An audit of the surface water outfalls in the River Ingrebourne - Outfall Safari

Similar documents
An audit of the surface water outfalls in the River Pinn - Outfall Safari

Report on the Hogsmill River Outfall Safari

An audit of the surface water outfalls in parts of the River Brent Catchment - Outfall Safari

Clearwater Photography UK

Outfall Safari. An audit of the surface water outfalls in the urban parts of the Alfreton Brook and Oakerthorpe Brook Catchments, Derbyshire

Tackling Pollution in Urban Rivers:

Polluted Surface Water Outfalls -what s the problem?

Why we need the Counters Creek storm relief sewer

Alma Road Rain Gardens, London

The Duke s River: Revitalising the link between the River Crane and the River Thames

WADDON PONDS MANAGEMENT AND MAINTENANCE PLAN 2017

Standard Operating Procedure: Outfall Inspections

Stormwater Program Coordinator: Title: Office Phone #: Emergency Phone #: Public Notice Coordinator: Title: Office Phone #: Emergency Phone #:

Landscape Partnership Scheme Summary

EDC 016/004 Annex A. Framework Masterplan Stakeholder and public engagement

Philadelphia Creek Trash Assessment (PCTA) Methodology Mill Run Creek Test Case

Technical note. Option 3a (cyan route) Project: To: A428 Bus Enhancement Scheme. Rid Hollands, Colin Young

Taking forward the All London Green Grid

THE CITY OF DELAWARE, OHIO ILLICIT DISCHARGE DETECTION AND ELIMINATION PLAN

Andrea Griffiths BSc HONS Partnership Officer Medway Valley Countryside Partnership. Medway Valley Countryside Partnership

Photo 1: Upper Rock Creek Trash, east of Ogontz Ave. Map 1: Map of Upper Rock Creek with photos of conduit openings

Preparing for MS4 in the Neponset Valley. December 4, 2015

How we chose our preferred sites

Waterways and wetlands investigations

Priors Farm Estate SuDS Retrofitting Project, Cheltenham

Letcombe Brook Project Officer

Arroyo Grande Creek Flood Control Channel Vegetation Management: A Photo Series

WILLIAM STREET STORM SEWER OUTFALL. PUBLIC INFORMATION CENTRE March 23, 2017

AT THE HEART OF LAND & WATER MANAGEMENT ON TWEED. tweedforum.org

Tookany Creek Watershed Trash Pollution Update Photographic Trash Surveys Jan- Mar, 2013

Just The Basics: Illicit Discharge. What does it mean to me?

Case studies. B1.1 Lloyds Crossing, Portland (USA)

MUNICIPAL SEPARATE STORM SEWER SYSTEM 2011 ANNUAL REPORT

Control of Floating Pennywort on the River Waveney Native Landscapes (Contractor) - Final Report. Paul Sims

URBAN FLOOD MANAGEMENT IN CYPRUS CASE STUDY IN NICOSIA URBAN AREA

Thank you for your letter of 26 June regarding the Committee s scrutiny of building regulations in Scotland.

Highlands Region Stormwater Management Program Guidance

Urban runoff in my neighborhood (Capitol Hill) is heavy with trash and other debris.

Renfrew Close, London

Welcome to our public exhibition

War Memorials A-Z AW.indd 1 12/04/ :06

The Fifth Continent Landscape Partnership Scheme

Greening streets, retrofit rain gardens, Nottingham

Christchurch City Council Civic Offices 53 Hereford Street Christchurch. Submission on: The Draft Annual Plan 2014/15

Garden Bridge Planning Application

INFORMATION PACK COULD YOU BE THE SCREWFIX #SFTA TRADE APPRENTICE OF 2017? IN ASSOCIATION WITH

Hartest river corridor survey

PDA SUBMISSION: Queen s Wharf, Brisbane (DEV2017/846)

Manor Ponds, Sheffield

SOUTHERN GRAMPIANS WETLANDS INFORMATION DAY Sunday 23 rd November 2014

Public Participation in Urban Planning Case of Lilongwe, Malawi

Yorkshire Sculpture Park Historic Landscape Management Plan. Volume I. July 2010

Severn River Sub-Watershed: BMP 09-Retrofit

Follow the Drop. Activity Overview Students observe and collect information about water runoff on their school property.

