BEACH AND INLET PROJECTS UPDATE
|
|
- Marilyn Norton
- 5 years ago
- Views:
Transcription
1 BEACH AND INLET PROJECTS UPDATE
2 USACE DELTA PROJECT
3 USACE Delta Project Project Extents
4 Elevation Elevation (ft NAVD88) (ft NAVD88) USACE Delta Project Project Cross-Section ft 120 ft Post-Matthew Post-Matthew Profile Profile 85 ft 110 ft Pre- Project Pre- Project MHW MHW Station Station Post- Project Post- Project MHW MHW Beach Fill Beach Template Fill Berm Template Only Mean High Water Mean High Water Ocean Ocean Sta Berm cy/ft ~40-55 cy/ft -18 Sta Distance to Baseline (ft)
5 USACE Delta Project Project Extents
6 USACE Delta Project Original Project Plan USACE plan showed a ~ ft berm from Town line to SE 63 rd street Base project is from Town line to SE 77 th (4,000 ) = 163,345 CY shown on plans Delta project is from SE 77 th to SE 58 th (6,000 ) = 251,526 CY Both have ~ cy/ft placement rate Unit rate for Delta work = $11.93/cy Town has allotted up to $3 million for this project Project was completed in summer Received pre- and post-project surveys in December
7 USACE Delta Project Project Results USACE showed a ~ ft berm from Town line to SE 63 rd street project was actually constructed to SE 58 th street as originally planned and with a 150 ft berm Base project is from Town line to SE 77 th (4,000 ) = 163,345 CY shown on plans 246,245 CY placed Delta project is from SE 77 th to SE 58 th (6,000 ) = 251,526 CY shown on plans 394,010 CY placed Unit rate for Delta work = $11.93/cy - $7.61/CY actual Total volume placed from Town line to SE 58 th street = 640,255 cy
8 USACE Delta Project Project Results
9 LOCKWOODS FOLLY PROJECTS - SDI-5 PERMIT - AIWW CROSSING - NEARSHORE PLACEMENT
10 Lockwoods Folly Projects
11 Hotspot Location
12 Hot Spot Shoreline Change and Dune Escarpment Feb 2018 Jun 2018 MHW Structure Mar 2015 (BD) Mar 2015 (AD) Feb 2018 Jun 2018
13 Lockwoods Folly Inlet Projects - SDI-5 Permit O Brien and Gere Have Been Working to Get This Permit for the Town Allows Town to complete projects like the USACE to currently permitted widths and depths for just the inlet itself Timeline for approval is now late January
14 Lockwoods Folly Inlet Projects - AIWW Crossing Project USACE Released a Plan Set In Early Fall That Showed Placing 88,000 CY of Material on West End Of Oak Island Placement on Oak Island due to lower number of easements required Moved western edge of placement area further east Contract has been awarded and USACE is awaiting final schedule before determining if Town can pay for additional material to be dredged out of bend widener and placed (bid showed $7.50/cy) Town of Holden Beach has requested as well so meeting will take place to discuss options if schedule allows for additional material to be dredged Special meeting may need to be called for Town to approve additional monies if additional material can be dredged/placed
15 Lockwoods Folly Inlet Projects - AIWW Crossing Project
16 Lockwoods Folly Projects Nearshore Placement Town Has Asked that Next Project Be Placed Near West End Hotspot Currently Estimated ~30,000 CY - $95,000 Town Share Channel to be dredged to -10 deep and 150 wide Total cost = $676,000 = 30 days of dredging Most of funding from State Shallow Draft Fund Material will be placed in nearshore area near historical hotspot Will also complete additional survey monitoring in future to track offshore feature and hotspot behavior
17 Lockwoods Folly Projects Nearshore Placement
18 Lockwoods Folly Projects Nearshore Placement
19 Lockwoods Folly Project Nearshore Placement
20 Lockwoods Folly Projects Nearshore Placement USACE Is Current Showing Limited Availability for Special Purpose Hopper Dredges Next Year Next few projects will likely be completed with sidecaster dredge at Federal expense Town and County has reminded USACE that local funds were provided contingent on beneficial placement of the material in the nearshore
21 DUNE MONITORING PROJECT
22 Dune Monitoring Project Bi-Weekly Monitoring May 15 August 31, 2018 Color, Temperature and Grain Size Monitoring
23 Dune Monitoring Project- Temperature Results Measurements set up to record hourly Temperature that produces 50% of each gender is 84.6 f Gender determined in middle third of incubation Average Min Temperature - Dune Stations: 74.1 F - Control Stations: 74.1 F Average Temperature - Dune Stations: 84.0 F - Control Stations: 83.0 F Average Max Temperature - Dune Stations: 89.9 F - Control Stations: 88.0 F
24 Dune Monitoring Project - Color Results Color improved when contractor changed where borrowing material from in pit CONTROL STATIONS OBSERVATION STATIONS Date Caswell Beach 5 th PL West 54 th PL West 51 st PL W 42 nd PL W 23 rd PL W 13 th PL W 3 rd PL E 11 th PL E 29 th PL E 37 th PL E 46 th ST SE 55 th ST SE Weather 5/14/2018 7/1 7/1 7/1 3/4 4/3 3/4 4/3 4/3 5/1 3/4 3/6 3/6 3/6 Sunny 5/21/2018 7/1 7/1 7/2 5/1 4/1 4/1 4/2 5/1 4/1 4/3 3/4 4/3 4/2 Sunny 6/5/2018 7/1 7/1 7/1 4/1 5/2 3/3 5/2 5/1 4/1 4/4 3/4 3/3 4/4 Sunny 6/21/2018 7/1 6/2 6/1 4/2 4/1 4/2 3/2 4/2 4/2 4/3 4/4 3/4 4/3 Sunny 7/3/2018 7/1 8/1 7/1 4/1 5/1 5/2 4/2 5/1 6/1 4/4 6/1 3/3 3/4 Sunny 7/20/2018 7/1 7/1 7/1 4/1 5/1 3/4 4/3 5/2 4/1 3/3 3/6 4/4 3/4 Wet Sand 8/9/2018 7/1 5/1 7/1 5/1 5/1 4/1 4/1 4/1 5/1 4/1 4/2 4/3 4/2 Sunny 8/24/2018 7/1 7/1 6/1 4/2 4/2 4/2 4/3 4/3 4/2 4/4 4/4 4/3 5/2 Sunny 9/11/2018 7/1 7/1 7/1 7/1 5/1 5/2 4/2 4/2 5/1 3/3 4/4 3/4 5/2 Sunny
