Chariho Regional School District Five-Year Capital Facilities Improvement Plan (2/10/15)

Similar documents
Briar Crest Elementary

CAPITAL OUTLAY REQUEST - IDENTIFIED AND EMERGING PROJECTS - RANKED 3-Jun-14

VOTER BOND REFERENDUM 2018 SUMMARY OF WORK PROPOSED

2014 Bond Project Guide

School District of Milton 5- Year Capital Maintenance and Improvement Plan

NYACK PUBLIC SCHOOLS CAPITAL IMPROVEMENT PLANNING PROCESS

Master Facility Planning Update School Board Meeting May 26, 2016

Tillamook High School Bond Projects

3. 21st Century Learning A. Districtwide Flexible Learning - Allowance for Flexible Furniture $600,000 Subtotal $600,000

TIFT COUNTY SCHOOLS E-SPLOST HISTORY

REPORT CARD TO THE COMMUNITY MAY 15, 2018

Oxford Hills School District Capital Renewal Plan Updated March 2017

Forest Hills Facilities Plan

FORT ERIE SECONDARY SCHOOL FACILITY INFORMATION. Lake Erie Corridor Secondary Schools Accommodation Review

Allisonville Elementary School Facilities Highlights Built: 1960 Last Major Renovation: 28 years ago Capacity: 650 Current Enrollment: 767

SITE SYSTEMS: FANNIE MAE EXPECTED USEFUL LIFE TABLES (FMEUL)

New High School Concept

DEERFIELD SCHOOL DISTRICT REFERENDUM Committed to Excellence and Equity in Educating Our Students

Campus Middle School 4785 South Dayton Street Greenwood Village, Colorado 80111

HVAC / Boilers / Hot Water. Expected Life Span. very rough estimates Condition/Issue Age. Athletics / Gyms

MUKWONAGO SCHOOL DISTRICT CAPITAL IMPROVEMENT / MAINTENANCE STUDY

2014 Bond District-wide Facility Repairs

MUKWONAGO AREA SCHOOL DISTRICT CAPITAL IMPROVEMENT / MAINTENANCE STUDY

Florence High School / Middle School Page 1 of 3 Florence, WI

2014 Bond District-wide Facility Repairs

Josefa Ortiz De Dominguez Elementary School

Edward Jenner Elementary Academy of the Arts

Greenwood Elementary School 5550 South Holly Street Greenwood Village, Colorado 80111

Genevieve Melody Elementary School

ALLISON ELEMENTARY SCHOOL 4315 Don Julio Blvd., North Highlands, CA 95660

Ichabod Crane Central School District 2018 Capital Project Preliminary Estimate

Joseph Brennemann Elementary School

MOUNT PLEASANT MIDDLE SCHOOL HVAC. M-01 Heating Plant: M-02 Heating & Ventilating Systems: Livingston School District Mount Pleasant Middle School

Sagebrush Elementary School East Temple Place Aurora, Colorado 80015

5 Year Capital Improvement Plan Update

Design Presentation. Chief Operations Officer Willie Burroughs

Richard Henry Lee Elementary School

Custodial Guide

HOLUM EDUCATION CENTER. Architectural. January 13, 2014 DeForest Area School District

Facilities Management Services

January 11, New benches installed. Paving of parking lot adjacent to piers and the canoe put-in. Near complete with clean up remaining.

PLATTEVILLE MIDDLE SCHOOL

SPLOST I, II, III,IV

Washington Irving Elementary School

State College Area School District High School South Building EXISTING CONDITIONS ASSESSMENT

Kenmore Town of Tonawanda Union Free School District : Capital Improvement Project Phase 2

Meadow Point Elementary School East Grand Avenue Aurora, Colorado 80015

NYC Department of Education

Charles W Earle Elementary School

Agustin Lara Elementary Academy

Francis M McKay Elementary School

VISION PLAN PRESENTATION - SEPTEMBER 28, 2013

Calmeca Academy of Fine Arts and Dual Language

Oscar DePriest Elementary School

2015 Building Condition Survey Summary Mosaic Associates Architects 02/19/16

Ashland School District Facility & Capacity Assessment Report 2005

Greater Albany Public Schools May 2017 Ballot Measure for School Repairs, Crowding and Job Training

