Rt. 29 Solutions Project Delivery Advisory Panel. January 7, 2016

Similar documents
Rt. 29 Solutions Project Delivery Advisory Panel. December 3, 2015

Route 29 Project Delivery Advisory Panel September 11, 2014 Meeting Minutes

Moving The Metro. A special construction update for the metro Omaha area.

Places29: List of Implementation Projects

Appendix 2. Implementation Project Descriptions Page A2-1

I-66 EASTBOUND WIDENING INSIDE THE BELTWAY PARDON OUR DUST MEETING

Rt 29 Solutions Hydraulic Planning Advisory Panel. September 28, 2017

4/8/2015 Item #10D Page 1

Citizen Information Meeting

PROJECT SHOWING MINUTES

Appendix 2. Implementation Project Descriptions

Chain Bridge Road Sidewalk Improvements Citizen Council Work Session

FANSHAWE PARK ROAD/RICHMOND STREET INTERSECTION IMPROVEMENTS. PUBLIC INFORMATION CENTRE 2 June 16, 2016

Rt 29 Solutions Hydraulic Planning Advisory Panel. September 14, 2017

I-25 / Rio Bravo Interchange. I-25 / Rio Bravo Interchange. Presenters 11/30/2016 THIRD PUBLIC MEETING DECEMBER 1, 2016 NMDOT CN A300280

I.T.S. PLAN ALONG I-95 INSTALL FIBER OPTIC LINE PROJECT SHOWING Tuesday, June 18, 2013, 1:30pm Ashland Residency Conference Room

Please see attached for more detailed project information. Project Schedule Designer Award by SBC Executive Sub-Committee December 21, 2015

Chesterfield County Project Update

ARGENTA TRAIL (CSAH 28/63) REALIGNMENT SOUTH PROJECT (CP 63-25)

TRANSPORTATION COMMITTEE

BOISE, IDAHO COUNCIL WORK SESSION AGENDA September 19, :00 PM City Hall - Council Chambers

Capital Projects in and near Odenton Town Center

Project Overview. Fairfax County Parkway Widening Fairfax County. Get Involved. Public Information Meeting. Contact Information

Downtown Redevelopment Project Update

WELCOME! 8 8:30 6: TH STREET IMPROVEMENTS. Open House. Presentation & Q&A

Hunt Highway CELESTE PEMBERTON, CFM, CPM PINAL COUNTY CARLOS SANCHEZ SORIA, PE T.Y. LIN INTERNATIONAL

Welcome to the. Open House

ARLINGTON COUNTY, VIRGINIA. County Board Agenda Item Meeting of January 28, 2017 SUPPLEMENTAL REPORT

Project Status. Construction is underway for Phase 3. Overall Project Area and Schedule. Schedule of Current Construction Phases.

PROPOSED IMPROVEMENTS

Middlebury RS 0174(8)

Meeting Purpose: Date and Time: Location: Attendance: Handouts:

Open House RIVER DES PERES GREENWAY: LANSDOWNE SHREWSBURY METROLINK TO FRANCIS R. SLAY PARK

The Ambassador Bridge/ Gateway Project

The Illinois Department of Transportation and Lake County Division of Transportation. Route 173, including the Millburn Bypass

WELCOME NEIGHBORS! April 11, 2019

I-485/ I-85 Interchange Charlotte, NC December 6, LANE The Lane Construction Corporation, 90 Fieldstone Court Cheshire, CT 06410

ALTERNATIVES. NCDOT made an early decision to first determine how to build the project (construction method) followed by what to build (alternatives).

Fairfax County Parkway (Route 286) Widening Project

We d like to thank you for attending this Wekiva Parkway Section 8 Preliminary Design Update hosted by the Florida Department of Transportation.

A/E REVIEW CHECKLIST SITE & LANDSCAPE

ROANOKE STREET IMPROVEMENTS CHRISTIANSBURG, VIRGINIA VDOT PROJECT # U R24 UPC #:

City of Richmond. Engineering Design Specifications

Project Overview. Get Involved. Public Information Meeting. Contact Information

ARLINGTON COUNTY, VIRGINIA. County Board Agenda Item Meeting of January 28, 2017 SUPPLEMENTAL REPORT-2

Public Hearing. Charlotte County-Punta Gorda MPO - Meeting Rooms A and B March 14, open house at 4 p.m., formal presentation at 5 p.m.