DC Clean Rivers Project - Green Infrastructure Program. ACEC What s New at DC Water?

Call for Artists for: Design and Construction of Environmental Art Activation Story Mill Community Park, Bozeman, MT

CTB3300WCx Introduction to Water and Climate

Introduction to the project Feedback from you to guide the plan Dig in to propel us forward quickly (survey) Clear understanding of roles moving

ANCHORAGE PARK REPORT CARD Assessing A Park s Appearance, Function, & Condition

FELTHAM MASTERPLAN CONSULTATION MARCH 2017 RESPONSE BY FRIENDS OF THE RIVER CRANE ENVIRONMENT (FORCE)

University of the District of Columbia Van Ness Campus Master Plan Community Open House 3. December 8, 2010

Friends of Troopers Hill - It's Your Neighbourhood 2018

PROJECT SCOPE OF WORK CITY OF TOWN AND COUNTRY STORMWATER PROGRAM

Start of works exhibition

Construction of upgraded stormwater outfall at the Ozone Road Jetty

Town of Vershire Road Erosion Inventory Report

APPLICATION BRIEFING Prepared For: Submitted by: Date: Subject:

Decent homes need decent spaces

FIRE SAFETY MANAGEMENT PLAN

ATU Annual Dissemination Event

The Chinese University of Hong Kong Campus Master Plan Stage 3 Stakeholders' Engagement Report

Highways England Environment Fund. Graeme Hull Tyne Tees Catchment Coordinator

Green Infrastructure: Implementation at the Community Level

With a World of Heritage So Rich

AR Wickes Elementary School (Cossatot River School District) 130 School Drive Wickes AR School Parent and Family Engagement Plan

South Carolina NPDES Permit # SCR Small Municipal Separate Storm Sewer System (SMS4) Annual Report Template

Valuing the social benefits of local infrastructure in Workington, ibuild briefing paper 9

WA PARKS FOUNDATION SWAN CANNING RIVERPARK

West London Dyke, April 1947 Flood. Forks of the Thames, July 2000 Flood. Source: UTRCA

The Nature Conservancy relies on volunteers to manage invasive shrubs at the Snake Mountain South Natural Area in Bridport.

Evaluation Criteria. Detailed Evaluation Criteria

Camden SMART Initiative Stormwater Management and Resource Training

Welcome to this public consultation event for the proposed South Western Relief Road. Thank you for taking the time to come along.

Initial OPW Designation APSR AFRR IRR Co-ordinates Easting: Northing: Fluvial non-tidal Fluvial tidal Coastal

Control and eradication of Invasive Non Native Plant Species in the UK

Saltmarsh Conference. 8 October in the Suffolk Coast & Heaths Area of Outstanding Natural Beauty

Ekin PATROL The First and Only Smart Patrol of the World

Encouraging collaboration:

Bourn Brook Water Vole and Invasive Plants Survey

Western Pennsylvania Conservancy Clairton & Harrison Community Greening Assessment Projects Request for Proposals July 2018

Environmental Statement Review for Infrastructure

SCHOOLYARD HABITATS BASELINE AUDIT, GRADES K-2

NERVIÓN LINEAR PARK GREEN WAY, SALBIO STATION-OLAKO SECTION PROVINCIAL COUNCIL OF ALAVA.