MARY CRAPO CENTER Miller Road, Swartz Creek, Michigan

John Palmer Elementary School

Columns REF, RESPONSIBLE and COMPL TD are provided for your numbering, assignments and control. REF ISSUE RESPONSIBLE COMPL TD

Cherry Hill Public Schools BUILDING A SOLID FUTURE

Warren County Schools Plant and Operations

NYC Department of Education

Master Project List Report

Major Public Facilities. Section 4

Kerrville ISD has called for a bond election in the amount of $88,960,000 for November 6, 2018

SCHOOLS + COMMUNITY rehabs, renovations, new construction

Ph: (907) Quality Homes

West Hartford Public School District

Sidney Sawyer Elementary School

Emergency Management Resource Guide. Appendix A: Crime Prevention Through Environmental Design CPTED Principles Checklist for Kentucky Public Schools

If there are emergency situations they should be reported to Maintenance Department immediately.

DeWitt Clinton Elementary School

Updated: 8/16/ Facilities Profile

EXISTING CONDITIONS SUMMARY

Custom Report // Priorities 1+2

NYC Department of Education

Smith Douglas Homes Presents HAYNESCREST TOWNHOMES

Vendor Application Form

Major Public Facilities. Section 7

State College Area School District High School North Building EXISTING CONDITIONS ASSESSMENT

Ohlone College Measure G Project Scope Revisions

Springpoint Architects, pc SECTION Childcare Center Architect s Project No TABLE OF CONTENTS Monroe County Comm. Sch. Corp.

LKA Partners. A Professional Corporation for Architecture/Planning. 430 North Tejon Street Colorado Springs, CO /

FOOD SERVICE May 6, 2016

Service Description Service Shop Customer Charge Comments. Electronic Shop. Electric Shop Yes additional circuits for equipment

George B Swift Elementary Specialty School

SCHEMATIC DESIGN PRESENTATION

DOCUMENT TABLE OF CONTENTS

NAZARETH AREA SCHOOL DISTRICT MAINTENANCE DEPARTMENT 357 Tatamy Road, Nazareth, PA FAX

Encumbered Balance (E-D) Branham HVAC Implementation Complete 100% 03/04/19 07/19/19 $765, $635, $635, $130, $0.

ALLEGHANY COUNTY PUBLIC SCHOOLS Maintenance Work Request Completion Analysis

Arena Elementary School 314 Willow St. Arena, WI 53503

Alessandro Volta Elementary School

OPERATING. Salaries, wages, and benefits personnel costs for repairs and maintenance functions, including living or accommodation allowances.

1354 CHECKLIST for Project Closeout

E-SPLOST V. Facts and Information. August 2018

Exhibit CC BALTIMORE COUNTY PUBLIC SCHOOLS

LONG-TERM OPERATIONS AND MAINTENANCE PLAN

Binghamton University Construction SUMMER 2012 HIGHLIGHTS

Transcription:

Chariho Regional School District Five-Year Capital Facilities Improvement Plan (2/10/15) School/Department FY 16 FY 17 FY18 FY19 FY20 Chariho Regional High School FY 16 FY 17 FY18 FY19 FY20 *Repair Bleachers (inside) 4,000 *Replace Football Bleachers (outside) 32,500 *Modify Existing Classroom Courtyard Doors 50,000 **Replace Furniture/Cafeteria Tables 4,000 4,000 4,000 4,000 4,000 **Maintenance of Track (MS/HS Split) 27,500 **Maintenance of Tennis Court (MS/HS Split) 2,000 2,000 2,000 2,000 2,000 ****Replace AC Rooftop Unit and extend to teacher's room 10,000 ****Install two fixed roof ladders & install roof access to water tank room 3,500 *****Install Swipe Key System 15,000 ******Install Door in HS Trainer's Room 7,000 ******Install HS Door Handles 4,500 4,500 4,500 4,500 4,500 TOTAL 46,500 38,000 14,000 43,000 60,500 Chariho Regional Middle School FY 16 FY 17 FY18 FY19 FY20 *Upgrade Dishwasher Exhaust 25,000 *Upgrade Kitchen Exhaust 40,000 *Resurface Boy's Locker Room Floor 8,000. **Replace Office Carpet 18,000 **Replace Furniture/Cafeteria Tables 4,000 4,000 4,000 4,000 4,000 **Refinish Gymnasium Floor 5,000 5,000 5,000 **Replace Lockers 50,000 50,000 **Remediate Oil Spill 17,000 10,000 10,000 **Replace Classroom Doors 8,000 8,000 **Maintenance of Tennis Court (MS/HS Split) 2,000 2,000 2,000 2,000 2,000 **Maintenance of Track (MS/HS Split) 27,500 ****Replace Lower Bowl Auditorium Seating 50,000 *****Replace Bathroom Petitions 20,000 ******Install AC rooftop unit for Self- Contained Classrooms 20,000 ******Resurface Girls' Locker Room Floor and Replace Lockers 15,000 ******Replace 4 Exterior Solid Steel Doors in Gym Hallway/Boys' Locker Room 8,000 ******Replace Double Wooden Doors from Hallway to Stage 2,000 ******Install New Security Cameras 4,525 TOTAL 135,525 63,500 97,000 56,000 84,000 2/11/2015 1