25 Dune Monitoring Project Grain Size Results Material met sediment grain size compatibility rules
26 Dune Monitoring Project Overall Results Final report was submitted to agencies October 1, 2018 with no comments received Temperatures recorded in dune stations were slightly warmer (approximately 1 degree avg) than control stations Most dune stations were installed on leeward side of dune crest which would be expected to be warmer Munsell color values were lower for non-nourished areas color improved when contractor moved Sediment grain size is compatible All nests laid in the dune restoration project area were relocated this year (11 of 51 nests laid 46 false crawls with 17 in dune restoration area)
27 ANNUAL MONITORING SURVEY (BEFORE FLORENCE)
28 Annual Monitoring Survey ( ) Completed just before Hurricane Florence arrived in early September Survey consists of: Beach profiles Eastern Channel Lockwoods Folly Inlet
29 Annual Monitoring Survey ( )
30 Annual Monitoring Survey ( ) Beach Profile Shoreline and Volume Change Results
31 Annual Monitoring Survey ( ) Volume Change
32 Annual Monitoring Survey ( ) Example Profiles
33 Annual Monitoring Survey ( ) Eastern Channel Results
34 Annual Monitoring Survey ( ) Lockwoods Folly Inlet Results Some movement of inlet throat to east Some deepening/straightening of inlet over bar
35 POST-FLORENCE MONITORING SURVEY
36 Post-Florence Monitoring Survey Elevated Water Levels and Wave Conditions ~3 Days
37 Post-Florence Monitoring Survey Elevated Water Levels and Wave Conditions ~3 Days ~3 Days
38 Post-Florence Monitoring Survey Beach Profile Shoreline and Volume Change Results After initial meeting with FEMA, appears that Town may qualify for emergency dune restoration project Will hopefully know something this Spring
39 Post-Florence Monitoring Survey Volume Change
40 Post-Florence Monitoring Survey Example Profiles
41 Post-Florence Monitoring Survey Example Profiles
42 Post-Florence Monitoring Survey Example Profiles Berm Loss Captured Offshore
43 Post-Florence Monitoring Survey Eastern Channel Results Shoaled Volume (cy) Date Range Beach Compatible Non Beach Compatible Combined Reach 1 Reach 2 Reach 3 Total Reach 4 Reach 5 Total Total Sep Oct ,230 1, ,650 2,182 4,103 Template - Oct ,883 4,318 15, , ,238
44 Post-Florence Monitoring Survey Lockwoods Folly Inlet Results Some minor shoaling within inlet over outer bar 0-2 where shoaling occurred September 2018 October 2018
45 FEMA TURTLE HABITAT PROJECT
46 FEMA Turtle Habitat Restoration Project Initial Project Budget for Volume of 364,000 cy FEMA authorization of $ 6,026,365 (75% of Cost) State/Town expected contribution of $ 2,008,788 Total project expected cost = $ 8,035,153 Additional Town Funds (Possible) Contribute $5 7 million: 435, ,000 cy Total potential project volume: 750,000-1,000,000 cy May also incorporate Post-Florence project volume depending on FEMA approval and reimbursement timeline
47 FEMA Turtle Habitat Restoration Project Project Extent Alternatives
48 FEMA Turtle Habitat Restoration Project Turtle Habitat Restoration ONLY Turtle Habitat: 20 ft wide dune at 10 ft NAVD88 with 70 ft berm at 7 ft NAVD88 14,000 ft (Sta ) Template Volume Required: 470,000 cy Turtle Habitat Restoration with Additional Town Volume Alternative A: 20 ft wide dune at 15 ft NAVD88 with 50 ft berm at 7 ft NAVD88 18,000 ft (Sta ) Template Volume Required: 1,408,000 cy Alternative B: 20 ft wide dune at 12 ft NAVD88 with 50 ft berm at 7 ft NAVD88 27,000 ft (Sta ) Template Volume Required: 1,404,000 cy
49 FEMA Turtle Habitat Restoration Project
50 FEMA Turtle Habitat Restoration Project Offshore Site #1 Preliminary volume estimate in permitted central reach borrow area: 400, ,000 cy Distance from project: maximum 5 mi Hopper dredge project Field investigations: Jan/Feb 19 Cultural Resource Survey: Magnetometer and Side- Scan (Geodynamics and Tidewater Atlantic Research) Central Reach Vibracoring (American Vibracore Services)
51 FEMA Turtle Habitat Restoration Project Offshore Site #1 Example Vibracores
52 FEMA Turtle Habitat Restoration Project Proposed Fee and Schedule Proposed Schedule 16 Months Finalize Construction by May 2020 Field investigations next 3 months Preliminary engineering and permitting next 3-9 months Final design and bidding next 9-12 months Project construction next months
53 MASTER PLAN
54 Overview of Master Plan Purpose and Need To Establish and Implement a Comprehensive, Long-Term, Non- Federal Beach and Inlet Management Program that will Restore and Maintain the Oceanfront Shoreline Of Oak Island. Provide Shore Protection for Residential Structures, Infrastructure, and Recreational Assets; and Preserve the Local Tourism-Based Economy. Consolidate the Shore Protection Planning and Management Activities of the Town Under a Unified, Regional Beach and Inlet Management Program.
