Adaptive Management Strategies for Resilient Coastlines: A Case Study on the Ft. Pierce, FL Breakwater Project

Similar documents
Improvement of the Atlantic Coast of New York City,

Beneficial Use at Deer Island A Decade of Design and Implementation. Mississippi Water Resources Conference Jackson, Mississippi April 3, 2012

Green or Grey Solutions? Why not both? Lessons from the Mid-Atlantic on Hybrid Living Shorelines

Sconset Geotextile Tube Update Sconset Bluff, Nantucket. Maria Hartnett, Associate

Pontchartrain Coastal Lines of Defense Program Figure 1 Figure 2 Figure 1

5 TH ANNUAL CAPE COASTAL CONFERENCE

July 22, 2013 REQUEST FOR PROPOSALS TO PROVIDE ENGINEERING DESIGN SERVICES FOR A PROJECT ALONG THE WESTERN SHORE OF MOBILE BAY

w ie v r e v O m e t S y S

Peoria Riverfront Development (Ecosystem Restoration) Upper Mid-sized Island Critical Restoration Project (September 2011)

Funding, Designing, and (eventually) Building Miles of Shoreline and Acres of Wetlands and Oyster Reefs on an Urbanized River!

ALTERNATIVE SHORELINE MANAGEMENT IN COASTAL MISSISSIPPI

GEOSYNTHETICS ENGINEERING: IN THEORY AND PRACTICE

BEACH AND INLET PROJECTS UPDATE

Living Shoreline Professionals Advanced Training. August 24 & 31, 2017 Hosted by Virginia Institute of Marine Science College of William & Mary

INSTALLATION OF GEOTEXTILE TUBES USED FOR COASTAL AND RIVERINE STRUCTURES GLOBAL SYNTHETICS PROTUBE GEOTEXTILE TUBE

Habitat Improvements to the Motor Island Shoreline in the Upper Niagara River, NY: A Collaborative Approach

2013 Summer Recap. Rockaway Beach

Natural Infrastructure for Coastal Resilience Unlocking Funding Resources

North Carolina Coastal Federation

River Mile 10.9 Removal Action Overview

State of the State New Jersey. Steve Jacobus NJDEP 06/10/15

EROSION & SEDIMENT CONTROL

OYSTER LAKE RESTORATION PROJECT

Coastal Planning in Texas. Tony Williams Senior Director of Planning Coastal Resources Division Texas General Land Office

CHAPTER Committee Substitute for Senate Bill No. 1472

Broward County Shore Protection Project Segment II. Physical Monitoring Plan

Options for Managing Coastal Erosion. Presentation by: Ashley Sprague

Introducing Green Infrastructure for Coastal Resilience

Hunts Point Landing, Bronx, New York

Shoreline Master Program Town of La Conner, Washington

September 30, 2011 REQUEST FOR PROPOSAL TO PROVIDE ENGINEERING DESIGN SERVICES FOR A PROJECT ALONG THE WESTERN SHORE OF MOBILE BAY

2014 HDR 2014 Architecture, HDR, Inc., all all rights reserved. reserved.

Presentation to Parks and Open Space Advisory. Committee September 22, 2016

New York City, 19 th c.

Sierra Club Comments on ACOE Public Notice NAE Re: Proposed Town Neck Beach Project at Sandwich, Massachusetts

E R O S I O N C O N T R O L

Living Shoreline Fundamentals

Dauphin Island s East End Beach and Barrier Island Restoration Project. April 16, :00 PM Dauphin Island Sea Lab, Shelby Hall

NORTH KINGSTOWN PILOT PROJECT May 9, 2016 North Kingstown Town Council

.MANAGED RETREAT. Need for managed retreat

APPLICATIONS IN FILTRATION AND DRAINAGE & EROSION CONTROL

Joe Pool Lake Lake Master Plan Public Information Meeting Presentation of Final Draft Revision July 31, 2018

