Campus Program Report WLAC Facilities Committee Meeting May 15, 2017 Page 1
DSA completed the initial review June 24, 2016 and the Design Builder is proceeding through the back check process. DSA reports the Access Compliance and Fire/Life Safety reviews were completed April 24, 2017 leaving only the Structural review to be completed. Once the Notice to Proceed is issued there will be approximately 1 month before the contractor mobilizes due to lead time on the building components. Plant Facilities Center (FMO) 1-Jun-11 22-May-17 30-Jan-18 A B B B B B B B B 40J - Storm Water Project Phase 2 - Pave Lot 7 3-Dec-15 5-Jul-17 14-Sep-17 A A B B Page 2
The Fire Alarm phase 2 package was approved by DSA on 5/10/2017. Guaranteed Maximum Price to be submitted and reviewed. To meet budget the scope has been reduced to Fire Alarm monitoring upgrade Phases 1 & 2, and the Fiber Optic upgrade. Because the fire alarm upgrade touches the Fine Arts and PE buildings, certification of the original DSA numbers is being undertaken. The task order for TDM Architects is in process. 40J-Physical Security and Hardware West 3-Mar-15 7-Jun-17 18-Oct-17 A B B B B B Page 3
The Collaboration phase is nearly complete. Notice to Proceed with the Design Phase will be issued after review of the pricing for the items requested by the BUG. Harper is expected to provide a recovery schedule. Since the date the Harper contract was signed, adverse weather has damaged the sound walls to a point that immediate repairs are needed but due to excessive costs for early mobilization and general conditions the Harper proposal greatly exceeded the $200,000 allowance. Therefore a change order has been drafted to remove this scope from the Harper contract and take it out for a competitive bid. Please note, in the total expended amount over $2.39M is the Master Planning project of which the sound walls are the last portion to be done and very small part of the budget, the next report will show this project separately. Technology Learning Center 2 28-Jul-16 7-Aug-18 29-Dec-19 A A A A A A A A A A A A A A A B B B B B B B B B B B B B B B B B Master Planning - Environmental Impact Report (Dismantle Sound Walls) 28-Jul-16 29-Jul-19 17-Oct-19 C C C C C C C C C C C C C C C C A A A A A A A A A A A B B B 40J-Trans/Access Imprv Lot 5 Tower & A-V Ramp 28-Jul-16 7-Aug-18 29-Dec-19 A A A A A A A A A A A A A A A B B B B B B B B B B B B B B B B B Page 4
The Building user group value engineering comments have been incorporated by the Architect and the plans are receiving one final check before TSK proceeds with the backcheck process.. The PMO Contracts department has verified the need for pre-qualification of bidders, this process will proceed after DSA Approval. Watson Center 2 16-Aug-17 27-Nov-17 20-Sep-18 A A A A A A A B B B B B B B B B B 40J-Trans/Access Imprv-ATA-Lot 2 Bridge 16-Aug-17 27-Nov-17 20-Sep-18 A A A A A A A B B B B B B B B B B Page 5
Re-programming for the existing chilled water piping extension has begun with Onyx Architects, Inc. Program documents are expected to be complete in mid May. Review of the programming document and a decision on the stand alone central plant verses connecting to the existing central plant is expected in June. 40J - Energy Efficiency Project 11-Aug-16 21-Nov-18 6-Dec-19 A A A A A A A A A A A A A A A A A A A B B B B B B B B B B B B Page 6
The CPT and Campus Facilities have just submitted more comments to be resolved by TSK, once completed the plans will be submitted for DSA back check. This package will be procured through the pre-qualified service provider method. 40J-Trans/Access Imprv - Remaining Priority 1 & 2 15-May-17 27-Jun-17 10-Mar-18 A A B B B B B B B B Page 7
Testing and commissioning of the new equipment has begun. is expected in May 2017. Central Plant Phase 2 13-Apr-16 21-Jul-16 30-May-17 Page 8