Impairments to Fire Protection Equipment

Similar documents
Risk Management Services

Table OUT OF SERVICE. Building Fire Video 1/15/ Inspection, testing and maintenance. Standards Further Referenced by FCNYS

Subject: Fire Protection Impairment Program Reference: NFPA (see bottom of page 5) Effective Date: August 2014 Distribution All YC Employees

UNIVERSITY OF ROCHESTER ENVIRONMENTAL HEALTH & SAFETY

DUQUESNE UNIVERSITY. Fire Protection System Impairment Program (Red etag Permit)

Fire System Impairment Policy

UC Irvine Environmental Health & Safety TITLE: FIRE WATCH AND OUT OF SERVICE NOTIFICATION

Hot Work Policy. Department of Risk Management. 1. Purpose. 2. Authority. 3. Scope

UNIVERSITY. Facilities Management

Chapter 12 HOT WORK OPERATIONS. Purpose:

Management Practices: Fire Protection Impairments November 2015

Date Issued: December 14, 2017 Revision: 2.1

HOT WORK PERMIT PROCEDURES

UNIVERSITY OF TOLEDO

Agency for Health Care Administration

1.2 To ensure the safety of all persons working in or occupying a building where a hot work operation is performed.

Builders Risk - Fire Prevention Inspection Checklist

Managing Fire Protection System Impairment

Safety & Security Services Services de Sûreté et Sécurité. Hot Work Protocol

John Jay College of Criminal Justice HOT WORK PERMIT STANDARD OPERATING PROCEDURES

Hot Work Program & Operational Guidelines. Environmental Health, Safety and Emergency Management (828)

I. Scope: II. Environmental Health and Safety Fire Alarm System Impairment Program - Guideline Revision Date: April, 2018

SURREY FIRE SERVICE. Construction Fire Safety Plan Bulletin

FIRE SAFETY AND PREVENTION POLICY

Xavier Field Office Fire Prevention Plan. for. Xavier Field Office Dana Avenue

HOT WORK SAFETY PROGRAM:

Safety Manual: Emergency Response

WELDING, CUTTING, AND BRAZING SAFETY PROGRAM

Statement of Policy. Fire Extinguisher Use Policy #: SMS-041

Chapter 18 Welding Table of Contents

Fire Prevention Plan

Austin Independent School District Police Department Policy and Procedure Manual

Evacuation Fire Safety Program

UNIVERSITY OF ROCHESTER ENVIRONMENTAL HEALTH & SAFETY

Written Fire Safety Plans

Safe Operating Procedure

2010 FIRE CODE OF NEW YORK STATE

Renovation Program. Renovation Program GENERAL

a) Establishment of emergency procedures to be followed at the time of an emergency;

HOT WORK OPERATIONS March 23, 2018

CLARK COUNTY FIRE DEPARTMENT Fire Hazard & Prevention Services 575 E. Flamingo Road, Ls Vegas, NV (702) FAX (702)

ADMINISTRATIVE SERVICES MANUAL

Emergency Action Fire Prevention Plan

Title: Fire Prevention During Welding, Cutting and Other Hot Work Plan (formerly the Cutting & Welding Policy)

FIRE PROTECTION PROGRAM

FIRE PREVENTION PLAN EMERGENCY ACTION

Fire Prevention Plan for Alter Hall 3743 Ledgewood Drive

Fire Prevention Plan for

SCALES NW EMERGENCY ACTION PLAN

Agency for Health Care Administration

Hot Work Permit. Can this job be avoided? Is there a safer alternative? Permit No.:

Fire Prevention Plan for Campus Services Building 1630 Musketeer Drive

Explosion Prevention & Suppression James Maness JEM Safety Consulting Rehoboth, DE.

Procedure DESCRIPTION/OVERVIEW

Introduction. Program Description. Section C.20 University of South Carolina Safety Program Guide FLAMMABLE AND COMBUSTIBLE LIQUIDS

BUILDING INSPECTION SAFETY PROGRAM MANUAL CHAPTER 5, REFERENCE # 1.4 August 1, 2009 OUT OF SERVICE (OOS) SPRINKLER AND STANDPIPE SYSTEMS

Fire Watch Program. Building Administrators Building Administrators will inform building occupants about fire watch events and building evacuations.

