TENNESSEE DEPARTMENT OF TRANSPORTATION Project Status. No Projects Under Development in Campbell County

Similar documents
TENNESSEE DEPARTMENT OF TRANSPORTATION Project Status. SR-37 No Projects US-19E Under Development in Carter County

TENNESSEE DEPARTMENT OF TRANSPORTATION Project Status. SR-37 US-19E No Projects Under Development in Carter County

Creative Engineering Group Inc, (Creative) Construction Engineering and Inspection (CEI) Professionals

Fall 2017 Construction Update

4.1 Build Alternative 1 Construction Phasing

Welcome. Northern Segment of Hwy 100 I-90 to South of Madison Street Meeting Goals:

Municipality of Anchorage. Community Council Survey Capital Projects Needs Ranking Survey (ALPHABETICAL) Airport Heights

Capital Projects in and near Odenton Town Center

2040 Long Range Transportation Plan

Capital Projects impacting Odenton Town Center

Public Works Project Delivery Report

I-25 / Rio Bravo Interchange. I-25 / Rio Bravo Interchange. Presenters 11/30/2016 THIRD PUBLIC MEETING DECEMBER 1, 2016 NMDOT CN A300280

I-4 Beyond the Ultimate. Florida Transportation Builders Association February 9, 2018

BID RESULTS OCTOBER 24, 2007

I.T.S. PLAN ALONG I-95 INSTALL FIBER OPTIC LINE PROJECT SHOWING Tuesday, June 18, 2013, 1:30pm Ashland Residency Conference Room

Construction Engineering & Inspection

FY 2018 TRANSPORTATION CAPITAL PROGRAM New Jersey Department of Transportation Projects

Town of Yucca Valley Capital Improvement Projects Report July 24, 2014

FY 2005 TRANSPORTATION CAPITAL PROGRAM

Rt. 29 Solutions Project Delivery Advisory Panel. January 7, 2016

Moving The Metro. A special construction update for the metro Omaha area.

Spring 2018 Construction Update

Hunt Highway CELESTE PEMBERTON, CFM, CPM PINAL COUNTY CARLOS SANCHEZ SORIA, PE T.Y. LIN INTERNATIONAL

Project Goal. RRRC Living Towns Planning Workshp. Town of Halifax Revitalization Project. Dynamic Planning & Management Duo: July 12, 2006

AGENDA ACTION ITEMS INFORMATION ITEMS

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Projects

Memorandum CITY OF DALLAS

The bid shall include the following items: 1) Bidder s Name. Address. Telephone Number. Address. 2) The amount of the bid per acre to Mow.

CITY OF LAKEWOOD 2012 THREE-MILE PLAN

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Project Descriptions ($ millions)

Exhibit A. SH 161 RTC Work Program of New Projects. Collin County

TRANSPORTATION & STREET DESIGN

New Stanton Project Update July 3, 2012

SR 483 Clyde Morris Boulevard FDOT District 5

BALL CAMP PIKE Phase II From Middlebrook Pike to Andes Road NEW CONSTRUCTION Spring 2007

City of Guelph - Wilson Street Parkade / Wilson Street Reconstruction Proposed Project Schedule April 21,

PROJECTS UNDER CONSTRUCTION

Interstate Traffic Interruptions Weekend of Oct 9, 2015-Oct 12, 2015

STATE OF TENNESSEE DEPARTMENT OF TRANSPORTATION ENVIRONMENTAL DIVISION

City of Waukee, Iowa Capital Plan PROJECTS BY DEPARTMENT

NASHVILLE AREA MPO FY TIP - ADOPTED DECEMBER

STREET IMPROVEMENT AND MAINTENANCE PROGRAMS

FOR IMMEDIATE RELEASE DATE: FRIDAY, SEPTEMBER 21, Road Commission of Kalamazoo County Weekly Project Updates HAVE YOU SIGNED UP?

North Carolina Department of Transportation Project Development and Environmental Analysis Branch

Highway 417 Expansion East

ALTERNATIVES. NCDOT made an early decision to first determine how to build the project (construction method) followed by what to build (alternatives).

