SECTION ELECTRICAL SYSTEMS COMMISSIONING

Similar documents
Michigan State University Construction Standards COMMISSIONING OF FIRE ALARM SYSTEMS PAGE

Fire Smoke Damper Actuator Replacements SECTION COMMISSIONING OF HVAC

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

SECTION SECURITY TESTING AND COMMISSIONING

SECTION GENERATOR PARALLELING CONTROLS

SECTION AUTOMATIC TRANSFER SWITCHES

SECTION AUTOMATIC TRANSFER SWITCHES

Emery County Senior Center Green River 06/07

SECTION AUTOMATIC TRANSFER SWITCHES

SECTION DIGITAL, ADDRESSABLE FIRE-ALARM SYSTEM

CONTENTS AUTOMATIC TRANSFER SWITCHES

1.1 DESCRIPTION A. The purpose of this section is to specify Division 23 responsibilities in the commissioning (Cx) process.

A. Product Data: Include rated capacities, operating characteristics, furnished specialties, and accessories.

SECTION ENCLOSED CONTROLLERS

WESTIN HOTEL. Smoke Control System. Testing Procedures Manual. October 10, Copyright Impact Engineering, Inc All Rights Reserved

AIRPORT OFFICE BUILDING. Smoke Control System. Testing Procedures Manual. September 10, 2016

SECTION GAS-FIRED RADIANT HEATERS

UFGS (November 2008) UNIFIED FACILITIES GUIDE SPECIFICATIONS

PROJ. NO SECTION PAGING, SPEAKERS AND HARD-WIRED CLOCK SYSTEMS

UFGS (August 2011) UNIFIED FACILITIES GUIDE SPECIFICATIONS

SECTION PACKAGED COMPRESSOR AND CONDENSER UNITS

SECTION PANELBOARDS. A. Drawings and general provisions of the Contract, including General and Supplementary Conditions, apply to this Section.

SECTION ISOLATED POWER SYSTEMS

D. Reference Standards (Utilize latest editions available):

CRESTRON: GREEN LIGHT NETWORK LIGHTING CONTROLS 1

B. Configuration of system shall be through Schneider Electric in Homewood, Illinois (Jerry Lanfear ).

Arc Flash Analysis: IEEE Method versus the NFPA 70E Tables July 2017 / 1910DB1702

SECTION Fire Pumps

SECTION P01 LIGHTING AND APPLIANCE PANELBOARDS - A-SERIES

.4 Do complete installation in accordance with latest Electrical Bulletins of the local inspection authority.

Moreno Valley Fire Department Fire Prevention Bureau. New and Existing Fire Alarm & Signaling Systems Guideline

Rancho Cucamonga Fire Protection District Prevention Bureau Standard

HMC ARCHITECTS 2495 Natomas Park Drive, Studio 100 Sacramento, California ADDENDUM NO. 3

1.3 REFERENCE STANDARDS

University of Houston Master Construction Specifications Insert Project Name SECTION DRY-PIPE FIRE SPRINKLER SYSTEM PART 1 - GENERAL

IN2 Lighting Control Devices

Design & Construction Standards, Revised January

SECTION DOMESTIC WATER PUMPS

SECTION AUTOMATIC TRANSFER SWITCH

Introduction Consultant shall incorporate the material in the DSS into the project specifications.

SECTION CENTRAL BATTERY INVERTERS. A. This Section includes fast-transfer central battery inverters with the following features:

SECTION LIGHTING CONTROLS

A. This Section includes the following lighting control devices:

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 11/06/2018

SECTION ROTARY-SCREW WATER CHILLERS

DESIGN AND CONSTRUCTION STANDARDS SPECIFICATION GUIDELINES

SPECIFICATIONS - DETAILED PROVISIONS Section Magnetic Flowmeters C O N T E N T S

SECTION COMMERCIAL-KITCHEN HOODS

A. Furnish and install luminaires, lamps, ballasts and in-line fuses as herein specified and shown on the Drawings.

A. AMERICAN ARCHITECTURAL MANUFACTURERS ASSOCIATION (AAMA) 101: Appendix Dissimilar Materials.

FIRE & LIFE SAFTEY STANDARD

Design and Commissioning of Lighting Control Systems. Rick Miller, PE, LC, LEED AP RNM Engineering, Inc. October 18, 2012