DRAFT REGULATORY GUIDE DG-1069 FIRE PROTECTION PROGRAM FOR NUCLEAR POWER PLANTS DURING DECOMMISSIONING AND PERMANENT SHUTDOWN

Contractor Safety. Workplace Safety & Environmental Division

Initial Version Revision No. 0 Next Review Date: Preparation: Safety Mgr Authority: President Issuing Dept: Safety Page: Page 1 of 6

CAMPUS COMMUNITY FIRE AND LIFE SAFETY POLICY

FIRE PREVENTION IN THE USE OF CUTTING OR WELDING PROCESSES

Purpose: To establish procedures for identifying fire hazards and preventing fires. Scope: All Central New Mexico Community College (CNM) Community.

Fire Prevention Plan for Residence Life 1625 Musketeer Drive

Chapter 4: Fire Protection Systems

OUTLINE FOR FIRE PREVENTION ACTIVITY

Temporary LPG Heat for Construction Sites Information Packet

This policy applies to all Hot Work jobs performed on the Calhoun mill property by AbitibiAbitibiBowater employees.

Hot Work Policy and Procedures

BURN NOTICE: KEEP THE HEAT AWAY!

Temporary LPG Heat for Construction Sites Work At Risk and Inspection Information Packet

Agency for Health Care Administration

CLARK COUNTY FIRE DEPARTMENT Fire Prevention Bureau

Vacant Building Loss Prevention Best Practices

This policy may also be used for routine work orders that are Life Safety in nature and cannot be completed within 45-days.

FIRE SAFETY PLAN. Ceramics/Sculpture Building 47 Service Rd 1 S Winnipeg, MANITOBA. May / Prepared by: Chris Pancoe

ALLIANZ PROPERTY RISK MANAGEMENT CHARTER

Fire Prevention Plan

Demolition Permit Application (Please print and complete ENTIRE form)

FIRE SAFETY DURING CONSTRUCTION, ALTERATION AND DEMOLITION

IIPP. Injury & Illness Prevention Program Hartog Drive San Jose CA Responsibilities. Workplace Hazards. Training. Incident Investigations

Cold weather regions where temperatures can fall below freezing present a threat to any building housing water-filled systems.

If there are more than ten people working other than on the ground floor,

Facilities Services Utilities Shutdown Request Form

Fire Prevention Plan for Cintas Center 1624 Musketeer Drive

This copy courtesy ARS/MPI. This document is from a CD-ROM distributed courtesy of Appendix R Solutions. and Matrix Press, Inc. You may not alter,

Fire Prevention Plan for St. Barbara Hall 3904 Winding Way

Iowa State Fire Marshal

Fire Prevention Plan. California State University, Chico

Code Red Consultants- Fire Door Inspection, Testing, and Maintenance 1/5/2018. Learning Objectives. NFPA 241 Implementation

Nirmal Chandra Sinha. Supposed to complete(dd/ MM/YYYY) Comments after Physical Inspection

University of Maryland FIRE EVACUATION PLAN Columbus Center POLICE FIRE MEDICAL EMERGENCY - 911

FIRE SAFETY POLICY & EMERGENCY EVACUATION POLICY

Slight Harm Moderate Harm Extreme Harm Low Trivial Risk Tolerable Risk Moderate Risk Medium Tolerable Risk Moderate Risk Substantial Risk

Savard Labor & Marine Staffing, Inc. Fire Prevention Program Rev3/14

RISK ENGINEERING GUIDELINE.