Morpeth Flood Alleviation Scheme. An Example of Partnership Funding & Community Engagement

The Moors at Arne Project, Managing Coastal Change

ENGINEERING CONSULTANT OFFICE FOR UTILITIES

Sewer Flooding Alleviation in the Counters Creek Catchment

Municipal Action Teams

INTERNATIONAL GUIDELINES

Building Great Neighbourhoods. Strathcona

Transcription:

An audit of the surface water outfalls in the River Ingrebourne - Outfall Safari December 2017 UK & Europe Conservation Programme Zoological Society of London Regent's Park London, NW1 4RY marineandfreshwater@zsl.org www.zsl.org/conservation/regions/uk-europe/london s-rivers

Acknowledgements This project, funded by The Postcode Local Trust and City Bridge Trust, has been delivered in partnership with Thames21 with the support of the Environment Agency and Thames Water. It would not have been possible without the help of all the dedicated volunteers who collected the data. Introduction Misconnected wastewater pipework, cross-connected sewers and combined sewer overflows are a chronic source of pollution in urban rivers. An estimated 3% of properties in Greater London are misconnected (Dunk et al., 2008) sending pollution, via outfalls, into the nearest watercourse. There is currently no systematic surveying of outfalls in rivers to identify sources of pollution and to notify the relevant authorities. The Outfall Safari is a survey method devised to address this evidence gathering and reporting gap. It was created by the Citizen Crane project steering group which consists of staff of Thames Water, Environment Agency (EA), Crane Valley Partnership, Friends of River Crane Environment, Frog Environmental and the Zoological Society of London (ZSL). It was first used on the River Crane in May 2016. Aims The aims of the River Ingrebourne Outfall Safari were to: Record and map the dry weather condition behaviour of surface water outfalls in the River Ingrebourne; Assess and rank the impact of the outfalls and report those that are polluting to the Environment Agency and Thames Water; Build evidence on the scale of the problem of polluted surface water outfalls in Greater London; and Recruit more volunteers and further engage existing volunteers in the work of the Ingrebourne and wider Roding, Beam and Ingrebourne Catchment Partnership. Method The survey of outfalls was conducted between 2 th October and 16 th October 2017. Six trained volunteers took part in the Outfall Safari. Volunteers were trained at the Ingrebourne Valley 12

Visitor Centre in Hornchurch. Training, delivered by ZSL, Thames21 and Thames Water included: An overview of water quality issues in the River Ingrebourne; Information on outfalls and how they become polluted; Information on Thames Water s surface water outfall team; Instruction on how to assess each outfall using the project App and how to upload information to the database; and A health and safety briefing and signing of the risk assessment. During the training, volunteers were assigned lengths of the River Ingrebourne to survey. Further coordination of survey dates and reaches was conducted by the volunteers on a closed Facebook group set up specifically for the Outfall Safari. Groups of volunteers were free to conduct the survey of their reach when convenient to them, within the survey period, provided there had been no rain for 48 hours prior to survey. A period of 48 hours of no rain is required before any survey work as rainfall and high surface water flows can obscure the negative impacts of outfalls by washing away sewage fungus, discoloured sediments and rag. Approximately 8.4 km of the River Ingrebourne was surveyed by the Outfall Safari in total. Of this, 6 km was surveyed by volunteers walking along the river banks and 2.4 km was surveyed in-channel by staff of ZSL, the Environment Agency and Thames21. The sections of river surveyed are shown in Figure 1. 13

Figure 1: Overview of River Surveyed on Ingrebourne Outfall Safari, October 2017

The majority of the survey work was conducted from the riverside path, with the occasional need to enter the river to properly assess and photograph outfalls. The risk assessment for riverside outfall surveying highlighted the need to assess conditions in the river before entering it and stressed that volunteers should only enter the river channel if the level was lower than Wellington boot depth (c.35cm). During the training volunteers were also shown images of Giant Hogweed (Heracleum mantegazzianum). It was essential that volunteers could identify Hogweed before undertaking any survey work as it is a relatively common plant along the banks of rivers in Greater London and can burn and blister skin if touched. In some reaches of the river, where it flows through private land or are inaccessible from the banks, the survey had to be conducted in-channel. More stringent health and safety rules applied to in-channel surveys all of which were led by ZSL and Thames21 staff. stabilising poles and life jackets were used by in-channel survey teams (see Figure 2). Waders, In addition to personal protective equipment (PPE) volunteers took a printed handout, designed to help with ranking the impacts of each outfall, and a smart phone or tablet loaded with a specially created data entry app. Figure 2: Photo of an In-Channel Survey Conducted by Staff of the Environment Agency, Thames21 and ZSL ZSL

