Comprehensive Roadside Management Project (CRMP)
|
|
- Moses Brooks
- 5 years ago
- Views:
Transcription
1
2
3
4 Caroline County Comprehensive Roadside Management Project (CRMP) DEPARTMENT OF PUBLIC WORKS/UTILITIES Mill Creek Rd Ruther Glen, Virginia CARMEL CHURCH CRMP MASTER PLAN
5 Table of Contents Introduction Scope of Project Timeline Site Conditions Design Conditions Cost Estimates Maintenance Plan Sponsorship/Acknowledgment Signs
6 Introduction In 2006, Virginia Senate Bill 260 approved the Virginia Department of Transportation s (VDOT) Comprehensive Roadside Management Program (CRMP). This action allowed VDOT to grant localities permission to provide landscaping in VDOT right-of-way areas. Additionally, the bill also cleared the way for localities to partner with private businesses, individuals or civic organizations to sponsor such activities within approved VDOT right-of-ways. Caroline County has received requests from the Carmel Church residential and business community to implement measures that increase the aesthetic qualities of the Carmel Church I95 interchange as well as reduce the number of vagrants and panhandlers that frequent the area. In September, 2016 staff members presented the Caroline County Board of Supervisors (BOS) with a plan to establish a Comprehensive Roadside Management Program, that once permitted by VDOT, would allow County staff to implement a grounds maintenance plan in the cloverleaf sections of the I95/Rt 207 interchange. At the BOS s direction, staff was asked to proceed with the CRMP process. Phase 1 project goals include removing trees, underbush, and woody vegetation 4 in diameter and less within the right-of way of the southbound entrance ramp circle to I95. The desired result is a more aesthetically pleasing area that also greatly reduces the likelihood of vagrants using the area for camping and temporary residency. Phases 2-4 include the remaining quadrants of the I95/Rt. 207 interchange. County staff could also develop a program through which public and private entities could donate funds towards the landscaping (with appropriate recognition signage) within these VDOT- maintained properties. Director Joseph Schiebel Department of Public Works/Utilities Comprehensive Roadside Management Program - Master Plan Page- 3
7 Scope of Project The overall CRMP project consists of four phases. Each phase involves mulching trees, underbrush, and woody vegetation 4 and less in diameter within one of the four cloverleaf right-of-way areas at the I95/Rt. 207 interchange. Mulching of vegetation larger than 4 in diameter will be allowed with prior VDOT approval only. This work will be completed using a low-impact track or rubber tire machine outfitted with a mulching head. The process reduces soil disturbance to a minimum while simultaneously covering the area with a thin layer of wood mulch that further protects the site from any stormwater or sediment runoff. The end result is a cleaner looking area that yields far better visibility into the right-of-way area. It is staff s hope this will improve the area s aesthetic properties and that increased visibility will deter vagrants and panhandlers from using the right-of-way as a temporary camping area. This long-term project is designed to be developed, managed, and maintained by Department of Public Works/Utilities staff. Phase Description Acres (Approx.) Completion Goal 1 Southbound Ent. Ramp Circle (NW Quadrant) 3.2 Spring Northbound 195 Exit Ramp (SE Quadrant) 5.1 Winter /18 3 Southbound I95 Entrance Ramp (SW Quadrant) 1.3 Winter /19 4 Northbound I95 Entrance Ramp (NE Quadrant) 5.7 Winter /20 Comprehensive Roadside Management Program - Master Plan Page- 4
8 Timeline DECEMBER 2016 PRESENT CRMP MASTER PLAN TO CAROLINE COUNTY BOARD OF SUPERVISORS The CRMP Master Plan and VDOT application will subsequently be submitted upon BOS recommendation. JANUARY 2017 STAKEHOLDER MEETING County staff will meet with VDOT residency representative to review and discuss the proposed CRMP. MARCH 2017 PUBLIC HEARING/ENDORSEMENT PROCESS BEGINS The first reading of the CRMP Master Plan is tentatively scheduled for March 28, 2017, during which the proposed landscaping activities will be made available for review. A formal resolution [of endorsement] from the BOS is tentatively planned for April The Dept. of Public Works/Utilities shall provide written notification to VDOT of the Board s intention to hold a public hearing no later than 14 days prior to such hearing. Such notification shall be made to the Virginia Department of Transportation, Asset Management Division Administrator, 1401 E. Broad Street, Richmond, Virginia APRIL - MAY 2017 COMPLETE WORK ON PHASE 1 Staff will either use equipment available in-house or use a qualified contractor to complete the work. The remaining phases will be completed at a rate of one-per-year beginning in (Phase , Phase , Phase ) Comprehensive Roadside Management Program - Master Plan Page- 5