55 Overview of Master Plan Verify Sediment Need for Initial Project and Over Next 50 Years (2-3 Mcy for Initial Project / 1 Mcy Every 6 Years = Mcy Preliminary Estimate No Storms) USACE Delta and FEMA Turtle Habitat Project Can Hopefully Reduce Volume Need May Need to Build In Phases Modeling to Refine Above Estimates Currently Ongoing
56 Overview of Master Plan Field Investigations Geotechnical vibracoring for sediment compatibility November 2018 vibracores Eastern Channel, LFI, AIWW bend widener Jan-Mar 2019 native sampling and vibracoring upland sites Additional offshore work planned for January- March central reach Other offshore areas and Frying Pan Shoals to be completed later - BOEM
57 Overview of Master Plan Lockwoods Folly Inlet Management Plan Analytical Analysis Digitize inlet throat and shoreline locations Look for patterns to determine safe corridor Cultural resources are a major constraint Modeling Field velocity studies of Lockwoods Folly Inlet for models late Jan/early February Test options to verify analytical results
58 Overview Summary USACE Delta Project - Completed Lockwoods Folly Inlet Initatives SDI-5 Permit Complete By February 2019 AIWW Crossing with Beach Placement Complete by May 2019 Nearshore Placement Complete Last Half of 2019 Dune Monitoring Report Complete Annual and Post-Florence Surveys Annual Survey - Completed Post-Florence Survey Complete by February 2019 FEMA Request for Post-Florence Reimbursement Discussions with FEMA Complete by Spring 2019
59 Overview Summary FEMA Turtle Habitat Project Field Investigations - Complete by March 2019 Engineering and Permitting Submittals - Complete by May 2019 Receive Permits and Finalize Construction Documents Complete by October 2019 Bid Project November 2019 Project Construction January May 2020 Master Plan Field Investigations Ongoing Discussions with BOEM and Others Concerning Frying Pan Shoals Estimate of Engineered Beach Volume Need Complete by Spring/Summer 2019 Environmental Studies and Documentation - Ongoing
60 Overview Summary
Goals and Strategies. Goals. Strategies. Long-term Beach and Shoreline Management Program
Goals and Strategies Goals Long-term Beach and Shoreline Management Program Qualify for and Maintain Static-line Exception Qualify for and Maintain FEMA Engineered Beach Lockwoods Folly Inlet Management
More informationImprovement of the Atlantic Coast of New York City,
Improvement of the Atlantic Coast of New York City, Rockaway Inlet to Norton Point Project at Sea Gate Meeting Purpose The U.S. Army Corps of Engineers, the New York State Department of Environmental Conservation,
More informationDauphin Island s East End Beach and Barrier Island Restoration Project. April 16, :00 PM Dauphin Island Sea Lab, Shelby Hall
Dauphin Island s East End Beach and Barrier Island Restoration Project Town of Dauphin Island, Alabama April 16, 2015 6:00 PM Dauphin Island Sea Lab, Shelby Hall Team Introduction South Coast Engineers
More informationNC Coastal Management Program Update. Mike Lopazanski Policy & Planning Section Chief April 3, 2015
NC Coastal Management Program Update Mike Lopazanski Policy & Planning Section Chief April 3, 2015 NC Coastal Area Management Act (1974) Balances competing coastal pressures through development permitting
More information4/8/2015 Item #10D Page 1
MEETING DATE: April 8, 2015 PREPARED BY: Christy Villa, Associate Civil Engineer DEPT. DIRECTOR: Glenn Pruim DEPARTMENT: Public Works CITY MANAGER: Larry Watt SUBJECT: NORTH COAST HIGHWAY 101 STREETSCAPE
More informationBroward County Shore Protection Project Segment II. Physical Monitoring Plan
Broward County Shore Protection Project Segment II USACE File No. SAJ-1999-05545 Broward County Shore Protection Project -Segment II Submitted To: Florida Department of Environmental Protection Office
More informationQUESTIONS AND ANSWERS Windsor Woods, Princess Anne Plaza & The Lakes Combined Drainage Project
QUESTIONS AND ANSWERS Windsor Woods, Princess Anne Plaza & The Lakes Combined Drainage Project PROJECT OVERVIEW Windsor Woods, Princess Anne Plaza and The Lakes are neighborhoods located in what was once
More informationHOLDEN BEACH EAST END SHORE PROTECTION PROJECT ENVIRONMENTAL IMPACT STATEMENT DRAFT
HOLDEN BEACH EAST END SHORE PROTECTION PROJECT ENVIRONMENTAL IMPACT STATEMENT DRAFT August 2015 Prepared for: US Army Corps of Engineers, Wilmington District Wilmington, NC and Town of Holden Beach Prepared
More information2013 Summer Recap. Rockaway Beach
2013 Summer Recap and Discussion on Rockaway Beach Reconstruction Tonight s Agenda Summer Beach Update Phase 2 Assumptions, Constraints and Regulations Rebuilding the Boardwalk Coastal Protection Rockaway
More informationBeneficial Use at Deer Island A Decade of Design and Implementation. Mississippi Water Resources Conference Jackson, Mississippi April 3, 2012
Beneficial Use at Deer Island A Decade of Design and Implementation Presented by Wendell Mears and William Roth Anchor QEA, LLC Mississippi Water Resources Conference Jackson, Mississippi April 3, 2012
More informationSierra Club Comments on ACOE Public Notice NAE Re: Proposed Town Neck Beach Project at Sandwich, Massachusetts
August 27, 2015 US Army Corps of Engineers New England District 696 Virginia Road Concord, MA 01742-2751 Attn: Phillip W. Nimeskern Dear Mr. Nimeskern, Sierra Club Comments on ACOE Public Notice NAE-2014-259
