Route 7/15 Norwalk. Route 7/15 Norwalk Project Project Advisory Committee Meeting #5. Wednesday, November 14 th, Norwalk City Hall

Similar documents
Executive Summary. NY 7 / NY 2 Corridor

Southern Gateway Project and Public Green

Alta Vista Transportation Corridor Environmental Study Report November 2005

Alternatives Development Three conceptual alternatives were developed for the Race Road/Jessup Village Planning Study and are described below:

Proposed FY 2004 TRANSPORTATION CAPITAL PROGRAM New Jersey Department of Transportation Projects

Mavis Road Class Environmental Assessment

Don Mills Crossing Study and Celestica Lands Development Application Community Meeting, Open House, and Breakout Discussions

July 12, Columbus City Council City Hall 90 West Broad Street Columbus, OH RE: I-70/71 Columbus Crossroads Project

I-90 Mississippi River Bridge & Interchange Project

Public input has been an important part of the plan development process.

FANSHAWE PARK ROAD/RICHMOND STREET INTERSECTION IMPROVEMENTS. PUBLIC INFORMATION CENTRE 2 June 16, 2016

Memorandum CITY OF DALLAS

WHAT IS THE PURPOSE OF THE OPEN HOUSE?

Urban Planning and Land Use

Route 1 Corridor Study

Second Line West Pedestrian/Cyclist Crossing of Highway 401 Class EA. Second Line West Pedestrian/Cyclist Crossing of Highway 401 Class EA

APPENDIX D: Visual and Aesthetic Conditions for NCCU Station Refinement. Durham-Orange Light Rail Transit Project

Adelaide Street / Canadian Pacific Railway (CPR) Grade Separation Class Environmental Assessment. Public Information Centre 3

CITY OF CHARLOTTESVILLE, VIRGINIA CITY COUNCIL AGENDA

Welcome. Walk Around. Talk to Us. Write Down Your Comments

This page left intentionally blank.

ALTERNATIVES. NCDOT made an early decision to first determine how to build the project (construction method) followed by what to build (alternatives).

Date: April 10, 2017 City Council Work Session April 24, 2017: Status Report on the Comprehensive Plan Update and Transportation Master Plan

The Village of Sugar Grove, in partnership with Kane County, the Illinois Department of Transportation, and the Illinois Tollway welcomes you to the

2017 General Obligation Bond

St. Clair Avenue West Area Transportation Master Plan

PROPOSED IMPROVEMENTS

REVIEW AND EVALUATION OF REGIONAL LAND USE

SH 199 Corridor Master Plan. Community Meeting No. 2 May 31, 2017

Section4 Design Vision & Implementation Plan

Gratigny Parkway East Extension Project Development & Environment (PD&E) Study

New Stanton Project Update July 3, 2012

CAG Meeting #4 Summary

March 1, PWG Meeting #4

WELCOME TO OPEN HOUSE TWO November 28, 2018

Reconfiguration of The Six Points Interchange. Community Update #2 June 18, 2014

Adelaide Street / Canadian Pacific Railway (CPR) Grade Separation. Public Information Centre #1

WELCOME TO OPEN HOUSE # 3

Slot Home Task Force Meeting #5 Phase 2 June 8, 2017

Guiding Principles for the SR 520 Replacement Project

Fifth and Detroit Street Design May 2017 Capital Improvements Committee. DOWNTOWN Street Design

Tonight s Agenda. Summary Presentation Open House. Group Discussion Next Steps: online community wide survey

SAWYER RANCH ROAD Pedestrian and Bicycle Improvements

Welcome. Tina Fischer. East Tampa Area Community Working Group September 25, Collaborative Labs, St. Petersburg College

PLAN ELEMENTS WORKSHOP. April 5, 2016

SHERIDAN PARKING STRUCTURE PUBLIC INFORMATION MEETING November 11, :00 pm - 8:00 pm

SBCAG STAFF REPORT. MEETING DATE: March 17, 2016 AGENDA ITEM: 5I

Institutional Master Plan The Arnold Arboretum of Harvard University

I-84 HARTFORD PROJECT HARTFORD, CONNECTICUT DRAFT PURPOSE AND NEED STATEMENT

BeltLine Corridor Environmental Study

Population and Demographics Alternatives Development Design Criteria Stormwater Management Guidelines Alternative 1: No Build

Eastside Transit Corridor Phase 2 Technical Study Update Community Outreach Meeting February 2017

I. DESCRIPTION OF PROPOSED ACTION... 1 A. General Description... 1 B. Historical Resume and Project Status... 2 C. Cost Estimates...