The App For ease of data collection from the river, the volunteers used an app created in Epicollect 5 (five.epicollect.net). Created by researchers at Imperial College, Epicollect is free and openly available. Once a project is set up in Epicollect it provides an app for remote data collection and upload, usable on GPS enabled smart phones and a web portal to access and download the data. The outfall assessment form created in the app consisted of ten questions for volunteers to fill in at each outfall. The questions are taken directly from the form that Thames Water use for assessing the impact of outfalls and are shown in Table 1. Table 1: Questions used in the Epicollect App to assess each Outfall and their Corresponding Impact Score Question Options EA score 1. Volunteer name 2. Date of survey 3. GPS location 4. Photo of the outfall 5. Description of the nearest landmark 6. Which bank is the outfall on (when looking downstream) 7. Ranking of the flow coming out of the outfall a. No Flow b. Trickle c. Low Flow d. Moderate Flow e. High Flow 8. Ranking of the visual impact of the outfall 9. Ranking of the aesthetics of the outfall a. No visible effect 0 b. Within 2m of outfall 2 c. Impact 2 to 10m 4 d. Impact 10 to 30m 6 e. Impact greater than 30m 10 a. No odour or visible aesthetics 0 b. Faint smell, slight discolouration 2 12

10. Other signs of pollution c. Mild smell, mild discolouration, small coverage of sewage fungus d. Strong smell, strong discolouration, large coverage of sewage fungus and/ or litter e. Gross smell, gross sewage 10 4 6 Conversion of Outfall Assessment to Impact Scores To assist with prioritisation of the outfalls, the Environment Agency provided a method of converting the assessment data to a numeric impact score for each outfall. These scores are shown in the right hand column in Table 1. Reporting Any outfall with an impact score 10, from the options in questions 8 and 9, were reported directly from the river to the Environment Agency s Incident Hotline and Thames Water. Both Thames Water, Environment Agency and the Catchment Partnership hosts also received a copy of this report. Data Processing Outfall data were checked to remove double entries and longitude and latitude coordinates were converted to National Grid References using www.gridreferencefinder.com. Results The volunteers photographed, located and assessed a total of 94 outfalls. Of this total 15 showed some signs of pollution and scored 0 and of these 14 had a score 4. The details of the outfalls with an impact score of 4 are given in Table 2. Two assessments are not included in Table 2 as either no outfall pipe was visible or because the pollution was not sewage-related: a) Sewage-polluted ditch entering the river from the left bank behind the industrial units on Bates Road Romford, RM3 0JS at 55564 91164. This was reported to Thames 13

Water (directly to Richard Pumfrett) by ZSL staff on 10/10/2017. An outfall was not visible but the impact of the pollution extended more than 30 metres downstream of the ditch (impact score of 16). Figure 3: Photo of Sewage-Polluted Ditch b) A pollution incident, also to the rear of Bates Road Romford RM3 0JH, was reported to the Environment Agency by a member of Environment Agency staff on 12/10/2017. Illegally plumbed pipes were seen discharging white oil or thinners into the river around the headwall of an outfall. The oily sheen could be seen on the surface of the river up to approximately 100m downstream of the point of discharge. c) Figure 4: Photo of Pollution near Bates Road The full 2017 River Ingrebourne Outfall Safari dataset is available from ZSL. 14