More informationEEA Capital Investment in Green Infrastructure
EEA Capital Investment in Green Infrastructure Goal: Advance local efforts to implement measures to increase natural storm damage protection, flood control, and community resilience State capital funding
More informationWelcome to the. Open House
Welcome to the 5th Street to Kinsman Road Open House November 14 5:30 7:00 p.m. Please sign in Project Overview In December 2016, City Council adopted SW 5th Street as the preferred alignment to connect
More informationCHAPTER Committee Substitute for Senate Bill No. 1472
CHAPTER 2007-99 Committee Substitute for Senate Bill No. 1472 An act relating to beaches and shores; amending s. 161.021, F.S.; amending a definition; amending s. 161.085, F.S.; restricting the use of
More informationSunshine Coast Council Coastal Management Overview. January 2016 edition
Sunshine Coast Council Coastal Management Overview January 2016 edition Mayor Mark Jamieson Mayor s foreword Our impressive beaches are fundamental to our Sunshine Coast lifestyle, economy and coastal
More informationSconset Geotextile Tube Update Sconset Bluff, Nantucket. Maria Hartnett, Associate
Sconset Geotextile Tube Update Sconset Bluff, Nantucket Maria Hartnett, Associate www.epsilonassociates.com Presentation Outline Project Setting & Need for Erosion Control Project Components Geotubes Sand
More informationWelcome. Tannery and Waterworks Parks Shoreline Improvements Environmental Assessment. Public Information Centre #1 November 27, pm to 8 pm
Welcome Tannery and Waterworks Parks Shoreline Improvements, Environmental Assessment Tannery and Waterworks Parks Shoreline Improvements Environmental Assessment #1 6 pm to 8 pm Why We Are Here Tannery
More informationComprehensive Study N A G L E H A R T R A Y A R C H I T E C T U R E GILBANE BUILDING C O M P A N Y P R O J E C T M A N A G E M E N T A D V I S O R S
N A G L E H A R T R A Y A R C H I T E C T U R E GILBANE BUILDING C O M P A N Y P R O J E C T M A N A G E M E N T A D V I S O R S BOE COW Meeting October 6, 015 Comprehensive Study North Shore School District
More informationAdaptive Management Strategies for Resilient Coastlines: A Case Study on the Ft. Pierce, FL Breakwater Project
Adaptive Management Strategies for Resilient Coastlines: A Case Study on the Ft. Pierce, FL Breakwater Project USACE Workshop November 21 st, 2013 By: Jenna Phillips Emphasis on Green or Nature-Based Engineering
More informationRuss J. Joffrion, P.E. Whitney Thompson, P.E.
A Case Study and Logistics Review on the Design and Construction of the Bayou Dupont Mississippi River Sediment Marsh Creation Project Jefferson and Plaquemines Parishes, LA Russ J. Joffrion, P.E. Whitney
More informationSHORE PROTECTION ACT STAFF S FINDINGS & RECOMMENDATIONS
SHORE PROTECTION ACT STAFF S FINDINGS & RECOMMENDATIONS TO: FROM: APPLICANT: AGENT: Shore Protection Committee: Commissioner Mark Williams, Chairman Mr. Richard Gardner Mr. Henry Morgan Mr. Zach Harris
More informationAttachment 5 -- PowerPoint. Item 6C- Attach 5- PPT Presentation Page 1 of 15
Attachment 5 -- PowerPoint Page 1 of 15 Sausalito Dunphy Park Status Update and Authorize Consulting Contract Amendments March 27, 2018 Page 2 of 15 Summary Current Status October 2017 bidders thanked,
More informationPeoria Riverfront Development (Ecosystem Restoration) Upper Mid-sized Island Critical Restoration Project (September 2011)
Peoria Riverfront Development (Ecosystem Restoration) Upper Mid-sized Island Critical Restoration Project (September 2011) Description The Corps of Engineers, Rock Island District (District) and the Illinois
More informationAnalogue to Digital Telecare. Technical Advisory Board. 21 st June 2017 Work Stream 3 Procurement
Analogue to Digital Telecare Technical Advisory Board 21 st June 2017 Work Stream 3 Procurement Euan Kidd Senior Procurement Specialist Euan.kidd@scotland-excel.org.uk 1 Purpose of Work stream 3 - procurement
More informationCity of Rockingham. Local Management Practices, Costs and Strategic Coastal Planning
City of Rockingham Local Management Practices, Costs and Strategic Coastal Planning Decision Making Process Considerations Climate Change Response Action Plan Ongoing observations/major Storm events Ongoing
More informationNC Division of Coastal Management
November 14, 2016 NC Division of Coastal Management NCBIWA Update NC Coastal Area Management Act (1974) Balances competing coastal pressures through development permitting and creation of a Coastal Resources
More informationQUESTIONS AND ANSWERS Windsor Woods, Princess Anne Plaza & The Lakes Combined Drainage Project
QUESTIONS AND ANSWERS Windsor Woods, Princess Anne Plaza & The Lakes Combined Drainage Project Project Overview... 2 Thalia Creek (Windsor Woods) Tide Gate... 6 Club House Road Drainage Project... 9 Updated
More informationPontchartrain Coastal Lines of Defense Program Figure 1 Figure 2 Figure 1
Pontchartrain Coastal Lines of Defense Program Coastal Sustainability Program February 2006 The Pontchartrain Coastal Lines of Defense Program consists of ten priority project areas within the Pontchartrain
More informationRiver Mile 10.9 Removal Action Overview
River Mile 10.9 Removal Action Overview November 13, 2014 CAG Meeting Modified from CPG s RM10.9 Removal Action Final Design Report dated Nov. 2013 1 River Mile 10.9 Removal Action Activities Dredging:
More informationROCKAWAY BOARDWALK Community Board 14 Parks Committee Meeting June 4, 2014