Fall 2017 Construction Update

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Projects

Capital Projects impacting Odenton Town Center

Cottage Grove Road Reconstruction. City of Madison Engineering

Construction Engineering & Inspection

Expo Line Transit Project. Project Status Update Meeting West End Corridor Segment C

STANDARD SPECIFICATIONS Book 2 ENGINEERING DRAWINGS INCLUDES ADDENDUMS

Tampa Palms CDD. Board Of Directors September, 2017

SITE PLAN REVIEW APPLICATION AND CHECKLIST

Rezoning Transportation Analysis Petition Number: General Location Identifier: , ,

Creative Engineering Group Inc, (Creative) Construction Engineering and Inspection (CEI) Professionals

I-95 Girard Avenue Interchange Near Neighbors Meeting. Project Status

INDEX EXECUTIVE SUMMARY...1 BASIC INFORMATION AND PROCEDURES...3 EXISTING CONDITIONS EXISTING UTILITIES

INFRASTRUCTURE EXISTING INFRASTRUCTURE A. Circulation B. Signals C. Drainage D. Utilities

Memorandum CITY OF DALLAS. Riverfront Boulevard Design From Continental Avenue to Cadiz Street

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Projects

Route 7 Reconstruction and Widening, Wilton. State Project Nos & 124. Wolf Pit Road to just north of Olmstead Hill Road

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Project Descriptions ($ millions)

ARCHITECTURAL REVIEW BOARD STAFF REPORT

CITY OF TUMWATER 555 ISRAEL RD. SW, TUMWATER, WA (360) (360) (FAX)

Project Goal. RRRC Living Towns Planning Workshp. Town of Halifax Revitalization Project. Dynamic Planning & Management Duo: July 12, 2006

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Projects

Prince William Street Project (Grant Avenue to Wellington Road)

SR 15 SECTION 088 CSVT SOUTHERN SECTION PUBLIC MEETING JUNE 16, 2015

(blank page) WestConnex New M Roads and Maritime Services Environmental impact statement

NEWSLETTER #03 BEAUDESERT ROAD LOGAN MOTORWAY

IOWA HIGHWAY 57 / WEST 1 ST STREET STUDY PUBLIC INFORMATIONAL MEETING APRIL 22, 2014

ARB ACTION MEMO. Mr. Wardell called the meeting to order at 1:03 p.m. and established a quorum.

SH 199 Corridor Master Plan. Community Meeting No. 2 May 31, 2017

Grand River Ravines Georgetown Township

Welcome to the Sellwood Bridge Project Pre-Construction Open House

SOUTH UNIVERSITY Street Design Alternatives in Progress

GYPSUM PARKWAY CORRIDOR ENHANCEMENT Gypsum, Colorado. Schematic Design January 2015

SR 483 Clyde Morris Boulevard FDOT District 5

The Capital Design Advisory Committee St. Mary s College of Maryland & Historic St. Mary s City

AGENDA ITEM: IOWA. west] that were not FISCAL IMPACT. the City of Clive. STAFF REVIEW. Resolution II. Amendment PREPARED BY: REVIEWED BY:

SECTION 4(f) DE MINIMIS DOCUMENTATION

TOWN OF PALM BEACH FOR IMMEDIATE RELEASE. Patricia Strayer, P.E., Town Engineer Phone: ,

February 17, Sara Ullman Planner I. Sincerley,

CRESCENT RESOURCES INC.

St. Laurent Transit Improvements Innes / Industrial to Smyth. Public Information Session December 2, 2015

Public Information Centre. Welcome

PLANNING COORDINATING COMMITTEE

CONFORMED AGREEMENT INCORPORATED REVISIONS PER AMENDMENT DATED: APRIL 2, 2013 FOR REFERENCE

Constructing PCCP Under High Traffic Volume

TOWN OF PALM BEACH FOR IMMEDIATE RELEASE. Patricia Strayer, P.E., Town Engineer Phone: ,

Tysons-Old Meadow Road Bike/Ped Improvements

Southern Gateway Project and Public Green

PROJECT UPDATE BON AIR ROAD BRIDGE REPLACEMENT AND MAGNOLIA AVENUE WATER QUALITY FACILITIES

NEWPORT NEWS/WILLIAMSBURG INTERNATIONAL AIRPORT DESIGN AND SUSTAINABILTY GUIDELINES

BOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM. Endorsement of Design for Route 7/George Washington Boulevard Overpass. Algonkian and Broad Run

Asbury Chapel Subdivision Sketch Plan

WELCOME TO OPEN HOUSE TWO November 28, 2018

TABLE OF CONTENTS. Building Great Neighbourhoods. Working together to make the most out of your neighbourhood.