Agency for Health Care Administration

CHAPTER 15: FIRE PREVENTION & AWARENESS POLICY

OXNARD FIRE DEPARTMENT Fire Watch Guidelines

Board Policy 6819 Fire Safety and Prevention Plan

Transcription:

Impairments to Fire Protection Equipment INTRODUCTION Buildings and equipment are provided with fire protection and/or detection systems to reduce property damage and interruption to business in the event of fire. These systems must be in service at the outbreak of fire to operate effectively. However, invariably there will be times when these systems must be shut down for maintenance, testing, system upgrade, or repair. Shutting systems off without taking proper precautions, or leaving these systems impaired longer than necessary, has been a contributing factor in many losses. In most cases, these losses could have been mitigated by properly managing the impairment. Developing a formal Impairment Management Policy that requires use of Impairment Permits is the best solution toward mitigating this risk. Empowering management to take full ownership and responsibility is critical, as they are most familiar with the fire systems and hazards. This document outlines the basic considerations needed to develop an effective Impairment Management Policy. Please contact your local Paragon Risk Engineering representative with any questions, or if you need assistance customizing a policy that meets your specific needs. LOSS EXAMPLES In January 1999, a fire occurred in a two-story frozen food preparation plant. A cooling unit overheated and ignited EPS (expanded polystyrene) insulation in a ceiling and roof assembly, allowing fire to spread across a false ceiling. Before the fire started, the automatic sprinkler system was shutdown because cleaning with high-pressure hoses and steam was causing false alarms. The fire department was not notified of the situation and the resultant loss was 15.8M. On 24 June 1999, a fire occurred in an old mill complex in a vacant one-story structure of wood-frame construction. Investigators believed that smoking materials caused the fire, which started in the grass outside the building. The warehouse s sprinkler system had been shut down before the fire and the resultant loss was 6.3M. If the sprinkler system had not been shut down, the fire would have likely been extinguished in the incipient stage. In August 2000, a fire occurred in a non-combustible building of general warehouse occupancy. The fire started in an electrical panel in a product storage room. Automatic sprinkler protection was shut down before the fire due to a water leak and the resultant loss was reported to be 8.8M. *The above are excerpts from the National Fire Protection Association (NFPA) Journal loss history IMPAIRMENT POLICY An impairment policy should include the following: A policy document that mandates use of a formal permit to monitor all impairments to fire protection and/or detection systems. Senior management support and endorsement for the policy. The policy should stipulate specific penalties for non-compliance. The policy should be effectively, and routinely, communicated to contractors and employees. The policy should be reviewed and improved periodically. Competent personnel trained to authorize and manage system impairments. A comprehensive checklist of precautions. Only competent personnel should manage or authorize impairments. These personnel should receive training so that they are familiar with the fire and explosion hazards and protection features at the site. They should also fully understand their operational responsibilities, which include initial site inspection, permit issuance, and a final check to ensure that

Paragon Risk Engineering Page: 2 of 5 protection/detection systems are restored to service. These individuals should be closely involved in the periodic policy review process. PRECAUTIONS The person authorizing and managing the impairment should consider the following points. If any of the following items are of concern, no permit should be issued until the condition is corrected. Affected area minimized. Duration minimized. Timing appropriate. Manpower sufficient. Contingency plans to restore protection promptly in the event of fire. Good Fire Department response anticipated. Combustibles relocated. Temporary automatic protection provided as practical or required. Manual protection satisfactory Ignition sources controlled and hazardous operations ceased. Hot Work Permit issued if required. Fire watch provided, if unreliable detection. Emergency Organization and Fire Department notified. Workers aware of permit requirements, required precautions, and/or the hazards involved. The person authorizing the impairment should always inspect the site and discuss the precautions with those performing the work prior to issuing a permit. They will be ultimately responsible for coordinating the fire watch, Emergency Organization and Fire Department participation, along with worker education. They should perform aggressive follow-up and should call the Fire Department after restoration. Minimize the size of the impaired area. Impairing multiple systems can result in an unnecessarily large exposure. Minimize the duration of the impairment by initially preparing the work area, and work continuously until the job is complete. If the impairment is due to planned work, make certain that the timing of the impairment is appropriate. Preplan with the Fire Department to assure that impairments will occur at a time when they can best respond. Have the Fire Department on-site for emergency impairments when all precautions can not be taken. Manpower is an important consideration with respect to minimizing the duration of the impairment, and for ensuring effective response to a fire. Workers need to understand the Impairment Policy, permit precautions, and should be familiar with the hazards in the affected area. Develop contingency plans to restore impaired protection promptly in the event of fire. Make temporary caps available to plug sprinkler lines. Assign personnel the responsibility of reopening sprinkler control valves quickly in the event of fire. Whenever possible, relocate combustible materials to eliminate or reduce the fire hazard. If practical, provide temporary partial protection if the impairment will be of extended duration (e.g. feed automatic sprinklers through fire department connections via hose lines). Ensure that adequate manual protection features are present (e.g. charged hose lines and portable fire extinguishers). Control all ignition sources and cease any hazardous operations. Pay particular attention to Hot Work, smoking, electrical equipment, static electricity, molten materials, spontaneous heating, and/or sparks or hot surfaces associated with mechanical equipment. Hot Work should only be performed if proper precautions are taken and the work is supervised via issuance of a Hot Work permit. Hot Work should not be performed if alternatives such as sawing, bolting, or gluing are practical, or if automatic fire protection systems are impaired. Request that the fire department stand by during emergency impairments to fire protection systems if Hot Work must be performed in an unprotected combustible occupancy. A fire watch should be conducted in the affected area unless in-service, full-coverage detection is provided. Hourly surveillance of all affected areas will be sufficient for most occupancies. Increased frequency should be considered in higher hazard occupancies. Always notify the Fire Department and Emergency Organization during the impairment. Solicit their participation as needed.