9 Site Conditions The CRMP includes the internal right-of-way areas within the I95/Rt. 207 interchange. These areas are primarily wooded and have a topography that ranges from flat to gently sloping. These areas are not scheduled for any future construction within VDOT s current six-year improvement plan. The site contains sufficient right-of-way to reasonably permit landscaping operations without safety or maintenance concerns. The proposed landscaping operations will not obstruct or interfere with existing drainage conditions. There are no underground utilities, pavement, sidewalks, or highway signage or signals that will conflict with the landscaping operations proposed under the project. Project Design/Description The CRMP activity will currently be limited to mulching all woody vegetation with a diameter of 4 or less. The goal is to remove unsightly brush and undergrowth while also improving site lines into the right-of-way areas. Additional elements such as flower gardens could be added in the future. Additional improvements will have to be permitted, have a public hearing conducted followed by BOS endorsement and VDOT approval. Per VDOT regulations Caroline County shall not, at any time, install lighting, flag or pennant poles, fountains or water features, landscaping that depicts a logo or name, any form of advertising, sculptures, or statues within the VDOT right-of-way. Additionally, the County shall not improve sight lines with the intent to provide greater visibility to any existing or future business or advertisement. Comprehensive Roadside Management Program - Master Plan Page- 6
10 Budget Impact Phase Description Acres (Approx.) Est. Cost Annual Maint. Cost * 1 Southbound Ent. Ramp Circle (NW Quadrant) 3.2 $9,000 $914 2 Northbound 195 Exit Ramp (SE Quadrant) 5.1 $14,000 $1,457 3 Southbound I95 Entrance Ramp (SW Quadrant) 1.3 $4,000 $371 4 Northbound I95 Entrance Ramp (NE Quadrant) 5.7 $16,000 $1,629 * County staff will ensure the Adherence to the established VDOT Comprehensive Roadside Management regulations (24 VAC ) (Chapter 121) which will include the submittal of a long-term maintenance plan for each designated area. Maintenance Plan The CRMP areas will undergo periodic maintenance on a five-year rotational cycle. Staff will return to each phase no less than every 5th year to perform similar mulching practices as were used in the first year of the project. This economical practice will keep undergrowth to a minimum within the CRMP areas. A formal maintenance agreeement shall be included as part of the CRMP submittal. Sponsorship/Signage Acknowledgment signs are a way of recognizing a company, business, or volunteer group that provides a highway-related service or funding. In addition to the specifications in 24 VAC D 2, in order to be recognized on an acknowledgment sign, an entity must provide a minimum cash or in-kind contribution to the permittee for the landscaping activity as specified below. Such contribution shall allow an acknowledgment sign for five years unless the need arises for removal or relocation of the sign. The cost of the acknowledgment sign shall not count toward the minimum contribution requirement. 1. Noncontrolled access primary and secondary highways: $7,500 contribution. 2. Controlled access primary and secondary highways: $8,500 contribution. 3. Interchanges on controlled access primary and secondary highways: $10,000 contribution. 4. Interstate interchanges: $20,000 contribution. SAMPLE Comprehensive Roadside Management Program - Master Plan Page- 7
11 CAROLINE COUNT Y DEPARTMENT OF PUBLIC WORKS/UTILITIES JOSEPH C. SCHIEBEL DIRECTOR CONTACT P.O. Box 424 Bowling Green, VA TELEPHONE Phone: (804) SOCIAL
PROJECT SHOWING MINUTES
PROJECT SHOWING MINUTES North Lynn Street Esplanade Improvements Project No. 0029-000-859, C501, B605 UPC No. 109813 November 1, 2017 10:00 a.m. 1911 North Ft. Myer Drive, LL-10, Arlington, VA Overview
More informationCOMMUNITY DESIGN. GOAL: Create livable and attractive communities. Intent
COMMUNITY DESIGN Intent An attractive, well-designed County will attract quality development, instill civic pride, improve the visual character of the community, and create a strong, positive image for
More informationPLANNING APPROVAL & SIDEWALK WAIVER STAFF REPORT Date: December 1, 2016
PLANNING APPROVAL & SIDEWALK WAIVER STAFF REPORT Date: December 1, 2016 NAME Dennis P. Wilkins LOCATION. CITY COUNCIL DISTRICT District 6 7078 Bruns Drive (Northeast corner of Bruns Drive and Cody Road)
More informationCHAPTER BEAUTIFICATION AND LANDSCAPE MANAGEMENT
APPLICATIONS FOR BEAUTIFICATION GRANTS (STARTING FISCAL YEAR 2017-2018) MUST ADHERE TO THE REQUIREMENTS OF RULE CHAPTER 14-40, FLORIDA ADMISTRATIVE CODE Including the pending revisions shown below CHAPTER
More information3.10 ROW Overlay District
3.10 A. Purpose The purpose of this Overlay District is to regulate items which could be placed or constructed within the Rights-of-way lying wholly or partially within the jurisdictional area of the Town
More informationBOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM. Endorsement of Design for Route 7/George Washington Boulevard Overpass. Algonkian and Broad Run
BOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM Date of Meeting: March 7, 2017 # 14 SUBJECT: ELECTION DISTRICTS: CRITICAL ACTION DATE: STAFF CONTACTS: Endorsement of Design for Route 7/George Washington
More informationRt. 29 Solutions Project Delivery Advisory Panel. December 3, 2015
Rt. 29 Solutions Project Delivery Advisory Panel December 3, 2015 Agenda item 1: Introductions Project Delivery Advisory Panel Technical Team 2 Agenda item 2: Interaction and Feedback Live Streaming Nov
More informationChain Bridge Road Sidewalk Improvements Citizen Council Work Session
Chain Bridge Road Sidewalk Improvements Citizen Council Work Session May 10, 2016 Project Location 2 Project Objectives Provide a continuous pedestrian facility (sidewalk) connection from Downtown City
More informationPotomac Headwaters Leaders of Watersheds Spring 2019 Application
Potomac Headwaters Leaders of Watersheds Spring 2019 Application Educating future generations of environmental stewards through classroom education and on the ground conservation practices at schools.
