PART 3 REQUIREMENTS FOR SPRINKLER SYSTEMS and SPRINKLER INSTALLERS

Size: px
Start display at page:

Download "PART 3 REQUIREMENTS FOR SPRINKLER SYSTEMS and SPRINKLER INSTALLERS"

Transcription

1 Page 1 of 42 CONTENTS Schedule of amendments for this part of the scheme document 3.0 Introduction 3.1 Business Licensing Requirements 3.2 Insurance 3.3 Language 3.4 Quality System 3.5 Safety System 3.6 LPS 1233 Inspection Procedures As 3.7 Temporary Recognised Sprinkler Installer (TRSI*) 3.8 Procedure to become an Approved Sprinkler Installer* 3.9 Resources (qualified staff*) 3.10 Competence and Training 3.11 System Design* 3.12 Document and Data Control 3.13 System Components 3.14 Process Control (installation*) 3.15 Control of Inspection, Measuring and Test Equipment 3.16 Contract Records* 3.17 Emergency Response 3.18 Service* and Maintenance 3.19 LPS 1233 Surveillances Audits 3.20 Returns to LPCB 3.21 Branch Offices 3.22 Sub-contracting* Appendix A Inspection Procedures As Appendix B Approved components*, Sprinkler Products Appendix C Flow scheme for the monitoring process of Temporary Recognised Sprinkler Installers (TRSI*) based on Inspection Procedures As Appendix D Definitions for Part 3 of LPS 1233 scheme document. Appendix E Hybrid Systems Appendix F Pre-Assessment Programme An * after a term means that a definition for that term can be found in Appendix D. Some expressions may be defined in other parts of this scheme document

2 Page 2 of 42 Schedule of amendments for this part of the scheme document Amendment reference Scheme document issue no. Clause Implementation date Details and August 2006 Requisite number of contracts completed by TRSI Chapters amended August 2006 LPS 1233 Surveillance Audits New paragraph with note added at the end of chapter A.7 1 August 2006 Issue of LPS 1233 Fire Protection System Certificates August 2006 Permanent Staff New paragraph inserted at A.7.1. Existing chapter A.7.1 re-numbered as A.7.2. Subsequent chapters re-numbered from A.7.3 onwards. Sentence added at the end of the first paragraph of chapter August 2006 Chapter deleted and subsequent chapters from to re-numbered. Appendix D 1 August 2006 Definition of Employment Agreement in Appendix D revised Appendix B 1 August 2006 Direct Reading Flow Meters Reference to Induction Flow Meters added August 2006 Paragraph wording revised. Reference to NCP deleted, involvement of CCV added August 2006 Reference to NCP web site deleted, reference to LPCB web site added. June COMPLETE REVISION OF SCHEME DOCUMENT July July 2009 Revised part 3, 3-O and 4. Clause is changed, text of Amendment No. 1 is included. February Criteria for temporary recognised companies rewritten. February , , , Additional training requirements for special products or systems.

3 Page 3 of February Appendix D Changing the definition of Certified components. February 2011 February 2011 February 2011 February 2011 February 2011 February 2011 February 2011 February 2011 February 2011 February Modification to the criteria of non-compliance and observation reports New paragraph added relating to satellite branches Background added of allowance to sub-contract. 3.2 Appendix B Vortex inhibitor removed from list Appendix C Completely re-written. 3.2 Appendix D NEN 1073 added to sprinkler rules. 3.2 Appendix E Reference to inspection bodies removed. 3.2 Appendix E BdB replaced by CS. 3.2 Appendix E Additional requirements for Extended Coverage Sprinklers plus some small changes. 3.2 Appendix F Small modification to audit programme. Changes will be marked with a vertical bar in the right hand margin.

4 Page 4 of Introduction The LPS 1233 scheme is operated by The Loss Prevention Certification Board (LPCB), a division of BRE Global Limited based in the United Kingdom, in collaboration with CCV (The Dutch Centre for Crime Prevention and Safety) under a Memorandum of Understanding signed between CCV and BRE Certification Limited on 16 February 2006 and has the support of insurers, the fire service and trade organisations in Holland. The day-to-day operation of this scheme is carried out by LPCB Nederland B.V. This part of the LPS 1233 scheme document covers the requirements for new, modified* or extended sprinkler systems*, which includes the requirements for Sprinkler Installers and inspection activities and should be read in conjunction with: - Part 1 LPS 1233 Scheme Details and General Requirements, - Part 2 Inspection Requirements. - Part 3-O Requirements for Maintenance and Supervision of Sprinkler Systems 3.1 Business Licensing Requirements For a sprinkler installing company to be eligible for entry into the LPS 1233 scheme, they shall have an entry in the register of business names in the country of origin for the activity concerned. 3.2 Insurance For a sprinkler installing company to be eligible for entry into the LPS 1233 scheme, they shall have a company liability insurance (AVB or equivalent) of at least 2,000, Language All documentation of the Temporary Recognised* or Approved Installer* shall be available either in Dutch or English. The technical staff (those listed in Table 3.1) of the Temporary Recognised* or Approved Installer*, shall be able to communicate verbally and in writing in either Dutch or English. 3.4 Quality System On initial entry into the LPS 1233 scheme as a Temporary Recognised Sprinkler Installer*, the sprinkler installing company, shall operate a quality management system complying with the requirements of NEN-EN-ISO 9001 covering the design*, supply, installation* and servicing* of fire sprinkler systems* or fire protection systems. The quality management procedures shall be supplemented with procedures and work instructions of the relevant parts of this scheme document (see appendix F). Within 12 months from the date of temporary recognition and before the sprinkler installing company can become an Approved Sprinkler Installer*, they shall hold a valid certificate for the quality management system to NEN-EN-ISO 9001, issued by an accredited certification body, with a specific scope for the design*, supply, installation* and servicing* of fire sprinkler systems* or fire protection systems. 3.5 Safety System On initial entry into the LPS 1233 scheme as a Temporary Recognised Sprinkler Installer*, the sprinkler installing company shall operate a safety management system according to VCA (or equivalent) covering the installation* and maintenance of fire sprinkler systems* or fire protection systems. Within 12 months from the date of temporary recognition, and before the sprinkler installing

5 Page 5 of 42 company can become an Approved Sprinkler Installer*, they shall hold a valid certificate for the safety management system according to VCA (or equivalent), issued by an accredited certification body, with a specific scope for the installation* and maintenance of fire sprinkler systems* or fire protection systems. 3.6 LPS 1233 Inspection Procedures As The Temporary Recognised* or Approved Sprinkler Installer* shall reference the LPS 1233 Inspection Procedures As in the appropriate places in their quality management control documentation and records. For sprinkler contracts* carried out under the LPS 1233 scheme, the Temporary Recognised* or Approved Sprinkler Installer* shall follow the Inspection Procedures As detailed in Appendix A. 3.7 Temporary Recognised Sprinkler Installer* (TRSI*) Before a candidate sprinkler installer will be granted temporary recognition the recognition process as described in chapter 1.3 of Part 1 of this scheme document shall be followed. The pre-assessment by LPCB consists of two steps and will last at least two days.: Step 1 : Review of documents. The candidate sprinkler installer needs to demonstrate that all requirements as detailed in Appendix F are fulfilled. For this purpose the candidate sprinkler installer shall submit her quality manuals along with the filled out Appendix F to LPCB. In this Appendix F the candidate sprinkler installer shall reference which document(s) relate to each item of the pre-assessment program (Appendix F). LPCB will review the documents submitted in her own office Step 2 : Assessment on the location of the candidate sprinkler installer. When all requirements of step 1 are fulfilled and all non-conformity reports have been closed out LPCB will set a date for an assessment in the office of the candidate sprinkler installer. This assessment on location shall take place within two months after step 1 has successfully been finalised. During the assessment on location remaining observation of step one (if any) will be dealt with as well as the sampling of a completely finished sprinkler contract*. When the review of the sample contract* concludes that the contract* has not been carried out satisfactorily a second sample of a finished contract* shall be carried out. If a second contract* is not available the procedure as described in will become in force If the candidate sprinkler installer has not carried out any contract* or only one contract* of which the conclusion of the review by LPCB was not satisfactorily a temporary recognition will not be granted. In that case the candidate sprinkler installer can receive a letter from LPCB in which LPCB declares that the candidate sprinkler installer is allowed to design and install sprinkler systems which could lead to a LPCB product certificate, however under the full supervision of LPCB. This supervision by LPCB shall consist of: a) Review of the CS* beforehand. b) Review of all correspondence with the Inspection Organisation (IO)* relating to design review. c) Review of all correspondence with the IO* relating to interim inspections. d) Review of all correspondence with the IO* relating to the final inspection(s).

