Rt. 29 Solutions Project Delivery Advisory Panel. December 3, 2015

Similar documents
Rt. 29 Solutions Project Delivery Advisory Panel. January 7, 2016

Route 29 Project Delivery Advisory Panel September 11, 2014 Meeting Minutes

Places29: List of Implementation Projects

Appendix 2. Implementation Project Descriptions Page A2-1

Rt 29 Solutions Hydraulic Planning Advisory Panel. September 14, 2017

Welcome to the. Open House

Appendix 2. Implementation Project Descriptions

Moving The Metro. A special construction update for the metro Omaha area.

Rt 29 Solutions Hydraulic Planning Advisory Panel. September 28, 2017

I.T.S. PLAN ALONG I-95 INSTALL FIBER OPTIC LINE PROJECT SHOWING Tuesday, June 18, 2013, 1:30pm Ashland Residency Conference Room

Open House RIVER DES PERES GREENWAY: LANSDOWNE SHREWSBURY METROLINK TO FRANCIS R. SLAY PARK

Fall 2017 Construction Update

Project Overview. Fairfax County Parkway Widening Fairfax County. Get Involved. Public Information Meeting. Contact Information

I-25 / Rio Bravo Interchange. I-25 / Rio Bravo Interchange. Presenters 11/30/2016 THIRD PUBLIC MEETING DECEMBER 1, 2016 NMDOT CN A300280

SOUTH UNIVERSITY Street Design Alternatives in Progress

Fairfax County Parkway (Route 286) Widening Project

Construction Engineering & Inspection

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Projects

CONFORMED AGREEMENT INCORPORATED REVISIONS PER AMENDMENT DATED: APRIL 2, 2013 FOR REFERENCE

Public Officials/Design Advisory Meeting #12. Bensalem Township Municipal building, 2400 Byberry Road Bensalem, PA

ARGENTA TRAIL (CSAH 28/63) REALIGNMENT SOUTH PROJECT (CP 63-25)

WELCOME NEIGHBORS! April 11, 2019

WELCOME! 8 8:30 6: TH STREET IMPROVEMENTS. Open House. Presentation & Q&A

Citizen Information Meeting

Please see attached for more detailed project information. Project Schedule Designer Award by SBC Executive Sub-Committee December 21, 2015

Rio/29 Small Area Plan. Design Plan & Implementation Framework Open House - January 25, 2018

Project Overview. Get Involved. Public Information Meeting. Contact Information

4/8/2015 Item #10D Page 1

The Illinois Department of Transportation and Lake County Division of Transportation. Route 173, including the Millburn Bypass

NEWSLETTER #03 BEAUDESERT ROAD LOGAN MOTORWAY

Cottage Grove Road Reconstruction. City of Madison Engineering

PROJECT SHOWING MINUTES

I-95 Girard Avenue Interchange Near Neighbors Meeting. Project Status

DESIGN SCENE SUBJECT INDEX

DESIGN & GREEN INFRASTRUCTURE UPDATE December 13, 2016

PROJECT UPDATE BON AIR ROAD BRIDGE REPLACEMENT AND MAGNOLIA AVENUE WATER QUALITY FACILITIES

Chesterfield County Project Update

I-66 EASTBOUND WIDENING INSIDE THE BELTWAY PARDON OUR DUST MEETING

ROANOKE STREET IMPROVEMENTS CHRISTIANSBURG, VIRGINIA VDOT PROJECT # U R24 UPC #:

Capital Projects in and near Odenton Town Center

Neighborhood Conservation (NC) Program CONCEPT DESIGN REVIEW MEETING NOTES

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Projects

(blank page) WestConnex New M Roads and Maritime Services Environmental impact statement

Public Hearing. Charlotte County-Punta Gorda MPO - Meeting Rooms A and B March 14, open house at 4 p.m., formal presentation at 5 p.m.