SECTION EXTERIOR LIGHTING

SECTION PACKAGED ROOFTOP AIR CONDITIONING UNITS

UNIFIED FACILITIES GUIDE SPECIFICATIONS

VACUUM BREAKER MEDIUM VOLTAGE AUTOMATIC TRANSFER SWITCHES

CITY OF LONG BEACH Department of Development Services BUILDING AND SAFETY BUREAU FIRE ALARM / ELECTRICAL FIRE PLAN REVIEW CHECKLIST

A. Hydraulic calculations shall be prepared in accordance with Chapter 23 of NFPA 13 with the following exceptions:

SECTION (16460) - LOW-VOLTAGE TRANSFORMERS

COUNTY OF KINGS KINGS COUNTY JAIL EXPANSION PHASE III

SECTION AUTOMATIC TRANSFER SWITCHES PART 1 - GENERAL

DTW Master Specification Section EMCS: Start Up, Verification and Commissioning

MODEL RLY-DIM-D INSTALLATION INSTRUCTIONS

SECTION SPLIT-SYSTEM AIR-CONDITIONERS

Revitalize Building Mechanical Systems (4619)

C. ASME Compliance: Fabricate and label water chiller heat exchangers to comply with ASME Boiler and Pressure Vessel Code: Section VIII, Division 1.

East Central College

KINGS COUNTY JAIL EXPANSION PHASE III COUNTY OF KINGS SECTION

NATIONAL ELECTRICAL CODE (NEC) & NFPA 70E ARC FLASH ELECTRICAL SAFETY

C. Shop Drawings: For boilers, boiler trim, and accessories. Include plans, elevations, sections, details, and attachments to other work.

1. Distribution panelboards. 2. Lighting and appliance branch-circuit panelboards. 3. Load centers.

SECTION PLUMBING/HVAC FINAL TESTING, ADJUSTING AND BALANCING

SECTION LOW VOLTAGE LIGHTING CONTROLS

SECTION ROTARY SCREW WATER CHILLERS Vibration Isolation Pumping Equipment (HVAC) Induced Draft Cooling Tower

Brown University Revised June 29, 2012 Facilities Design & Construction Standards SECTION ELECTRICAL DESIGN CRITERIA

CAN/ULC-S INTEGRATED SYSTEMS TESTING OF FIRE PROTECTION AND LIFE SAFETY SYSTEMS

SECTION LIGHTING CONTROL DEVICES AND CONTROL PANELS

SECTION FUNCTIONAL PERFORMANCE TESTING (FPT) PROCEDURES - CONSTRUCTION MANAGER EDITION

CxA to Answer this Section

SECTION CENTRIFUGAL WATER CHILLERS Vibration Isolation Pumping Equipment (HVAC) Induced Draft Cooling Tower

Update all extract references to NFPA documents (including NFPA 72) in Chapter 3 and related annex material to the latest editions.

CAN/ULC-S1001, INTEGRATED SYSTEMS TESTING OF FIRE PROTECTION & LIFE SAFETY SYSTEMS Simon Crosby, LEL, CET, CFPS October 21, 2015

DETEX ARCHITECTURAL SPECIFICATIONS, June 2012 AO19 SERIES HEAVY DUTY LOW-ENERGY ELECTRIC SWING DOOR OPERATOR

Are You Prepared? The impending impact of Code on Servicing Security Systems

A. Air-conditioning and Refrigeration Institute (ARI) - Standard 550/590, latest edition, and ARI certification program.

CAN/ULC S Integrated Systems Testing of Fire Protection and Life Safety Systems and Fire Protection Commissioning

SECTION SPLIT-SYSTEM AIR-CONDITIONERS

Union County Vocational - Technical Schools Scotch Plains, New Jersey

Guide Specification Model CTG Automatic Transfer Switch

CAN/ULC-S1001, INTEGRATED SYSTEMS TEST OF FIRE PROTECTION AND LIFE SAFETY SYSTEMS

A. This Section includes transfer switches rated 600 V and less, including the following:

XRRS Specification Fire Ready Hood

NFPA 2001: Standard for Clean Agent Fire Extinguishing Systems NFPA 70: National Electrical Code (NEC) NFPA 72: National Fire Alarm Code

UNIFIED FACILITIES GUIDE SPECIFICATIONS

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

VERIFICATION OF FIRE ALARM SYSTEMS

City of Duluth Festival Center 04/25

MODEL FPT-130 SINGLE POINT FREEZE PROTECTION HEAT TRACE CONTROL

1. Division 26 Section Electrical General Requirements. 2. Division 26 Section "Wiring Devices" for wall-box dimmers and manual light switches.