6 Page 6 of 42 e) Review of all documents as rerquired by described in Appendix A.7. f) When the results of a) e) are satisfactorily, LPCB will carry out a visit at the site of the client of the candidate sprinkler installer. g) Depending on the results of the first project supervised by LPCB temporary recognition can either be granted or the supervision of a second contract* is required. h) The correspondence and documents as mentioned in a) e) shall be submitted to LPCB during the course of the contract* by the candidate sprinkler installer. i) LPCB will charge the cost for the supervision to the candidate sprinkler installer. Subject to at least meeting the requirements of clauses 3.1 to 3.6 and and having undergone a successful preliminary assessment audit and closed out any resulting reports, the candidate sprinkler installer will be given temporary recognition until such time as they meet the requirements for approval During the period of temporary recognition LPCB shall monitor the contract* of the TRSI* and the TRSI* shall follow the procedure detailed in Appendix C To allow continuation of temporary recognition, the TRSI* shall satisfactorily carry out a number of contracts as follows : - at least 2 sprinkler contracts* (not including fire work storage risks <10,000 kg) within one year of being given temporary recognition, - at least 5 sprinkler contracts* (not including fire work storage risks <10,000 kg) within two years of being given temporary recognition, - between 6 to10 sprinkler contracts* with various hazard classification* within 3 years of being given temporary recognition, and - by the end of the third year of being given temporary recognition, be installing at least 3,000 sprinklers per year. Note : In case of a TRSI* a contract* is also understood as follows : - A complete new sprinkler system including water supply ; - A complete new sprinkler system connected to an existing water supply ; - An alteration or modification to an existing sprinkler system whereby the alteration or modification includes at least 150 new sprinkler heads to be installed. - The TRSI* is not allowed to sub-contract design and/or installation work during temporary recognition. The TRSI* is allowed to hire (CAD) draughtsman and/or fitters under the restriction of permanent supervision of qualified staff of the VES during the work Between the preliminary and the full assessment audit, the TRSI* shall be subject to six-monthly one-day surveillance audits which will focus on the technical content of contracts* The T.R.S.I. will also undergo Service Programme surveillance audits (see part 3- O.12) which normally will last half a day. 3.8 Procedure to become an Approved Sprinkler Installer* For a TRSI* to be eligible for assessment to become an Approved Sprinkler Installer*, they must first have satisfied the criteria of

7 Page 7 of Before becoming an Approved Installer* the T.R.S.I shall at least have one Service Programme Contract reviewed by LPCB On the basis of the information and results as described in and and the results of the supervision as described in Appendix C, LPCB will decide if the two-day assessment audit can go ahead If the TRSI* has not met the requirements as described above within the maximum period of three years LPCB will carry out a special visit to the TRSI* within 30 days after this period, as described in chapter 1.11 of Part 1 of this scheme document. If, as a result of this special visit, the TRSI* has not met the requirements the TRSI* will be suspended as described in chapter 1.11 of Part 1 of this scheme document. The period of suspension is maximum three months. If the TRSI* still does not meet the requirements after this period the temporary recognition and the certificate will be withdrawn. 3.9 Resources (qualified staff*) Design* Department For each office in the LPS 1233 scheme, the Temporary Recognised* or Approved Sprinkler Installer* shall have an in-house design* department with the minimum number of Sprinkler Technicians* with an employment agreement* specified in Table Minimum Number of Qualified Staff* in Each Office For each office in the LPS 1233 scheme, the Temporary Recognised* or Approved Sprinkler Installer* shall have an employment agreement* with a sufficient number of qualified staff* as specified in Table 3.1. All employees mentioned in Table 3.1 shall be permanent staff*. The number of qualified staff* required is related to the number of sprinklers installed* in a given year. When assessing the number of sprinkler heads installed* each year, and thereby the minimum number of qualified staff* required, the average number of the three previous years shall be used. Table 3.1 Resources Number of Sprinkler Heads installed* per year Project Manager* Sprinkler Technician* Draughtsman* Head Fitter* Up to 5,000 1 (1) 1 (1) Up to 10, Up to 20, Up to 30, Up to 40, Fitter* For each extra 20, Maintenance Engineer* See Note 2

8 Page 8 of 42 Note 1 For less than 5,000 sprinklers installed* per year in the above table, the Project Manager* and Sprinkler Technician* roles can be combined. But for over 5,000 sprinklers installed* per year, the roles in the above table cannot be combined. Note 2 For Temporary Recognised* or Approved Sprinkler Installer* that install* up to 5,000 sprinklers per year, it is acceptable for a Maintenance Engineer* to also be considered as a Head Fitter* (for details on service and maintenance see Part 3-O). Should an Approved Sprinkler Installer* not install* a minimum of 3,000 sprinklers per year, for two consecutive years, their status will be changed to that of a TRSI* and will be subject to the criteria for TRSI*. Details of installed* sprinklers will be taken from the Approved Sprinkler Installer s* Contract Logs*. Explanation: The rational behind the decision to require an Approved Sprinkler Installer* to install* at least 3,000 sprinkler heads per year is to ensure that they retain the capability and experience to design*, procure, install*, test, commission and service* sprinkler systems* Competence and Training The Temporary Recognised* or Approved Sprinkler Installer* shall determine the knowledge and experience requirements for the qualified staff* listed in Table 3.1 above taking into account the requirements of clauses through to The competency of qualified staff* shall be evaluated periodically and always at the start of their employment or contract. The Temporary Recognised* or Approved Sprinkler Installer* shall also determine how qualified staff* can obtain the required training. The qualification and experience requirements for each of the positions listed in Table 3.1 are set out below Project Manager* A Project Manager* shall: - hold NCP/Certoplan Sprinkler Technology I and II diplomas, or equivalent. - have a minimum of 5 years experience in the sprinkler industry, of which at least 2 years has been at the level of a Sprinkler Technician* or hold an HBO diploma in an engineering subject. - demonstrable being educated or trained by manufacturers, or their representatives, of specific products or systems (to be applied in the sprinkler system) of which the manufacturer declares that such an education or training is of vital importance Sprinkler Technician* A Sprinkler Technician* shall: - hold NCP/Certoplan Sprinkler Technology I and II diplomas, or equivalent. - have a minimum of 3 years experience in the sprinkler industry or hold an MBO diploma in an engineering subject. - demonstrable being educated or trained by manufacturers, or their representatives, of specific products or systems (to be applied in the sprinkler system) of which the manufacturer declares that such an education or training is of vital importance Draughtsman*

9 Page 9 of 42 A Draughtsman* shall: - hold an NCP/Certoplan Sprinkler Technology I diploma, or equivalent. - have a minimum of 2 years experience in the sprinkler industry or hold an MBO diploma in an engineering subject. - demonstrable being educated or trained by manufacturers, or their representatives, of specific products or systems (to be applied in the sprinkler system) of which the manufacturer declares that such an education or training is of vital importance Head Fitter* Fitter* A Head Fitter* shall: - hold a VSI-A diploma, or equivalent. - have at least 5 years experience in the installation* of sprinkler systems*, or hold an VMBO diploma in an engineering subject with at least 2 years experience in the installation* of sprinkler systems*. - demonstrable being educated or trained by manufacturers, or their representatives, of specific products or systems (to be applied in the sprinkler system) of which the manufacturer declares that such an education or training is of vital importance. A Fitter* shall: - have undergone suitable training Maintenance Engineer* 3.11 System Design* For requirements see part 3-O General The Temporary Recognised* or Approved Sprinkler Installer* shall be directly responsible for the design*, the installation*, the testing and the commissioning of the sprinkler system Design* Standard All sprinkler systems* shall be designed in accordance with Sprinkler Standards* acceptable under the LPS 1233 scheme (see Appendix D) and specified in the Contract Specification (CS)*. Any incomplete, ambiguous or conflicting requirements shall be resolved with the LPCB All minor deviations*, not detailed in the CS*, shall be the subject of a written agreement between the Temporary Recognised* or Approved Sprinkler Installer* and LPCB All major deviations*, not detailed in the CS*, shall be the subject of a written agreement between the Temporary Recognised* or Approved Sprinkler Installer*, the CS* writer, LPCB and other interested parties such as the authority, client, insurer and fire department Design* Verification The sprinkler system* design* shall be verified by an in-house Sprinkler Technician* or Project Manager* who has not been directly involved in

10 Page 10 of 42 the design* of the contract* The verification of the design* by the Temporary Recognised* or Approved Sprinkler Installer* shall be carried out before the design* is submitted for external review Design* verifications are to be carried out in accordance with the Temporary Recognised* or Approved Sprinkler Installer* control documentation and records and shall be systematic and thorough. Design* output (aid memoir) checklists (containing a sufficient number of items) shall be used to ensure that the design* is thoroughly checked. Any deviations*, errors or omissions to the Sprinklers Standards* and the CS* must be satisfactorily addressed prior to the design* being issued. Design* verifications shall be fully documented and records kept for review by LPCB Design* Validation Internal site inspections are to be carried out by the Temporary Recognised* or Approved Sprinkler Installer* in accordance with their ISO 9001 control procedures and shall be systematic and thorough to ensure that the sprinkler system* has been installed* in accordance with the approved design*. Internal site inspection checklists (containing a sufficient number of items) shall be used to ensure that the sprinkler system* is thoroughly inspected. Any deviations*, errors or omissions identified against the Sprinkler Standards* and the CS* shall be rectified. Internal site inspections shall be fully documented and records kept for review by LPCB. The records shall also include the re-inspection/signoff of any defects found during internal inspection Testing and commissioning shall be carried out by the Temporary Recognised* or Approved Sprinkler Installer* in accordance with their ISO 9001 control documentation and records and the Sprinkler Standards*. Records shall be kept of all flow test results and functional testing of equipment and alarms. Test results shall be compared against system requirements for adequacy. Records shall be available detailing the set values of all instruments and the operational sequences of equipment and alarms The validation process shall include the review of all final documentation such as pressure test and completion certificates, as-built drawings, inspection records, flow test results, functional test results of devices, commissioning reports and Maintenance and Supervision specification*, including the set values of components and equipment Internal site inspection, including the rectification of any defects found, testing and commissioning shall be carried out before the sprinkler system* is offered for external inspection Document and Data Control Temporary Recognised* or Approved Sprinkler Installer* shall: have access to current technical data, including specifications, Sprinkler Standards*, commissioning and service*/maintenance instructions from all