Derby-Shelton Bridge Pedestrian and Bicyclist Enhancements [1]

FANSHAWE PARK ROAD/RICHMOND STREET INTERSECTION IMPROVEMENTS. PUBLIC INFORMATION CENTRE 2 June 16, 2016

Comprehensive Roadside Management Project (CRMP)

TOWN OF PALM BEACH FOR IMMEDIATE RELEASE. Patricia Strayer, P.E., Town Engineer Phone: ,

PLANNING COORDINATING COMMITTEE

DESIGN PUBLIC HEARING APRIL 24, 2018 MUNICIPAL OFFICE BUILDING HARDWICK, MASSACHUSETTS 7:00 PM FOR THE PROPOSED

TRANSPORTATION COMMITTEE

PennDOT Public Meeting. S.R. 3044, Section A01 Castle Shannon Boulevard Roadway Improvement Project

FROM DUPONT CIRCLE NORTH TO CALIFORNIA STREET, NW. Welcome!

Meeting Purpose: Date and Time: Location: Attendance: Handouts:

The Capital Design Advisory Committee St. Mary s College of Maryland & Historic St. Mary s City

I-485/ I-85 Interchange Charlotte, NC December 6, LANE The Lane Construction Corporation, 90 Fieldstone Court Cheshire, CT 06410

West Dennis Center: Bass River to Old Main Street. West Dennis Business District: Old Main Street to Dennis Commons

Project will Replace: Utilities Curb Pavement Lighting. City of Madison

St. Laurent Transit Improvements Innes / Industrial to Smyth. Public Information Session December 2, 2015

4.1 Build Alternative 1 Construction Phasing

Spring 2018 Construction Update

Constructing PCCP Under High Traffic Volume

PROPOSED IMPROVEMENTS

SBCAG STAFF REPORT. MEETING DATE: March 17, 2016 AGENDA ITEM: 5I

INDEX EXECUTIVE SUMMARY...1 BASIC INFORMATION AND PROCEDURES...3 EXISTING CONDITIONS EXISTING UTILITIES

2016 REVISIONS COMMENT FORM RULES AND REGULATIONS FOR CONSTRUCTION IN THE PUBLIC WAY COMMENT PERIOD: JUNE 1 TO JUNE 30, 2015

University Park Subdivision Street Assessment Report

The Ambassador Bridge/ Gateway Project

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Project Descriptions ($ millions)

Title 11 Streets and Sidewalks

Welcome to the Sellwood Bridge Project Pre-Construction Open House

Fifth and Detroit Street Design May 2017 Capital Improvements Committee. DOWNTOWN Street Design

Tampa Palms CDD. Board Of Directors September, 2017

CURRICULUM VITAE REZA MARSHAL, MECE, PE, PTOE

STANDARD SPECIFICATIONS Book 2 ENGINEERING DRAWINGS INCLUDES ADDENDUMS

Rezoning Transportation Analysis Petition Number: General Location Identifier: , ,

Tysons-Old Meadow Road Bike/Ped Improvements

North Carolina Department of Transportation Project Development and Environmental Analysis Branch

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Projects

ROAD CONSTRUCTION. 36 June 2014 ROADS&BRIDGES

BOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM

IOWA HIGHWAY 57 / WEST 1 ST STREET STUDY PUBLIC INFORMATIONAL MEETING APRIL 22, 2014

2017 Investment in Infrastructure Expo February 28, 2017 Jason Jonas, P.E. Public Works Director

Middlebury RS 0174(8)

Chain Bridge Road Sidewalk Improvements Citizen Council Work Session

Capital Projects impacting Odenton Town Center

SH 199 Corridor Master Plan. Community Meeting No. 2 May 31, 2017

Elgin O Hare Western Access Project Local Advisory Committee. February 10, 2014

Creative Engineering Group Inc, (Creative) Construction Engineering and Inspection (CEI) Professionals

TABLE OF CONTENTS. Building Great Neighbourhoods. Working together to make the most out of your neighbourhood.