More information4.1.A NORTHWEST QUADRANT MASTER PLAN
4.1.A NORTHWEST QUADRANT MASTER PLAN (Ordinance 0-16-27, dated October 17, 2016) Goal: Transform the Northwest Quadrant into the cultural centerpiece of Deerfield. Objectives: 1. Maintain the cluster of
More informationCommunity Development Rezoning Report REZ14-006
Community Development Rezoning Report REZ14-006 Planning Commission Board of Supervisors March 4, 2014 March 26, 2014 Applicant M & N Real Estate, LLC Tax Map Id 125-(A)- L20E,125-(A)- L20E1, portion of
More informationDRIVEWAY REGULATIONS
TOWN OF NEW LONDON PLANNING BOARD DRIVEWAY REGULATIONS INSTRUCTIONS TO APPLICANTS FOR THE CONSTRUCTION OR ALTERATION OF DRIVEWAYS IMPORTANT: READ CAREFULLY BEFORE FILLING OUT ATTACHED APPLICATION Revised
More informationPLANNED DEVELOPMENT (MASTER PLAN & UNIT PLAN)
Central Permit Center 555 Santa Clara Street Vallejo CA 94590 Business License Building Fire Prevention Planning Public Works 707.648.4310 707.648.4374 707.648.4565 707.648.4326 707.651.7151 PLANNED DEVELOPMENT
More informationGENERAL INFORMATIONaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
To: Planning and Zoning Commission From: City Staff Date: November 15, 2016 Re: Case #16026 Raymore Activity Center Site Plan GENERAL INFORMATIONaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa Applicant/ Property Owner:
More informationThe Illinois Department of Transportation and Lake County Division of Transportation. Route 173, including the Millburn Bypass
The Illinois Department of Transportation and Lake County Division of Transportation welcome you to this Public Hearing for U.S. Route 45 from Illinois Route 132 to Illinois Route 173, including the Millburn
More informationThe Corporation of Delta COUNCIL REPORT Regular Meeting. Human Resources and Corporate Planning Department
t t, 11,. I., I To: From: Mayor and Council The Corporation of Delta COUNCIL REPORT Regular Meeting Human Resources and Corporate Planning Department F.24 Date: February 24, 2016 Veteran Affairs Canada
More information6.8 SCENIC HIGHWAYS Introduction
6.8 SCENIC HIGHWAYS 6.8.1 Introduction The Scenic Highways Element is an optional General Plan element authorized by Section 65303 of the Government Code. The Scenic Highways Element is intended to establish
More informationCITY OF TUMWATER 555 ISRAEL RD. SW, TUMWATER, WA (360) (360) (FAX)
CITY OF TUMWATER 555 ISRAEL RD. SW, TUMWATER, WA 98501 (360) 754-4180 (360) 754-4126 (FAX) Email: cdd@ci.tumwater.wa.us APPENDIX II-C SHORT FORM CONSTRUCTION STORMWATER POLLUTION PREVENTION PLAN (SWPPP)
More informationMichigan State University Barrier-Free/Accessibility Project Status Summary March 2017
Projects Completed FY14, FY15 and FY16 (arranged alphabetically) Abrams Planetarium Install automatic door opener on main doors of the Planetarium. Completed: Summer 2016 Cost: $13,000 Akers Hall Renovations
More informationCommunity Development Rezoning Report REZ16-018
Community Development Rezoning Report Planning Commission Board of Supervisors March 1, 2016 March 23, 2016 Applicant Tax Map Id Present Zoning Proposed Zoning Location Medical Center 125-(17)- L1, 125-(17)-
More informationPotomac Headwaters Leaders of Watersheds Spring 2019 Application
Potomac Headwaters Leaders of Watersheds Spring 2019 Application Educating future generations of environmental stewards through classroom education and on the ground conservation practices at schools.
More informationSouthern Gateway Project and Public Green
Southern Gateway Project and Public Green Transportation and Trinity River Project Committee May 23, 2016 Purpose of Presentation Provide the history and an overview of the Southern Gateway Project (SGP)
More informationResponse: The public school use, including the SWM facility, is within the R-1 District.
