closing of a front end in case of a radiation monitor failure. During stored beam the dose outside a beamline can only increase slowly, leaving enough time for a manual verification before, if necessary, deciding to close the corresponding front end. Finally, inside every beamline PSS a local key is

foreseen to by-pass the radiation monitor in case of a technical problem with the latter. The installation and integration into the PSS of radiation monitors is scheduled for the winter shutdown 22-23. All 42 optics hutches will be equipped. Figure 1 shows one of the installed monitors. Figure 1: Picture of one of the radiation monitors installed outside an optics hutch. References [1] P. Colomp, Application de la directive Euratom/96/29 à l ESRF, 1999, thesis, not published [2] P. Berkvens & P. Colomp, Radiation measurements around ESRF beamlines, these proceedings