Ballston Station Multimodal Study. Stakeholder Meeting October 5, 2010

Welcome to the LYNX Blue Line Extension Transit Station Area Plans Public Workshop No. 3. Presentation will begin at 6:00 P.M.

PROJECT ADVISORY COMMITTEE (PAC) MEETING #1 Meeting Summary Date: March 27, 2017 Norwalk City Hall Community Room Time: 6:30pm

This Review Is Divided Into Two Phases:

Atlanta BeltLine Corridor Environmental Study. Scoping Meeting August 2008

Asheville Design Center March 2010

The Illinois Department of Transportation and Lake County Division of Transportation. Route 173, including the Millburn Bypass

PD&E STUDY SR 9/I-95 FROM SOUTH OF SR 870/COMMERCIAL BOULEVARD TO NORTH OF CYPRESS CREEK ROAD FM # ETDM 14222

Report to: Development Services Committee Report Date: April 24, 2017

CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF NOVEMBER 15, 2016

Workshop 3. City of Burlington Waterfront Hotel Planning Study. September 14, The Planning Partnership

North York Centre South Service Road

Wheaton CBD & Vicinity Sector Plan D E S I G N G U I D E L I N E S

Community Meeting US 101/Peninsula Avenue Interchange Project JUNE 25, 2015

(blank page) WestConnex New M Roads and Maritime Services Environmental impact statement

Memorandum CITY OF DALLAS. Riverfront Boulevard Design From Continental Avenue to Cadiz Street

Richmond Road Complete Street Meeting #1, April 25, 2016

Laird in Focus Community Information Session

GLEN ROAD PEDESTRIAN BRIDGE ENVIRONMENTAL ASSESSMENT STUDY PUBLIC INFORMATION CENTRE #2 OCTOBER 24, 2017

AMITY STATION Revised Concept Plan Review West Rosemary Street Chapel Hill, NC September 27, 2016

Southeast Extension to RidgeGate Parkway Scoping Booklet

AGENDA ACTION ITEMS INFORMATION ITEMS

Project Overview. Get Involved. Public Information Meeting. Contact Information

MDX SR 836/DOLPHIN EXPRESSWAY SOUTHWEST EXTENSION

Stakeholders Advisory Working Groups (SAWGs) Smart Growth and TOD Land Use (#11) SAWG Meeting

FDOT D4 Complete Streets

North Commuter Parkway and Traffic Bridge Project Market Sounding

University of Saskatchewan CAMPUS MASTER PLAN. Senate Meeting Preliminary Presentation. April 21, 2018 DIALOG ECS DA WATT

SOUTH UNIVERSITY Street Design Alternatives in Progress

Public Meeting Final Recommendations August 8, 2013

Commissioners Road West Realignment Environmental Assessment

Update. What is the Osborne Bridge Rehabilitation project all about and how is it being planned? Neighbourhood Advisory Committee (NAC)

METRO Gold Line BRT CBAC Meeting. August 23, 2018

DRAFT Civic Center Station Area Plan. Executive Summary

PREPARED FOR: PLATTEVIEW ROAD CORRIDOR STUDY EXECUTIVE SUMMARY

4.1 Build Alternative 1 Construction Phasing

Midtown Corridor Alternatives Analysis. Appendix A - Initially Considered Alternatives Screening

City of Toronto. Emery Village Transportation Master Plan

North Carolina Department of Transportation Project Development and Environmental Analysis Branch

Toronto Complete Streets Guidelines Stakeholder Advisory Group #

BACKGROUND, GOALS, STUDY AREA, EVALUATION CRITERIA, ORGANIZATION

Introduction to the Project

Interstate 229 Major Investment Study Exit 9 Benson Rd Sub-Study

1.0 INTRODUCTION & BACKGROUND

Access Management Strategies for Major Corridors. Town of Amherst, New York Erie County

