startup. Construction of contractor entrance off University City Blvd connecting to Lot 8 has started.

Similar documents
Fall 2017 Construction Update

PennDOT Public Meeting. S.R. 3044, Section A01 Castle Shannon Boulevard Roadway Improvement Project

MARINA BAY NEIGHBORHOOD PRESENTATION. City of Richmond Officer Bradley A. Moody Memorial Underpass. April 11, 2012

Downtown Redevelopment Project Update

Please see attached for more detailed project information. Project Schedule Designer Award by SBC Executive Sub-Committee December 21, 2015

OPEN HOUSE. Sunnyside Avenue Traffic Calming & Green Street Treatments. February 19, 2014

Capital Projects impacting Odenton Town Center

BOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM

CAMPUS PLANNING COMMITTEE STAFF REPORT SAMARITAN SPORTS MEDICINE INSTITUTE AT OSU 10/21/2013

TIRZ 17/Redevelopment Authority Capital Improvements Plan Projects

Burton Station Village Community Meeting February 26, 2014

OHIO DEPARTMENT OF NATURAL RESOURCES (ODNR S) STATEWIDE DAM CONSTRUCTION MONITORING PLAN. Presented by: Chad R. Davis, PE

At Your Disposal CUP Amendment, Lot 20, Village Service Commercial, at 128 Bastille Dr. (PLN17-208)

Speedway Mall Project Frequently Asked Questions

City of La Palma Agenda Item No. 5

COLLIER BOULEVARD (CR 951) CORRIDOR

Hunt Highway CELESTE PEMBERTON, CFM, CPM PINAL COUNTY CARLOS SANCHEZ SORIA, PE T.Y. LIN INTERNATIONAL

UNIVERSITY OF NORTHERN IOWA

SR 15 SECTION 088 CSVT SOUTHERN SECTION PUBLIC MEETING JUNE 16, 2015

Proposed Staging Plan For:

Cottage Grove Road Reconstruction. City of Madison Engineering

Expo Line Transit Project. Project Status Update Meeting West End Corridor Segment C

Rt. 29 Solutions Project Delivery Advisory Panel. January 7, 2016

Grand River Ravines Georgetown Township

Expo Light Rail Line. Expo Line Community Meeting Phase 2 Design Update November 2011

UNIVERSITY OF NORTHERN IOWA

ROANOKE STREET IMPROVEMENTS CHRISTIANSBURG, VIRGINIA VDOT PROJECT # U R24 UPC #:

Capital Projects in and near Odenton Town Center

WELCOME! 8 8:30 6: TH STREET IMPROVEMENTS. Open House. Presentation & Q&A

MAIN STREET RECONSTRUCTION PROJECT PRE-CONSTRUCTION PUBLIC INFORMATION SESSION AGENDA

ARTICLE IX SPECIAL PERMIT USES

SOUTH UNIVERSITY Street Design Alternatives in Progress

TOWN OF PALM BEACH FOR IMMEDIATE RELEASE. Patricia Strayer, P.E., Town Engineer Phone: ,

Ohlone College Measure G Project Scope Revisions

APPENDIX F: DETAIL DRAWINGS

Oconomowoc Area School District Facility Construction Update August 25, 2017

Shell Beach Road Streetscape Frequently asked Questions

WHEREAS, the CCSD has agreed to reimburse the City for the cost of the sidewalk, trail, and the bioretention area

Public Information Centre. Welcome

Campus Sign Plan. Adopted by the Campus Planning Committee Adopted: June 26, 2006 Revised: April 14, 2016

Construction and Landscaping on Public Property

UNIVERSITY OF NORTHERN IOWA

Kittson Parkway / Watershed Park Parking Lot

SUPPORTING DOCUMENT STORMWATER POLLUTION PREVENTION PLAN (SWPPP) NARRATIVE

TOWN OF PALM BEACH FOR IMMEDIATE RELEASE. Patricia Strayer, P.E., Town Engineer Phone: ,

Planning & Zoning Board Meeting. DRAFT Comprehensive Transportation Plan Update, February 23, 2018 version

Northeast Anthony Henday Drive Manning Freeway to Whitemud Drive Welcome to this Construction Information Session

ORDINANCE AN ORDINANCE TO ADD A NEW SECTION 4.N. IN THE ZONING CODE FOR THE TOWN OF MIDDLETOWN, RELATING TO MIXED-USE DEVELOPMENT

FEDERAL ENERGY REGULATORY COMMISSION FIELD INSPECTION REPORT

AMEND DMENT H HOSPITAL

Project phasing plan (if applicable) 12 copies of site plan

Cypress High School Site Improvement Project

DIVISION 32 EXTERIOR IMPROVEMENTS

THREE-YEAR CAPITAL IMPROVEMENT PLAN FY

VILLAGE OF MOUNT PROSPECT 2016 STREET RESURFACING PROGRAM Frequently Asked Questions (FAQ s)

California State University, Monterey Bay Campus Parking Relocation Project Attachment to Notice of Exemption

NEWPORT NEWS/WILLIAMSBURG INTERNATIONAL AIRPORT DESIGN AND SUSTAINABILTY GUIDELINES

Municipality of Anchorage. Community Council Survey Capital Projects Needs Ranking Survey (ALPHABETICAL) Airport Heights

ARTICLE 17 SITE PLAN REVIEW

CIF Project #810.3: Durham Region MRF Baler Final Report

REQUEST FOR COUNCIL ACTION 6A AGENDA ITEM

Prepared for: East Park Leadership Conservation Center Prepared by: CVM Construction Managers, Inc.