Transcription:

Rt. 29 Solutions Project Delivery Advisory Panel January 7, 2016

Agenda item 1: Introductions Project Delivery Advisory Panel Technical Team 2

Agenda item 2: Interaction and Feedback Live Streaming Dec 3, 2015 Nov 12, 2015 Unique Viewers: 23 11 Streams: 42 31 Average Minutes per stream: 21 35 3

Agenda item 2: Interaction and Feedback (continued) For the period Dec 1, 2015 - Jan 4, 2016 Inbox comments: 7 emailed to project inbox 1 regarding pavement on Rt 29 north of Albemarle Sq 1 regarding employment opportunities 1 regarding damage claim 1 looking for Rio rendering 1 thank you for addressing parking issue in Best Buy parking lot 2 regarding pavement on Rt 29 south between Hollymead and Polo Grounds Web Provide Input: 1 new comment and response Regarding yield on Rt 250 WB at Rt. 29 ramp Project Hotline 844-220-5540: 6 calls 3 requesting information about Ashwood Blvd signal work 1 regarding the sign at the entrance to Forest Lakes 2 no-message calls 4

Agenda item 3: Report on PDAP Feedback Rio - Pedestrian lighting, landscaping, hardscaping Rt 29 Widening - Pedestrian refuge area; buffer for Shared Use Path Rt 29 / Rt 250 - Guardrail and landscaping The above will be covered under agenda items 7, 8 and 9. 5

Agenda item 4: Panel Feedback and Suggestions for Future Agenda Items Open Discussion 6

Agenda item 5: Construction Milestones as of Jan 1, 2016 Rio Road GSI 2015 2016 December January February March April May June July August September October November December Utility Relocation Drive Abutment Piles Set retaining wall piles and widen roadway Through lane excavation, bridge construction Temp. Signals Utilities relocation 29 Widening ROW Acquisition Phase 1 Grading and Drainage Phase 1 Paving Berkmar Hillsdale ROW Acquisition South Abutment Excavation Rough Grading South of River Utility Relocation ROW Acquisition 90% Plan Preparation Final Design Adv for Bids MSE Wall South Abutment Pile Driving Utility Relocation 29/250 Pavement Widening Final Paving Sound Barrier Construction Complete Under way Complete Late 7

Agenda item 6: Rt. 29 Solutions Project Updates Rt. 250 / 29 Interchange Work this week Continue installation of storm drainage structures in the median of Route 250 Continue installation of storm drainage structures along the Barracks Road on ramp Complete sidewalk/ramp installation along Route 29 Complete installation of median strip along Route 29 8

Rt. 250 / 29 Interchange (continued) Significant lane closures this week Daytime - outside lanes of Route 250 EB and WB from Hydraulic to Barracks (1/5) Daytime - inside lanes of Route 250 EB and WB from Hydraulic to Barracks (1/6 1/7) Nighttime Alternating short-duration closures on Route 29 NB and SB at Route 250 bridge Ramp shoulder closures for storm drain installations 9

Rt. 250 / 29 Interchange (continued) Work next two weeks Continue installation of storm drainage structures in the median of Route 250 Continue installation of storm drainage structures along the Barracks Road on ramp Complete installation of MSE wall panels Continue construction of Route 250 turn lane extension 10

Rt. 250 / 29 Interchange (continued) Anticipated significant upcoming lane closures Inside lanes of Route 250 EB and WB from Hydraulic to Barracks Ramp shoulder closures for storm drain installations 11

Rio Grade-Separated Intersection Work this week Grading for under drain, curb & gutter, and sidewalk in widening areas Storm drain construction Complete SunTrust retaining wall Continue Fashion Square retaining wall Continue gas main relocation Complete CenturyLink splicing Complete driving abutment B piles Install tie-back piles 12