ROCKAWAY BOARDWALK Community Board 14 Parks Committee Meeting June 4, 2014 Introduction 2 Agenda Design Update Construction Update Local Hiring Update 3 Community Input 7 Meeting Date September 17, 2013
More informationSHORE PROTECTION ACT STAFF S FINDINGS & RECOMMENDATIONS
SHORE PROTECTION ACT STAFF S FINDINGS & RECOMMENDATIONS TO: FROM: Shore Protection Committee: Commissioner Mark Williams, Chairman Mr. Richard Gardner Mr. Henry Morgan Mr. Zach Harris Mr. Bill Hodges Department
More informationSF REC & PARK MOSCONE RECREATION CENTER: EAST SITE. Supervisor Mark Farrell District 2. Project Manager Dan Mauer Recreation and Parks Department
SF REC & PARK MOSCONE RECREATION CENTER: EAST SITE COMMUNITY WORKSHOP: MEETING #3 WEDNESDAY, FEBRUARY 10, 2016 Supervisor Mark Farrell District 2 Project Manager Dan Mauer Recreation and Parks Department
More informationIntroduction to the Seahurst Park Ecosystem Restoration Project: A Process of Transformation. Presented by Peter Hummel, ASLA, LEED AP
Introduction to the Seahurst Park Ecosystem Restoration Project: Presented by Peter Hummel, ASLA, LEED AP September 16, 2014 Environmental Science Center Public Education Series 0 Acknowledgements Project
More informationEmpowering Local Action for Coastal Resilience in Massachusetts. Bruce K. Carlisle MA Office of Coastal Zone Management
Empowering Local Action for Coastal Resilience in Massachusetts Bruce K. Carlisle MA Office of Coastal Zone Management Context Coastal communities continue to face both chronic and acute storm surge, erosion,
More informationGLX Project Green Line Extension Project GLX WORKING GROUP PRESENTATION OCTOBER 2, 2014
GLX Project Green Line Extension Project 1 Agenda Welcome GLX Sustainability Project Overview & Updates Upcoming Public Meetings Station Meeting Lechmere Station Meeting Union Sq. & Washington St. Working
More informationTown of Lyons Parks Flood Recovery Planning Process. Photograph courtesy of Ed Bruder
Town of Lyons Parks Flood Recovery Planning Process Photograph courtesy of Ed Bruder Lyons Parks and Recreation Flood Recovery Update 1. Meadow Park Phase II - Project PW20B1 Estimated Completion: Summer
More informationNatural Resource Adaptation Action Area Addressing Sea Level Rise in Estuarine Ecosystems TO: TOWN OF YANKEETOWN MAY
Natural Resource Adaptation Action Area Addressing Sea Level Rise in Estuarine Ecosystems TO: TOWN OF YANKEETOWN MAY 6 2013 University of Florida Conservation Clinic Vivek Babbar, Student Associate, J.D.
More informationThere is an ongoing regulatory concern that
FWRJ Alternatives for Beach Stormwater Outfalls: Preliminary Assessment for City of Naples Reshma Thummadi, Ronald Cavalieri, Andy Holland, and Gregg Strakaluse There is an ongoing regulatory concern that
More information2016 Annual Inspection Report
2016 Annual Inspection Report for Compliance with the Coal Combustion Residuals Rule (40 CFR Part 257) Hayden Station 13125 U.S. Highway 40 Hayden, Colorado 81638 January 18, 2017 Table of Contents Certification...
More informationDon t Flood The Rodeo! Preparing for Fort Worth s New Arena
Don t Flood The Rodeo! Preparing for Fort Worth s New Arena T F M A S P R I N G C O N F E R E N C E APRI L 27 2017 Scott Hubley, P.E., CFM Justin Oswald, P.E., CFM Christopher Johnson, P.E., CFM PHOTO
More informationBroward County Coastal Engineering Consultant Services For Segment III Shore Protection T P1 R. Harvey Sasso, P.E. Danielle Irwin, CFM
Coastal Systems International, Inc. Broward County Coastal Engineering Consultant Services For Segment III Shore Protection T2112588P1 R. Harvey Sasso, P.E. Danielle Irwin, CFM Experts in Coastal Engineering,
More informationTOWN OF NEW CASTLE - Master Plan Update
Our Presentation Today (1) Recap the Master Planning Process To Date (2) Present the Outline of the Master Planning Work Plan (3) Present the Calendar for the Master Plan (4) Outline the scope of a Downtown
More informationPort of San Diego Sea Level Rise Ad Hoc Committee Meeting 1 of 3.. September 18, 2018
Port of San Diego Sea Level Rise Ad Hoc Committee Meeting 1 of 3. September 18, 2018 Agenda Welcome Introductions Rules of the Ad-Hoc Presentation Background Vulnerability Assessment Results Non-Agenda
More informationRhode Island Shoreline Change Special Area Management Plan
Rhode Island Shoreline Change Special Area Management Plan Draft Document Outline REVISED 10/12/2017 VOLUME 1 Executive Summary & How to Use this Document (Draft by Dec 2017) 1. Introduction (Revised draft
More informationLawrencetown Beach & Rainbow Haven Beach
Lawrencetown Beach & Rainbow Haven Beach Public Engagement Session Wednesday, September 27 th, 2017 6:00pm 8:00pm Cole Harbour Place 51 Forest Hills Pkwy, Dartmouth Agenda Welcome & Introductions Overview
More informationLake Nokomis Shoreline Enhancement Project
Lake Nokomis Shoreline Enhancement Project Community Meeting 2 February 13, 2018 Agenda Current Problems Project Goals Project Status Existing Conditions Community Input Draft Schematic Design Long-term
More informationWLAC Facilities Committee Meeting. September 18, 2017
Campus Program Report WLAC Facilities Committee Meeting September 18, 2017 Page 1 DSA approved the plans on May 15, 2017. Notice to Proceed was issued June 8, 2017 and the project remains on schedule for
More informationVirginia Beach and Sea Level Rise: Where Do We Go From Here?