Mavis Road Class Environmental Assessment

Turkey Creek Corridor

LEGEND. Existing Transit Services in Project Area. I-84 / I-91 INTERCHANGE STUDY I-84 / I-91 Transit Map. Connecticut Department of Transportation

Welcome to the. Open House

2017 Asphalt Contractors Association of Florida Pavement Awards

The Grand Army of the Republic Corridor

Transportation Projects Quarterly Report. Morrisville Planning Department May 22, 2018

San Francisco DPW Construction Contract Awards (FY 09-10)

Northeast Anthony Henday Drive Manning Freeway to Whitemud Drive Welcome to this Construction Information Session

Southern Gateway Project and Public Green

Open House RIVER DES PERES GREENWAY: LANSDOWNE SHREWSBURY METROLINK TO FRANCIS R. SLAY PARK

PUBLIC HEARING. Thursday, December 14, 2017 FDOT Urban Office 2198 Edison Avenue Jacksonville, FL 32204

We d like to thank you for attending this Wekiva Parkway Section 8 Preliminary Design Update hosted by the Florida Department of Transportation.

Secrest Short Cut and Monroe Expressway Small Area Plan AUGUST 29, 2018

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Projects

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Projects

FOR IMMEDIATE RELEASE DATE: FRIDAY, SEPTEMBER 28, Road Commission of Kalamazoo County Weekly Project Updates HAVE YOU SIGNED UP?

FDOT/FTBA Construction Conference Work Plan

I-75/I-475 Interchange Upgrade Project Informational Meeting Tuesday, July 27, 2010

2017 Investment in Infrastructure Expo February 28, 2017 Jason Jonas, P.E. Public Works Director

Mississippi Drive Corridor Revitalization. A DestinationTransportation Project...

REGIONAL TRANSPORTATION COMMISSION OF SOUTHERN NEVADA AGENDA ITEM

Proposed FY 2004 TRANSPORTATION CAPITAL PROGRAM New Jersey Department of Transportation Projects

The Ambassador Bridge/ Gateway Project

Public Officials/Design Advisory Meeting #12. Bensalem Township Municipal building, 2400 Byberry Road Bensalem, PA

Route 29 Project Delivery Advisory Panel September 11, 2014 Meeting Minutes

PLANNING COORDINATING COMMITTEE

TOWN OF PALM BEACH FOR IMMEDIATE RELEASE. Patricia Strayer, P.E., Town Engineer Phone: ,

Comprehensive Development Guide

2018 Capital Improvements Report

City of Kearney Capital Improvement Update October 1, TH STREET AND 17TH AVENUE IMPROVEMENTS

(blank page) WestConnex New M Roads and Maritime Services Environmental impact statement

FOR IMMEDIATE RELEASE DATE: FRIDAY, AUGUST 31, Road Commission of Kalamazoo County Weekly Project Updates HAVE YOU SIGNED UP?

startup. Construction of contractor entrance off University City Blvd connecting to Lot 8 has started.

SH 199 Corridor Master Plan. Community Meeting No. 2 May 31, 2017

MAIN STREET RECONSTRUCTION PROJECT PRE-CONSTRUCTION PUBLIC INFORMATION SESSION AGENDA

Route 9 Gateway Project. October 9, 2014 Informational Meeting

Henderson County Project Prioritization Discussion

Western Belfast Bypass almost finished

Project Status. Construction is underway for Phase 3. Overall Project Area and Schedule. Schedule of Current Construction Phases.

Date: Thursday, August 21, 2014

TIRZ 17/Redevelopment Authority Capital Improvements Plan Projects

City of Jersey City. Department of Administration Division of Engineering Traffic and Transportation

RUTHERFORD NASHVILLE AREA MPO FY TIP - ADOPTED DECEMBER

INFRASTRUCTURE EXISTING INFRASTRUCTURE A. Circulation B. Signals C. Drainage D. Utilities

ADOPTED AT NOVEMBER 15, 2012 PACC MEETING

A summary of Federal transportation obligations in the Knoxville TPO Planning Area between October 1, 2014 and September 30, 2015

2017 General Obligation Bond

Memorandum CITY OF DALLAS. Riverfront Boulevard Design From Continental Avenue to Cadiz Street

Project will Replace: Utilities Curb Pavement Lighting. City of Madison

Index to Projects by Project Name

SR 15 SECTION 088 CSVT SOUTHERN SECTION PUBLIC MEETING JUNE 16, 2015

PennDOT Public Meeting. S.R. 3044, Section A01 Castle Shannon Boulevard Roadway Improvement Project