Architectural Specification Sheet

Transcription:

SECTION 16990 PART 1 - GENERAL 1.01 SECTION INCLUDES A. Section Includes: 1. General requirements for Commissioning (Cx) of lighting systems components, lighting controls and HVAC systems line voltage interconnection components, including installation, start-up, testing and documentation according to Construction Documents and Commissioning Plan (CxP). 2. Standard procedures for the execution of commissioning work shall be in conformance with Division 1, Section 01810 General Commissioning Requirements. Coordinate all work with the Commissioning Agent (CxA). 1.02 RELATED SECTIONS: NOTE TO PROJECT ARCHITECT: EDIT THIS SECTION AS APPLICABLE TO EACH PROJECT. 1. Provisions of Division 01 apply to this section. 2. Section 01810: General Commissioning Requirements. 3. Section 01820: Maintenance & Operations Staff Demonstration & Training. 4. Section 15700: Heating, Ventilation, and Air Conditioning Equipment. 5. Section 15990: HVAC Systems Commissioning. 6. Section 16950: Environmental Control and Energy Management Systems. 7. Section 15995: Building Management System Commissioning. 8. Section 16010: Basic Electrical Requirements. 9. Section 16050: Basic Electrical Materials and Methods. 10. Section 16060: Grounding and Bonding. 11. Section 16120: Low Voltage Wires (600 Volt AC). 12. Section 16220: Motors and Drives. 13. Section 16420: Motor Control Centers and Motor Control Devices. 14. Section 16500: Lighting. 15. Section 16515: Lighting Control Systems. 16. Section 16555: Theatrical Lighting and Stage Dimming Systems (Middle and High Schools). 16990-1

17. Section 16556: Theatrical Lighting and Stage Dimming Systems (Elementary Schools). 18. Project Commissioning Plan. 1.03 REFERENCES A. Applicable codes, standards, and references: all inspections and tests shall be in accordance with the following applicable codes and standards, except as provided otherwise herein: 1. National Electrical Testing Association NETA. 2. National Electrical manufacturer s Association NEMA. 3. American Society for Testing and Materials ASTM. 4. Institute of Electrical and Electronic Engineers IEEE. 5. American National Standards Institute ANSI. 6. National Electrical Safety Code NESC. 7. California Building Code CBC. 8. California Electrical Code CEC. 9. Insulated Power Cables Engineers Association IPCEA. 10. Occupational Safety and Health Administration OSHA. 11. National Institute of Standards and Technology NIST. 12. National Fire Protection Association NFPA. 13. ANSI/NFPA 70 National Electrical Code. 14. ANSI/NFPA 70B Electrical Equipment Maintenance. 15. NFPA 70E Electrical Safety Requirements for Employee Work Places. 16. ANSI/NFPA 101 Life Safety Code. 1.04 SUBMITTALS A. Submittals shall include the following: 1. Submit required Cx submittals in accordance with Division 1 Specification Sections. 2. Copy of the Architect s reviewed and accepted submittals to the CxA via the OAR. 3. List of team members who will represent the Contractor in the Pre-functional Equipment Checks and Functional Performance Testing, at least two (2) weeks prior to the start of Pre-functional Equipment Checks. 4. Detailed manufacturer installation and start-up, operating, troubleshooting and maintenance procedures, checklist documentation and field checklist forms to be used by factory or field technicians, and a copy of full details of Ownercontracted tests, full factory testing reports, if any, and Warranty information, including responsibilities of Owner to keep Warranty in force, clearly defined. 16990-2

5. Detailed manufacturer s recommended procedures and schedules for Prefunctional Equipment Checks, supplemented by Contractor s specific procedures, and Pre-functional Tests, at least four (4) weeks prior to the start of Pre-functional Performance Tests. 6. After facility s commission is complete, submit all completed Pre-functional Equipment Checklists and Functional Performance Test checklists organized by system and by subsystem. Bind all information in a single package. The results of failed tests shall be included along with a description of the corrective actions taken. NOTE TO PROJECT ARCHITECT: EDIT THE FOLLOWING ARTICLE AS APPLICABLE TO REFLECT PROJECT SPECIFIC REQUIREMENTS. 1.05 MEETINGS, SEQUENCING AND SCHEDULING A. Meetings: Attend (Cx) meetings as required under Section 01810 and the Cx Plan. B. Sequencing and Scheduling: The work described in this Section shall begin only after all work required in related Division 16 Sections has been successfully completed, and all tests, inspection reports and Operation & Maintenance manuals required in Division 16 Sections have been submitted and approved. The start-up and Pre-functional Equipment Checklists shall be completed and submitted to the Owner s Authorized Representative (OAR) prior to the Functional Performance Tests. Refer to the project Cx Plan for more details. 1. Coordinate all electrical work with the work of other trades prior to scheduling of any Cx procedures. 2. Coordinate the completion of all electrical testing, inspection, and calibration prior to start of Cx activities. 3. Cx activities shall be scheduled in accordance with project s Cx plan. 1.06 QUALITY CONTROL NOTE TO PROJECT ARCHITECT: EDIT THE FOLLOWING ARTICLE AS APPLICABLE TO REFLECT PROJECT SPECIFIC REQUIREMENTS. A. Comply with Owner s Quality Control Specifications, Sections 01400 01405, as applicable. B. Incorporate manufacturer's recommended Cx procedures for the systems and equipment to be commissioned under this Section. PART 2 - PRODUCTS 2.01 TEST EQUIPMENT A. Equipment to be utilized in the commissioning process shall meet the following requirements: 1. Provide test equipment as necessary for the equipment and systems to be commissioned. 16990-3