11 Page 11 of 42 manufacturers of specialist fire protection equipment or sub-systems installed* or serviced* and make this information readily available to all necessary personnel, especially installation* and maintenance engineers*; maintain any computer software packages for hydraulic calculations to the version compliant with the current revision of the Sprinkler Standards* in use; carry out periodic checks on any hydraulic calculation package in use for consistency of results System Components The Temporary Recognised* or Approved Sprinkler Installer* shall undertake to use only approved components* for sprinkler and sprinkler servicing contracts* carried out under the LPS 1233 scheme. Components which shall be approved are listed in Appendix B of this part of the LPS 1233 scheme document The Temporary Recognised* or Approved Sprinkler Installer* shall produce a P&ID (Process and Instrumentation Diagram) of each contract*. With the P&ID a detailed component legend of all components installed shall be included, at least detailing the following information of each component: - Reference number; - Manufacturer; - Type; - Diameter; - Total number of each component Process Control (installation) The installation* of the sprinkler system* shall be controlled by the Temporary Recognised* or Approved Sprinkler Installer* to ensure that the quality of workmanship is to a good standard and is in compliance with the Sprinkler Standards* and the CS*. The installation* process shall be defined and documented in the installers ISO 9001 control documentation and records. The installation process shall also detail the material take off, including pipe prefabrication lists, the purchase procedures and the communication between the design department, the purchase department and the responsible head fitter on the job All design* changes required during installation* shall be authorised by the Project Manager* before being implemented and shall be fully documented Before installation*, a check shall be carried out to ensure that the correct materials are being used as specified on the design* drawings and other related contract* documents and that the materials are not damaged or faulty The Temporary Recognised* or Approved Sprinkler* shall ensure that immediately prior to fitting all sprinkler pipework, it is internally inspected for freedom of blockage and debris Control of Inspection, Measuring and Test Equipment Pressure gauges used for hydraulic pressure testing of the sprinkler system* shall

12 Page 12 of 42 be calibrated and their serial number recorded on the pressure test certificate Grooving tapes or callipers shall be used to check the correct dimensions of grooves against the manufacture s specification Contract Records* Contract records* shall be maintained for the period stated in the Temporary Recognised* or Approved Sprinkler Installer* ISO 9001 quality management system, but in no case less than 10 years Emergency Response This chapter has been transferred to Part 3-O Maintenance and Supervision Specification* The Temporary Recognized* or Approved* shall submit a detailed Maintenance and Supervision Specification* based on the CS*, the applicable sprinkler (maintenance) standards (see Appendix D) as well as all relevant contractual documents. The Maintenance and Supervision Specification* shall be part of the delivery of the sprinkler system* product by the Temporary Recognized* or Approved Installer*. The Maintenance and Supervision Specification* shall be sent to LPCB for approval (see Appendix As) Any incomplete, ambiguous or conflicting requirements shall be resolved with the author of the CS* and/or other interesting parties All minor deviations*, not detailed in the CS*, shall be the subject of a written agreement between the Temporary Recognized* or Approved Installer*and the author of the CS* All major deviations*, not detailed in the CS*, shall be the subject of a written agreement between the Temporary Recognized* or Approved Installer*, the author of the CS*, LPCB and other interested parties such as the authority, client, insurer and fire department Operation and Maintenance Manual The operation and maintenance manual shall at least comprise the following: - Manufacturers data sheet of all the components and sub-systems used in the sprinkler system*. - Description of the operation of the sprinkler system*. - All approved drawings, calculations and relevant documents. - Detailed instructions of the sprinkler system* shutdown. - Detailed instructions to prepare the sprinkler system* for cold weather. - Component certificates where required. - Instructions how to handle when there is a fire or a leakage Detailed Customized Periodic Test Programme. All sprinkler standards* require periodic tests (daily, weekly, monthly etc.) of the sprinkler system*. The Temporary Recognised* or Approved Installer* shall provide forms for each test activity including instructions to carry out the test and where

13 Page 13 of 42 required to record the set values of components and the measured values during testing. The set values shall be taken from the commissioning report of the sprinkler system*. The forms shall also indicate pass/fail criteria, where applicable. In such a way it will be clear for the owner, if the owner carries out the test him/herself, when to call in the Temporary Recognized* or Approved Installer*to bring the system back in its normal state condition*. The forms shall be retained in the logbook of the sprinkler system. The forms shall be made available to LPCB, when requested during an audit Detailed Customized Inspection Programme (in principle to be carried out by the owner of the system) Sprinkler systems* can only perform as expected when the conditions of the use of the buildings or processes on the premises are as described in the CS* and/or the applicable sprinkler standards*. These conditions are no part of the sprinkler systems hardware and software, but should be managed by the owner of the system. In order for the owner to carry out this management, the Temporary Recognized* or Approved Installer* shall include a customized inspection programme (user manual) as part of the Maintenance and Supervision Specification*. The conditions as described above depend on the specific parameters of the premises, but shall at least include the following: - Categorization of commodities; - Storage heights per commodity; - Condition of fire separations; - Clearance between storage and sprinkler heads; - Temperature conditions in buildings Detailed Customized Maintenance Programme The Temporary Recognized* or Approved Installer* shall provide a detailed customized maintenance programme for all the components and sub-systems in the sprinkler system*. Per component at least the following shall be detailed : - Component description; - Activities to be carried out per component according to the applicable sprinkler standard* and /or the recommendation of the component or subsystem manufacturer, including the frequencies of maintenance; - Set values of components (when applicable); - Possibility to record the measured values of components (when applicable); - Possibility to record repairs or revisions including the required spare parts LPS 1233 Surveillance Audits Surveillance audit frequency - acceptable performance LPCB will carry out a two-day surveillance audit to each office of the Approved Sprinkler Installer* every 12 months or a one-day surveillance audit every 6 month, to ensure continuing compliance with the LPS 1233 scheme requirements. The Approved Sprinkler Installer* can choose for a two-day or one-day audit. LPCB will audit the Approved Sprinkler Installer* for their: compliance with the relevant clauses of Parts 1 and 3 of the LPS 1233 scheme document;

14 Page 14 of 42 compliance with the LPS 1233 Inspection Procedures As for LPS 1233 certificated systems; continuing technical competence. The LPCB surveillance audit programmes will at least sample the following in a repeating three year cycle: a contract* in the process of installation*; a completed contract*; several servicing* contracts. Audits may include site visits. Every three year LPCB will review the installers quality management procedures for compliance with the requirements of this scheme document. However, the audit frequency and duration shall be increased to a maximum of two two-day audits per year to take extra sample contracts in each of the following situations: In the previous year 50% or less of the sprinkler or servicing contracts carried out by the Temporary Recognised* or Approved Sprinkler Installer* have been carried out according to this scheme document; In the previous year not more than 4 sprinkler or servicing contracts have been carried out by the Temporary Recognised* or Approved Sprinkler Installer* according to this scheme document. For the purpose of setting the surveillance regime, contract details will be taken from Temporary Recognised* or Approved Sprinkler Installer* Contract Log*. The approval or recognition of sprinkler installers gives the assurance that fire protection systems* will be designed, installed and serviced* according to the CS* and applicable technical standards. The proof of this assurance is the issue of a product certificate on new installed systems* or on the service and maintenance of existing systems as a result of compliance with the inspection and certification procedures. For this reason, product certification of systems and service and maintenance cannot be voluntary within this scheme document. This means that sprinklers installers can only be recognised or approved when the systems* they install or service are initially intended to become certificated. When systems or services are not carried out according to this scheme document, which is sometimes inevitable when compliance with sprinkler standards is not possible, this must be agreed with the client and clearly stated in the contract. The sprinkler installer is not allowed to use the LPCB Certification mark on any document related to a system or service that is not carried out under LPS 1233 procedures. Any contract, not carried out according to the requirements of this scheme document will not have any scheme benefits, such as following up any related third party complaint and will not be dealt with by LPCB or the CvD. The approval of the Temporary Recognised* or Approved Sprinkler Installer* only applies to contracts which are carried out fully in accordance with the LPS 1233 scheme documents, which includes the inspection activities Surveillance audit frequency - unacceptable performance Where the LPCB technical surveillance audit reveals significant non-compliances, the audit frequency and duration may be increased until the Temporary Recognised* or Approved Sprinkler Installer* performance returns to a satisfactory standard.

15 Page 15 of 42 Some examples of the areas that may cause an increase in the frequency of audits would be: - design* standards falling below acceptable levels; - installer not following LPS 1233 procedures; - breaches of management systems and ISO procedures; - poor execution of site work Non-compliance and observation reports At the end of each surveillance audit any non-compliance or observation identified by the LPCB assessor during the audit will be presented to the Temporary Recognised* or Approved Sprinkler Installer* for acceptance and agreement of the required date for completion. In principle for non-compliances this period is 60 days and for observation the required action shall be taken before the next audit. Temporary Recognised* or Approved Sprinkler Installer* are required to return the report to the LPCB by the due date, unless otherwise agreed by the LPCB, with supporting documentation. Statements of intent are not acceptable for noncompliances, corrective actions must be completed and implemented Closing out site based non-compliances or observations 3.20 Returns to LPCB In order to close out a non-compliance or observation that require site work, objective evidence is required that the work has been carried out. LPCB cannot accept verbal or written statements without supporting objective evidence. There are a number of different forms of objective evidence that are acceptable, for example: - A copy of a site instruction (a document issued to the installation* department or sub-contractor to request work to be carried out on site) detailing the work required in sufficient detail (with where appropriate a marked up drawing) with a signature by the Head Fitter* or Fitter* confirming that the work has been completed and counter-signed by the Project Manager*. - A photograph (hard copy or digital) of the site showing the completed work. Note - From the image it should be possible to identify the particular location on site and see that the work has been carried out. The Temporary Recognised* or Approved Sprinkler Installer* shall provide annually to LPCB when requested details of the number of sprinkler heads and alarm valves it has installed* during a given year. The Temporary Recognised* or Approved Sprinkler Installer* shall maintain a completed Contract Log* which shall include details of all sprinkler contracts* carried out. The Contract Log* shall list all sprinkler contracts* carried out regardless of whether an LPS 1233 Fire Protection System Product Certificate has been issued. The Contract Log* can be obtained from Branch Offices A Branch Office is a Approved Sprinkler Installer s* office which is not entirely selfsufficient and relies on the support of another office, in the same group of companies, for activities such as design*, procurement, installation*,