Virginia Beach and Sea Level Rise: Where Do We Go From Here? Clay Bernick City of Virginia Beach Environment & Sustainability Office Bayfront Advisory Committee Presentation July 19, 2012 Five Items to
More informationAshbridges Bay Erosion and Sediment Control Project
Ashbridges Bay Erosion and Sediment Control Project Project Brief Overview Toronto and Region Conservation Authority, in partnership with the City of Toronto, intends to carry out remedial erosion control
More informationCitizen Information Meeting
Prince William County Government Citizen Information Meeting Vint Hill Road Extension May 11, 2016 Benefits: Route 28 Corridor Improvement Program Estimated significant cost savings versus bidding these
More informationCoffey Neighborhood Park Master Plan/Design/Rebuild Workshop. August 4, :00pm 4:00pm
Coffey Neighborhood Park Master Plan/Design/Rebuild Workshop August 4, 2018 2:00pm 4:00pm 1 Agenda Welcome/Introductions Neighborhood Meeting Goals Master Planning Process Coffey Park Amenities (pre-fire
More informationRESILIENCY, ADAPTATION, & SUSTAINABILITY AT THE CITY OF ST. AUGUSTINE
RESILIENCY, ADAPTATION, & SUSTAINABILITY AT THE CITY OF ST. AUGUSTINE PROGRAM UPDATE JANUARY 14, 2019 MICHAEL G. CULLUM, P.E. DIRECTOR, PUBLIC WORKS PROGRESSION OF PLANNING FOR RESILIENCY / ADAPTATION
More informationWESTERN ILLINOIS UNIVERSITY
WESTERN ILLINOIS UNIVERSITY Quad Cities Riverfront Campus Preliminary Master Plan Presentation 2 February 1, 2006 Achieving Future Flexibility 1. Monitor space needs as the new buildings come on line and
More informationCountywide Recycling and Disposal Facility Weekly Progress Report 08/22/08
Countywide Recycling and Disposal Facility Weekly Progress Report 08/22/08 This Weekly Progress Report is prepared by Countywide and submitted to the OEPA weekly by the close of business on each Friday.
More informationTOWN OF JUPITER. Honorable Mayor and Members of Town Council Andrew D. Lukasik, Town Manager
DATE: June 07, 2016 TO: THRU: TOWN OF JUPITER Honorable Mayor and Members of Town Council Andrew D. Lukasik, Town Manager FROM: Thomas V. Driscoll, P.E., Director of Engineering, Parks & Public Works SUBJECT:
More informationNational Grid Residential & C&I Active Demand Reduction Demonstration Projects. MA EEAC March 15, 2017
National Grid Residential & C&I Active Demand Reduction Demonstration Projects MA EEAC March 15, 2017 Residential DR: What are We Testing? Impact of calling DR events using Direct Load Control of Wi-Fi
More informationApril 11, 2016 Park Board Chair and Commissioners General Manager Vancouver Board of Parks and Recreation New Brighton Salt Marsh - Preferred Concept
TO: FROM: SUBJECT: April 11, 2016 Park Board Chair and Commissioners General Manager Vancouver Board of Parks and Recreation New Brighton Salt Marsh - Preferred Concept RECOMMENDATION A. THAT the Vancouver
More informationSB1 Grant. Regional Sea Level Rise Adaptation Guidance for Transportation Infrastructure PRESENTED BY SARAH PIERCE & SARAH RICHMOND OCTOBER 4, 2018
SB1 Grant Regional Sea Level Rise Adaptation Guidance for Transportation Infrastructure PRESENTED BY SARAH PIERCE & SARAH RICHMOND OCTOBER 4, 2018 Project Team SANDAG (Sarah Pierce, Katie Hentrich) Dudek
More informationTHE TOWN OF WASAGA BEACH
THE TOWN OF WASAGA BEACH Downtown Development Master Plan Committee of the Whole Presentation January 26 th 2017 Uses within this designation should reflect a dependence on tourism as opposed to the permanent
More information30% Design Technical Report
NAPLES BEACH RESTORATION AND WATER QUALITY IMPROVEMENT PROJECT Outfalls 3, 4, 5 & 6 May 2016 Erickson Consulting Engineers, Inc. www.ericksonconsultingengineers.com Outfall 6 www.stantec.com Naples Beach
More informationSCADA / Electrical Refurbishment Construction Contract. Tommy B. Strowd, P.E., Director Operations & Maintenance
SCADA / Electrical Refurbishment Construction Contract Tommy B. Strowd, P.E., Director Operations & Maintenance SCADA Supervisory Control And Data Acquisition LWDD Interbasin Study (c. 1992) concluded
More informationLower Don River West Remedial Flood Protection Project TABLE OF CONTENTS. Page. Executive Summary
TABLE OF CONTENTS Page Executive Summary 1.0 INTRODUCTION...1-1 1.1 Purpose of the Undertaking...1-1 1.2 Study Area Description...1-1 1.3 Description of the Undertaking...1-1 1.4 Rationale for the Undertaking...1-2
More informationPUBLIC SPACES MASTER PLAN UPDATE (POPS) Crystal City Citizen s Review Council October 24, 2018
PUBLIC SPACES MASTER PLAN UPDATE (POPS) Crystal City Citizen s Review Council October 24, 2018 1 PLANNING CONTEXT Arlington County Comprehensive Plan UPDATE Related Documents: CIP Sector Plans Area Plans
More informationA New Plan For The Calgary Region June calgary.ca call 3-1-1
A New Plan For The Calgary Region June 2009 calgary.ca call 3-1-1 Introduction Since January 2006, The City of Calgary has been actively participating with the member municipalities of the Calgary Regional
More informationPublic Visioning City of Kelso Planning Commission
