FACTS 59 5 580 $ 700 YEARS OFFICES STATEWIDE EMPLOYEES MILLION IN REVENUE Established in 1959 by Bartlett Cocke, Jr. San Antonio (headquarters) Austin Baytown Fort Worth Houston Bartlett Cocke General Contractors is an EMPLOYEE OWNED company Bartlett Cocke General Contractors has delivered more than $5 billion worth of educational facilities
FIRST STEPS Website: www.bartlettcocke.com/vendor-opportunities Scroll down to current projects Bid dates Lead Estimator s name and email Contact Lead Estimator and ask him/her to add you to the Building Connected database so you will begin receiving invitations to bid
CURRENT PROJECTS
QUALIFICATIONS SUBMITTAL PROCESS Review entire questionnaire before beginning process Upload required documents in PDF format Qualifications not required to submit a bid, but must be complete and up-to-date prior to beginning any work with us Direct questions to subqual@bartlettcocke.com Our Estimating Coordinator will review your Qualifications Submittal to ensure it is complete
HELPFUL HINTS Consistently bid work! Come by and introduce yourself. Pay attention to the website to find out about projects early (before they are out to bid). Turn in GREAT references! Turn in proposals as complete as possible. Indicate what services you intend to include/omit in your bid. Scale your bids to what fits your resources. Joint venture. Make sure your bid is competitive cost-wise. Turn in bid by advertised deadline. Debrief. Be persistent. DON T GIVE UP!
UPCOMING OPPORTUNITIES Alamo Colleges Palo Alto College - $ 83 M San Antonio ISD 2016 Bond $ 98.3 M Comal ISD High School #4 - $ 98.8 M Comal ISD High School #5 - $ 123.8 M Santikos Cibolo Crossing - $ 24 M
Palo Alto College Capital Improvement Plan Manufacturing Building / Welcome Center $ 28.0 M Construction Budget Schematic Design Budget September 2018 Design Development Budget December 2018 Bid Package 1 (Site, Utilities, Foundation) January / February 2019 Bid Package 2 (Balance of Work) April / May 2019
Palo Alto College Capital Improvement Plan Natatorium & Gym Renovations: $ 14.6 M Construction Budget Schematic Design Budget September / October 2018 Design Development Budget January / February 2019 60% CD Budget March / April 2019 Bid Package June / July 2019
Palo Alto College Capital Improvement Plan Palomino Center Health Technology Renovations: $ 3.4 M Construction Budget Schematic Design Budget January / February 2019 Design Development Budget April / May 2019 60% CD Budget August 2019 Bid Package October / November 2019
Palo Alto College Capital Improvement Plan Physical Plant Improvements: $ 2.0 M Construction Budget Ongoing not fully defined Complete by May 2020
Palo Alto College Capital Improvement Plan Science Lab Renovations: $ 1.4 M Construction Budget Schematic Design Budget July / August 2019 Design Development Budget October / November 2019 Bid Package March / April 2020
Palo Alto College Capital Improvement Plan Phase 2 Improvements: $ 13.3 M Construction Budget Scope & Schedule not fully defined pending funding
San Antonio ISD
San Antonio ISD Irving Academy: - Budget $17.5 million - Bid Docs Scheduled to be out 11/20/18 - Scope of Work: - Converting Campus from the Middle School to an Academy (Pre-K thru 8) - Adding windows for Daylight - Mechanical, Electrical, Plumbing Renovation and Upgrades - Locker Room renovations - Gym renovations - Administrative area renovations - Kitchen Renovations - Classroom Renovations
San Antonio ISD Fox Tech High School: - Budget $19.6 million - Bid Docs Scheduled to be out 11/26/18 - Scope of Work: - Kitchen and Cafeteria Renovations - Science Classroom additions and renovations - Classroom renovations and additions - Mechanical, Electrical, and Plumbing Upgrades - Circulation Space Renovations - Restroom Renovations
San Antonio ISD Jefferson High School: - Budget $44.8 million - Bid Docs Scheduled to be out: Pkg 0-06/2018 Pkg 1-07/2018 Pkg 2-03/2019 - Scope of Work: - PKG 0+1 Structural Modifications, Underfloor Drainage for Gym & Cafeteria - PKG 2 - Mechanical, Electrical, Plumbing Renovation and Upgrades - Gym & Locker Room renovations - Kitchen and Dining Renovations - Classroom Renovations - Roof replacement
San Antonio ISD Edison High School: - Budget $16.4 million - Bid Docs Scheduled to be out 09/28/18 - Scope of Work: - Demolition of existing and construction of a New Competition Gym. - Renovations and Additions to the existing Field House. - Renovations and Additions to the existing Girls Gym. - Renovations and Additions to the Theatre and Theatre Support Areas. - MEP modifications and relocations - Track Repair