Agenda 1. Introductions 2. St Elizabeths East Overview 3. Stage One Infrastructure Improvements 1. Role of the D.C. Department of General Services and D.C. Department of Transportation 2. DC Water Tower 3. Timeline for Stage 1 Infrastructure Improvements 4. Questions 2
St. Elizabeths East - 5 Year Anticipated Use Plan Project Address: 2700-2730 Martin Luther King Jr. Ave., SE Existing Conditions to Historic Campus: Primarily a Vacant Historic Campus, except Gateway DC (pavilion) and the R.I.S.E. Demonstration Center Adjacent District Uses: St Elizabeths Hospital; Unified Communication Center, 801 East Men s Shelter Site Size: 183 acres Underlying Zoning: StE District Buildable Envelope: +5 million square feet (multiple parcels) Notes: Site is a National Historic Landmark and is specially zoned as the StE District Transportation Attributes: Adjacent to Congress Heights Metro Station (Metro Green Line); located along major transportation corridors Martin Luther King Jr. Avenue, Alabama Avenue, and access from I- 295 and Suitland Parkway
St. Elizabeths East - Phase One 5 Year Plan Anticipated 5 Year Use Map Blue Red Purple Green Phase 1 Development Residential - Townhomes/Multifamily Phase 1 Development Mixed Use Buildings In-Use - Gateway DC - RISE Demonstration Center Events DC s Planned Development - Washington D.C. Entertainment and Sports Complex Phase One Key Features: 10 9 11 14 12 Green space 17 Mixed-Use (Parcel 17) Townhomes (Parcel 10/14) Multi-family (Parcel 11) Entertainment (Parcels 9/12) +30,000 SF of Retail ; 171,000 SF of Office; 30,000 SF Innovation Greenspace +60 homes Townhomes (30% affordable); +15 live-work-units 250 units multifamily units (80% affordable) in 6 historic buildings and one center amenity building; +14,000 SF innovation/arts/culture space 5,000 seat Entertainment and Sports Arena for use as a concert/ entertainment venue, Wizards Training Facility and arena for Mystics and other sports teams
INFRASTRUCTURE & STABILIZATION 5 Construction of a new infrastructure network to provide a complete street system within the East Campus, including: Urban local roadways New wet and dry utilities Telecom conduits Bicycle/ pedestrian facilities Network will be constructed in two phases, with Stage 1 commencing Summer 2016
Stage One Infrastructure Improvements Site Preparation - Pathway at St Elizabeths East
STAGE 1 PHASE 1 - ROADWAY / TYPICAL SECTIONS
STAGE 1 -- PHASE 1 PROPOSED UTILITIES
STAGE 1 -- PHASE 2 INFRASTRUCTURE PROJECT LIMITS
STAGE 1 PHASE 1 TRANSPORTATION INFRASTRUCTURE AND UTILITIES IMPROVEMENTS PROJECT SCHEDULE MILESTONES August 2015 Early December 2015 Late January 2016 Early March 2016 Late March 2016 Early July 2016 Summer 2018 Cancellation Of Previous Solicitation For Infrastructure Improvements 65% Plans Completed For DDOT & DOEE Reviews Issuance Of Design Build Request For Proposals (RFP) By DGS For Roads & Utilities RFP Due Date For Bids To DGS Notice To Proceed (NTP) Issued For 100% Plans NTP Issued By DGS For Start Of Construction Of Roads & Utilities Completion Of Construction Of Roads & Utilities For Stage 1 Phase 1
St. Elizabeth's East Campus 2MG Elevated Water Tower, Washington DC
DC Water - Water Tower DC Water plans to construct an elevated two million gallon water storage tower on the East Campus to provide the required pressure, water storage and fire protection for the Anacostia Second High Service Area. The tower was initially designed with a screen, but the concept was rejected by CFA in 2014. As such, DC Water is working to construct the tower only, with mitigation efforts to-be-agreed-upon later. Regulatory Actions (2014) CFA Approved Water Tower only project. HPRB Approved Water Tower only project. Directed DC Water to enter into an MOA with OP and DMPED for future mitigation. NCPC - Approved Water Tower only project. ANC 8C Approved Water Tower only project. Zoning Commission Approved water tower only project.
Water Tower Function Increased water pressure To provide additional supply during peak usage periods For fire fighting / public safety purposes Emergency reserve in the event of mechanical failures in the system Additional capacity to support economic development
Water Tower Construction Schedule Advertise for Bids. December 6, 2015 Bid Opening.. January 2016 DC Water Board Approval.. March 2016 Notice to Proceed to Construction Contractor. April 2016 Construction Complete and Tower in Operation.. April 2018
Water Tower Mitigation Schedule Begin Preparation of RFQ for Design Competition Participants. October 2015 Advertise RFQ December 2015 Community Workshop #1.. December 2015 Receive and Review Qualifications.. January 2016 Community Workshop #2 (mitigation preferences developed) January 2016 Select Four Design Firms to Compete... February 2016 RFP for Four Selected Firms May 2016 Receive Design Concepts for Mitigation... September 2016 Present Concepts to CFA and Others.. November 2016 Approval and Commence Design. December 2016 Design and Construction- Varies with Concept(s) Selected and Tower Construction Schedule