Community Sensitive Design: (Context Sensitive Design)

University of the District of Columbia Van Ness Campus Master Plan Community Open House 3. December 8, 2010

Transcription:

Route 7/15 Norwalk Project Project Advisory Committee Meeting #5 Route 7/15 Norwalk PAC Meeting #5 November 14, 2018 Wednesday, November 14 th, Norwalk City Hall

Route 7/15 Norwalk - AGENDA Introductions Reviewing role of PAC SUMMARY OF 9/17 MEETINGS Purpose & Need Comments Summary of PAC #4 Landscape Workshop Alternative Review Alternatives Assessment Screening Next Steps/Questions

Route 7/15 Norwalk - Role of PAC To be instrumental in helping to craft a successful outcome, by: 1. Attend meetings, review material and educate yourself 2. Share viewpoints and ideas in project dialog 3. Link between the study team and the community - in both directions 4. Help reach consensus on project issues and alternates - honor differences in opinion and perspective 5. Support the consensus of the PAC

SUMMARY Route OF 7/159/17 Norwalk MEETINGS

Route 7/15 Norwalk - Purpose and Need Update Include landscape into integration goal Integrate the Project Roadways and Landscape with the Environment and Neighborhood context Move the footnote on landscape guidelines into full text as documented in the National Register of Historic Places nomination and State Scenic Road designation, following recommendations in the Merritt Parkway Guidelines for General Maintenance and Transportation Improvements, Merritt Parkway Landscape Master Plan, and Merritt Parkway Bridge Restoration Guide

Route 7/15 Norwalk - Needs & Deficiencies Report What we heard o Are you considering bicycle and pedestrian access at Grist Mill? o Why was there little reference to landscape deficiencies?

Route 7/15 Norwalk - Landscape Workshop What are the most appealing landscape/visual features within the project area? o Views of natural and built environments o Parkway feel for traffic calming o Plant variety/visibility

Route 7/15 Norwalk - Landscape Workshop What are the least appealing landscape/visual features within the project area? o Glover Avenue Apartments- New construction is too visible o Construction staging areas o Route 7 cloverleaf o Non-original bridges

Route 7/15 Norwalk - Landscape Workshop What is most important to you? Views Structures (Bridges) Maintenance Scale o Topography/landscape relationship o Hierarchy of plant materials to create intimate scale o Note contrast to I-95 Vegetation/Natural Resources

ALTERNATIVES Route 7/15 REVIEW Norwalk

Route 7/15 Norwalk ALTERNATIVE SCREENING PURPOSE Allows for wide range of alternatives to be considered in a conceptual manner Move from many to a few alternatives to be fully evaluated within the NEPA/CEPA process (Environmental Assessment and Environmental Impact Evaluation) Multi-Level approach o Purpose and Need o Goals and Objectives o Other Considerations

LEVEL Route 1 SCREENING 7/15 Norwalk (PURPOSE AND NEED)

Route 7/15 Norwalk ALTERNATIVE SCREENING Project team took a step back to review all alternatives discussed in prior Environmental Assessment and stakeholder workshops Quick evaluation of traffic operations and key needs/goals Why o Do any have merit based on current purpose and need/goals o Confirm issues still exist

Route 7/15 Norwalk ALTERNATIVE SCREENING Level 1 (Purpose and Need) The key criteria to meet the Purpose & Need: Roadway System Linkages: Does the alternative provide complete connections between Route 7 and the Merritt Parkway? Mobility Improvements: Does the alternative provide connections between Main Avenue and Route7 and improve mobility for all users (motorists, pedestrians and bicyclists) at project interchange areas? Safety Considerations: Does the alternative improve safety in the vicinity of Interchange 39 and 40 on the Merritt Parkway?