Loudoun County School Board Dulles North Elementary School (ES-31) CMPT 2017-0006 and SPMI 2017-0015 First Response to Referral Comments Zoning Administration Comments dated October 2, 2017 Comment 1:
More informationAccess Management and Site Plan Review. Robert W. Hofrichter Asst Administrator, Transportation and Mobility Planning Division April 2014
Access Management and Site Plan Review Robert W. Hofrichter Asst Administrator, Transportation and Mobility Planning Division April 2014 Access Management 2 Access Management What is Access Management?
More informationDescription of Preferred Alternative
Chapter 2 Description of Preferred Alternative 2.1 Introduction This chapter of the programmatic Sammamish Town Center Sub-area Plan Final EIS provides a more detailed description of the Preferred Alternative
More information4/8/2015 Item #10D Page 1
MEETING DATE: April 8, 2015 PREPARED BY: Christy Villa, Associate Civil Engineer DEPT. DIRECTOR: Glenn Pruim DEPARTMENT: Public Works CITY MANAGER: Larry Watt SUBJECT: NORTH COAST HIGHWAY 101 STREETSCAPE
More informationUNIVERSITY OF NORTHERN IOWA
UNIVERSITY OF NORTHERN IOWA Municipal Separate Storm Sewer System September 2008 Report Permit Number 07-09-0-04 August 2008 Prepared by: University of Northern Iowa Environmental Health and Safety Office
More informationTown of West Point Plan of Development
Town of West Point Plan of Development Plan Submission In accordance with Section 70-51(b) of the Town Code, the Zoning Administrator shall establish a written policy for the form, format, content and
More informationHISTORIC SITE AND MONUMENT COMMISSION (HSMC) Instructions for Historical Markers, Monuments, and Public Art Application
HISTORIC SITE AND MONUMENT COMMISSION (HSMC) Instructions for Historical Markers, Monuments, and Public Art Application This document is for information purposes only and does not need to be submitted
More informationARLINGTON COUNTY, VIRGINIA. County Board Agenda Item Meeting of January 28, 2017 SUPPLEMENTAL REPORT-2
ARLINGTON COUNTY, VIRGINIA County Board Agenda Item Meeting of January 28, 2017 SUPPLEMENTAL REPORT-2 DATE: January 27, 2017 SUBJECT: The Virginia Department of Transportation s Transform I-66 Inside the
More informationMountain RECOMMENDATlON: After staff presentation and review of the revised format for sample
COUNTY OF ALBEMARLE PLANNING STAFF REPORT SUMMARY Project Name: Places29 Draft Master Plan: Staff: David Benish Chapter 8 - Implementation Followup Planning Commission Worksession: Board of Supenrisors
More informationWELCOME! 8 8:30 6: TH STREET IMPROVEMENTS. Open House. Presentation & Q&A
WELCOME! 168 TH STREET IMPROVEMENTS 6:30 Open House 7 8 Presentation & Q&A 8 8:30 Open House WELCOME Todd Pfitzer City of Omaha Engineer Bob Stubbe City of Omaha Public Works Director Jon Meyer Project
More informationR E S O L U T I O N. Designation: R-2A (1-Family, 2-acre Minimum Lot Size)
PLANNING BOARD Arthur Adelman, Chair TOWN OF NORTH CASTLE WESTCHESTER COUNTY 17 Bedford Road Armonk, New York 10504-1898 R E S O L U T I O N Telephone: (914) 273-3542 Fax: (914) 273-3554 www.northcastleny.com
More informationPLANNED UNIT DEVELOPMENT APPLICATION
PLANNED UNIT DEVELOPMENT APPLICATION CITY OF THE DALLES Community Development Department 313 Court Street The Dalles, OR 97058 (541) 296-5481, ext. 1125 Fax (541) 298-5490 www.ci.the-dalles.or.us Date
More informationRequest Modification of Conditions of a Conditional Use Permit approved October 14, Staff Recommendation Approval. Staff Planner Stephen White
Applicant Property Owner Public Hearing September 13, 2017 City Council Election District Lynnhaven Agenda Item 3 Request Modification of Conditions of a Conditional Use Permit approved October 14, 2003.
More informationProject Overview. Get Involved. Public Information Meeting. Contact Information
Get Involved VDOT representatives will review and evaluate information received as a result of this meeting. Please fill out the comment sheet provided in this brochure if you have any comments or questions.