Debra Larson and Director Malcolm Dougherty

Transcription:

I-75 No Projects Under Development in Campbell County PIN: 115778.00 TRUCK CLIMBING LANE, MP 135.5 TO MP 140.1(NBL) Length - 4.6 (Widen) The right-of-way and/or utility process is underway. I-75 PIN: 115778.01 TRUCK CLIMBING LANE, MP 144.9 TO MP 147.6(NBL) Length - 2.7 (Widen) This project is currently advertised for the July 10, 2015 contract letting. I-75 PIN: 121764.00 SOUTHBOUND WELCOME CENTER EXIT RAMP (INCLUDES 1,500 FEET INTO KENTUCKY) Length - 0.3 (Miscellaneous Safety Improvements) The engineering is scheduled to begin in the 4th Quarter Calendar Year 2015. SR-9 US-25W PIN: 118429.00 BRIDGE OVER BIG CREEK, LM 24.15 IN LAFOLLETTE Length - 0.0 (Bridge Rehabilitation) This project is in the early stages of development. SR-9 US-25W PIN: 118819.00 FROM I-75 TO SR-63 (RSAR) Length - 22.8 (Miscellaneous Safety Improvements) This project is in the early stages of development. SR-9 PIN: 120521.00 FROM HUNTERS BRANCH ROAD TO MAIN STREET (RSA) Length - 2.8 (Miscellaneous Safety Improvements) SR-9 PIN: 121765.00 INTERSECTION AT ELKINS ROAD (PHASE II) Length - 0.4 (Turn Lanes) This project is in the early stages of development. Page: 1

SR-63 PIN: 101406.00 SCOTT COUNTY LINE TO I-75 Length - 6.5 (Widen) SR-63 PIN: 101407.01 FROM LAFOLLETTE URBAN BOUNDARY TO FRONTIER ROAD/WOODSON LANE Length - 4.8 (Widen) SR-63 PIN: 101407.02 FROM FRONTIER ROAD/WOODSON LANE TO CLAIBORNE COUNTY LINE Length - 5.2 (Widen) SR-63 PIN: 101406.04 INTERSECTION OF SR-297 AND WEST OF OLD SR-63 TO WEST OF STINKING CREEK ROAD(TRUCK CLIMBING LANE) (EPD) Length - 2.0 (Widen) This project is in the early stages of development. SR-297 PIN: 115674.00 BRIDGE OVER LICK FORK CREEK, LM 5.25 Length - 0.0 (Bridge Replacement) SR-297 PIN: 115677.00 BRIDGE OVER ELK FORK CREEK, LM 14.79 Length - 0.0 (Bridge Replacement) PIN: 117272.00 NORTH 11TH STREET, BRIDGE OVER CSX RAILROAD IN LAFOLLETTE, LM 0.27 Length - 0.1 (Bridge Replacement) Page: 2

PIN: 118830.00 MIDDLESBORO HIGHWAY, FROM SR-63 TO DOAKS CREEK ROAD (RSAR) Length - 5.3 (Miscellaneous Safety Improvements) This project is in the early stages of development. SIA PIN: 118137.00 INDUSTRIAL ACCESS ROAD SERVING MATIX CORP. AND CAMEL MANUFACTURING IN CARYVILLE Length - 2.0 (Reconstruction) The right-of-way and/or utility process is underway. Page: 3

I-75 No Projects Under Construction in Campbell County BRIDGE OVER KOPPERS ROAD (NBL) AND SR-63 (SBL) (BRIDGE REPLACEMENT) CNP201 LET TO CONTRACT: 5/15/2015 BELL & ASSOCIATES CONSTRUCTION, L.P. BID PRICE : $5,269,406.15 EST. COMPLETION DATE: MAY, 2017 SR-9 US-25W FROM EAST OF JANEWAY LANE TO I-75 (RESURFACE & SAFETY) LENGTH - 3.640 CNP029 LET TO CONTRACT: 2/13/2015 ROGERS GROUP, INC. BID PRICE : $1,514,209.04 VARIOUS LOCAL ROADS IN (LOCAL ROADS SAFETY INITIATIVE) (MISCELLANEOUS SAFETY IMPROVEMENTS) LENGTH - 0.020 CNN308 LET TO CONTRACT: 10/17/2014 SUPERIOR PAVEMENT MARKING, INC. BID PRICE : $328,854.70 MORGAN - ANDERSON - CAMPBELL COUNTIES SR-116 FROM SR-62 IN MORGAN COUNTY TO CAMPBELL/ANDERSON COUNTY LINE (RSAR) (MISCELLANEOUS SAFETY IMPROVEMENTS) LENGTH - 15.950 CNN344 LET TO CONTRACT: 10/17/2014 ROGERS GROUP, INC. BID PRICE : $1,092,665.53 EST. COMPLETION DATE: AUGUST, 2015 Page: 4