Table 2: Details and Photos of River Ingrebourne Outfalls with an Impact Score 4 Photo ID Numb er Location Details NGR Bank Side Outfall Score Photo 18 Paines Brook, under Dagnam Park Drive 50 metres into Central Park, near to RM3 9DD 54246 92386 Left 4 23 End of school playground, near field, Chudleigh Road, Romford, near RM3 9BX 54185 92489 Left 4 25 End of school playing fields, Chudleigh Road, Romford, near RM3 9BU 54155 92551 Right 4 15

28 By tunnel at Whitchurch Road, south side; where Carter s Brook joins Paine s Brook, near RM3 9EG 54097 92762 Right 6 29 Junction between Tees Drive and Priory Road, Romford, RM3 9AL 53991 93105 Right 6 38 South of footbridge 100 metres north of St. Neot s Road bridge, Romford, RM3 9JP 54837 91642 Left 6 39 50 metres north of St. Neot s Road bridge, Romford, RM3 9JP 54844 91560 Right 4 16

52 Behind 30 Ingreway, Romford, RM3 0BW 56019 91480 Right 8 73 Downstream of Hornchurch FC Stadium (outfall setback in a 5 metre-long ditch), Upminster, RM14 2LL 55244 86405 Left 8 86 Children s playground, Suttons Lane, Hornchurch, RM12 6RU 53746 84887 Right 8 17

88 Hurst Park Ave, Hornchurch RM12 6DJ 54339 85540 Right 6 89 Bevan Way, Hornchurch, RM12 6DT - 15 metres upstream from picnic bench 54709 85778 Right 6 18

90 Under Hacton Lane bridge, Upminster, RM14 2NL 54896 85916 Right 8 91 Downstream of raised sewer pipe, near Hacton Lane, Upminster, RM14 2NL 54917 85929 Left 4 Discussion This Outfall Safari surveyed approximately 8.4 km of the River Ingrebourne and 14 polluting outfalls (score of 4). This is approximately 15% of all outfalls assessed, which is comparable to the proportion of polluting outfalls on other London catchments including the River Pinn. The consistently high number of polluting surface water outfalls that have been reported through the Outfall Safaris to date demonstrates the likely scale of the problem across Greater London. 19

The findings of this report further support the need to increase efforts to properly address this pollution source which compromises the ecological value of rivers in London. Some outfalls pollute intermittently and may not have been detected as a problem during the survey but this report represents an audit of how outfalls, within the surveyed area, were behaving during the survey. Outfalls could intermittently cause more serious problems than impact scores may suggest depending on what was observed at the time of the Outfall Safari survey. Similarly, volunteers noted that an outfall downstream of Hornchurch FC stadium (photo ID number 73) had been reported as polluting prior to the Outfall Safari but on the occasion(s) it had been visited by Thames Water was not seen to be polluting. This suggests this outfall is an example of one that intermittently pollutes. Areas of very overgrown vegetation obscured views of outfalls or prevented access to parts of the River Ingrebourne more often than had been observed for Outfall Safaris on other catchments in Greater London. It is therefore possible that outfalls were missed and that the data presented in this report is an underestimation of the scale of the problem on the River Ingrebourne. It is suggested that if this catchment was to be revisited for future outfall survey work that it should be conducted at a time of year when riparian plant growth has died back or in the initial stages of spring regrowth (December April). Sections of the river were also missed during this survey due to staff time constraints and the dense riparian plant growth. We recommend any future surveys also include the sections missed by this one. An Outfall Safari is also being carried out on the River Ravensbourne in October and November 2017 in partnership with Thames21. The results of this Outfall Safari and the preceding five Outfall Safaris will be presented collectively in one London-wide report which will include recommendations to reduce existing and prevent future misconnections. References Dunk, M.J., McMath, S.M., Arikans, J., 2008. A new management approach for the remediation of polluted surface water outfalls to improve river water quality. Water Environ. J. 22, 32 41. Contact details Joe Pecorelli: Project Manager Conservation Programmes, joe.pecorelli@zsl.org 20