Chariho Career and Technical Center FY 16 FY 17 FY18 FY19 FY20 **Replace Septic System 60,000 60,000 ******Upgrade Culinary Kitchen 195,000 TOTAL 195,000 60,000 60,000 - - Hope Valley Elementary School FY 16 FY 17 FY18 FY19 FY20 *Provide Accessible Path to Courts and Fields 10,000 *Replace Wood Fiber Tile Ceilings 15,000 *Provide Elevator in 1935 Building 175,000 175,000 *Repair 1955 Building Exterior Masonry 10,000 *Replace VAT and Carpet 50,000 *Replace Window Treatments 16,000 *Replace Roof on 1955 Addition 135,250 135,250 *Upgrade Master Clock 16,000 *Upgrade Intercom 90,000 *Upgrade Fire Alarm System 34,000 *Add Grease Interceptor for Pot Sink 5,000 *Replace Galvanized Water Pipe 12,000 *Upgrade Corridor Ventilation 35,000 *Upgrade Kitchen Exhaust Fan 6,500 *Replace Display Cases 4,500 **Replace Furniture 2,000 2,000 2,000 2,000 *****Install Auto Door Closures 7,200 ******Refinish HV Gym Floor 15,000 ******Playground Fence 3,336 ******Interior Doors of the Old Section 30,000 TOTAL 73,436 249,250 185,950 218,000 265,000 Richmond Elementary School FY 16 FY 17 FY18 FY19 FY20 Replace Remaining Concrete Curb 18,000 *Create, Sign and Stripe Passenger Drop-Off Area 5,000 *Correct Approaches to Accessible Entrances 9,000 *Provide Curb Cut and Accessiblility to Flag 1,000 *Redesign Traffic Areas 25,000 75,000 *Upgrade Intercom, ****Including Cafeteria 40,000 *Provide New or Repaired Chain Link Fence 3,000 *Repave Play Area Behind School 30,000 *Provide Accessible Paths to Play Structures 3,000 2/11/2015 2