16 Page 16 of 42 commissioning and servicing* Conditions An office can only be considered a Branch Office if its main office is listed as an LPS 1233 Approved Sprinkler Installer* The application for a Branch Office may be coordinated through the main office responsible for the Branch Office The Branch Office shall have NEN-EN-ISO-9001 certification from a accredited Certification Body for the following scope: Design*, supply, installation* and servicing* of fire sprinkler systems* or fire protection systems. Note It is acceptable for the Branch Office to be listed on the ISO 9001 certificate of the main office or on a group company certificate The Branch Office shall have a current VCA (or equivalent) certificate. Note It is acceptable for the Branch Office to be listed on the VCA (or equivalent) certificate of the main office or on a group company certificate The Branch Office shall at least have the requisite number of qualified staff in accordance with Table 3.1 for an installer that installs* up to 5000 sprinklers per year. The total required number of qualified staff* for the main office plus the Branch Office(s) shall comply with Table 3.1 and shall be based on the total number of sprinklers installed* by the main office plus the Branch Office(s) The Branch Office shall undergo a one-day assessment audit by LPCB to confirm their eligibility to be recognised as a Branch Office and to confirm their compliance with the LPS 1233 scheme requirements Where the Branch Office installs* less than 3000 sprinklers per year, all designs* carried out by the Branch Office shall be verified by qualified staff* working at the main office. If the Branch Office installs* more than 3000 sprinkler heads per year, designs* may be verified by qualified staff* based at the Branch Office. Designs* shall be verified in accordance with clause Records shall be kept both at the Branch Office and the main office where less than 3000 sprinklers per year are installed* by the Branch Office Where the Branch Office installs* less than 3000 sprinkler heads per year, all work installed* by the Branch Office shall be inspected by qualified staff* working at the main office. If the Branch Office installs* more than 3000 sprinkler heads per year, inspections may be carried out by qualified staff* based at the Branch Office. Designs* shall be validated in accordance with clause Records shall be kept both at the Branch Office and the main office where less than 3000 sprinklers per year are installed* by the Branch Office The Branch Office shall maintain its own Contract Log* of installed*

17 Page 17 of 42 contracts* Branch Offices shall be subject to a one-day surveillance audit by LPCB each year to confirm their continued suitability to be recognised as a Branch Office and to confirm that they continue to meet the requirements of the LPS 1233 scheme Details of the Branch Office will be listed on the LPS 1233 approval certificate of the main office. The Branch Office will also be listed on the LPCB web site alongside that of the main office The Branch Office will pay an annual fee in accordance with the current LPS 1233 fee schedule The LPS 1233 approval status of each office (branch or main office) of the Approved Sprinkler Installer* shall be clear on contracts* and tenders, letterheads and publicity literature Should the level of work of a Branch Office exceed 3,000 sprinklers per year for two consecutive years, the Branch Office shall be subject to the same number of surveillance audits as a stand alone office (either temporary recognized or approved) and shall meet the full requirements of the LPS 1233 scheme The Branch Office may at any time choose to operate independently and not have its work reviewed or inspected by engineers from the main office provided it has sufficient resources of its own to carry out independent design* reviews and site inspections. It would however, be subject to full surveillance visits as a stand alone office and shall meet the full requirements of the LPS 1233 scheme Special organisational structures may be acceptable for approval, full details are to be submitted to the CvD for consideration and acceptance Branch Offices, other than the type described above, shall not carry out any sprinkler activity under the LPS 1233 scheme Beside branch offices it is possible that temporary recognised or approved sprinkler installers carry out work from several locations, so called Satellite Branches. For satellite branches the same requirements apply as for Branch Offices with the restriction that Satellite Branches will not be printed on the certificate nor on the LPCB website. The only difference between a Satellite Branch and the office of the temporary recognised or approved sprinkler installer is a physical distance. The (semi) annual assessment audits will one year take place in the Satellite Branch and the other year at the main office of the temporary recognised or approved sprinkler installer Sub-contracting* In principle a temporary recognised or approved sprinkler installer shall have a number of qualified staff according to table 3.1 to be able to carry out an annual average number of contracts*. However, if peaks occur in the number of contracts* there is the possibility to sub-contract certain activities, including the core activities design* and installation*. Sub-contracting* of the following activities is allowable under the LPS 1233

18 Page 18 of 42 scheme: - Underground piping works - Supply of pumping sets, complete with control equipment - Supply, and erection of (approved) water storage tanks - Supply of fire and sprinkler alarm systems - Supply and installation of cabling for fire and sprinkler alarm systems - Supply and installation of fire and alarm systems, according to NCP Fire and Alarm scheme, in case of pre-action and deluge systems - Supply of pre-fabricated piping - Sprinkler system* design* work - Sprinkler system* installation* works - Constructional aspects of the contract* The criteria for the selection and evaluation of sub-contractors shall be carried out by the Temporary Recognised* or Approved Sprinkler Installer* in compliance with their ISO 9001 quality procedures The Temporary Recognised* or Approved Sprinkler Installer* shall keep the overall responsibility for the contract* The Temporary Recognised* or Approved Sprinkler Installer* shall provide to their sub-contractor documented technical requirements to ensure full compliance to the Sprinkler Standards* and the CS* including where appropriate reference to the use of certified components* and qualified staff* as required by this scheme The Temporary Recognised* or Approved Sprinkler Installer* is responsible for ensuring that their sub-contractors comply fully with all relevant clauses of this LPS 1233 scheme document. Especially for subcontracted design and installation work a subcontractor shall comply to the same criteria as the Temporary Recognised* or Approved Sprinkler Installer*; evidence shall be made available to LPCB on request The Temporary Recognised* or Approved Sprinkler Installer* shall provide the subcontractor for design or installation work with all their LPS 1233 procedures and work instructions related to the subcontracted work The Temporary Recognised* or Approved Sprinkler Installer* shall adequately monitor the performance of their sub-contractor to ensure that the standard of workmanship and compliance to the Sprinkler Standards* and the CS* is satisfactory The Temporary Recognised* or Approved Sprinkler Installer* shall carry out the verification (where the work includes design*) and validation (witnessing of testing) of the activities being sub-contracted and keep records for review by LPCB.

19 Page 19 of 42 APPENDIX A - INSPECTION PROCEDURES As A.0 General This appendix describes the procedure to be followed to allow the sprinkler system* to be issued with an LPS 1233 Fire Protection System Product Certificate. The flow diagram below shows the whole procedure, after which each step in the process is explained. Finally, a set of guidelines is included regarding the procedures in relation to modifications* to sprinkler systems*. A.0.1 For each sprinkler contract* subject to LPS 1233 product certification, the Temporary Recognised* or Approved Sprinkler Installer* (hereafter abbreviated as IN) shall allocate a unique project number. This number shall be used on all correspondence relating to the contract*. A.0.2 The points of departure for product certification in accordance with the LPS 1233 scheme shall be laid down in the CS*. A.0.3 A.0.4 A.0.5 The realisation of the complete sprinkler contract* shall be carried out by an IN. Inspection activities shall be carried out by an Inspection Organization (hereafter abbreviated as IO) who has a licence agreement with LPCB. The procedures that must be followed to achieve a product certificate on a sprinkler system* is shown in the LPS 1233 Inspection Procedures As Flow diagram.

20 Page 20 of 42 LPS 1233 Inspection Procedures As Flow Diagram

21 Page 21 of 42 A.1 ACCEPTATION OF CONTRACT SPECIFICATION (CS)* BY LPCB A.1.1 The IN shall submit to LPCB the CS* for acceptation prior to the start of the sprinkler contract*. A.1.2 LPCB will review the CS* on the basis of the applicable sprinkler standards* and this scheme document. A.1.3 LPCB will notice the IN in writing whether a Product Certificate can or cannot be issued by LPCB. A.1.4 If the specified product does not comply, LPCB will notice the IN in writing about the reasons for not being able to issue a Product Certificate on the basis of the CS*. A.2 DESIGN* OF THE SPRINKLER SYSTEM* A.2.1 The IN will produce the design* of the system based on the specification as laid down in the CS* as well as all relevant contractual documents. A.2.2 A.2.3 As part of the design* the IN produces the necessary hydraulic calculations and determines the final installation* of the system based on the design* and the CS*. Amongst others this will include the water supply, choice of materials and components, system monitoring details, etc. For systems eligible for product certification the IN shall send to the IO two copies of the design* drawings, including the hydraulic calculations, water supply data and all relevant information for example choice of materials and components. A.3 DESIGN* REVIEW A.3.1 First the IO needs to determine whether the documents sent for approval by the IN are sufficient to carry out a review. When a review is not possible the IO will notify the IN in writing and the IN must resubmit the appropriate documents. Next the IO reviews all documents against the requirements as laid down in the CS* and the appropriate Sprinkler Standards*. A way for the IO to prove that all elements of the design* review has been carried out is the use of check lists. The IO takes into account all deviations* agreed and recorded. A A A A All errors and deviations* from the CS* and/or appropriate Sprinkler Standards* will be marked up on one set of the drawings, hydraulic calculations and/or other documents. All documents shall be stamped with the approval status (see clause A.4). All remarks regarding the design* will be sent to the IN in writing, together with one set of stamped drawings (without marks). The period in which the IO needs to review or reply to the documents, received for approval, is ten working days at the most.

22 Page 22 of 42 A The marked up drawings, hydraulic calculations and other documents together with a copy of the letter with remarks, sent to the IN, shall be retained in the project file of the IO. A.4 APPROVAL STATUS A.4.1 C - Status: This is a rejection of the design*/installation* and may be due to a number of minor deviations*, one or more major deviations*, insufficient information, incorrect calculations or lack of written evidence of agreement for any deviations*. A The IN will need to effect the necessary corrective measures and re-submit the design* and/or other documents to the IO prior to commencement of the work on site. A.4.2 B - Status: This is a qualified approval of the design*/installation* and can be due to one or more minor deviations*. A A A This qualified approval should not normally prevent the IN from continuing with the works on site. The IN shall inform the IO in writing which corrective measures will be carried out prior to installation* of the system. The IN will need to effect the necessary corrective measures and re-submit the design* to the IO prior to completion of the contract*. A.4.3 A.4.4 A Status: This is an unqualified approval of the design*/installation*. LPS 1233 Document approval stamps: INSPECTION ORGANISATION S NAME A APPROVED DATE: NAME: SIGNED: INSPECTION ORGANISATION S NAME B APPROVED SUBJECT TO NOTED COMMENTS SEE LETTER: DATE: NAME: SIGNED:

PART 3-O REQUIREMENTS FOR SPRINKLER SYSTEMS MAINTENANCE AND SUPERVISION. 3-O Introduction O.1 Scope of Maintenance and Supervision...