Route 7/15 Norwalk PAC Meeting #5 November 14, 2018 ALTERNATIVE SCREENING Level 1 (Purpose and Need) Criteria Purpose & Need Roadway System Linkage Linkage between Route 7 and Merritt Parkway Mobility Improve mobility for all users (motorists, pedestrians, and cyclists) at project interchange areas* Safety Considerations Safety in vicinity of Interchanges 39 and 40** ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. NO- BUILD 1 2 2A 3 4 5 6 7A 8 9 10 11 12 12A 13 14 15 16 17 18 19B 20B 21C 21D 22 23 24B 25 26 Concept developed but refined as Alt 2A so discarded Concept developed but refined as Alt 12A so discarded Ability to Meet Purpose and Need Meets P&N Moderately Meets P&N Does Not Meet P&N More Analysis Needed Concept refined as Alt. 21D so discarded Concept developed at same time as Alt. 21C. Alt. 21C was previously determined to be the better version of this alternative. How was the Ability to Meet Purpose and Need Determined? Criteria Roadway System Linkage Linkage between Route 7 and Merritt Parkway Meets P&N ( g ) if Moderately Meets P&N ( g ) if Does Not Meet P&N ( g ) if Connections are made in all directions to/from Route 7 and Merritt Parkway N/A. Connections are not made in all directions to/from Route 7 and Merritt Parkway Mobility Improve mobility for all users (motorists, pedestrians, and cyclists) at project interchange areas* Safety Considerations Safety in vicinity of Interchanges 39 and 40** Vehicular connections are provided between Main Avenue and Route 7 and all connections are maintained between Merritt Parkway and Creeping Hemlock Drive. Local road network improvements are apparent. No apparent geometric deficiencies (e.g., inadequate distances, tight ramps) are identified. Vehicular connections are provided between Main Avenue and Route 7 but not all connections are maintained between Merritt Parkway and Creeping Hemlock Drive. Local road network improvements may or may not be apparent. Some apparent geometric deficiencies such as short weaving distances between ramps are maintained or adjacent on- and/or off-ramps are proposed Vehicular connections are not provided between Main Avenue and Route 7 and/or no connections are maintained between Merritt Parkway and Creeping Hemlock Drive. The local road network is not improved. Many apparent geometric deficiencies such as short weaving distances, inadequate acceleration/deceleration lanes, etc. are proposed or past assessments specifically denoted safety concerns.

Route 7/15 Norwalk ALTERNATIVE SCREENING Level 1 (Purpose and Need) Criteria Meets P&N ( ) if Roadway System Linkage Linkage between Route 7 and Merritt Parkway Mobility Improve mobility for all users (motorists, pedestrians, and cyclists) at project interchange areas* Safety Considerations Safety in vicinity of Interchanges 39 and 40** Connections are made in all directions to/from Route 7 and Merritt Parkway Vehicular connections are provided between Main Avenue and Route 7 and all connections are maintained between Merritt Parkway and Creeping Hemlock Drive. Local road network improvements are apparent. No apparent geometric deficiencies (e.g., inadequate distances, tight ramps) are identified.

Route 7/15 Norwalk ALTERNATIVE SCREENING Level 1 (Purpose and Need) Criteria Roadway System Linkage Linkage between Route 7 and Merritt Parkway Moderately Meets P&N ( N/A. ) if Mobility Improve mobility for all users (motorists, pedestrians, and cyclists) at project interchange areas* Safety Considerations Safety in vicinity of Interchanges 39 and 40** Vehicular connections are provided between Main Avenue and Route 7 but not all connections are maintained between Merritt Parkway and Creeping Hemlock Drive. Local road network improvements may or may not be apparent. Some apparent geometric deficiencies such as short weaving distances between ramps are maintained or adjacent on- and/or off-ramps are proposed

Route 7/15 Norwalk ALTERNATIVE SCREENING Level 1 (Purpose and Need) Criteria Does Not Meet P&N ( ) if Roadway System Linkage Linkage between Route 7 and Merritt Parkway Mobility Improve mobility for all users (motorists, pedestrians, and cyclists) at project interchange areas* Safety Considerations Safety in vicinity of Interchanges 39 and 40** Connections are not made in all directions to/from Route 7 and Merritt Parkway Vehicular connections are not provided between Main Avenue and Route 7 and/or no connections are maintained between Merritt Parkway and Creeping Hemlock Drive. The local road network is not improved. Many apparent geometric deficiencies such as short weaving distances, inadequate acceleration/deceleration lanes, etc. are proposed or past assessments specifically denoted safety concerns.