CAMPBELL - COCKE COUNTIES I-75 AT LM'S 27.30, 28.15 AND 29.20 IN ; AND I-40 AT LM'S 14.75 AND 15.70 IN COCKE COUNTY (MEDIAN BARRIER WALL) CNN935 LET TO CONTRACT: 8/29/2014 J. RANCK ELECTRIC, INC. BID PRICE : $772,293.00 I-75 FROM MP 142 (NORTH OF LA FOLLETTE) TO MP 157(SOUTH OF JELLICO) (RSAR) (MISCELLANEOUS SAFETY IMPROVEMENTS) LENGTH - 15.500 CNN232 LET TO CONTRACT: 7/11/2014 RMD HOLDINGS, LTD DBA NATIONWIDE CONSTRU BID PRICE : $657,242.26 STINKING CREEK ROAD (01280), BRIDGE OVER I-75, LM 16.36 (BRIDGE REPAIR) CNN236 LET TO CONTRACT: 7/11/2014 POTTER SOUTH EAST LLC BID PRICE : $69,863.00 I-75 FROM NORTH OF SR-63 TO NORTH OF MILE MARKER 147 (RESURFACING) LENGTH - 5.980 CNM946 LET TO CONTRACT: 12/6/2013 APAC-ATLANTIC, INC. BID PRICE : $2,649,030.25 I-75 FROM NORTH OF SR-9 TO NORTH OF SR-63 (RESURFACING) LENGTH - 6.430 CNM946 LET TO CONTRACT: 12/6/2013 APAC-ATLANTIC, INC. BID PRICE : $3,079,569.55 Page: 5

CLAIBORNE COUNTY SR-32 No US-25E Projects Under Development in Claiborne County PIN: 118734.00 INTERCHANGE AT SR-345 Length - 0.0 (New Interchange) The engineering is scheduled to begin in the 3rd Quarter Calendar Year 2015. CLAIBORNE COUNTY SR-33 PIN: 117530.00 FROM MAIN STREET TO YOUNGSTOWN ROAD Length - 1.1 (Miscellaneous Safety Improvements) The right-of-way and/or utility process is underway. CLAIBORNE COUNTY SR-33 PIN: 119825.00 FROM MOUNTAIN ROAD TO FIRST AVENUE IN NEW TAZEWELL (RSAR) Length - 2.8 (Miscellaneous Safety Improvements) The environmental studies are complete. CLAIBORNE COUNTY SR-63 PIN: 101409.00 FROM LINE TO HALL LANE Length - 4.8 (Widen) CLAIBORNE COUNTY SR-63 PIN: 105763.00 FROM WEST OF OLD TOWN CREEK TO SR-32 (US-25E) (EPD) Length - 6.2 (Reconstruction) Page: 6

CLAIBORNE COUNTY SIA No Projects Under Construction in Claiborne County INDUSTRIAL ACCESS ROAD SERVING HOMESTEADER TRAILERS IN NEW TAZEWELL (CONSTRUCTION-NEW) LENGTH - 0.254 CNP068 LET TO CONTRACT: 2/13/2015 GLASS MACHINERY & EXCAVATION, INC. BID PRICE : $668,547.83 EST. COMPLETION DATE: NOVEMBER, 2015 CLAIBORNE COUNTY VARIOUS LOCAL ROADS IN CLAIBORNE COUNTY (LOCAL ROADS SAFETY INITIATIVE) (SAFETY) CNN368 LET TO CONTRACT: 12/5/2014 VOLUNTEER HIGHWAY SUPPLY CO. INC. BID PRICE : $332,585.70 EST. COMPLETION DATE: AUGUST, 2015 CLAIBORNE COUNTY SR-345 INTERSECTION AT SR-32 (US-25E) IN TAZEWELL (TURN LANES) LENGTH - 0.060 CNN938 LET TO CONTRACT: 10/17/2014 CHARLES BLALOCK & SONS, INC. BID PRICE : $798,349.60 UNION - CLAIBORNE COUNTIES SR-33 INTERSECTIONS AT KETTLE HOLLOW ROAD/LITTLE VALLEY ROAD, SR-170 & LONE MOUNTAIN ROAD (INTERSECTION IMPROVEMENTS) LENGTH - 0.012 CNM077 LET TO CONTRACT: 2/15/2013 TWIN K CONSTRUCTION, INC. BID PRICE : $1,995,408.90 Page: 7