Agenda Item # 1. Meeting Date September 21, Prepared By. Approved By

Mountain RECOMMENDATlON: After staff presentation and review of the revised format for sample

Cleveland Innerbelt Bridge / Central Viaduct City Planning Commission November 6, 2009

SECTION 4(f) DE MINIMIS DOCUMENTATION

COMMUNICATION URBAN DESIGN REVIEW BOARD CITY OF DES MOINES, IOWA MAY 16, 2017 MEETING

City of Richmond. Engineering Design Specifications

I-494 Rehabilitation Project SP (I-394 to Fish Lake Interchange) June 2014 Section 4(f) De Minimis Determination

Executive Summary. The goals of the Plan are to:

Mavis Road Class Environmental Assessment

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Projects

Transcription:

Rt. 29 Solutions Project Delivery Advisory Panel December 3, 2015

Agenda item 1: Introductions Project Delivery Advisory Panel Technical Team 2

Agenda item 2: Interaction and Feedback Live Streaming Nov 12, 2015 Oct 29, 2015 Unique Viewers: 11 27 Streams: 31 42 Average Minutes per stream: 35 58 3

Agenda item 2: Interaction and Feedback (continued) For the period Nov 10 - Nov 30 Inbox comments: 4 emailed to project inbox 1 regarding stop signs at Branchlands and Hillsdale 1 regarding noise from nighttime pile driving 1 regarding noise from pile driving and lane closures 1 regarding contractor parking in Best Buy parking lot Web Provide Input: 2 new comments from 1 individual Opposes Rio GSI and concerned about noise from pile driving Project Hotline 844-220-5540: 7 calls 1 inquiring how subcontractors can be hired 1 thank you for repairing driveway 2 noise from pile driving 1 regarding the extended lane closures 1 from Wendy s regarding holiday lane closures 1 regarding windshield damage 4

Agenda item 3: Report on PDAP Feedback Rt 29 at Rt 250 - Guardrail and landscaping Have asked VDOT to reevaluate guardrail and develop a landscape plan Expect options before Dec 31. Hillsdale connection from Whole Foods to Seminole Square Entire Hillsdale project scheduled to be advertised for bids Mar 31, 2016 Construction sequencing can be considered at that time October 2015 accidents between 29th Place and Woodbrook 4 accident reports filed 1 Rio: rear end NB at red light (8pm, dry) 1 Rio: NB to SB u-turn made from wrong left-turn lane (11am, dry) 1 at Woodbrook: side swipe NB, lane change (8:30pm, dry) 1 at Fashion Sq Drive: angle, Rt 29 NB vehicle ran red light (4:30pm, wet) 5

Agenda item 4: Panel Feedback and Suggestions for Future Agenda Items Open Discussion 6

Agenda item 5: Construction Milestones As of: 12/1/2015 December, 2015 January, 2016 Activity Rio Road GSI Route 29 Widening Berkmar Drive Hillsdale 29/250 Interchange Scheduled Completion Actual Completion Activity Scheduled Completion Waterline Relocation 12/18/15 Ashwood Temp. Signal 12/23/15 Communications Relocation 12/29/15 N. Hollymead Temp. Signal 12/23/15 Actual Completion Activity Scheduled Completion Actual Completion Activity VDOT Over the shoulder review First Draft Plats (high priority parcels) Scheduled Completion Gasline Relocation 1/16/16 90% Plan Submittal 1/28/16 Drive Abutment Piles 1/16/16 Actual Completion Activity Scheduled Completion 12/9/15 MSE Wall Complete 12/14/15 12/15/15 Actual Completion February, 2016 BMP 6 (Albemarle Square) Roadway Widened for Phase 2 2/1/16 2/29/16 Communications and Power Relocation ROW Acquisition Complete 2/12/16 ROW Acquisition 2/26/16 2/26/16 29S/250W PavementWidening 2/23/16 March, 2016 BMP 4 (SB Lanes) 3/1/16 Gasline Relocation 3/31/16 Retaining Wall Piles and Tiebacks 3/31/16 South of River Rough Grading South Abutment Excavation 3/31/16 Final ROW Plats 3/1/16 3/31/16 Advertisement 3/31/16 Final Paving and Striping 3/29/16 Phase 1 Drainage 4/8/16 Utility Relocation 4/29/16 Sound Barrier 4/19/16 April, 2016 Phase 1 Pavement 4/15/16 Phase 1 Traffic Shift 4/20/16 Phase 2 Traffic Shift 5/23/16 South Abutment Pile Driving 5/31/16 Bid Period Ends 5/16/16 Install Overhead Signs 5/18/16 May, 2016 Notice of Award 5/30/16 Construction Complete 5/21/16 7