Building Ecological Solutions to Coastal Community Hazards: Guidance and NJ Coastal Community Assistance

Coastal and River Erosion Control. Erosion

GEOTEXTILE TUBES AS ECONOMICAL AND ENVIRONMENTAL REPLACEMENT OF ROCKFILL FOR CONSTRUCTION OF POLDER DIKE IN SAEMANGEUM PROJECT, KOREA

EEA Capital Investment in Green Infrastructure

Floating Wetlands Pilot Project:

INSTALLATION GUIDELINES. Mirafi FM Filter Geotextiles for Basal Filtration Applications

Karen A. Duhring Marine Advisory Scientist Center for Coastal Resources Management Virginia Institute of Marine Science College of William & Mary

Learning Objectives. Thinking about Tomorrow s Waterfront Parks Lessons from Hurricane Sandy and Beyond. Hurricane Sandy

NC Coastal Management Program Update. Mike Lopazanski Policy & Planning Section Chief April 3, 2015

Section Specification for Geotextile Used in Permanent Erosion Control Application

Balancing Conservation and Development on the Jordan River

April 11, 2016 Park Board Chair and Commissioners General Manager Vancouver Board of Parks and Recreation New Brighton Salt Marsh - Preferred Concept

Russ J. Joffrion, P.E. Whitney Thompson, P.E.

Waterfront Redevelopment. City Council Briefing May 15, 2006

ORDINANCE NO

Natural Resource Adaptation Action Area Addressing Sea Level Rise in Estuarine Ecosystems TO: TOWN OF YANKEETOWN MAY

Geotextile Tube Structures: Example Contract Specifications

Monitoring and Maintenance Permit Process

City of Rockingham. Local Management Practices, Costs and Strategic Coastal Planning

Mitigation + Adaptation Strategies for Historic Structures and Sites

Restoring Water Ecosystems in NYC Parks

An Integrated Approach for Water Management Examples from The Netherlands. Addressing Climate Change and Sea Level Rise

HILCORP ALASKA, LLC KALOTSA PAD

REVETMENT WORKS- MUSKERS BEACH

Part 4: CRS Stormwater Management Activity (450) and Urban Flooding Best Practices

Lawrencetown Beach & Rainbow Haven Beach

EXHIBIT A CITY OF FORT WALTON BEACH, FLORIDA COASTAL MANAGEMENT & CONSERVATION

Design Guidelines for the Enhancement and Creation of Estuarine Habitats in the Middle Reaches of the Lower Columbia River

FirstLight Power Shoreline Management Manual Sustainable Shoreline Designs: From Long Island to Lake Erie Webinar Series

Yes Local NOAA Marine Fisheries (expertise and assistance)

SILT FENCE MACHINE SLICED ERO-1A STEEL FENCE POST (T-POST), MINIMUM 5' LONG, 6' MAXIMUM SPACING.

Lessons Learned from Katrina and Reducing Vulnerability Fall 2011

Coastal Engineer IV, Mott MacDonald, Morado Circle, Suite 300, Austin, TX 78759, USA, T: ,

field note Culvert foundation improvement design concepts The challenge of low-cost culvert foundations

NC Division of Coastal Management

A. INTRODUCTION B. CUMULATIVE EFFECTS ANALYSIS

Storm Water Quality and Shoreline Restoration Improvements - Grant Funding Request City of Mound Carlson Park Bolton & Menk Project No.