GRAINGER COUNTY SR-1 No US-11W Projects Under Development in Grainger County PIN: 101410.00 FROM RUTLEDGE TO BEAN STATION Length - 11.5 (Location and Environmental Study) The environmental studies are complete. GRAINGER COUNTY SR-1 US-11W PIN: 101410.02 FROM RUTLEDGE TO WEST OF HELTON ROAD (EPD) Length - 5.6 (Widen) GRAINGER COUNTY SR-1 US-11W PIN: 101410.01 FROM WEST OF HELTON ROAD TO BEAN STATION (EPD) Length - 5.0 (Widen) GRAINGER COUNTY SR-32 US-25E PIN: 118733.00 OFF SETTING INTERSECTION AT SR-131 Length - 0.0 (Intersection Improvements) GRAINGER COUNTY SR-131 PIN: 120383.00 ENTRANCE NEAR WASHBURN SCHOOL (FLASHING SCHOOL SIGNS) Length - 0.4 (Flashing School Sign) Page: 8

GRAINGER COUNTY SR-131 No Projects Under Construction in Grainger County FROM NORTH OF WILLIAMS CREEK TO SR-32 (RESURFACING) LENGTH - 9.230 CNP027 LET TO CONTRACT: 2/13/2015 NY-MAC ENTERPRISES, INC. BID PRICE : $278,633.97 EST. COMPLETION DATE: SEPTEMBER, 2015 GRAINGER COUNTY JOPPA MOUNTAIN ROAD, FROM SR-1 TO SR-131 (RSAR) (RSAR) LENGTH - 4.650 CNP081 LET TO CONTRACT: 2/13/2015 HIGHWAY MARKINGS, INC. BID PRICE : $145,136.65 GRAINGER COUNTY SR-1 US-11W INTERSECTION AT BROADWAY DRIVE, LM 30.23 (SIGNALIZATION) CNN347 LET TO CONTRACT: 10/17/2014 STANSELL ELECTRIC COMPANY, INC. BID PRICE : $163,735.00 GRAINGER COUNTY VARIOUS LOCAL ROADS IN GRAINGER COUNTY (LOCAL ROADS SAFETY INITIATIVE) (MISCELLANEOUS SAFETY IMPROVEMENTS) CNN269 LET TO CONTRACT: 8/29/2014 HIGHWAY MARKINGS, INC. BID PRICE : $399,227.65 Page: 9

HAMBLEN COUNTY SR-34 No US-11E Projects Under Development in Hamblen County PIN: 101419.01 FROM SR-32 IN MORRISTOWN TO WEST OF OLD STAGECOACH ROAD IN RUSSELLVILLE Length - 5.0 (Preliminary Engineering) HAMBLEN COUNTY SR-34 US-11E PIN: 101419.03 FROM SR-32 IN MORRISTOWN TO NEAR MORRIS BOULEVARD Length - 3.8 (Construction-New) This project is in the early stages of development. HAMBLEN COUNTY SR-34 US-11E PIN: 101419.04 FROM NEAR MORRIS BLVD TO WEST OF OLD STAGECOACH ROAD IN RUSSELLVILLE (EPD) Length - 1.6 (Construction-New) This project is in the early stages of development. HAMBLEN COUNTY SR-34 US-11E PIN: 101419.02 FROM WEST OF OLD STAGECOACH ROAD IN RUSSELLVILLE TO STEADMAN ROAD (EPD) Length - 3.7 (Construction-New) HAMBLEN - JEFFERSON COUNTIES SR-66REL PIN: 100248.01 NORTH OF I-81 AT SR-341 IN JEFFERSON COUNTY TO SR-160 IN MORRISTOWN Length - 5.7 (Paving) This project is in the early stages of development. Page: 10