Agenda item 6: Rt. 29 Solutions Project Updates Rt. 250 / 29 Interchange Work this week Complete sidewalk/ramp replacement at Route 29 and Morton Drive intersection Complete median strip in median of Route 29 Continue installation of MSE panels and backfill Complete installation of concrete leveling pad for MSE panels on west end Begin preparations for curb installation along Best Buy ramp Continue storm drain installation on Barracks Road on ramp Continue storm drain installation on Barracks Road off ramp 8

Agenda item 6: Rt. 29 Solutions Project Updates (continued) Rt. 250 / 29 Interchange (continued) Significant lane closures this week Route 29 inside turn lane closures for median backfill and grading Route 29 SB lane shoulder closures to construct sidewalk improvements Ramp shoulder closures for storm drain installations 9

Agenda item 6: Rt. 29 Solutions Project Updates (continued) Rt. 250 / 29 Interchange (continued) Work next two weeks Complete storm drain installation on Barracks Road on ramp Complete storm drain installation on Barracks Road off ramp Complete installation ADA sidewalk ramps at various locations Complete widening of Barracks Road off ramp Continue installation of MSE panels and backfill 10

Agenda item 6: Rt. 29 Solutions Project Updates (continued) Rt. 250 / 29 Interchange (continued) Anticipated significant upcoming lane closures Route 29 inside turn lane closures to construct guardrail and median Route 29 SB lane shoulder closures to construct sidewalk improvements Ramp shoulder closures for storm drain installations 11

Agenda item 6: Rt. 29 Solutions Project Updates (continued) Rio Grade-Separated Intersection Work this week Wells Fargo to Rio curb construction Storm drain construction Complete waterline testing and begin trunk tie-ins Continue retaining wall at SunTrust Fashion Square curb construction Fashion Square retaining wall construction Drive abutment B piles Install retaining wall piles Continue gas main relocation CenturyLink splicing 12

Agenda item 6: Rt. 29 Solutions Project Updates (continued) Rio Grade-Separated Intersection (continued) Significant lane closures this week (nighttime) Extended lane closure hours expired (returned to 9:00 pm 6:00 am) Rio crossover closed at nighttime restricting thru movements and left turn movements Rte. 29 triple lane closures northbound and southbound Rio East and West closures with local business access open 13

Agenda item 6: Rt. 29 Solutions Project Updates (continued) Rio Grade-Separated Intersection (continued) Work next two weeks SB 29 at Title Max curb construction Storm drain construction in all quadrants Waterline connections to existing trunk lines Complete retaining wall at SunTrust Fashion Square retaining wall construction Drive abutment A piles Install retaining wall piles Continue gas main relocation CenturyLink north switch splicing and connections 14

Agenda item 6: Rt. 29 Solutions Project Updates (continued) Rio Grade-Separated Intersection (continued) Anticipated significant upcoming lane closures (nighttime) Rio crossover closed at nighttime restricting thru movements and left turn movements Rt. 29 triple lane closures northbound and southbound Rio East and West closures with local business access open (reduced frequency) 15

Agenda item 6: Rt. 29 Solutions Project Updates (continued) Rt. 29 Widening Work this week Place fill in median Complete clearing of trees SBL right side Qwest Business (CenturyLink) directional bore for fiber relocation Retrofit signal beacon NB near Ashwood Dominion VA Power setting poles Fiberlight directional bores Temporary signal construction (Ashwood and Hollymead) 16

Agenda item 6: Rt. 29 Solutions Project Updates (continued) Rt. 29 Widening Significant lane closures this week (nighttime) Route 29 left lane closure NB and SB Periodic short-term total closure for temporary signal construction 17

Agenda item 6: Rt. 29 Solutions Project Updates (continued) Rt. 29 Widening (continued) Work next two weeks Place fill in median Qwest Business (CenturyLink) directional bore for fiber relocation Retrofit signal beacon NB near Ashwood Install temporary signals at Ashwood and Hollymead Dominion VA Power setting poles Fiberlight directional bores 18