Shoreline Master Program Update Public Visioning City of Kelso Planning Commission November 13, 2012 Schedule Jurisdiction Inventory Analysis Visioning Topics Process Governing Principles Structure of
More informationAlbion Hills Conservation Area Master Plan. Public Information Session
Albion Hills Conservation Area Master Plan Public Information Session 1 03.25.2014 Meeting Agenda 1. Project Introduction Property History Current Use Master Plan Process 2. Draft Vision Goals and Objectives
More informationA. INTRODUCTION B. CUMULATIVE EFFECTS ANALYSIS
Chapter 4: Cumulative Effects A. INTRODUCTION The New York City Department of Parks and Recreation plans to reconstruct the Rockaway Beach Boardwalk in the borough of Queens, New York City, which Hurricane
More informationDoing Business with Bartlett Cocke General Contractors
Doing Business with Bartlett Cocke General Contractors FACTS 59 5 580 $ 700 YEARS OFFICES STATEWIDE EMPLOYEES MILLION IN REVENUE Established in 1959 by Bartlett Cocke, Jr. San Antonio (headquarters) Austin
More informationTHE COMMUNITY-DRIVEN DESIGN PROCESS
THE COMMUNITY-DRIVEN DESIGN PROCESS A PUBLIC DRIVEN PROCESS STEERING COMMITEE THE COMPREHENSIVE PLAN OPPORTUNITIES AND CONSTRAINTS THE COMMUNITY DRIVEN DESIGN PROCESS A Public Driven Process Beginning
More informationBoulder County Comprehensive Drilling Plan Surface Owner Meeting. Thursday, Oct. 19, 2017
Boulder County Comprehensive Drilling Plan Surface Owner Meeting Thursday, Oct. 19, 2017 Contact Crestone Crestone Peak Resources Quick Facts www.crestonepeakresources.com cdpboulder@crestonepr.com (720)
More informationOconee Rivers Greenway Project. TSPLOST 2018 Project # 5 Project Concept Sub-projects 7, 8, 9, 10, & 11. Mayor & Commission Work Session
Oconee Rivers Greenway Project Project # 5 Project Concept Sub-projects 7, 8, 9, 10, & 11 Mayor & Commission Work Session February 13, 2018 North Oconee River Greenway 1 Project # 05 - Oconee Rivers Greenway
More informationVaughan Metropolitan Centre (VMC) Black Creek Renewal CLASS ENVIRONMENTAL ASSESSMENT
PUBLIC INFORMATION CENTRE Vaughan Metropolitan Centre (VMC) Black Creek Renewal Wednesday, May 10, 2017 6:00 p.m. to 8:00 p.m. Add photo Project Management, Environmental Assessment, Stormwater Management
More informationSUMMARY. Support the Southeast Arkansas Regional Intermodal Facility.
SUMMARY THE I-69 LOCATION STUDY The proposed I-69 Location Study from El Dorado to McGehee, Arkansas, represents one section (Section of Independent Utility No. 13) of the nationally designated I-69 Corridor
More informationUnderstanding Surface Water Runoff at Breneman Farms
Understanding Nutrient & Sediment Loss at Breneman Farms 4 Understanding Surface Water Runoff at Breneman Farms Kevan Klingberg, Dennis Frame and Fred Madison UW Extension/Discovery Farms AnitaThompson
More informationUNIVERSITY OF NORTHERN IOWA
UNIVERSITY OF NORTHERN IOWA Municipal Separate Storm Sewer System September 2008 Report Permit Number 07-09-0-04 August 2008 Prepared by: University of Northern Iowa Environmental Health and Safety Office
More informationRemi Mendoza City Planning Academy March 13, 2017
Remi Mendoza City Planning Academy March 13, 2017 1 What is the General Plan? The 2030 General Plan 5-Year Update (2035 General Plan) Questions and Answers 2 Guidebook for development and growth Required
More informationRequest for an Exception to the Napa County Road and Street Standards
F Request for an Exception to the Napa County Road and Street Standards Shed Creek Winery Use Permit P16-327 and Use Permit Exception to the Conservation Regulations P17-178 Planning Commission Hearing
More informationCi.ty e>f -V--:1rgi.rria Beach
Ci.ty e>f -V--:1rgi.rria Beach VBgov.com OFFICE OF THE CITY MANAGER (757) 38 242 (757) 427-5626 FAX January 18, 2019 MUNICIPAL CENTER BUILDING 1, ROOM 234 2401 COURTHOUSE DRIVE VIRGINIA BEACH, VA 23456-9001
More informationDesign Guidelines for the Enhancement and Creation of Estuarine Habitats in the Middle Reaches of the Lower Columbia River
Design Guidelines for the Enhancement and Creation of Estuarine Habitats in the Middle Reaches of the Lower Columbia River Astoria, May 16, 2012 1 Outline I. Nature of Project/Background II. Approach to
More informationPreliminary Regulatory and Engineering
Preliminary Regulatory and Engineering Overview For the Isle of Palms, South Carolina Prepared by: Applied Technology & Management, Inc. 941 Houston Northcutt Boulevard, Suite 201 Mount Pleasant, South
More informationNational Grid Residential Active Demand Reduction Demonstration Project. MA EEAC Demand Reduction Sub-Committee February 23, 2017
National Grid Residential Active Demand Reduction Demonstration Project MA EEAC Demand Reduction Sub-Committee February 23, 2017 What are we testing? Impact of calling DR events using Direct Load Control
More information.MANAGED RETREAT. Need for managed retreat
602 MANAGED RETREAT hazards. This strategy is based on a philosophy of moving out of harm's way, and is proactive in recognizing that the dynamics of the coastal zone should dictate the type of management