30% Design Technical Report

TREASURE ISLAND PHASE ONE PROJECTS PUBLIC ART PROJECT OUTLINE

PUBLIC SPACE/AMENITY PROJECTS

STREAM ALTERATION PRACTICES

Bioengineering Shoreline Protection

Louisiana Lawmakers Approve Historic Hurricane Protection Plan

Phase 1 Habitat Replacement & Reconstruction

J. K. Gupta, Scientist D, Bureau of Indian Standards

Empowering Local Action for Coastal Resilience in Massachusetts. Bruce K. Carlisle MA Office of Coastal Zone Management

COASTAL MANAGEMENT ELEMENT. Last amended December 6, 2016 as part of the 2016 EAR

Goals and Strategies. Goals. Strategies. Long-term Beach and Shoreline Management Program

Appendix to Amicus Curiae Brief: Selected Provisions of the South Carolina Beachfront Management Act

1. Seattle Central Waterfront Park

Scarborough Waterfront Project

Presenta/on Outline. Sea Level Rise Adapta/on Guidelines for Sea Dikes & Coastal Development 11/24/11

Karyn M. Erickson, PE, D.CE, F.ASCE

Lake Nokomis Shoreline Enhancement Project

Post Construction BMPs

SECTION TABLE OF CONTENTS GEOTEXTILE TUBES PARAGRAPH TITLE PAGE NOS.

A TWENTY YEAR PLAN TO RESTORE NAPLES BAY. Natural Resources Manager

WATERFRONT PLACE CENTRAL MIXED USE REDEVELOPMENT PROJECT

Transcription:

Adaptive Management Strategies for Resilient Coastlines: A Case Study on the Ft. Pierce, FL Breakwater Project USACE Workshop November 21 st, 2013 By: Jenna Phillips

Emphasis on Green or Nature-Based Engineering Solutions for Resiliency

OUTLINE Background & Project Goals Construction Materials Tolerances Site Conditions Installation Lessons Learned

Project Location

Project Location Ft. Pierce Inlet Downtown Waterfront Indian River Lagoon

Original Marina Layout

2004 Hurricane Frances

2004 Hurricane Season

Project Funding City applied for FEMA public funding assistance for the amount exceeding the City s insurance coverage FEMA s Hazard Damage Mitigation program provides funding for improvements that reduce the magnitude and cost of damages from future storms According to FEMA, Hurricane Frances had a recurrence interval of approx. 9 years Low recurrence interval was key in showing that substantial island construction could be economically justified Hurricane Frances was just one of four damaging storms to hit FL which helped to shift the political landscape to allow more robust solutions

Project Evolution & Timeline September 2004 Hurricanes Frances Feb 2005 Plans for restoration begin Nov 2006 Numerical modeling work beings Feb 2007 Physical model testing at Queens University in Canada August 2009 project went before FL Governor & Cabinet for final approval. Board set moratorium on subsequent large filling projects until 2 years post-construction monitoring Dec 2010 US Army Corps issues permit with special conditions Late 2011 Project went to bid Feb 2012 NTP issued

Project Purpose Project Goals 100-Yr Storm Protection Positive Environmental Impact Eco-Tourism/ Aesthetically Pleasing Physical Model Queens University

Project Layout 12 Island Breakwaters & 1 Peninsular Structure Total of 14.66 Acres Ecological Enhancements Oyster Recruitment 1.28 Acres Mangrove Habitat 1.54 Acres Juvenile Fish & Shorebird Habitat Native Plantings $18.9 Million Construction Cost NTP Issued February 2012 Construction Finished End of July 2013 Phase I Phase II replacement of dock structures

Design Criteria 100 Yr Storm Event: Fetch Length: 22 km Water Depth: 12 to 18 ft Design Wave Ht: 6.2 ft Wave Period: 5.1 sec Surge Elev: +10.5 NGVD For 50 Yr Event: Limit interior wave ht to < 1.15 ft Promote water quality/flushing within marina basin

Tern Island Island Geometry 10.5 Acres 1,500 lf x 300 ft 7 Groin Structures Sand Backfill in Interior Ecological Enhancements Living Shoreline Natural Limestone Reefs Roosting Areas

Construction Components Geotextile Tubes 10,700 lf Perimeter Dike for Island Creation Structural Core of Groins Bench for Living Shoreline Marine Mattress 250,000 sf Foundation for Stone Placement & Scour Apron Geotextile Tube Protection Matrix for Oyster Recruitment & Mangrove Plantings