Rio Grade-Separated Intersection (continued) Significant lane closures this week (nighttime) Rio crossover closed at nighttime restricting thru movements and left turn movements. Right turns will be open. Rte. 29 triple lane closures northbound and southbound 13

Rio Grade-Separated Intersection (continued) Work next two weeks Grading for under drain, curb & gutter, and sidewalk in widening areas Storm drain construction Continue Fashion Square retaining wall Continue gas main relocation Complete CenturyLink splicing Splice/drive/restrike abutment piles Install tie-back piles Install 4 Fire Department Connection pipe 14

Rio Grade-Separated Intersection (continued) Anticipated significant upcoming lane closures (nighttime) Rio crossover closed at nighttime restricting thru movements and left turn movements. Right turns will be open. Rt 29 triple lane closures northbound and southbound 15

Rt. 29 Widening Work this week Place fill in median Temporary drainage structure installations Qwest Business (CL) directional bore for fiber relocation Dominion VA Power setting poles Fiberlight directional bores Pavement repair 16

Rt. 29 Widening Significant lane closures this week (nighttime) Route 29 left lane closure NB and SB 17

Rt. 29 Widening (continued) Work next two weeks Place fill in median Temporary drainage structure installations Qwest Business (CenturyLink) directional bore for fiber relocation Dominion VA Power setting poles Fiberlight directional bores Temporary signal construction at Ashwood and Hollymead 18

Rt. 29 Widening (continued) Anticipated significant upcoming lane closures (nighttime) Route 29 left lane closure NB and SB Periodic short-term total closure for temporary signal construction 19

Berkmar Extended Work this week Erosion control repairs Grading for abutment A Continue excavation and hauling to 29 Widening Continue phase III archaeological recovery Significant lane closures this week Shoulder closure at Berkmar and Hilton Heights 20

Berkmar Extended (continued) Work next two weeks Grading for abutment A Continue excavation and hauling to 29 Widening Continue phase III archaeological recovery Significant upcoming lane closures Shoulder closure at Berkmar and Hilton Heights 21

Signal Updates Work this week Project list submission for evaluation Meeting to review project list Significant lane closures this week None Work next two weeks Begin design on signal improvements Significant upcoming lane closures None 22

Hillsdale Extended City followed up with Albemarle County on MOU for the storm water management basin VDOT & City working to resolve temporary construction easement request for Parcel 025 (Whole Foods) Plan revisions were submitted for ROW offer packages to be completed and presented to owners this week Demolition plan to be developed for Seminole Sq commercial building by week of Jan 11 City provided comments and VDOT will check with USPS on approval for easement documents this week City is obtaining approvals for sole source / proprietary items (i.e. retaining walls) 23

Agenda item 7: Rio GSI - Pedestrian lighting, landscaping, hardscaping At Dec 3 PDAP, we indicated that pedestrian lighting alignment was being investigated further. Result: Pedestrian lighting will be aligned on local lanes Jan 4 meeting with Kennon Williams and Lane-Corman to review certain details resulted in one item for review: plantings on bridge deck There will not be an irrigation system on bridge deck Plant watering would be covered under County s entrance corridor agreement Options are: proceed with plantings as planned designate an available space for public art 24

Agenda item 8: Rt 29 Widening - Pedestrian refuge area, landscaped buffer Asked VDOT Research Council to review current state-of-the-practice Received report from VTRC Dec 29, 2015 VDOT project team review results are: Rt 29 pedestrian refuge design meets current state-of-the-practice Landscaping would enhance buffer between roadway and shared use path Appropriate landscaping of the buffer will be added to project plans 25

Agenda item 9: Rt 250 / 29 Interchange - Guardrail, landscaping Reviewed three options for guardrail and landscaping plans with the city 1. Retain galvanized guardrail and add enhanced landscaping plan (approximately $50,000) 2. Replace galvanized guardrail and posts with powder coated guardrail without adding enhanced landscaping (approximately $170,000) 3. Replace galvanized guardrail and add enhanced landscaping (approximately $220,000) City requests Option 1. VDOT can contract for enhanced landscaping plan in the Q4 2016 or Q1 2017. 26

Agenda item 10: New Business 27

Agenda item 11: Adjourn 28

Rt. 29 Solutions Project Delivery Advisory Panel January 7, 2016