More informationDESIGN CRITERIA PACKAGE
RFQ: 17-C-00003 DESIGN-BUILD SERVICES FOR THE DESIGN CRITERIA PACKAGE PREPARED BY: JAMES E. JACKSON, JR. AIA CITY ARCHITECT CONTRACT ADMINISTRATION DEPARTMENT and INTERFLOW ENGINEERING, L.L.C DESIGN CRITERIA
More informationTown of Florence Florence County, WI DRIVEWAY ORDINANCE
Town of Florence Florence County, WI 08-10-09 DRIVEWAY ORDINANCE 1.01 PURPOSE The purpose of this Ordinance is to regulate the establishment, construction, improvement, modification or reworking of a driveway
More informationWestern Pennsylvania Conservancy Clairton & Harrison Community Greening Assessment Projects Request for Proposals July 2018
Western Pennsylvania Conservancy Clairton & Harrison Community Greening Assessment Projects Request for Proposals July 2018 Proposal Information The Western Pennsylvania Conservancy (WPC) is seeking proposals
More informationCITY PLANNING COMMISSION AGENDA. ITEM NO: 6.a 6.b STAFF: LONNA THELEN
Page 156 CITY PLANNING COMMISSION AGENDA ITEM NO: 6.a 6.b STAFF: LONNA THELEN FILE NO(S): A. - CPC ZC 08-00069 QUASI-JUDICIAL B. - CPC CU 08-00070 QUASI-JUDICIAL PROJECT: APPLICANT: OWNER: PHIL LONG VALUCAR
More informationSUPPORTING DOCUMENT STORMWATER POLLUTION PREVENTION PLAN (SWPPP) NARRATIVE
SUPPORTING DOCUMENT STORMWATER POLLUTION PREVENTION PLAN (SWPPP) NARRATIVE Please complete this narrative form and submit with your SWPPP drawings. Refer to Kitsap County Stormwater Design Manual Vol.
More informationWILDFLOWER MANAGEMENT PROGRAM
Approved: Effective: January 22, 2014 Office: Production Support Topic No.: 650-030-001-h Department of Transportation PURPOSE: WILDFLOWER MANAGEMENT PROGRAM To increase the visibility and enjoyment of
More informationLOCATION AND DESIGN DIVISION
VIRGINIA DEPARTMENT OF TRANSPORTATION LOCATION AND DESIGN DIVISION INSTRUCTIONAL AND INFORMATIONAL MEMORANDUM GENERAL SUBJECT: Landscape Architecture Program NUMBER: SPECIFIC SUBJECT: Integration of Landscape
More informationVDOT Vegetation Management Policy
VDOT Vegetation Management Policy Appropriation Act Item 436 H (2010) Report to the Chairmen of House Appropriations and Transportation Committees and Senate Finance and Transportation Committees Virginia
More informationEnhance the High Line Canal Projects
Enhance the High Line Canal Projects Joint Project Proposal for Arapahoe County Open Spaces Funding Partner Sponsors: South Suburban Park and Recreation District City of Centennial City of Littleton October
More informationDESIGN & GREEN INFRASTRUCTURE UPDATE December 13, 2016
DESIGN & GREEN INFRASTRUCTURE UPDATE December 13, 2016 Welcome & Introduction Michael J. Finn, P.E. City Engineer Summary of Public Outreach to Date Ground the work in established principles December 2015
More informationThe Town Board of the Town of Vienna, County of Dane, State of Wisconsin, does ordain and adopt as follows.
ORDINANCE DRIVEWAYS AND CULVERTS NO. 6-5-06 ORDINANCE CONCERNING DRIVEWAY AND CULVERT REQUIREMENTS 1-1-1 Driveway Permits; Culvert Requirements 1-1-2 Driveway and Culvert Location, Design and Construction
More informationOVERMOUNTAIN VICTORY TRAIL BURKE CALDELL CORRIDOR FEASIBLITY STUDY REQUEST FOR QUALIFICATIONS CALDWELL COUNTY PATHWAYS
OVERMOUNTAIN VICTORY TRAIL BURKE CALDELL CORRIDOR FEASIBLITY STUDY REQUEST FOR QUALIFICATIONS CALDWELL COUNTY PATHWAYS Caldwell County Pathways along with our co-partners City of Lenoir, Town of Gamewell,
More informationMowing and Haying in the Right of Way AMC Transportation & Infrastructure Policy Committee
Mowing and Haying in the Right of Way AMC Transportation & Infrastructure Policy Committee Nancy Daubenberger Assistant Commissioner- Engineering Services March 1, 2018 Roadway Miles and Green Space MnDOT
More informationCity of Miami MIAMI RIVER BASIN WATER QUALITY IMPROVEMENT REPORT FOR FIRST AND SECOND QUARTER 2010
Action Items 1. Storm water* a. Retrofit drainage in remaining areas of Miami River starting with Pinehurst neighborhoods This project included drainage work that consist of French drains, solid piping,
More informationProject: Developer/Designer: Reviewer: I. Narrative: 1. Project Description: Describes the nature and purpose of the land disturbing activity.