PART 3-O REQUIREMENTS FOR SPRINKLER SYSTEMS MAINTENANCE AND SUPERVISION. 3-O Introduction O.1 Scope of Maintenance and Supervision... CONTENTS Schedule of amendments for this part of the scheme document Page 1 of 14 3-O Introduction...3 3-O.1 Scope of Maintenance and Supervision...3 3-O.2 Certification conditions...5 3-O.3 LPS 1233 Service

More information

LPS 1014 Scheme Requirements for certificated fire detection and alarm system firms. Presented by - Reg Grigg LPCB

LPS 1014 Scheme Requirements for certificated fire detection and alarm system firms. Presented by - Reg Grigg LPCB LPS 1014 Scheme Requirements for certificated fire detection and alarm system firms Presented by - Reg Grigg LPCB The aim of this brief presentation Why are LPCB schemes specified? pedigree, experience,

More information

Loss Prevention Standard

Loss Prevention Standard Loss Prevention Standard LPS 1500: Issue 2.1 provide compartmentation in buildings This standard defines the requirements for companies installing fire resisting compartment systems approved by LPCB to

More information

Loss Prevention Standard

Loss Prevention Standard Loss Prevention Standard LPS 1531: Issue 1.1 companies installing or applying passive fire protection This Loss Prevention Standard is the property of BRE Global Ltd. and is made publicly available for

More information

Guidance from the Group of Notified Bodies for the Construction Products Regulation 305/2011/EU

Guidance from the Group of Notified Bodies for the Construction Products Regulation 305/2011/EU GNB-CPR AG Guidance from the Group of Notified Bodies for the Construction Products Regulation 305/2011/EU NB-CPR/AG/03/002r3 Issued: 24 May 2013 APPROVED GUIDANCE GNB-CPR AG position paper Guidance to

More information

For the Design, Installation, Commissioning & Maintenance of Fire Detection and Fire Alarm Systems

For the Design, Installation, Commissioning & Maintenance of Fire Detection and Fire Alarm Systems BAFE Scheme: SP203-1 Version 7.1: January 2019 FIRE SAFETY REGISTER Fire Protection Industry Scheme, Reference SP203-1 For the Design, Installation, Commissioning & Maintenance of Fire Detection and Fire

More information

Circuit Breakers JANUARY The electronic pdf version of this document found through is the officially binding version

Circuit Breakers JANUARY The electronic pdf version of this document found through   is the officially binding version STANDARD FOR CERTIFICATION No. 2.9 Approval Programmes Type Approval Programmes for EU recognised organisation Mutual Recognition (MR) No. MR-E001 Circuit Breakers JANUARY 2013 The electronic pdf version

More information

7.3 Design and Development Design and development planning Design and development inputs Design and development outputs 7.3.

7.3 Design and Development Design and development planning Design and development inputs Design and development outputs 7.3. Rev. 1 03/05/2015 ANNEX A to the Yokogawa Corporation of America Quality Assurance Manual For Additional Requirements selectively applied to ATEX and IECEx certified products CONTENTS 1. Scope 2. Purpose

More information

For the Design, Installation, Commissioning & Maintenance of Fire Detection and Fire Alarm Systems

For the Design, Installation, Commissioning & Maintenance of Fire Detection and Fire Alarm Systems BAFE Scheme: SP203-1 Version 5: May 2011 Fire Protection Industry Scheme, Reference SP203 Part 1 For the Design, Installation, Commissioning & Maintenance of Fire Detection and Fire Alarm Systems British

More information

SECTION SECURITY TESTING AND COMMISSIONING

SECTION SECURITY TESTING AND COMMISSIONING SECTION 280800 - SECURITY TESTING AND COMMISSIONING PART 1 - GENERAL 1.1 WORK INCLUDES A. General Description: This specification section covers the provision of preliminary testing, acceptance testing,

More information

GASTEC QA. Evaluation Guideline KE 191. Amendment A1 Excess flow valves. KE A1 March 2012

GASTEC QA. Evaluation Guideline KE 191. Amendment A1 Excess flow valves. KE A1 March 2012 KE 191 - A1 March 2012 GASTEC QA Evaluation Guideline KE 191 Amendment A1 Excess flow valves Foreword and introduction These GASTEC QA Approval requirements amendment have been accepted by the Board of

More information

Conformity assessment procedures for the Alarm Components Scheme

Conformity assessment procedures for the Alarm Components Scheme Conformity assessment procedures for the Alarm RD_070, Issue 20 This guide describes the conformity assessment procedures for Alarm Components. This Alarm certifies that Alarm Components comply with technical

More information

GASTEC QA. Evaluation Guideline KE 192. Amendment A1 Rubber materials for seals and diaphragms for gas appliances and gas equipment

GASTEC QA. Evaluation Guideline KE 192. Amendment A1 Rubber materials for seals and diaphragms for gas appliances and gas equipment KE 192 - A1 March 2012 GASTEC QA Evaluation Guideline KE 192 Amendment A1 Rubber materials for seals and diaphragms for gas appliances and gas equipment Foreword and introduction These GASTEC QA Approval

More information

Chief Operating Officer Giampiero Belcredi

Chief Operating Officer Giampiero Belcredi CONTENTS 1. PURPOSE AND SCOPE 2. GENERAL PRINCIPLES AND GUARANTEES FOR THE CLIENT 3. ACCESS REQUIREMENTS FOR CERTIFICATION 4. ASSESSMENT PROCESS REQUIREMENTS 5. SUSPENSION AND REVOCATION OF THE CERTIFICATION

More information

PQS Quality Assurance protocol. TITLE: Cold Room/Freezer Room:

PQS Quality Assurance protocol. TITLE: Cold Room/Freezer Room: PQS Quality Assurance protocol WHO/XXX Original: English Distribution: General TITLE: Cold Room/Freezer Room: Note that this protocol is intended to form part of the contract documentation for a new cold

More information

GASTEC QA. Approval Requirements 31-1

GASTEC QA. Approval Requirements 31-1 KE 31-1 March 2012 GASTEC QA Approval Requirements 31-1 for the GASTEC QA product certificate for Sealing materials for metallic threaded joints in contact with 2nd and 3rd family gases and hot water Part

More information

CO-ORDINATION OF NOTIFIED BODIES PPE Regulation 2016/425 RECOMMENDATION FOR USE

CO-ORDINATION OF NOTIFIED BODIES PPE Regulation 2016/425 RECOMMENDATION FOR USE CO-ORDINATION OF NOTIFIED BODIES PPE Regulation 2016/425 PPE-R/00.017 Version 2 RECOMMENDATION FOR USE Number of pages: 5 Approval stage : Approved on : Origin : Horizontal Committee, C2D Ad hoc group

More information

BRL-K21030/02 5 August Certification of Alarm Communication. Certification Alarm Transmission Systems (ATS) Alarm Transmission Systems

BRL-K21030/02 5 August Certification of Alarm Communication. Certification Alarm Transmission Systems (ATS) Alarm Transmission Systems 5 August 2014 Certification of Alarm Communication Certification (ATS) Kiwa N.V. - 1-5 Augustus 2014 Preface This Evaluation Guideline (Certification Scheme) has been accepted by the Kiwa Board of Experts

More information

Building Standards Division. Whisky Maturation Warehouses Storage Buildings (Class 1) Automatic Fire Suppression Systems

Building Standards Division. Whisky Maturation Warehouses Storage Buildings (Class 1) Automatic Fire Suppression Systems Building Standards Division Whisky Maturation Warehouses Storage Buildings (Class 1) Automatic Fire Suppression Systems Crown Copyright 2015 Produced by the Buildings Standards Division February 2015 Version

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017 SECTION 21 0800 - COMMISSIONING OF FIRE SUPPRESSION SYSTEMS GENERAL 1.1 SUMMARY General 1. Work under this contract shall meet the requirements of Division 01, General Requirements, Conditions of Contract,

More information

GASTEC QA. Approval Requirements 31-2

GASTEC QA. Approval Requirements 31-2 KE 31-2 March 2012 GASTEC QA Approval Requirements 31-2 for the GASTEC QA product certificate for Sealing materials for metallic threaded joints in contact with 2nd and 3rd family gases and hot water Part

More information

Shipboard incinerators with capacities up to 4000 kw

Shipboard incinerators with capacities up to 4000 kw STANDARD FOR CERTIFICATION No. 2.9 Approval Programmes Type Approval Programmes for Marine Equipment Directive (MED) No. 431.90 - MED A.1/2.7 Shipboard incinerators with capacities up to 4000 kw JANUARY

More information

MARINE GYRO COMPASS STANDARD FOR CERTIFICATION. DET NORSKE VERITAS Veritasveien 1, N-1322 Høvik, Norway Tel.: Fax:

MARINE GYRO COMPASS STANDARD FOR CERTIFICATION. DET NORSKE VERITAS Veritasveien 1, N-1322 Høvik, Norway Tel.: Fax: STANDARD FOR CERTIFICATION No. 2.9 MARINE GYRO COMPASS JANUARY 2003 Veritasveien 1, N-1322 Høvik, Norway Tel.: +47 67 57 99 00 Fax: +47 67 57 99 11 FOREWORD is an autonomous and independent Foundation

More information

Loss Prevention Standard

Loss Prevention Standard Loss Prevention Standard LPS 1196: Issue 1.2 This Loss Prevention Standard is the property of BRE Global Ltd. and is made publicly available for information purposes only. Its use for testing, assessment,

More information

SHOP PRIMERS FOR CORROSION PROTECTION OF STEEL PLATES AND SECTIONS

SHOP PRIMERS FOR CORROSION PROTECTION OF STEEL PLATES AND SECTIONS STANDARD FOR CERTIFICATION No. 2.9 SHOP PRIMERS FOR CORROSION PROTECTION OF STEEL PLATES AND SECTIONS OCTOBER 2009 Veritasveien 1, NO-1322 Høvik, Norway Tel.: +47 67 57 99 00 Fax: +47 67 57 99 11 FOREWORD

More information

DTW Master Specification Section EMCS: Start Up, Verification and Commissioning

DTW Master Specification Section EMCS: Start Up, Verification and Commissioning Page 1 of 6 PART 1 GENERAL 1.1 RELATED SECTIONS.1 Related Sections..1 The contractor is to ensure that all related work is co ordinated among all specification sections, as well as between Division 11,

More information

Technical Assessment Guideline Applicable for the Kiwa KQ Certification Scheme:

Technical Assessment Guideline Applicable for the Kiwa KQ Certification Scheme: Technical Assessment Guideline Applicable for the Kiwa KQ Certification Scheme: Solar products and components Accreditation Kiwa Italia S.p.A. Via Treviso 32/34 31020 San Vendemiano (TV) Italia Tel: +39

More information

No previous protocol.