HAMBLEN COUNTY SR-344 No Projects Under Construction in Hamblen County FROM SR-34 TO HAWKINS COUNTY LINE (RESURFACE & SAFETY) LENGTH - 5.000 CNP176 LET TO CONTRACT: 5/15/2015 APAC-ATLANTIC, INC. BID PRICE : $686,640.55 EST. COMPLETION DATE: SEPTEMBER, 2015 HAMBLEN COUNTY SR-34 FROM WEST OF OLD STAGECOACH ROAD IN RUSSELLVILLE TO STEADMAN ROAD (EPD/PHASE 1) (MISCELLANEOUS SAFETY IMPROVEMENTS) LENGTH - 4.090 CNP096 LET TO CONTRACT: 3/27/2015 SUPERIOR TRAFFIC CONTROL - MEMPHIS, INC. BID PRICE : $52,048.55 EST. COMPLETION DATE: AUGUST, 2015 HAMBLEN COUNTY SR-32 US-25E BRIDGES (R&L) OVER SR-34 AND NORFOLK SOUTHERN R/R, LM'S 6.97 AND 6.98 (BRIDGE REPAIR) CNN235 LET TO CONTRACT: 12/5/2014 HIGHWAYS, INC. BID PRICE : $940,317.45 HAMBLEN COUNTY SR-113 INTERSECTION AT CHUCKY RIVER ROAD/FISH HATCHERY ROAD (INTERSECTION IMPROVEMENTS) LENGTH - 0.085 CNN336 LET TO CONTRACT: 12/5/2014 WHALEY & SONS, INC. BID PRICE : $725,690.40 Page: 11

HAMBLEN - JEFFERSON COUNTIES SR-66REL NORTH OF I-81 AT SR-341 IN JEFFERSON COUNTY TO SR-160 IN MORRISTOWN (STAGE CONSTRUCTION-NEW) LENGTH - 5.041 CNM089 LET TO CONTRACT: 5/24/2013 CHARLES BLALOCK & SONS, INC. BID PRICE : $43,048,750.69 EST. COMPLETION DATE: AUGUST, 2016 HAMBLEN COUNTY SR-32 US-25E INTERCHANGE AT COLLEGE PARK DRIVE IN MORRISTOWN (NEW INTERCHANGE) LENGTH - 0.928 CNK802 LET TO CONTRACT: 8/5/2011 SUMMERS-TAYLOR, INC. BID PRICE : $16,486,981.09 EST. COMPLETION DATE: AUGUST, 2015 HAMBLEN - JEFFERSON COUNTIES I-81 INTERCHANGE AT SR-32(US-25E), LM 0.51; SR-32, SOUTH OF AGRICULTURAL PARK BLVD TO NORTH OF PROGRESS PKWY (MODIFY INTERCHANGE) LENGTH - 1.189 CNK014 LET TO CONTRACT: 6/17/2011 CHARLES BLALOCK & SONS, INC. BID PRICE : $20,281,305.25 Page: 12

MORGAN COUNTY SR-29 US-27 No Projects Under Development in Morgan County PIN: 101411.05 FROM SOUTH OF WHETSTONE ROAD TO NORTH OF SR-328 Length - 1.9 (Reconstruction) The right-of-way and/or utility process is underway. MORGAN COUNTY SR-29 US-27 PIN: 101411.02 FROM NORTH OF SR-328 TO NORTH OF RAY CROSS RD/MOSSY GROVE RD(FORMERLY WESTMINSTER RD) Length - 2.5 (Reconstruction) The right-of-way and/or utility process is underway. MORGAN COUNTY SR-29 US-27 PIN: 101411.03 NORTH OF RAY CROSS RD/MOSSY GROVE RD(FORMERLY WESTMINSTER RD) TO SR-62 IN WARTBURG Length - 4.9 (Reconstruction) ROANE - MORGAN COUNTIES SR-29 US-27 PIN: 101411.00 FROM SR-61 IN HARRIMAN (ROANE COUNTY) TO SR-62 IN MORGAN COUNTY Length - 9.7 (Location and Environmental Study) The environmental studies are complete. ROANE - MORGAN COUNTIES SR-29 US-27 PIN: 101411.01 FROM SR-61 IN HARRIMAN IN ROANE COUNTY TO NORTH OF SR-328 IN MORGAN COUNTY Length - 3.7 (Right-of-Way) The right-of-way and/or utility process is underway. Page: 13