Paragon Risk Engineering Page: 3 of 5 Paragon Risk Engineering can be contacted with any questions that arise. If you require assistance with an impairment, please call us and one of our consultants will promptly return your call. SIGN OFF Tel: +1 (0) 888 505-4859 Dial 701 E-mail: impairments@paragonconsults.com After the impaired fire protection/detection system has been restored to service, the permit should be returned to the person or department who authorized the work. The time that the systems were restored should be recorded and the permit signed by the person(s) doing the work. The person or department who authorized the work should physically verify that the protection has been placed back in service before signing off. Impairment Permits should be maintained on file for documentation and policy review purposes. SAMPLE PERMIT The attached permit is included to assist the clients of Paragon Risk Engineering in developing their own Impairment permit. This permit can be amended as required, as a permit that is tailored to meet the needs of your specific site is much more effective than a generic form. We suggest that a two-part permit be employed. The person who authorizes the impairment should retain one copy for follow-up, and the other should be retained at the work site, preferably attached to the control device for the impaired protection. Printouts with copies can accomplish the same objective for sites that have infrequent impairments.

Paragon Risk Engineering Page: 4 of 5 Sprinkler System Impairment Sheet Attention : IMPAIRMENT DESK E-mail Address : impairments@paragonconsults.com Phone No/Fax No : 1-888-505-4859 From : Date : Company :. City : Fax No : Phone No : Location : Ref No : PLANNED IMPAIRMENT System to be Shutdown ( Please indicate by placing and ' x ' in the box ) Automatic Sprinkler System Fire Pump ( s ) Alarm System Fire Main Firewater Storage Tank Other ( e.g. CO2, Halon etc ) Comments : Reason for Shutdown : Area Affected : Start Time / Date : Estimated Duration : Precautions being followed : ( Please indicate by placing and ' x ' in the box ) Use shut off tag X Notify Fire Department X Notify department heads Notify Alarm Company Cease all hazardous operations Work to be continuous X Hose / extinguishers available Additional watchman surveillance Ban welding / cutting / hotwork Emergency connection planned

Paragon Risk Engineering Page: 5 of 5 No Smoking Continuous Fire Watch Other ( Please Specify ) Change to Impairment Conditions : Time Restored : pm INSTRUCTIONS : 1 Fill out Section 1 prior to shutdown ( 48 hours before where possible ) e-mail to address above 2 Fill out Section 2 and resend e-mail if there are any changes to the impairment. 3 Fill out Section 3 when the impairment is restored and e-mail Contact Paragon Risk Engineering if you require consultation: Tel: +1 (0) 888 505-4859 E-mail: impairments@paragonconsults.com