No previous protocol. PQS Quality Assurance protocol WHO/PQS/E06/TR03.VP2.1 Original: English Distribution: General TITLE: Programmable electronic temperature and event logger systems with integral alarm and auto-dialler options

More information

Kiwa Regulations for Certification in accordance with the CPR

Kiwa Regulations for Certification in accordance with the CPR 1 May 2014 Kiwa Regulations for Certification in accordance with the CPR EC Regulation No. 305/2011 (CPR) 1 May 2014 Kiwa Regulations for Certification in accordance with the CPR EC Regulation No. 305/2011

More information

INTERNATIONAL STANDARD

INTERNATIONAL STANDARD INTERNATIONAL STANDARD IEC 61508-2 First edition 2000-05 BASIC SAFETY PUBLICATION Functional safety of electrical/electronic/ programmable electronic safety-related systems Part 2: Requirements for electrical/electronic/

More information

RADAR REFLECTOR STANDARD FOR CERTIFICATION. DET NORSKE VERITAS Veritasveien 1, N-1322 Høvik, Norway Tel.: Fax:

RADAR REFLECTOR STANDARD FOR CERTIFICATION. DET NORSKE VERITAS Veritasveien 1, N-1322 Høvik, Norway Tel.: Fax: STANDARD FOR CERTIFICATION No. 2.9 RADAR REFLECTOR JANUARY 2003 Veritasveien 1, N-1322 Høvik, Norway Tel.: +47 67 57 99 00 Fax: +47 67 57 99 11 FOREWORD is an autonomous and independent Foundation with

More information

GASTEC QA. Approval Requirements 200. for the GASTEC QA product certificate for fusion fittings and saddles made from Polyethylene (PE)

GASTEC QA. Approval Requirements 200. for the GASTEC QA product certificate for fusion fittings and saddles made from Polyethylene (PE) KE 200 March 2012 GASTEC QA Approval Requirements 200 for the GASTEC QA product certificate for fusion fittings and saddles made from Polyethylene (PE) Foreword These GASTEC QA Approval requirements have

More information

Pressure Equipment Directive PED 2014/68/EU Commission's Working Group "Pressure"

Pressure Equipment Directive PED 2014/68/EU Commission's Working Group Pressure D. EVALUATION ASSESSMENT PROCEDURES Guideline D-01 Guideline related to: Annex III, module G Is design approval by a notified body required under module G? Module G does not explicitly require formal design

More information

SAFETY CODES COUNCIL ORDER. BEFORE THE FIRE TECHNICAL COUNCIL On June 21, 2012

SAFETY CODES COUNCIL ORDER. BEFORE THE FIRE TECHNICAL COUNCIL On June 21, 2012 SAFETY CODES COUNCIL #1000, 10665 Jasper Avenue N.W., Edmonton, Alberta, Canada, T5J 389 Tel: 780-413-0099 I 1-888-413-0099 Fax: 780-424-5134 I 1-888-424-5134 www.safetycodes.ab.ca COUNCIL ORDER No. 0015423

More information

For Building Managers: outsourcing the maintenance of fire safety and security systems

For Building Managers: outsourcing the maintenance of fire safety and security systems For Building Managers: outsourcing the maintenance of fire safety and security systems Changes revision table Date Rev # Paragraph / Page Change DISCLAIMER This document is intended solely for guidance

More information

INTERNATIONAL STANDARD

INTERNATIONAL STANDARD INTERNATIONAL STANDARD IEC 61511-2 First edition 2003-07 Functional safety Safety instrumented systems for the process industry sector Part 2: Guidelines for the application of IEC 61511-1 Reference number

More information

Guidelines for designating and monitoring notified bodies in Norway

Guidelines for designating and monitoring notified bodies in Norway Guidelines for designating and monitoring notified bodies in Norway Version 13.12.2010 The Ministry of Trade and Industry has also prepared a Norwegian version of these guidelines. Questions may be directed

More information

Abu Dhabi Conformity Assessment Scheme for Fire Pumps

Abu Dhabi Conformity Assessment Scheme for Fire Pumps Abu Dhabi Conformity Assessment Scheme for Fire Pumps Assessment and Surveillance Plan Page i TABLE OF CONTENTS DEFINITIONS... 1 1 ABOUT THE ABU DHABI QUALITY AND CONFORMITY COUNCIL... 2 2 FOREWORD...

More information

GASTEC QA. Approval Requirements 15. for the GASTEC QA product certificate for Steel pipes and sockets for the transport of gas. KE 15 January 2012

GASTEC QA. Approval Requirements 15. for the GASTEC QA product certificate for Steel pipes and sockets for the transport of gas. KE 15 January 2012 KE 15 January 2012 GASTEC QA Approval Requirements 15 for the GASTEC QA product certificate for Steel pipes and sockets for the transport of gas Foreword These GASTEC QA Approval requirements have been

More information

SUWANNEE RIVER WATER MANAGEMENT DISTRICT REQUEST FOR BID NO. 15/16-003AO FIRE ALARM SYSTEM INSTALLATION AND MONITORING.

SUWANNEE RIVER WATER MANAGEMENT DISTRICT REQUEST FOR BID NO. 15/16-003AO FIRE ALARM SYSTEM INSTALLATION AND MONITORING. SUWANNEE RIVER WATER MANAGEMENT DISTRICT REQUEST FOR BID NO. 15/16-003AO FIRE ALARM SYSTEM INSTALLATION AND MONITORING Table of Contents Section Title Page 1 Introduction 2 2 Proposed Schedule 2 3 Instructions

More information

GASTEC QA. Approval Requirements 6

GASTEC QA. Approval Requirements 6 KE 6 March 2012 GASTEC QA Approval Requirements 6 for the GASTEC QA product certificate for Plumbing fittings with ends for capillar soldering and/or thread connections Foreword These GASTEC QA Approval

More information

Summer Works Scheme 2010

Summer Works Scheme 2010 WCMS 01/2009 TO: PRIMARY AND POST PRIMARY SCHOOL AUTHORITIES Summer Works Scheme 2010 Devolved Capital Grants for Water Conservation Measures in Primary and Post Primary School Buildings Guide for School

More information

GROUNDING AVOIDANCE SYSTEM (GAS)

GROUNDING AVOIDANCE SYSTEM (GAS) STANDARD FOR CERTIFICATION No. 2.9 GROUNDING AVOIDANCE SYSTEM (GAS) JANUARY 2003 Veritasveien 1, N-1322 Høvik, Norway Tel.: +47 67 57 99 00 Fax: +47 67 57 99 11 FOREWORD is an autonomous and independent

More information

GASTEC QA. Approval Requirements 136

GASTEC QA. Approval Requirements 136 KE 136 January 2012 GASTEC QA Approval Requirements 136 for the GASTEC QA product certificate for Polyethylene (PE) valves for plastic piping systems for the supply of gaseous fuels Foreword These GASTEC

More information

Awarding body monitoring report for: Institute of Legal Executives (ILEX) February 2008 QCA/08/3734

Awarding body monitoring report for: Institute of Legal Executives (ILEX) February 2008 QCA/08/3734 Awarding body monitoring report for: Institute of Legal Executives (ILEX) February 2008 QCA/08/3734 2008 Qualifications and Curriculum Authority 2 Contents Introduction...4 Regulating external qualifications...4

More information

BRL-K14026/ Evaluation Guideline. for the Kiwa product certificate for Extractable shower hoses for sanitary tapware

BRL-K14026/ Evaluation Guideline. for the Kiwa product certificate for Extractable shower hoses for sanitary tapware 2017-05-12 for the Kiwa product certificate for Extractable shower hoses for sanitary tapware Preface This evaluation guideline has been accepted by the Kiwa Board of Experts Watercycle (CWK), in which

More information

DIRECTIVE NO: D-B

DIRECTIVE NO: D-B DIRECTIVE NO: D-B6 100604 1 LOW PRESSURE THERMAL FLUID PLANT AUTOMATED CONTROL SYSTEMS Date of Issue: June 4, 2010 General Details This directive is being issued to owners, licensed contractors, consulting

More information

CONTENTS AUTOMATIC TRANSFER SWITCHES

CONTENTS AUTOMATIC TRANSFER SWITCHES CONTENTS AUTOMATIC TRANSFER SWITCHES PART 1 GENERAL 1.1 Related Documents 1.2 Summary 1.3 References 1.4 Quality Assurance 1.5 Submittals 1.6 Delivery, Storage and Handling 1.7 Instructions And Training

More information

Guide to Membership Assessments

Guide to Membership Assessments Issue 10 July 2008 Guide to Membership Assessments 1. Introduction This guide is intended to assist companies in preparing for an assessment visit by SELECT. It supplements the SELECT Assessment Criteria

More information

Michigan State University Construction Standards COMMISSIONING OF FIRE ALARM SYSTEMS PAGE

Michigan State University Construction Standards COMMISSIONING OF FIRE ALARM SYSTEMS PAGE PAGE 280800-1 SECTION 280800 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

Standards and third party certification

Standards and third party certification Protecting People, Property and the Planet Standards and third party certification Nigel Firkins Content Developer, Fire Suppression BRE/NFCC Fire Protection Seminar Fit for purpose and reliable in service?