Route 7/15 Norwalk PAC Meeting #5 November 14, 2018 ALTERNATIVE SCREENING Level 1 (Purpose and Need) Criteria Purpose & Need Roadway System Linkage Linkage between Route 7 and Merritt Parkway Mobility Improve mobility for all users (motorists, pedestrians, and cyclists) at project interchange areas* Safety Considerations Safety in vicinity of Interchanges 39 and 40** ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. NO- BUILD 1 2 2A 3 4 5 6 7A 8 9 10 11 12 12A 13 14 15 16 17 18 19B 20B 21C 21D 22 23 24B 25 26 Concept developed but refined as Alt 2A so discarded Concept developed but refined as Alt 12A so discarded Ability to Meet Purpose and Need Meets P&N Moderately Meets P&N Does Not Meet P&N More Analysis Needed Concept refined as Alt. 21D so discarded Concept developed at same time as Alt. 21C. Alt. 21C was previously determined to be the better version of this alternative.

Alternative 15 N

Alternative 15 Ability to Meet Project Purpose and Need Roadway System Linkage Connections are not made in all directions to/from Route 7 and Merritt Parkway. There is no connection between southbound Route 15 and northbound Route 7. Mobility Vehicular connections are not provided between Main Avenue and Route 7. Some of the vehicular connections are maintained between Merritt Parkway and Creeping Hemlock Drive. Local road network improvements are apparent. Safety Geometric deficiencies (weaving movements and distances along SB Route 15 within cloverleaf Route 7 interchange) are apparent. N

COMMENTS/QUESTIONS

Route 7/15 Norwalk PAC Meeting #5 November 14, 2018 ALTERNATIVE SCREENING Level 1 (Purpose and Need) Criteria Purpose & Need Roadway System Linkage Linkage between Route 7 and Merritt Parkway Mobility Improve mobility for all users (motorists, pedestrians, and cyclists) at project interchange areas* Safety Considerations Safety in vicinity of Interchanges 39 and 40** ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. ALT. NO- BUILD 1 2 2A 3 4 5 6 7A 8 9 10 11 12 12A 13 14 15 16 17 18 19B 20B 21C 21D 22 23 24B 25 26 Concept developed but refined as Alt 2A so discarded Concept developed but refined as Alt 12A so discarded Ability to Meet Purpose and Need Meets P&N Moderately Meets P&N Does Not Meet P&N More Analysis Needed Concept refined as Alt. 21D so discarded Concept developed at same time as Alt. 21C. Alt. 21C was previously determined to be the better version of this alternative.

Alternative Alternate 12A 12A N

Alternative 12A Ability to Meet Project Purpose and Need Roadway System Linkage Connections are made in all directions to/from Route 7 and Merritt Parkway. Mobility Vehicular connections are provided between Main Avenue and Route 7. Some of the vehicular connections are maintained between Merritt Parkway and Creeping Hemlock Drive. Local road network improvements are apparent. Safety Geometric deficiencies (successive merge points along SB Route 15 within short distances) are apparent. N The Alternative meets Project Purpose and Need.

Alternative 20B N

Alternative 20B Ability to Meet Project Purpose and Need Roadway System Linkage Connections are made in all directions to/from Route 7 and Merritt Parkway. Mobility Vehicular connections are provided between Main Avenue and Route 7. Vehicular connections are maintained between Merritt Parkway and Creeping Hemlock Drive. Local road network improvements are apparent. Safety No apparent geometric deficiencies. N The Alternative meets Project Purpose and Need.

Alternative 21C

Alternative 21C Ability to Meet Project Purpose and Need Roadway System Linkage Connections are made in all directions to/from Route 7 and Merritt Parkway. Mobility Vehicular connections are provided between Main Avenue and Route 7. Vehicular connections are maintained between Merritt Parkway and Creeping Hemlock Drive. Local road network improvements are apparent. Safety Geometric deficiencies (Multiple weaves within Route 7/15 interchange (each quadrant)) are apparent. The Alternative meets Project Purpose and Need.