Richmond Elementary School FY 16 FY 17 FY18 FY19 FY20 *Replace Weather Stripping at Windows; Replace Screens 6,000 *Replace Window Treatments 20,000 *Replace Asphalt Shingle Roof 182,500 182,500 *Repair Exterior East Foundation 18,000 *Repair Damaged Masonry 10,000 *Replace Plumbing Fixtures in Newer Portions of Building 50,000 *Kitchen Hood Suppression System 7,500 *Upgrade Toilet Exhaust System 60,000 *Upgrade Kitchen/Café Exhaust System 77,000 ** Upgrade Alarm System 10,000 **Remove Asbestos Floor Tiles 30,000 30,000 **Sheetrock Ceilings 10,000 **Replace Furniture 2,000 2,000 2,000 2,000 **Replace Gutters 20,000 **Replace Kitchen Landing 10,000 **Install AC in Library 8,000 **Waterline Payments 32,500 32,500 32,500 32,500 32,500 **Replace Septic System 100,000 ****Install Kindergarten Playground Fence 5,000 ******Repair Sheds 7,500 ******Replace Interior Doors 51,000 TOTAL 202,100 282,500 171,500 267,000 355,000 Charlestown Elementary School FY 16 FY 17 FY18 FY19 FY20 *Construct Islands to Define Parking/Entrance 70,000 *Provide Accessibility to Entrances 7,500 *Clean and Re-Set Catch Basins; Replace Pipes 80,000 *Correct Accessibility to Fields and Playgrounds 14,000 *Provide Signage and Islands to Segregate Buses from Parking 5,000 *Pulverize and Re-Pave Parking Lot and Drive; Provide Curbing 25,000 55,000 *Replace Concrete Walks and Curbs 56,000 *Replace Damaged Interior Doors 20,000 *Replace Corridor Ceiling Tiles/Grid 16,500 *Upgrade Dishwasher Exhaust System 25,000 *Upgrade Gymnasium Return Register 5,000 *Upgrade Gymnasium Storage/Office HVAC 25,000 **Remove Asbestos Floor Tiles 30,000 **Replace Furniture/Cafeteria Tables 2,000 2,000 2,000 2,000 ****Install Shades re: SmartBoards 2,000 2/11/2015 3

Charlestown Elementary School FY 16 FY 17 FY18 FY19 FY20 ******Install Security Cameras 5,600 ******Ceiling Fan Replacements in Cafeteria 3,000 ******Hot Water Line Replacement 10,000 TOTAL 42,700 27,000 289,500 32,000 75,000 Ashaway Elementary School FY 16 FY 17 FY18 FY19 FY20 *Provide/Repair Chain Link Fence 3,000 *Clean Catch Basins and Drainage Manholes 5,000 *Repair Rear Stairs 20,000 *Make Nature Trail ADA Compliant 3,000 *Pulverize and Repave Parking Lot and Drive 25,000 45,000 *Provide Accessible Pathways to Play Structures 3,000 *Create Separation from Parent Drop-Off Loop and Play Areas with Curbs/Planters 20,000 *Add Concrete Pad for Dumpster and Screen 10,000 *Provide Dedicated Bus Drop-Off Area 25,000 *Replace Interior Doors 50,000 *Provide Smoke Vents for Stage 15,000 *Replace Windows 175,000 175,000 *Upgrade Electrical Service 81,000 *Upgrade Intercom 50,000 50,000 *Replace Plumbing Fixtures 65,000 65,000. *Upgrade Make-up Air for Generator 10,000 *Upgrade Corridor Ventilation 35,000 *Upgrade Gymnasium Distribution System 77,000 **Install Elevator 300,000 **Replace Furniture/Cafeteria Tables 3,500 2,000 2,000 2,000 2,000 **Replace Gymnasium Floor 55,000 **Refinish Stage 5,000 **Replace Underground Septic Piping 75,000 **Upgrade Gymnasium/Restroom Ventilation 9,500 ****** Install 4 Security Cameras 3,676 ******Install New Floor for Portable Building 5,534 TOTAL 96,310 152,500 499,000 376,000 352,000 The RYSE School FY 16 FY 17 FY18 FY19 FY20 TOTAL - - - - - 2/11/2015 4

Administration Building FY 16 FY 17 FY18 FY19 FY20 ******Install new Buzzer System 3,000 TOTAL 3,000 - - - - Maintenance and Technology Building FY 16 FY 17 FY18 FY19 FY20 TOTAL - - - - - District FY 16 FY 17 FY18 FY19 FY20 **Replace Maintenance Vehicles 25,000 25,000 ******Facility Study Update 25,000 TOTAL 50,000-25,000 - - GRAND TOTALS 844,571 872,750 1,341,950 992,000 1,191,500 Housing Aid (386,336) CTC Categorical Aid (195,000) Out-of-Scope Wiring Reimbursement (42,000) 221,235 *Existing Facilities Evaluation, Kaestle Boos Associates, Inc., February 16, 2011 **FY12-FY16 Capital Plan (Duplicate Entries Have Been Eliminated) *** Added 2011-2012 ****Added 2012-2013 *****Added 2013-2014 ******Added 2014-2015 2/11/2015 5