Geotextile Tubes High strength polypropylene, woven geotextile with UV stabilization MacTube OS500 Approx 500 ppi Tube Sizes: 45 circumference 30 circumference Custom lengths

MacTube Design Considerations: Geotextile Tubes Tube Geometry GEOCOPS Fabric & Seam Strength (Factor of Safety) Pumping pressures Sediment characteristics of fill material (upland borrow site) External Stability Calcs (Courtesy of Prof. Leschinsky)

Marine Mattress Compartmental structures composed of high density, flexible, UV stabilized, polypropylene geogrid. Dual Project Purpose: Protective Cushion Layer for 2.5 to 5 ton Limestone Boulders Tube Foundation/Scour Protection Mattress Types: BX EG 027 6 Thickness UX EG115 12 Thickness

Mattress Dimensions: Lengths = 10, 15, 20, & 25 Width = 5 & 6.5 Stone Fill: Marine Mattress Ranges from 2 to 6 in diameter Approx. Weight = 110 pcf (12 x 20 mat weights ~5.5 Tons)

Marine Mattress: Bi-Axial Onsite Preparation

Marine Mattress: Uni-Axial Onsite Preparation

Geotextile Tubes Horizontal +/- 12 Vertical varied based on application Marine Mattresses Varied based on application. Tube coverage = 3 Perimeter = 0 Interior = 8-12 Construction Tolerances

Site Conditions Water Depths No Impact on mattress and tube installations. Water Clarity Impacted marine mattress installations. Currents Impacted tube installations; V = 2 m/s

Production Rates 450 CY in approximately 4 hours Corresponds to ~100 LF of 45 Circ. Tube Geotextile Tube Installation Installation Methodology 1. Install scour protection. 2. Deploy tube at slack tide. 3. Anchor tube in place. 4. Fill until design elevation achieved.

Production Rates 450 CY in approximately 4 hours Corresponds to ~100 LF of 45 Circ. Tube Geotextile Tube Installation Installation Methodology 1. Install scour protection. 2. Deploy tube at slack tide. 3. Anchor tube in place. 4. Fill until design elevation achieved.

Production Rates 450 CY in approximately 4 hours Corresponds to ~100 LF of 45 Circ. Tube Geotextile Tube Installation Installation Methodology 1. Install scour protection. 2. Deploy tube at slack tide. 3. Anchor tube in place. 4. Fill until design elevation achieved.

Marine Mattress Installation Peak Production Rates 70 Top Cover Mats 30 to 40 Perimeter Mats Installation Methodology 1. PVC stakes guide installations. 2. Crane and lifting bar for rough placement. 3. Guide and divers make final adjustments.

Marine Mattress Installation Peak Production Rates 70 Top Cover Mats 30 to 40 Perimeter Mats Installation Methodology 1. PVC stakes guide installations. 2. Crane and lifting bar for rough placement. 3. Guide and divers make final adjustments.

Marine Mattress Installation Peak Production Rates 70 Top Cover Mats 30 to 40 Perimeter Mats Installation Methodology 1. PVC stakes guide installations. 2. Crane and lifting bar for rough placement. 3. Guide and divers make final adjustments.

Lessons Learned Scour protection b/w tube installations. Incorporate straps into bag designs. Site conditions will dictate installation rates. Perform periodic inspections. Experience a must for tube/mattress installations in adverse conditions with tight tolerances.

Project Benefits 100-yr Storm Protection Ecological Benefits Living Shorelines Natural Limestone Armor Reefs Roosting Areas Increase in Revenue Marina Capacity Eco-tourism Serves as pilot study for future projects

July 2013 Substantial Completion

July 2013 Substantial Completion

Thank You Jenna Phillips Coastal Engineer/Technical Manager jphillips@maccaferri-usa.com (301) 331-3787