MORGAN COUNTY SR-116 No Projects Under Construction in Morgan County BRIDGE OVER STOCKSTILL CREEK, LM 2.06 (BRIDGE REPLACEMENT) LENGTH - 0.094 CNP032 LET TO CONTRACT: 5/15/2015 POTTER SOUTH EAST LLC BID PRICE : $400,663.13 EST. COMPLETION DATE: NOVEMBER, 2015 MORGAN COUNTY SR-29 US-27 FROM PETIT LANE TO SOUTH OF SR-62 (RESURFACE & SAFETY) LENGTH - 3.610 CNP117 LET TO CONTRACT: 3/27/2015 APAC-ATLANTIC, INC. BID PRICE : $366,456.85 EST. COMPLETION DATE: AUGUST, 2015 ROANE - MORGAN COUNTIES SR-29 US-27 FROM SR-61 IN HARRIMAN TO SOUTH OF WHETSTONE ROAD IN MORGAN COUNTY (RECONSTRUCTION) LENGTH - 3.370 CNP047 LET TO CONTRACT: 2/13/2015 CHARLES BLALOCK & SONS, INC. BID PRICE : $62,793,238.69 EST. COMPLETION DATE: MAY, 2018 MORGAN COUNTY VARIOUS LOCAL ROADS IN MORGAN COUNTY (LOCAL ROADS SAFETY INITIATIVE) (SAFETY) CNN369 LET TO CONTRACT: 12/5/2014 SUPERIOR TRAFFIC CONTROL - MEMPHIS, INC. BID PRICE : $330,505.56 EST. COMPLETION DATE: AUGUST, 2015 MORGAN COUNTY SIA STATE INDUSTRIAL ACCESS ROAD SERVING COBB-VANTRESS INC. (CONSTRUCTION-NEW) LENGTH - 0.800 CNN335 LET TO CONTRACT: 10/17/2014 WHALEY & SONS, INC. BID PRICE : $1,150,022.06 EST. COMPLETION DATE: AUGUST, 2015 Page: 14

MORGAN - ANDERSON - CAMPBELL COUNTIES SR-116 FROM SR-62 IN MORGAN COUNTY TO CAMPBELL/ANDERSON COUNTY LINE (RSAR) (MISCELLANEOUS SAFETY IMPROVEMENTS) LENGTH - 15.950 CNN344 LET TO CONTRACT: 10/17/2014 ROGERS GROUP, INC. BID PRICE : $1,092,665.53 EST. COMPLETION DATE: AUGUST, 2015 MORGAN COUNTY SR-52 (RUGBY BYPASS), FROM RELOCATED BREWSTERTOWN ROAD TO SCOTT COUNTY LINE (CONSTRUCTION-NEW) LENGTH - 2.431 CNJ307 LET TO CONTRACT: 10/29/2010 CHARLES BLALOCK & SONS, INC. BID PRICE : $13,494,558.95 Page: 15

SCOTT COUNTY SR-29 No Projects Under Development in Scott County PIN: 101414.00 FROM NORTH OF WOLF CREEK ROAD TO OLD US-27 AT ROBBINS (EPD) Length - 3.7 (Widen) SCOTT COUNTY SR-29PROP US-27 PIN: 105764.00 ONEIDA BYPASS; 5-LN SECTION NORTH OF ONEIDA TO 5-LN SECTION SOUTH OF ONEIDA Length - 2.9 (Construction-New) The engineering is scheduled to begin in the 4th Quarter Calendar Year 2015. SCOTT COUNTY SR-52 PIN: 101415.00 FROM MORGAN COUNTY LINE TO SR-29 (US-27) (EPD) Length - 4.8 (Reconstruction) SCOTT COUNTY SR-63 PIN: 118596.00 FROM WATER PLANT ROAD TO PARK ROAD IN HUNTSVILLE Length - 0.2 (Bicycles and Pedestrian Facility) The right-of-way and/or utility process is underway. SCOTT COUNTY PIN: 107719.00 LAYS ROAD, BRIDGE OVER STRAIGHT FORK CREEK LM 0.01 Length - 0.0 (Bridge Replacement) Page: 16