More information

CERTIFICATION SAFETY & BEYOND

CERTIFICATION SAFETY & BEYOND CERTIFICATION SAFETY & BEYOND Ferhun Emeksiz & R.M ( Max) Bradbury Client Manager & Fire Products Program Manager Global-Mark Pty Ltd Content Product Certification Understanding the framework Fundamental

More information

Procedure for the Approval of New Fire Detection and Alarm Technologies

Procedure for the Approval of New Fire Detection and Alarm Technologies VdS Guidelines for Automatic Fire Detection and Fire Alarm Systems VdS 3469en Procedure for the Approval of New Fire Detection and Alarm Technologies VdS 3469en : 2016-01 (01) Publisher and publishing

More information

IOWA STATE FIRE MARSHAL DIVISION Attn: Licensing Administrator

IOWA STATE FIRE MARSHAL DIVISION Attn: Licensing Administrator IOWA STATE FIRE MARSHAL DIVISION Attn: Licensing Administrator 215 E Seventh Street; Des Moines, IA 50319 Email: sfmlicense@dps.state.ia.us APPLICATION CHECKLISTS (EFFECTIVE IMMEDIATELY) 1. DO NOT mail

More information

Bold items are particular to the City of Euless

Bold items are particular to the City of Euless EULESS FIRE DEPARTMENT FIRE MARSHAL S OFFICE INFORMATION LINE: Revised 8/2004 Fire Chief Lee Koontz Fire Marshal Paul Smith EFD-FMO 3-1 2003 International Fire & Building Code as Amended NFPA Standards

More information

CHAPTER 61G15-32 RESPONSIBILITY RULES OF PROFESSIONAL ENGINEERS CONCERNING THE DESIGN OF FIRE PROTECTION SYSTEMS

CHAPTER 61G15-32 RESPONSIBILITY RULES OF PROFESSIONAL ENGINEERS CONCERNING THE DESIGN OF FIRE PROTECTION SYSTEMS CHAPTER 61G15-32 RESPONSIBILITY RULES OF PROFESSIONAL ENGINEERS CONCERNING THE DESIGN OF FIRE PROTECTION SYSTEMS 61G15-32.001 61G15-32.002 61G15-32.003 61G15-32.004 61G15-32.005 61G15-32.006 61G15-32.007

More information

Plan Submittal Checklist

Plan Submittal Checklist City of Aurora Public Works Department HIGH-PILED COMBUSTIBLE STORAGE Plan Submittal Checklist Building Division 15151 E. Alameda Parkway, Ste 2400 Aurora, CO 80012 303-739-7420 Fax: 303-739-7551 Project

More information

FIRE & LIFE SAFTEY STANDARD

FIRE & LIFE SAFTEY STANDARD Title: Effective Date: 01/01/14 Revised Date: 1/1/14 Code References: Title 16, Chapter 16.16 of the Roseville Municipal Code, NFPA 72 Note: This standard is a summary of Fire Department clarifications

More information

Council Directive 93/68/EEC of 22 July 1993 amending Directives

Council Directive 93/68/EEC of 22 July 1993 amending Directives Council Directive 93/68/EEC of 22 July 1993 amending Directives 87/404/EEC (simple pressure vessels), 88/378/EEC (safety of toys), 89/106/EEC (construction products), 89/336/EEC (electromagnetic compatibility),

More information

SOCIETY OF FIRE PROTECTION ENGINEERS POSITION STATEMENT P THE ENGINEER AND THE TECHNICIAN DESIGNING FIRE PROTECTION SYSTEMS.

SOCIETY OF FIRE PROTECTION ENGINEERS POSITION STATEMENT P THE ENGINEER AND THE TECHNICIAN DESIGNING FIRE PROTECTION SYSTEMS. SOCIETY OF FIRE PROTECTION ENGINEERS POSITION STATEMENT P-01-05 THE ENGINEER AND THE TECHNICIAN DESIGNING FIRE PROTECTION SYSTEMS October, 2005 Society of Fire Protection Engineers - 1 - Position Statement

More information

Rancho Cucamonga Fire Protection District Prevention Bureau Standard

Rancho Cucamonga Fire Protection District Prevention Bureau Standard Rancho Cucamonga Fire Protection District Prevention Bureau Standard Title: Fire Alarm and Monitoring Systems Standard # 9-3 Effective: May 2002 Number of Pages: 7 Updated: December 2016 for consistency

More information

7.0 SAMPLE PERMITS, FORMS AND CHECKLISTS SELF INSPECTION CHECKLIST

7.0 SAMPLE PERMITS, FORMS AND CHECKLISTS SELF INSPECTION CHECKLIST 7.0 SAMPLE PERMITS, FORMS AND CHECKLISTS The Permits, forms and checklists shown within this section are an example of the type of controls that should be in place to help effectively manage Health & Safety

More information

D. Reference Standards (Utilize latest editions available):

D. Reference Standards (Utilize latest editions available): 1.01 Scope of Standard A. This standard provides general requirements of The Sam Houston State University for fireextinguishing systems other than water-based fire suppression systems. This document is

More information

RULEBOOK ON ELECTROMAGNETIC COMPATIBILITY

RULEBOOK ON ELECTROMAGNETIC COMPATIBILITY RULEBOOK ON ELECTROMAGNETIC COMPATIBILITY ("Official Gazette of RS, issue No. 13/2010) I INTRODUCTION Scope Article 1 This Rulebook stipulates the essential requirements that shall be met with regard to

More information

RULES OF DEPARTMENT OF COMMERCE AND INSURANCE DIVISION OF FIRE PREVENTION CHAPTER FIRE PROTECTION SPRINKLER SYSTEM CONTRACTORS

RULES OF DEPARTMENT OF COMMERCE AND INSURANCE DIVISION OF FIRE PREVENTION CHAPTER FIRE PROTECTION SPRINKLER SYSTEM CONTRACTORS RULES OF DEPARTMENT OF COMMERCE AND INSURANCE DIVISION OF FIRE PREVENTION CHAPTER 0780-02-07 FIRE PROTECTION SPRINKLER SYSTEM CONTRACTORS TABLE OF CONTENTS 0780-02-07-.01 Definitions 0780-02-07-.08 Installation,

More information

Application for the Issue of Initial SJIB Grade (ECS) Card

Application for the Issue of Initial SJIB Grade (ECS) Card Please return this form with one passport style photograph with your name and National Insurance number printed on the reverse. Application for the Issue of Initial SJIB Grade (ECS) Card Scottish Joint

More information

INTERNATIONAL STANDARD

INTERNATIONAL STANDARD INTERNATIONAL STANDARD IEC 61511-3 First edition 2003-03 Functional safety Safety instrumented systems for the process industry sector Part 3: Guidance for the determination of the required safety integrity

More information

Design & Construction Standards, Revised January

Design & Construction Standards, Revised January PART 1 GENERAL 1.01 Scope of Standard A. This standard provides general requirements of The University of Texas at Austin for fire-extinguishing systems other than water-based fire suppression systems.

More information

PROCEDURES FOR APPROVAL OF LIFE-SAVING APPLIANCES AND FIRE SAFETY SYSTEMS, EQUIPMENT AND PRODUCTS

PROCEDURES FOR APPROVAL OF LIFE-SAVING APPLIANCES AND FIRE SAFETY SYSTEMS, EQUIPMENT AND PRODUCTS (05/2011) PROCEDURES FOR APPROVAL OF LIFE-SAVING APPLIANCES AND FIRE SAFETY SYSTEMS, EQUIPMENT AND PRODUCTS 3rd EDITION May 2011 Responsible Authority The Design, Equipment and Boating Safety Branch is

More information

Third Party Certification:

Third Party Certification: Third Party Certification: What does it mean for businesses? Introduction If you work in any part of the fire safety industry you will at least have heard of Third Party Certification (TPC) but you may

More information

D. The work addressed in this section consists of a fire protection system, which may include coordination with one or more of the following:

D. The work addressed in this section consists of a fire protection system, which may include coordination with one or more of the following: PART 1 GENERAL 1.01 Scope of Standard A. This standard provides general requirements of Sam Houston State University for the design and construction of standpipe systems to include combination standpipe

More information

CERTIFICATION MANUAL FOR NF PROGRAMMES MANAGED BY EUROVENT CERTITA CERTIFICATION: GENERAL PROVISIONS

CERTIFICATION MANUAL FOR NF PROGRAMMES MANAGED BY EUROVENT CERTITA CERTIFICATION: GENERAL PROVISIONS Certification body mandated by AFNOR Certification 48/50 rue de la Victoire 75009 PARIS Telephone: +33 (0) 1 75 44 71 71 www.eurovent-certification.com/www.certita.fr CERTIFICATION MANUAL FOR NF PROGRAMMES

More information

BRL-K602. Datum Evaluation Guideline

BRL-K602. Datum Evaluation Guideline Datum 2018-09-04 for the Kiwa product certificate for valves, control valves and non-return valves for drinking water transport and drinking water distribution systems Preface This evaluation guideline

More information

INTERNATIONAL STANDARD

INTERNATIONAL STANDARD INTERNATIONAL STANDARD IEC 61784-5-14 Edition 1.0 2010-07 colour inside Industrial communication networks Profiles Part 5-14: Installation of fieldbuses Installation profiles for CPF 14 IEC 61784-5-14:2010(E)

More information

(1135/2016) Translation from Finnish Legally binding only in Finnish and Swedish Ministry of Economic Affairs and Employment, Finland

(1135/2016) Translation from Finnish Legally binding only in Finnish and Swedish Ministry of Economic Affairs and Employment, Finland Translation from Finnish Legally binding only in Finnish and Swedish Ministry of Economic Affairs and Employment, Finland Electrical Safety Act (1135/2016) By decision of Parliament, the following is enacted:

More information

1.3 REFERENCE STANDARDS

1.3 REFERENCE STANDARDS SECTION 28 4600 FIRE DETECTION AND ALARM PART 1 -GENERAL 1.1 SECTION INCLUDES A. Fire alarm system design and installation, including all components, wiring, and conduit. B. Circuits from protected premises

More information

PQS Independent type-testing protocol

PQS Independent type-testing protocol PQS Independent type-testing protocol WHO/XXX Original: English Distribution: General TITLE: Integrated electronic maximum-minimum thermometer, with factory programmed alarms, for vaccine refrigerators

More information

To: All SAAS Accredited Certification Bodies Subject: Clarification to Emergency and Health & Safety Requirements in the SA8000 Standard

To: All SAAS Accredited Certification Bodies Subject: Clarification to Emergency and Health & Safety Requirements in the SA8000 Standard SOCIAL ACCOUNTABILITY ACCREDITATION SERVICES To: All SAAS Accredited Certification Bodies Subject: Clarification to Emergency and Health & Safety Requirements in the SA8000 Standard Background: After an

More information

DIVISION 21: FIRE SUPPRESSION SYSTEMS SECTION Fire Protection Systems Protecting Cold Storage and Unheated Warehouses

DIVISION 21: FIRE SUPPRESSION SYSTEMS SECTION Fire Protection Systems Protecting Cold Storage and Unheated Warehouses PART 1 - GENERAL 1.1 SCOPE A. Through Class III Commodity Classification, up to 12.2m of single, double or multiple row rack storage, up to 14.6m building height (VanQuish Fire Sprinkler System). Cartoned

More information

MAINTENANCE AND TESTING OF FIRE SPRINKLER SYSTEMS

MAINTENANCE AND TESTING OF FIRE SPRINKLER SYSTEMS MAINTENANCE AND TESTING OF FIRE SPRINKLER SYSTEMS Introduction When properly installed and maintained, automatic fire sprinkler systems have proven to be the most effective means for protecting life and

More information

GK/GN0612. Guidance on Signalling Lockout Systems to Protect Railway. Undertaking Personnel. Railway Group Guidance for GK/RT0212.

GK/GN0612. Guidance on Signalling Lockout Systems to Protect Railway. Undertaking Personnel. Railway Group Guidance for GK/RT0212. GN Published by Rail Safety and Standards Board Evergreen House 160 Euston Road London NW1 2DX Copyright 2007 Rail Safety and Standards Board Limited GK/GN0612 Issue One: August 2007 Railway Group Guidance

More information

Cable Ties JULY The electronic pdf version of this document found through is the officially binding version

Cable Ties JULY The electronic pdf version of this document found through  is the officially binding version p pproval roramms for U rcos orasato Mutual coto (M)No. 2.9 STANDARD FOR CERTIFICATION Approval Programmes Type Approval Programmes for EU recognised organisation Mutual Recognition (MR) No. MR-E012 Cable

More information

Functional Safety: the Next Edition of IEC 61511

Functional Safety: the Next Edition of IEC 61511 HazAus2015/1507 Functional Safety: the Next Edition of IEC 61511 Mirek Generowicz Engineering Manager I&E Systems Pty Ltd Level 2, 445 Hay Street Perth WA 6000 Abstract The functional safety standard IEC

More information

APPENDIX H (DESIGN SUBMISSION CRITERIA)

APPENDIX H (DESIGN SUBMISSION CRITERIA) APPENDIX H (DESIGN SUBMISSION CRITERIA) FIRE ALARM SYSTEM As per ACCORD standard Part 5, section 5.7 Fire Alarm System Design to be verified by ACCORD Chief Safety Inspector. Testing of the installation

More information

MGN 453 (M) Maritime and Coastguard Agency Logo MARINE GUIDANCE NOTE

MGN 453 (M) Maritime and Coastguard Agency Logo MARINE GUIDANCE NOTE Maritime and Coastguard Agency Logo MARINE GUIDANCE NOTE MGN 453 (M) FIRE PROTECTION Fire Retardant Treatment for Floor Coverings, Suspended Textile Materials, Upholstery Materials and Bedding Components

More information

EMERGENCY LIGHTING COMPLETION CERTIFICATE For small installations and verification of existing installations

EMERGENCY LIGHTING COMPLETION CERTIFICATE For small installations and verification of existing installations A DETAILS OF THE CLIENT Client/ B DETAILS OF THE EMERGENCY LIGHTING INSTALLATION Extent of the installation covered by this certificate The Owner 19 Walker Grove, Hatfield, Hertfordshire 19 Walker Grove,

More information

BRL-K618/ Evaluation Guideline. for the Kiwa product certificate for Water meters

BRL-K618/ Evaluation Guideline. for the Kiwa product certificate for Water meters /08 2018-01-15 for the Kiwa product certificate for Water meters Preface This evaluation guideline has been accepted by the Kiwa Board of Experts Watercycle (CWK), in which all relevant parties in the

More information

TECHNICAL BULLETIN No: 0040

TECHNICAL BULLETIN No: 0040 National Security Inspectorate Sentinel House, 5 Reform Road, Maidenhead, SL6 8BY E: nsi@nsi.org.uk W: nsi.org.uk Dated: 12 October 2017 To: 1. All NSI NACOSS Gold and System Silver Companies 2. Applicant

More information

RULES OF THE TENNESSEE ALARM SYSTEMS CONTRACTORS BOARD CHAPTER GENERAL PROVISIONS TABLE OF CONTENTS

RULES OF THE TENNESSEE ALARM SYSTEMS CONTRACTORS BOARD CHAPTER GENERAL PROVISIONS TABLE OF CONTENTS RULES OF THE TENNESSEE ALARM SYSTEMS CONTRACTORS BOARD CHAPTER 0090-01 GENERAL PROVISIONS TABLE OF CONTENTS 0090-01-.01 Purpose 0090-01-.08 Insurance Requirements 0090-01-.02 Definitions 0090-01-.09 Fees

More information

SECTION WET-PIPE SPRINKLER SYSTEMS

SECTION WET-PIPE SPRINKLER SYSTEMS SECTION 21 13 13 WET-PIPE SPRINKLER SYSTEMS PART 1 - GENERAL 1.1 SCOPE OF WORK A. Design, installation and testing shall be in accordance with NFPA 13 except for specified exceptions. B. The demolition

More information

SECTION DIGITAL, ADDRESSABLE FIRE-ALARM SYSTEM

SECTION DIGITAL, ADDRESSABLE FIRE-ALARM SYSTEM SECTION 283111 - DIGITAL, ADDRESSABLE FIRE-ALARM SYSTEM PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division

More information

These periods commence upon receipt of the data and in the case of a business relationship, after the contract or the contact has ended.

These periods commence upon receipt of the data and in the case of a business relationship, after the contract or the contact has ended. Falck and privacy Falck is committed to a safe, reliable and sustainable service of high quality. This also applies to managing your personal data. You can expect from us that your data are safe with us

More information

The European Radio Equipment Directive 2014/53/EU

The European Radio Equipment Directive 2014/53/EU TÜV SÜD Slide 1 The European Radio Equipment Directive 2014/53/EU 28 March 2017 Meet the speaker behind the voice Jon Lea Senior Engineer (Product Certification), TÜV SÜD 30 years experience in the testing

More information

Session Four Functional safety: the next edition of IEC Mirek Generowicz Engineering Manager, I&E Systems Pty Ltd

Session Four Functional safety: the next edition of IEC Mirek Generowicz Engineering Manager, I&E Systems Pty Ltd Abstract Session Four Functional safety: the next edition of IEC 61511 Mirek Generowicz Engineering Manager, I&E Systems Pty Ltd The functional safety standard IEC 61511 provides a framework for managing

More information

Co-ordination of the Group of Notified Bodies for the Construction Products /Regulation 305/2011/EU

Co-ordination of the Group of Notified Bodies for the Construction Products /Regulation 305/2011/EU GNB-CPR AG Co-ordination of the Group of Notified Bodies for the Construction Products /Regulation 305/2011/EU NB-CPR/AG/03/003r8a Issued: 18 December 2013 APPROVED GUIDANCE GNB-CPR position paper Generic

More information

Application for Up-Grade Approved Electrician

Application for Up-Grade Approved Electrician Please return this form with one passport style photograph with your name and National Insurance number printed on the reverse. Application for Up-Grade Approved Electrician Scottish Joint Industry Board

More information

Australian Standard. Functional safety Safety instrumented systems for the process industry sector

Australian Standard. Functional safety Safety instrumented systems for the process industry sector AS IEC 61511.2 2004 IEC 61511-2:2003 AS IEC 61511.2 Australian Standard Functional safety Safety instrumented systems for the process industry sector Part 2: Guidelines for the application of AS IEC 61511.1

More information

FIRE AND LIFE SAFETY EDUCATOR II NFPA 1035, Chapter 5, 2015 Edition

FIRE AND LIFE SAFETY EDUCATOR II NFPA 1035, Chapter 5, 2015 Edition Official Skill Sheets for Practical Skills Evaluation Ontario, Canada NFPA 1035, Chapter 5, 2015 Edition National Fire Protection Association Standard for Fire and Life Safety Educator Professional Qualifications

More information

Florida Senate SB 982 By Senator Bennett

Florida Senate SB 982 By Senator Bennett By Senator Bennett 1 A bill to be entitled 2 An act relating to electrical and alarm system 3 contracting; amending s. 489.503, F.S.; 4 requiring certain contractors to be certified 5 pursuant to part

More information

Evaluation Guideline. regarding the Product Certificate GASKEUR Label HR (High Efficiency, Heating):2010 for Central Heating Appliances

Evaluation Guideline. regarding the Product Certificate GASKEUR Label HR (High Efficiency, Heating):2010 for Central Heating Appliances 1st February 2011 regarding the Product Certificate GASKEUR Label HR (High Efficiency, Heating):2010 for Central Heating Appliances Foreword This has been adopted by the Kiwa Board of Experts of Energy

More information