More informationKaryn M. Erickson, PE, D.CE, F.ASCE
Discipline/Specialty Project Management and Principal Engineer for Large Scale Multi-Disciplinary Coastal Restoration Projects Coastal Engineering Services, Coastal Structures, Planning and Design and
More informationFact Sheet Regulating Oceanfront Accessory Structures Updated June 10, 2013
What is being considered? Fact Sheet Regulating Oceanfront Accessory Structures Updated June 10, 2013 The Town of Duck is considering an ordinance that would limit how close pools, decks, and other accessory
More informationTransportation Committee
Transportation Committee Business Item No. 2013-286SW Meeting date: October 14, 2013 For the Metropolitan Council meeting of October 16, 2013 Subject: Southwest Light Rail Transit (Green Line Extension):
More informationPublic Services Department
Public Services Department PAUL SMITH PUBLIC SERVICES DIRECTOR Memorandum Date: July 24, 2018 To: Honorable Mayor and Board of Commissioners Through: Mark LeCouris, City Manager From: Paul Smith, Public
More informationPlanning and New Starts Development Committee. February 25, 2016
Planning and New Starts Development Committee February 25, 2016 VB TRANSIT EXTENSION 2 Status of VBTES DEIS No Federal Environmental Decision Document Decision to build project with only State and City
More informationClimate Change and Physical Development Threats, Challenges and Adaptation Responses in Coastal Communities: Grand Riviere, Trinidad
Climate Change and Physical Development Threats, Challenges and Adaptation Responses in Coastal Communities: Grand Riviere, Trinidad Michelle Mycoo Ph.D. and Michael Sutherland Ph.D. Geomatics Engineering
More informationSF REC & PARK STANYAN STREET IMPROVEMENT. Supervisor London Breed District 5. Project Manager Dan Mauer Recreation and Parks Department
SF REC & PARK STANYAN STREET IMPROVEMENT PLANNING PRESENTATION WEDNESDAY, OCTOBER 19, 2016 Supervisor London Breed District 5 Project Manager Dan Mauer Recreation and Parks Department Design Team William
More informationRESPONSES TO PUBLIC CONCERNS AND QUESTIONS
RESPONSES TO PUBLIC CONCERNS AND QUESTIONS Stations and Summary Questions for Public Meeting #2 June 23, 2015 General Questions / Concerns: 1. Is there any way this development can raise revenue for the
More informationOwasco Sewer District No. 3
Owasco Sewer District No. 3 Town of Owasco, Cayuga County Public Hearing October 4, 2014 and October 9, 2014 Town Supervisor - Ed Wagner Town Board Michael J. Aldrich Anthony Gucciardi Tim Kerstetter Richard
More informationFoothills Solar and Substation
CITY OF LOVELAND Foothills Solar and Substation SPECIAL REVIEW NEIGHBORHOOD MEETING, DECEMBER 17, 2015 Neighborhood Meeting Outline Welcome and Introductions Purpose of the meeting General Description
More informationGibsons Foreshore & Seawalk Improvements
Gibsons Foreshore & Seawalk Improvements Open House (5:00-7:00 pm) Town of Gibsons October 6, 2016 Town of Gibsons Foreshore & Seawalk Improvements 1 Session 3: Open House (Charrette Participants, Designers,
More informationCoastal Engineer IV, Mott MacDonald, Morado Circle, Suite 300, Austin, TX 78759, USA, T: ,
LA QUINTA TERMINAL MITIGATION PROJECT: LARGE SCALE DREDGED MATERIAL BENEFICIAL RE-USE FACILITY FOR ESTUARINE HABITAT CREATION IN CORPUS CHRISTI BAY, TX Luis M. Maristany, P.E. 1, Aaron G. Horine, P.E.
More informationFacilities Planning & Construction Report nd Quarter Ending December 31, 2016
Facilities Planning & Construction Report 2016 17 2 nd Quarter Ending December 31, 2016 Overview District SRID Spending (MG100) Summary By College By Site District Program Overview Construction Design
More informationMemorandum. AECOM Technical Services Inc. Page 1
Memorandum To: Gregg R. Strakaluse, P.E. and Andy Holland, P.E. From: Ronald Cavalieri, P.E. Prepared By: Reshma Thummadi, P.E. Date: September 20, 2013 Subject: Permitting of Subaqueous Stormwater Outfalls
More informationHistoric Ottawa Beach Waterfront Walkway Park Township
Historic Ottawa Beach Waterfront Walkway Park Township Project Description: Public access improvements to the shoreline of Lake Macatawa are the final steps in completing the park master plan for the Historic
More informationStrategies for Summer Utility Savings. Residential Environmental Program Series May 15, 2013
Strategies for Summer Utility Savings Residential Environmental Program Series May 15, 2013 Are FC Summers Getting Hotter? 200 Fort Collins Annual Hours 90 F or Above 150 100 50 1970 1980 1990 2000 2010
More informationRe: Alameda Point Update Review and Comment on SunCal s September 19, 2008 Development Concept
Alameda Reuse and Redevelopment Authority Memorandum ITEM 10-A To: From: Honorable Chair and Members of the Alameda Reuse and Redevelopment Authority Debra Kurita Executive Director Date: November 5, 2008
More informationGrand River Ravines Georgetown Township
Grand River Ravines Georgetown Township Project Description: The Grand River Ravines County Park property is composed of the 68-acre former Fillmore at the Bend Open Space purchased in 1999 and two more
More information