SCOTT COUNTY SR-63 No Projects Under Construction in Scott County FROM PERKINS STREET TO LINE (EPD/PHASE 1) (MISCELLANEOUS SAFETY IMPROVEMENTS) LENGTH - 10.540 CNP054 LET TO CONTRACT: 3/27/2015 SUPERIOR PAVEMENT MARKING, INC. BID PRICE : $72,363.45 EST. COMPLETION DATE: OCTOBER, 2015 SCOTT COUNTY SR-29 US-27 FROM SOUTH OF WOLF CREEK ROAD TO OLD HIGHWAY 27 (EPD/PHASE 1) (MISCELLANEOUS SAFETY IMPROVEMENTS) LENGTH - 3.880 CNP054 LET TO CONTRACT: 3/27/2015 SUPERIOR PAVEMENT MARKING, INC. BID PRICE : $146,957.85 EST. COMPLETION DATE: OCTOBER, 2015 SCOTT COUNTY SR-297 FROM ENTRANCE TO BIG SOUTH FORK RECREATIONAL AREA TO SR-29 (RESURFACE & SAFETY) LENGTH - 8.950 CNP031 LET TO CONTRACT: 2/13/2015 APAC-ATLANTIC, INC. BID PRICE : $887,520.40 SCOTT COUNTY VARIOUS LOCAL ROADS IN SCOTT COUNTY (LOCAL ROADS SAFETY INITIATIVE) (SAFETY) CNN369 LET TO CONTRACT: 12/5/2014 SUPERIOR TRAFFIC CONTROL - MEMPHIS, INC. BID PRICE : $308,099.35 EST. COMPLETION DATE: AUGUST, 2015 Page: 17

UNION COUNTY SR-33 No Projects Under Development in Union County PIN: 101416.00 KNOX COUNTY LINE TO SOUTH OF SR-144 LEFT Length - 5.2 (Reconstruction) The right-of-way and/or utility process is underway. UNION COUNTY SR-61 PIN: 119880.01 FROM SOUTH OF ARCHER ROAD TO NORTH OF BOWER HOLLOW ROAD (PHASE 2) Length - 1.8 (Miscellaneous Safety Improvements) This project is in the early stages of development. UNION COUNTY SR-144 PIN: 118829.00 FROM SR-131 TO SR-33 (RSAR) Length - 5.0 (Miscellaneous Safety Improvements) The environmental studies are complete. Page: 18

UNION COUNTY SR-61 No Projects Under Construction in Union County FROM NEAR ARCHER ROAD TO JIM TOWN ROAD IN LUTTRELL (RSAR) (MISCELLANEOUS SAFETY IMPROVEMENTS) LENGTH - 4.520 CNP091 LET TO CONTRACT: 3/27/2015 HIGHWAY MARKINGS, INC. BID PRICE : $114,845.85 EST. COMPLETION DATE: SEPTEMBER, 2015 UNION COUNTY SR-61 FROM SR-33 TO NORTH OF ARCHER ROAD (EPD/PHASE 1) (MISCELLANEOUS SAFETY IMPROVEMENTS) LENGTH - 3.300 CNP091 LET TO CONTRACT: 3/27/2015 HIGHWAY MARKINGS, INC. BID PRICE : $73,047.25 EST. COMPLETION DATE: SEPTEMBER, 2015 UNION COUNTY VARIOUS LOCAL ROADS IN UNION COUNTY (LOCAL ROADS SAFETY INITIATIVE) (SAFETY) CNN368 LET TO CONTRACT: 12/5/2014 VOLUNTEER HIGHWAY SUPPLY CO. INC. BID PRICE : $290,800.45 EST. COMPLETION DATE: AUGUST, 2015 UNION COUNTY SR-33 BRIDGE OVER CLINCH RIVER, LM 15.69 (BRIDGE REPLACEMENT) LENGTH - 0.895 CNM070 LET TO CONTRACT: 2/15/2013 KAY & KAY CONTRACTING, LLC BID PRICE : $18,309,878.15 Page: 19

UNION - CLAIBORNE COUNTIES SR-33 INTERSECTIONS AT KETTLE HOLLOW ROAD/LITTLE VALLEY ROAD, SR-170 & LONE MOUNTAIN ROAD (INTERSECTION IMPROVEMENTS) LENGTH - 0.012 CNM077 LET TO CONTRACT: 2/15/2013 TWIN K CONSTRUCTION, INC. BID PRICE : $1,995,408.90 Page: 20