City of Charlottesville, Virginia Erosion and Sediment Control Plan Review Checklist 610 East Market Street, Charlottesville, VA 22902 Telephone 434-970-3182; Fax 434-970-3359 Project: Developer/Designer:
More informationSubmitted by: Phillip L. Harrington, Director, Department of Public Works. Framework for Green Infrastructure Plan Development
Page 1 of 8 Office of the City Manager CONSENT CALENDAR June 13, 2017 To: From: Honorable Mayor and Members of the City Council Dee Williams-Ridley, City Manager Submitted by: Phillip L. Harrington, Director,
More informationOpen House RIVER DES PERES GREENWAY: LANSDOWNE SHREWSBURY METROLINK TO FRANCIS R. SLAY PARK
Open House 10.12.16 RIVER DES PERES GREENWAY: LANSDOWNE SHREWSBURY METROLINK TO FRANCIS R. SLAY PARK MEETING AGENDA Great Rivers Greenway and Project Partners River des Peres Greenway Overview Project
More informationSTAFF REPORT FOR STANDARD COASTAL DEVELOPMENT PERMIT #CDP FEBRUARY 26, 2015 CPA - 1 PO BOX 238 APTOS, CA 94001
STAFF REPORT FOR STANDARD COASTAL DEVELOPMENT PERMIT #CDP 2014-0030 FEBRUARY 26, 2015 CPA - 1 OWNER/APPLICANT: AGENT: REQUEST: HANS HEIM PO BOX 238 APTOS, CA 94001 JAMES HAY PO BOX 762 MENDOCINO, CA 95460
More informationPARKLET PROPOSAL PACKAGE & PROCESS
500.3 I PARKLETS The term parklet refers to a small temporary constructed seating or community gathering area over an on-street parking space or an extension of the sidewalk into the operating State highway
More informationARLINGTON COUNTY, VIRGINIA. County Board Agenda Item Meeting of January 28, 2017 SUPPLEMENTAL REPORT
ARLINGTON COUNTY, VIRGINIA County Board Agenda Item Meeting of January 28, 2017 SUPPLEMENTAL REPORT DATE: January 26, 2017 SUBJECT: The Virginia Department of Transportation s Transform I-66 Inside the
More informationGloucester County PLAN SUBMITTER'S CHECKLIST
Page 1 of 9 Gloucester County PLAN SUBMITTER'S CHECKLIST FOR EROSION AND SEDIMENT CONTROL PLANS Please fill in all blanks and please reference the plan sheets/pages where the information may be found,
More informationRt. 29 Solutions Project Delivery Advisory Panel. January 7, 2016
Rt. 29 Solutions Project Delivery Advisory Panel January 7, 2016 Agenda item 1: Introductions Project Delivery Advisory Panel Technical Team 2 Agenda item 2: Interaction and Feedback Live Streaming Dec
More informationPublic Hearing. Charlotte County-Punta Gorda MPO - Meeting Rooms A and B March 14, open house at 4 p.m., formal presentation at 5 p.m.
Public Hearing Charlotte County-Punta Gorda MPO - Meeting Rooms A and B March 14, 2019 open house at 4 p.m., formal presentation at 5 p.m. Welcome to the Public Hearing for the Harborview Road (CR 776)
More informationANNUAL PARKWAY TREE DONATION PROGRAM. Dear Kenilworth Resident:
ANNUAL PARKWAY TREE DONATION PROGRAM Dear Kenilworth Resident: It is parkway tree planting time again in Kenilworth. The Village s Parkway Tree Donation Program is a great way for residents to directly
More informationCAPA ASPHALT & AIRPORT PAVEMENT MARCH 27, 2019
CAPA ASPHALT & AIRPORT PAVEMENT MARCH 27, 2019 PRESENTERS William Epp, PE, SE Colorado Division Manager Senior Vice President Brett Holt, PE Project Manager WHO WE ARE A nationally recognized transportation
More informationHOUSE & GARDENS. Opportunities to Get Involved with. Holiday Splendor: Trains & Trees
HOUSE & GARDENS Opportunities to Get Involved with Holiday Splendor: Trains & Trees HOUSE & GARDENS Welcome to Holiday Splendor Cranbrook House & Gardens invites you to discover the magic of the season
More informationDEPARTMENT OF PUBLIC WORKS & UTILITIES
CITY OF PORT ANGELES DEPARTMENT OF PUBLIC WORKS & UTILITIES URBAN SERVICES STANDARDS AND GUIDELINES January 2017 Craig Fulton, P.E., Director TABLE OF CONTENTS "URBAN SERVICES STANDARDS AND GUIDELINES"
More information8 February 9, 2011 Public Hearing APPLICANT: 7-ELEVEN, INC.