PART 3 EXECUTION 2. Provide testing equipment and accessories that are free of defects and certified for use. 3. Provide testing equipment with current calibration labels per NIST Standards. 4. All testing equipment shall be UL Listed. 3.01 COMMISSIONING PROCESS REQUIREMENTS A. Work to be performed prior to commissioning: 1. Complete all phases of the work so the system(s) can be started, tested, adjusted, balanced, and otherwise commissioned. 2. Start-up services required to bring each system into full operational state and ready for functional performance testing: a. Completion of prefunctional checklists. b. Manufacturer s Authorized Representative Start-up as required c. Contractor start-up d. Testing. e. Motor rotation check. f. Control sequences of operation. g. Full and part load performance. 3. If modifications or corrections to the installed systems are required to bring the system(s) to acceptance levels due to Contractor s incorrect installation or defective materials, such modifications or corrections shall be made at no additional cost to the Owner. 4. Start-up services required to bring each system into full operational state and ready for functional performance testing: a. Completion of prefunctional checklists. b. Manufacturer s Authorized Representative Start-up as required c. Contractor start-up d. Testing. e. Motor rotation check. f. Control sequences of operation. g. Full and part load performance. 5. Commissioning shall not start until each system is complete and the above items are completed and approval has been received by the OAR B. Pre-commissioning Responsibilities: Inspection, calibration and testing of the equipment and apparatuses to commission the following systems: 16990-4

1. Electrical Lighting Systems. 2. Lighting Controls. 3. HVAC line voltage electrical components. 4. Line voltage interface of Environmental Controls and Energy Management System with other systems. C. Commissioning Process Requirements: 1. Refer to Section 01810 General Commissioning Requirements, related sections and Cx Plan for information on meetings, start-up plans, Pre- Functional and Functional Performance Testing (FPT), operations & maintenance data, and other Commissioning activities. 3.02 PREPARATION A. Provide certified electricians or other qualified personnel as required with tools and equipment necessary to perform all Cx activities. B. Provide equipment manufacturer s factory representative(s) for commissioning of classrooms lighting and its control system, Theatrical Lighting Controls, and Energy Management and Environmental Control Systems as required by the Cx Plan. C. Provide certified testing agency personnel and/or report(s) as required in the Cx Plan. 3.03 TESTING A. Testing documentation shall include the following minimum information: 1. Test number. 2. Equipment used for the test, with manufacturer and model number and date of last calibration. 3. Date and time of the test. 4. Indication of whether the record is the first commissioning test or a retest following correction of a previously identified problem or issue. 5. Identification of the system, subsystem, assembly, or equipment. 6. Conditions under which the test was conducted, including (as applicable) ambient conditions, set points, override conditions, and status and operating conditions that impact the results of the test. 7. Systems and assemblies test results, performance and compliance with contract requirements. 8. Issue number, if any, generated as the result of the test. 9. Name and signature(s) of witnesses and the person(s) performing the test. B. Test lighting and controls systems performance to verify operation, functionality, light levels, energy usage, and compliance with construction documents. 16990-5