TOWNSHIP OF HOWELL TOWNSHIP OF HOWELL ENGINEERING PROJECTS STATUS REPORT OCTOBER 19, Resurfacing of Aldrich Road West Contract # 11-06

GPCID Mall Boulevard & Gwinnett Place Drive Complete Street: Sectional View of Concepts

theme 4 : Penn connects...

4-Town Comprehensive Plan DRAFT 7/30/07

4.1.A NORTHWEST QUADRANT MASTER PLAN

This is the East Carolina University Comprehensive Facilities Master Plan Final Draft Plan Review. This workbook reviews the campus draft master plan

8 October 14, 2015 Public Hearing

Ashbridges Bay Erosion and Sediment Control Project

NEW WATER CONNECTION PROCEDURES FOR HOPE AND EDENVILLE TOWNSHIP RESIDENTS

Federal Project No.: OC-095-1(365), OC-095-1(367)

Pennsy Greenway Trail

2.4 FUTURE LAND USE ELEMENT Goals, Objectives and Policies

DATE ISSUED: March 12, 2014 REPORT NO: 101. Old Globe Way Improvements and San Diego Zoo Employee Parking Structure

MASTER PLAN WORKSHOP South Campus Precinct

a. Site Topography and Relationship to Surrounding Topography

ARLINGTON COUNTY, VIRGINIA

City of Westbrook. 2 York Street Westbrook, Maine (207) Fax:

Arts Council update Landscape Contest! st Place: Front Yard

Memorandum CITY OF DALLAS. Riverfront Boulevard Design From Continental Avenue to Cadiz Street

Spring 2018 Construction Update

Urban Planning and Land Use

OPERATION & MAINTENANCE

Achieving a Vision. Master Plan 2009 Belknap Campus August 10 11, UofL Belknap Campus Master Plan Update

APPENDIX J PERFORMANCE STANDARDS FOR GRAVEL MINE, PIT MINE, OR QUARRY

Contractor Environment, Safety & Health (ESH) Briefing. Suite 100 Bldg. 726 Billerica, MA

HEALTH SCIENCES BUILDING REDEVELOPMENT PROJECT

Strachan Ave. Overpass Community Design Update. October 26, 2010 Stephen Lipkus Executive Director Georgetown South Project GO Transit

Coxwell Station Easier Access

Mark-up of the effect of the proposed Bronte Village Growth Area OPA No.18 on the text of section 24, Bronte Village, of the Livable Oakville Plan

The Van Ness Campus. Weekly Construction Bulletin #259

AGENDA ACTION ITEMS INFORMATION ITEMS

I-4 Beyond the Ultimate. Florida Transportation Builders Association February 9, 2018

ROME WATERFRONT VILLAGE PROJECT NARRATIVE January 25, 2018

Subarea 5 Southern Gateway. Vision. Mobility The proposed street network will create developable blocks that are scaled appropriately for the area.

Shelbyville, KY Stormwater Best Management Practices. Section 2 EROSION PREVENTION AND SEDIMENT CONTROL PLAN

A. INTRODUCTION AND SUMMARY OF FINDINGS B. EXISTING CONDITIONS. Table 10-1 Adjacent Storm Drains

City of Bonney Lake Allan Yorke Park. MASTER PLAN SUMMARY REPORT June 30, 2016

TURN TO THE RIVER CITY PLAZA LANDSCAPE DESIGN CONCEPT May 25, 2016

Transcription:

Campus Construction Situation Report #6 March 15, 2012 Hechenbleikner Lake Dam No change from previous notice Dewatering maintenance continues. Major construction activity will begin mid April and with an expected completion date in early August 2012. Expect construction traffic on Broadrick Boulevard with minimal impact on vehicular and pedestrian traffic. Residence Hall Phase XI Site grading and earthwork continues. Access to Hunt Village is now via a temporary paved connector road off Cameron Blvd. There is no access to Lot 9A via High Rise Road presently for others. Contractor personnel are using Cameron Blvd access via a construction entrance. Roadway signage has been posted showing access roads. Residence Hall Phase X Contractor continues to grade site and removing unsuitable soils. Heavy truck traffic will be encountered for the next few weeks on Cameron Blvd. Regional Utility Plant 4 No change from previous notice Contractor started work on south side of parking lot 8 along with stormwater modifications to parts of the lot. Few parking spaces will be ropedoff in preparation for work startup. Construction of contractor entrance off University City Blvd connecting to Lot 8 was started. Football & CRI Campus No change from previous notice Gas line installation to begin March 14 th in the vicinity of Motorsports and Bioinformatics. Minor traffic impacts due to contractor mobilization maybe encountered. PORTAL Notice to Proceed was issued to contractor and bids have been received. Increase construction activity to begin in two weeks or so. Watch for increase traffic at the CRI entrance. Campus Construction Situation Report #5 March 9, 2012 begin mid April and with an expected completion date in early August 2012. Expect construction traffic on Broadrick Boulevard with minimal impact on vehicular and pedestrian traffic. Residence Hall Phase XI Site grading and earthwork underway. Access to Hunt Village is now via a temporary paved connector road off Cameron Blvd. There is no access to Lot 9A via High Rise Road presently for others. Contractor personnel are using Cameron Blvd access via a construction entrance. Roadway signage has been posted showing access roads. Residence Hall Phase X Contractor is grading site and removing unsuitable soils. Heavy truck traffic will be encountered for the next few weeks on Cameron Blvd. Regional Utility Plant 4 Contractor starting work on south side of parking lot 8 along with storm water modifications to parts of the lot. Few parking spaces will be roped off in preparation for work startup. Construction of contractor entrance off University City Blvd connecting to Lot 8 has started.

Football & CRI Campus Gas line installation will begin March 14 th in the vicinity of Motorsports and Bioinformatics. Minor traffic impacts due to contractor mobilization maybe encountered. Campus Construction Situation Report #4 February 29th, 2012 begin mid April and with an expected completion date in early August 2012. Expect construction traffic on Broadrick Boulevard, with minimal impact on vehicular and pedestrian traffic. Residence Hall Phase XI Contractor clearing site, construction fence erected and installing erosion control structures. Access to Parking Lots 9 & 9A from High Rise Road limited to residences of Hunt Village only. Student access to parking lots 9 & 9A will change to a temporary connector road off Cameron Blvd on Monday, March 5 th and will not have access via High Rise Road. Residence Hall Phase X Parking Lot 22 is closed. Contractor grading site, removing trees, and installing erosion control structures. Regional Utility Plant 4 Contractor starting work on south side of parking lot 8 along with storm water modifications to parts of the lot. Few parking spaces will be roped off in preparation for work startup. Construction of contractor entrance off University City Blvd. connecting to Lot 8 will be starting today, February 29, 2012.

Campus Construction Situation Report #3 February 24, 2012 begin mid April and with an expected completion date in early August 2012. Expect construction traffic on Broadrick Boulevard with minimal impact on vehicular and pedestrian traffic. Residence Hall Phase XI Contractor mobilized and began site clearing, construction fence installation and access road construction to Parking Lots 9 & 9A from Cameron Blvd. Student access to parking lots 9 & 9A to change once temporary connector road is completed in the next few weeks (watch for signs on High Rise Road and Cameron Blvd). Residence Hall Phase X Parking Lot 22 is closed. Contractor removing parking lot pavements and site grading has started. Regional Utility Plant 4 Contractor to start work March 5 th in south side of parking lot 8 along with storm water modifications to parts of Parking Lot 8. In mid March construction a contractor entrance off University City Blvd connecting to Lot 8 will follow. Few parking spaces may be roped off in preparation for work startup March 2 nd.

Campus Construction Situation Report #2 February 16, 2012 Hechenbleikner Lake Dam De watering maintenance continues. Expect construction traffic on Broadrick Boulevard to have minimal impact on vehicular and pedestrian traffic. Major construction activity will begin mid April and has an expected completion date in early August 2012. Residence Hall Phase XI Contractor mobilization is progressing slower than expected. Initial work will be to construct temporary access roads connecting Cameron Blvd to Parking Lots 9 & 9A, and to clear the project site. Work will begin February 20th with signage being posted on Friday February 17. Expect construction traffic on Cameron Boulevard (South Entrance area) and in the vicinity of Lots 9 and 9a. Residence Hall Phase X Parking Lot 22 is closed. Contractor has mobilized with site fencing having been erected. Regional Utility Plant 4 Contractor to start work March 5 th in south side of parking lot 8 along with storm water modifications to parts of Parking Lot 8. In mid March construction a contractor entrance off University City Blvd connecting to Lot 8 will follow. Contractor Routes

Campus Construction Situation Report #1 February 12, 2010 Hechenbleikner Lake Dam Dewatering is underway. Fish and turtles have been relocated to Davis Lake. Expect construction traffic on Broadrick Boulevard with minimal impact on vehicular and pedestrian traffic. Major construction activity will begin mid April and with an expected completion date in early August 2012. Residence Hall Phase XI Contractor mobilizing to start construction. Initial work will be to construct temporary access roads connecting Cameron Blvd to Parking Lots 9 & 9A and to clear the project site. Work to start no later than February 17. Expect construction traffic on Cameron Boulevard (South Entrance area) and in the vicinity of Lots 9 and 9a. Residence Hall Phase X Parking Lot 22 has been closed in anticipation of contractor mobilization this weekend.