Agenda item 6: Rt. 29 Solutions Project Updates (continued) Rt. 29 Widening (continued) Anticipated significant upcoming lane closures (nighttime) Route 29 left lane closure NB and SB Periodic short-term total closure for temporary signal construction 19

Agenda item 6: Rt. 29 Solutions Project Updates (continued) Berkmar Extended Work this week Continue excavation and hauling to 29 Widening Continue phase III archaeological recovery Review 100% roadway plan revisions Review final drainage and Stormwater Management report revisions Significant lane closures this week (nighttime) Shoulder closure at Berkmar and Hilton Heights for hauling excavated material to 29 Widening 20

Agenda item 6: Rt. 29 Solutions Project Updates (continued) Berkmar Extended (continued) Work next two weeks Continue excavation and hauling to 29 Widening Continue Phase III archaeological recovery Anticipated significant upcoming lane closures (nighttime) Shoulder closure at Berkmar and Hilton Heights for hauling excavated material to 29 Widening 21

Agenda item 6: Rt. 29 Solutions Project Updates (continued) Signal Updates Work this week Planning for Hydraulic/Rio loop communications upgrades Significant lane closures this week None Work next two weeks Meeting to develop final list of projects to move forward Begin project design Anticipated significant upcoming lane closures None 22

Agenda item 6: Rt. 29 Solutions Project Updates (continued) Hillsdale Extended Construction Advertisement date Mar 31, 2016 Established schedule to meet milestones leading up to Mar 31 Stormwater management MOU revised for signatures Established schedule for future signal warrant analysis Utility cost determination form sent from City to VDOT (Form UT-9) Met with Seminole Square and business owner regarding utility relocation 1st review of RW plat preparation will occur no later than Dec 15 Over-the-shoulder review of 90% plans Dec 9 23

Agenda item 7: Berkmar Bridge Design Construction cost (millions), not including maintenance, for: 2-lane bridge on 4-lane right-of-way as designed $18 4 lanes now $26 2 additional lanes in 2041; new structure $27 2 lanes with substructure for 4 lanes now; place deck in 2041 $28 2 lanes now; widen to 4 lanes in 2041 $30 Requests for projects statewide $7 billion; VDOT has $1 billion available Will continue with construction of 2-lane bridge on 4-lane right of way. Need for 4-lane bridge and roadway will be evaluated as traffic grows. Future funding subject to inclusion in MPO long-range plan and CTB priorities. 24

Agenda item 8: Rt 29 Widening, Signals for Pedestrians and Bicyclists Questions concerning: Pedestrian signal timing Pedestrian refuge area Future pedestrian crossings at Ashwood and Rio Mills Intersection lighting for pedestrian crossings Signal timing for bicyclists Polo Grounds Ashwood Hollymead Rio Road 25

Agenda item 9: Pedestrian Lighting, Landscaping and Hardscape We will incorporate recommendations from SELC and Kennon Williams with few exceptions: Will not use brick or cobblestone. But will use stamped brick and cobblestone patterns and colors recommended by SELC and Kennon Williams. Will not extend pedestrian lights on Rio East or West. But will extend north and south on Rt 29 (specific distance being determined). Will not remove the railing between the retaining wall and sidewalk on the bridge deck. Will not use the single planter option on the bridge deck. But will use the variable size planters recommended by SELC and Kennon Williams. Lighting recommendations continue to be investigated. Intent is to accommodate to extent practical. 26

Agenda item 10: Placemaking Feedback from both SIR and Albemarle County is to name general area Rio and to use geographic designations for the corners. Options for PDAP to consider: Agree on recommendation to name area Rio with geographic corners: Rio NE, Rio SE, Rio NW, Rio SW Consider other names including those mentioned by group participants. Examples include, but are not limited to: Rio Crossing Rio 29 Rio Place Rio Crossroads Rio at 29 Rio Ville Rio Square Rio@29 Rio Corner 27

Agenda item 11: Toy Lift VDOT and LANE-Corman Individual donations Corporate donation Volunteering Use of message board Use of lights Clean up assistance Will be with WINA at Toy Lift for Friday morning radio broadcast 28

Agenda item 12: New Business 29

Agenda item 13: Adjourn 30

Rt. 29 Solutions Project Delivery Advisory Panel December 3, 2015