. 8 February 9, 2011 Public Hearing APPLICANT: REQUEST: Conditional Use Permit for an automobile service station with a convenience store ADDRESS / DESCRIPTION: 2448 Nimmo Parkway PROPERTY OWNER: COURTHOUSE
More informationRESOLUTION NO. R Refining the route, profile and stations for the Downtown Redmond Link Extension
RESOLUTION NO. R2018-32 Refining the route, profile and stations for the Downtown Redmond Link Extension MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Capital Committee Board PROPOSED ACTION 09/13/2018
More informationWildflowers grow in the new community park on Oakwood Road
Wildflowers grow in the new community park on Oakwood Road PLANNING AREA - NEW PARKS An important element in the plan for the City of Delafield is to look ahead for future park needs. The City has the
More informationGovernor John Sevier Scenic Highway Corridor Study
Governor John Sevier Scenic Highway Corridor Study 2017-2018 Agenda 1. Review Timeline of Governor John Sevier Scenic Highway Corridor 2. State of TN Scenic Highway & Parkway Statutes 3. Transportation
More informationCharge for the Fire Station No. 8 History and Legacy Working Group Established by the County Manager on February 5, 2018
Charge for the Fire Station No. 8 History and Legacy Working Group Established by the County Manager on February 5, 2018 The Fire Station No. 8 History and Legacy (FS8HL) Working Group is established and
More informationADOPTED AT NOVEMBER 15, 2012 PACC MEETING
ADOPTED AT NOVEMBER 15, 2012 PACC MEETING STAFF MEMORANDUM TO PACC-TECH TO: PACC-Tech FROM: Elaine K. Echols, AICP, Missy Creasy, AICP, and Julia Monteith, AICP TOPIC: Review of Area B Recommendations
More informationCOUNCIL ATTACHMENT 2 HIGHWAY 7 CORRIDOR AND VAUGHAN NORTH-SOUTH LINK
COUNCIL ATTACHMENT 2 HIGHWAY 7 CORRIDOR AND VAUGHAN NORTH-SOUTH LINK Welcome! The purpose today is to: Present the Study Background; Describe Alignment Alternatives Analyzed; Present the Evaluation of
More informationGlenborough at Easton Land Use Master Plan
Implementation 114 9.0 IMPLEMENTATION 9.1 OVERVIEW This chapter summarizes the administrative procedures necessary to implement the proposed land use plan, infrastructure improvements, development standards,
More information3/22/2011. City Council City Hall Wilmington, North Carolina Dear Mayor and Councilmembers:
ITEM C2 OFFICE OF THE CITY MANAGER (910) 341-7810 FAX(910)341-5839 TDD (910)341-7873 3/22/2011 City Council City Hall Wilmington, North Carolina 28401 Dear Mayor and Councilmembers: Attached for your consideration
More informationPARKS MEMORIALS AND DONATIONS POLICY
PARKS MEMORIALS AND DONATIONS POLICY Purpose: The purpose of this policy is to establish guidelines, standards and procedures for the installation and care of donated park improvements, either as a result
More informationFairfax County Parkway (Route 286) Widening Project
Fairfax County Parkway (Route 286) Widening Project Route 29 (Lee Highway) to Route 123 (Ox Road) State Project No. 0286-029-259, P101; UPC 107937 Fairfax Station HOA Meeting January 30, 2018 7:00 to 9:00
More information[TEMPLATE FOR] STORMWATER FACILITIES OPERATION AND MAINTENANCE PLAN. [date] [revision date]
Instructions to preparer: This template provides instructions, format, organization, and some recommended content for your O&M Plan. Instructions and notes in yellow highlight should be deleted prior to
More informationTHREE-YEAR CAPITAL IMPROVEMENT PLAN FY
THREE-YEAR CAPITAL IMPROVEMENT PLAN FY2016 2018 Annual CIP Development Process Public Works & Engineering Divisions Prepare List of Capital Needs and Recommended Deferred Maintenance Public Works & Engineering
More informationROANOKE STREET IMPROVEMENTS CHRISTIANSBURG, VIRGINIA VDOT PROJECT # U R24 UPC #:
ROANOKE STREET IMPROVEMENTS CHRISTIANSBURG, VIRGINIA VDOT PROJECT # U000-154-R24 UPC #: 108868 VICINITY MAP This project is to be constructed in accordance with the Virginia Department of Transportation
More informationFlorence County Small Commercial Land Disturbance Permit Application
Florence County Small Commercial Land Disturbance Permit Application Florence County Engineering Division 518 South Irby Street Florence, S.C. 29501 Phone (843) 676-8600 Fax (843) 676-8667 Tax Map Number:
More informationCITY OF KEIZER MASTER PLAN APPLICATION & INFORMATION SHEET
CITY OF KEIZER MASTER PLAN APPLICATION & INFORMATION SHEET PRE-APPLICATION CONFERENCE Prior to the actual filing of a Master Plan application, it is strongly recommended that the applicant contact Planning
More informationCan Urban Redevelopment Restore Aquatic Resources
Can Urban Redevelopment Restore Aquatic Resources with Standards for Stormwater Retention and Landscape Performance? Rebecca C. Stack District of Columbia Department of the Environment Industry, Agriculture,
More informationPrincess Anne Road. Phase VII (CIP 2-195) Citizens Information Meeting
Citizens Information Meeting Princess Anne Road Phase VII (CIP 2-195) Wednesday, May 5, 2004 4:30 PM to 7:00 PM Red Mill Elementary School 1860 Sandbridge Road Virginia Beach, VA Welcome to the Citizens
More informationCITY OF KITCHENER CONDITIONS REQUIRED FOR ISSUANCE OF SITE PLAN APPROVAL
CITY OF KITCHENER CONDITIONS REQUIRED FOR ISSUANCE OF SITE PLAN APPROVAL The following is a list of conditions requiring completion to the City s Satisfaction prior to Site Plan Approval being granted
More informationPart 5. Environmental Protection Overlay District Regulations
Part 5 Environmental Protection Overlay District Regulations Section 501. Statement of Intent. As established through the goals, objectives and policies of the Amity Township Comprehensive Plan, it is
More informationPlaces29: List of Implementation Projects
Important Points to Keep in Mind When Using This List Places29: List of s Each of the projects in this List represents an action needed to implement the Places29 Master Plan. The projects are grouped first
More informationCity of Tacoma Planning and Development Services
Agenda Item D-1 City of Tacoma Planning and Development Services To: Planning Commission From: Elliott Barnett, Planning Services Division Subject: Application #2014-08 Open Space Element Update Meeting
More informationBay County RESTORE Act Direct Component Proposals The project will encompass all of Unincorporated Bay County as a whole.