1. Contractor shall start up, test and document results under the observation of the CxA. 2. Contractor shall execute the Functional Performance Test (FPT) under the observation of the CxA who will record the results of the Functional Performance Test procedures. 3. Equipment & Components to be tested: Refer to Article 3.01, B. 4. Functions and Testing Conditions: a. Occupancy sensors and timer controls for lighting: 1) Verify that all specified functions and features are set up, debugged and fully operable at time of test. 2) Verify that occupant override feature functions properly and as intended in the contract documents. 3) Verify that sensor durations are set properly. 4) Test the sequence of operation for all features and modes and confirm that adjustable timing matches the design specifications and contract documents. b. Electric lighting dimming, photocells and controls: 1) Test the dimming controls during daytime when conditions are such that controls should be dimming electric lighting. Verify that amperage changes in light fixtures are proportional to external light changes. Verify that dimmed light levels at the specified work plane remain within specified limits. 2) Verify that delays and ramp times are set and functioning so that the speed of change of light fixture output is slow enough to not bother occupants and in compliance with the specifications. 3) Verify that dimming does not cause lower than specified light levels in adjacent non-dimmed spaces. 4) Verify that the controls and sensors cannot be easily overridden or disabled by occupants. 5) Verify that dimming systems in places of assembly are interfaced with the Central Fire Alarm system. Dimmed lighting in these areas shall come back to full bright during a fire alarm condition. c. Illumination Levels, Night Conditions: 1) Verify that lighting throughout the building is operating automatically. 2) Test with doors closed (to simulate actual occupancy) and after finishes are complete. 16990-6

d. Illumination Levels, Day Conditions: 1) Verify that lighting throughout the building is operating automatically. 2) Test with doors closed (to simulate actual occupancy), after finishes are complete, and room is furnished. 3) Test at different times during the day, or under Ownerapproved simulated conditions, to ensure proper system response and to determine that lighting levels are within specified requirements. 4) Test the system for the different pre-determined settings. Quiet time, AV mode, and normal standard class operation. e. Lighting Power Density: Perform the test with all interior lighting turned on and any manual or automatic controls temporarily overridden. The lighting power shall be measured at the building s electrical panels. Measurements shall be taken at least one (1) minute after all lighting in the building is on. f. Emergency Lighting System: Verify that the system operates automatically under any condition, without human intervention, and that it resets back to normal operations after the power failure is over or cleared. 5. Acceptance Criteria: a. Lighting Controls: For the conditions, sequences and modes tested, the dimming/occupancy/photocell/timing controls, integral components and related equipment respond to changing conditions and parameters appropriately as defined in the Contract Documents. b. Illumination Levels: Average light levels in the tested space at the work plane elevation shall not be less than 10% below nor greater than 20% above the specified light level range for the space. c. Lighting Power Density: Average instantaneous lighting power density is +/- 10% of that indicated in the Construction Documents. Power factors on lighting circuits shall be 0.95, or as required by lighting fixture specifications. 6. Sampling Strategy for Identical Units: a. Lighting Controls: Test all automatic interior lighting controls. b. Illumination Levels: At least 50% of all space zones and rooms, chosen by the Owner, shall be verified as realizing proper light levels. If 25% of the spaces in the first sample fail the Functional Performance Tests, test another 10% of the untested space zones and rooms (the 2nd sample). If 10% of the spaces in the 2nd sample fail, test all remaining spaces. 16990-7

c. Power Density: Test all lighting circuits. C. HVAC Electrical Component Testing. Contractor shall: 1. Document HVAC Division 16 electrical components using the startup procedure submitted by Contractor and accepted by the CxA. 2. Complete all requirements of the Prefunctional Checklists. 3. Verify the following information prior to HVAC system equipment startup. a. Voltage. b. Phase. c. Motor Size. d. Lock Rotor Amperage. e. Full Load Amperage. g. Minimum and Maximum Circuit Ampacity. h. Feeder protection or branch circuit protection, breaker or fuse size as applicable. 4. Coordinate and check corresponding unit electrical protection size and code required clearances. D. Contractor shall participate and perform all Cx related testing requirements prescribed under Sections 01810 and the approved project Cx Plan. 3.04 ADJUSTING A. Systems improperly adjusted, incorrectly installed equipment and/or deficient Contractor performance may result in additional work being required for Cx acceptance. 1. Contractor shall perform all work required to correct installations not meeting contract requirements at no additional cost to the Owner. B. Corrective work shall be completed in a timely manner to permit completion of the Cx process. 1. Contractor shall refer to the Cx Plan for retesting requirements necessary to achieve required system performance. 2. If the systems Cx deadline, as defined in the Cx Plan, goes beyond the scheduled completion of Commissioning without resolution of the problem, the Owner reserves the right to obtain supplementary services and/or equipment to resolve the problem. 3.05 TRAINING A. Provide training and documentation as required in applicable Division 16 specification sections, and related sections. END OF SECTION 16990-8