Alternative 26 N

Alternative 26 Ability to Meet Project Purpose and Need Roadway System Linkage Connections are made in all directions are made to/from Route 7 and Merritt Parkway. Mobility Vehicular connections are provided between Main Avenue and Route 7. Vehicular connections are maintained between Merritt Parkway and Creeping Hemlock Drive. Local road network improvements are apparent. Safety No apparent geometric deficiencies. The Alternative meets Project Purpose and Need.

Route 7/15 Norwalk COMMENTS/QUESTIONS

Route 7/15 Norwalk ALTERNATIVE 21C 2 Bridges separate traffic to Route 15 SB and Route 7 SB One Route 7 SB exits Short 415 Weave Ramp Section Short 400 Weave 2 lane ramp segment Long deceleration lane Alignment impacts CLP Towers One lane ramp no signalization CD Roadway to Route 15 NB One lane ramp 450 Weave Section Loop Ramp R-300

Route 7/15 Norwalk ALTERNATIVE 21D Combines 2 Bridges to 1 Bridge over Route 7. Provides access to both Route 15 SB and Route 7 SB. Adds second lane due to traffic demand Improve ramp weave from 400 to 1000. Added third lane due to traffic demand Add second lane due to traffic demand Two Route 7 SB exits Reduced decel. lane Ramp weave eliminated with second Route 7 SB exit Added signal and modified ramp for 2 lanes Tighter ramp geometry avoids impact to CLP towers Improve ramp geometry by tightening loop ramp, R=275. Improve weave from 450 to 600. Separate NB Route 15 Entrance Ramps (no CD). Allows for tighter footprint at Main Ave

Route 7/15 Norwalk ALTERNATIVE 21D

Route 7/15 Norwalk PAC Meeting #5 November 14, 2018 Level 1 (Purpose and Need) Screening Results ALT. ALT. ALT. ALT. Criteria NO-BUILD 12A 20B 21D 26 Purpose & Need Roadway System Linkage Linkage between Route 7 and Merritt Parkway Mobility Improve mobility for all users (motorists, pedestrians, and cyclists) at project interchange areas* Safety Considerations Safety in vicinity of Interchanges 39 and 40**

Route 7/15 Norwalk - Discussion Does Level 1 alternative screening make sense? Do we need to further review any additional alternatives?

PAC Meeting #5 November 14, 2018 Route 7/15SCREENINGNorwalk ALTERNATIVES LEVEL 2

Route 7/15 Norwalk PAC Meeting #5 November 14, 2018 ALTERNATIVES SCREENING Level 2 (Goals & Objectives) Criteria NO-BUILD ALT 12A ALT 20B ALT21D ALT 26 Purpose & Need (Level 1 Screening Results) Roadway System Linkage Linkage between Route 7 and Merritt Parkway Mobility Improve mobility for all users (motorists, pedestrians, and cyclists) at project interchange areas Safety Considerations Safety in vicinity of Interchanges 39 and 40 Goals & Objectives Reduce Congestion Long-Term Serviceability -Improved connections to alternate modes of transportation (rail, bus, bike ) -Compatible with City/Regional initiatives Optimizing Value Gained from Public Investment - Cost effective solutions - Reducing maintenance costs - Minimizing impacts of construction to public -Implementing sustainable practices Integrate Project Roadways and Landscape with Environment/Neighborhood context - Design consistent with MP historic/scenic character including preserving/restoring historic bridges where practical - Preserving, enhancing surviving historic landscape, where practical. - Creating new landscape design consistent with Parkway's original design intent

PAC Meeting #5 November 14, 2018 Route 7/15 Norwalk NEXT STEPS

Route 7/15 Norwalk - NEXT STEPS PAC o Refinement of Level 2 criteria (Winter 2019) Continue historic property impact consultation o Section 106 sub-committee (Winter 2019) Landscape sub-committee follow up o Strong overlap with Section 106 committee o We will continue with landscape discussion as part of the Section 106 committee and as project design moves forward

Route 7/15 Norwalk PAC Meeting #5 November 14, 2018