Proj # Bay PRP 2014-016 Project Name Bay County Master Plan and Capital Improvement Strategic Plan Update Project Proposer, affiliation, web site Project Description Proj. Size (acres) Economic Environmental
More informationSoil Erosion & Sediment Control Plan Requirements for Submittal to the Cape Atlantic Conservation District
Soil Erosion & Sediment Control Plan Requirements for Submittal to the Cape Atlantic Conservation District The following is a list of the minimum requirements required on Soil Erosion and Sediment Control
More informationI.T.S. PLAN ALONG I-95 INSTALL FIBER OPTIC LINE PROJECT SHOWING Tuesday, June 18, 2013, 1:30pm Ashland Residency Conference Room
I.T.S. PLAN ALONG I-95 INSTALL FIBER OPTIC LINE PROJECT SHOWING Tuesday, June 18, 2013, 1:30pm Ashland Residency Conference Room PROJECT SHOWING AGENDA I. Welcome A. Sign In Sheet; Non-Disclosure Agreement
More informationMeridian Hills Improvements
Meridian Hills Improvements Public Information Meeting Background The Town Planning Committee - ad hoc committee established December 2005 Volunteer members Create a long-range plan of improvements that
More informationPotential Green Infrastructure Strategies May 6, 2015 Workshop
Potential Green Infrastructure Strategies May 6, 2015 Workshop Background The City of Cortland is developing the Tioughnioga Urban Headwaters Green Infrastructure Action Plan with funding from the National
More informationPARTF Scoring System for Grants
PARTF Scoring System for Grants The members of the N.C. Parks and Recreation Authority use the PARTF scoring system as one of several tools to select grant recipients. Please provide all of the information
More informationARLINGTON COUNTY, VIRGINIA. County Board Agenda Item Meeting of June 16, 2018
ARLINGTON COUNTY, VIRGINIA County Board Agenda Item Meeting of June 16, 2018 DATE: June 7, 2018 SUBJECT: Z-2604-18-1 Rezoning from R-6 and R-5 Single Family Residential Districts to S-3A Special District
More informationLocal Growth Planning in North Central Green Line Communities
2018 April 30 Page 1 of 6 EXECUTIVE SUMMARY This report outlines a high-level scope for local growth planning for north central Green Line communities. The catalyst for this review is the significant investments
More informationPROJECT BACKGROUND. Preliminary Design Scope and Tasks
PROJECT BACKGROUND Preliminary Design Scope and Tasks The purpose of this Study is the development of preliminary designs for intersection improvements for Trunk Highway (TH) 36 at the intersections of
More informationZoning Ordinance Chapter 10
CHAPTER 10 - WASHES SECTION 10.0 GENERAL: A. The purpose of this Ordinance is to establish standards for development in or near Major and Minor Washes as defined in Appendix A Glossary of Terms and Definitions
More informationARTICLE 6: Special and Planned Development Districts
ARTICLE 6: Special and Planned Development Districts 6-10 Traditional Neighborhood Development (TND) District 6-10.10 Purpose and Intent The Traditional Neighborhood Development (TND) District provides
More information2 January 13, 2010 Public Hearing APPLICANT: AUTOBELL CAR WASH, INC
REQUEST: Conditional Use Permit (car wash) 2 January 13, 2010 Public Hearing APPLICANT: AUTOBELL CAR WASH, INC PROPERTY OWNER: MESSER 1060 INDEPENDENCE BOULEVARD STAFF PLANNER: Carolyn A.K. Smith ADDRESS
More informationRZC Public View Corridors and Gateways
RZC 21.42 Public View Corridors and Gateways 21.42.010 Purpose 21.42.020 Scope and Authority 21.42.030 Administration 21.42.040 Gateways Design 21.42.050 Unidentified Public Views 21.42.060 Identification
More informationThe Arlington County Park and Recreation Commission and Department of Parks, Recreation and Cultural Resources. PEG APPLICATION FORM Fiscal Year 2012
The Arlington County Park and Recreation Commission and Department of Parks, Recreation and Cultural Resources PEG APPLICATION FORM Fiscal Year 2012 I. Location of Proposed Project: Park Name (if applicable):
More informationI-66 EASTBOUND WIDENING INSIDE THE BELTWAY PARDON OUR DUST MEETING
I-66 EASTBOUND WIDENING INSIDE THE BELTWAY From the Dulles Connector Road (Route 267) to Fairfax Drive (Route 237) PARDON OUR DUST MEETING Bill Cuttler, PE (VDOT District Construction Engineer, Northern
More information