A Proposal for the Development of an Eco Park in Aya Nagar, New Delhi. Greha

Similar documents
Resolution XII NOTING also that with the increasingly rapid urbanization, wetlands are being threatened in two principle ways:

Draft Resolution XII.10

John M. Fleming Managing Director, Planning and City Planner. Old East Village Dundas Street Corridor Secondary Plan Draft Terms of Reference

PRESENTATION ON JOHANNESBURG S BIODIVERSITY PROGRAMME

The Gianyar Declaration 2017

Goals AND Guiding principles

MAGALIESBURG DEVELOPMENT INITIATIVE (MDI)

Design Guidance. Introduction, Approach and Design Principles. Mauritius. November Ministry of Housing and Lands. .. a

14.5 HOPEFIELD: (REFER PLAN 39 AND PLAN 40)

CITY OF COLWICH COMPREHENSIVE PLAN LAND USE LAND USE 1

13 THORNHILL YONGE STREET STUDY IMPLEMENTATION CITY OF VAUGHAN OPA 669 AND TOWN OF MARKHAM OPA 154

WATERFORD Plan of Preservation, Conservation and Development Supplement Part 1 - Policy Element

With the promotions and publicity of green. Moving Towards Sustainable Campus Design. Deciphering Green Architecture

SA N T I AG O D ES EA D O 1 AILET S U STA I N A B L E C I T Y S I M U L ATO R R A 710/21/161

2040 LUP is a part of the Comprehensive Plan and carries the same legal authority. Economic Challenges

CHAPTER 2 URBAN PLANNING AND DEVELOPMENT IN INDIA AND THE CASE CITY OF CHENNAI

ENGINEERING CONSULTANT OFFICE FOR UTILITIES

Transportation. Strategies for Action

Published in March 2005 by the. Ministry for the Environment. PO Box , Wellington, New Zealand ISBN: X.

Call for Artists for: Design and Construction of Environmental Art Activation Story Mill Community Park, Bozeman, MT

KTDC HOTELS & RESORTS LIMITED MASCOT SQUARE, TRIVANDRUM - 33

EXHIBIT A. Tax Increment Reinvestment Zone No. 1 (Town Center) First Amended Project Plan 1

PSRC REVIEW REPORT & CERTIFICATION RECOMMENDATION

Preliminary Plan Framework: Vision and Goals

The Dreispitz in Basel / Switzerland: New economy on old sites

LEADERS IN URBAN TRANSPORT PLANNING. Ahmedabad Urban Development Authority

Urban Development and Planning in Vienna

Delhi May 6-7, Paper to be published in Urban Update during South Asian Cities Summit organized by AIILSG and UCLG, New

CITY OF HAMILTON PUBLIC WORKS DEPARTMENT Environmental Services Division

KONZA TECHNOPOLIS DEVELOPMENT AUTHORITY

CANADA 952.0M 7,500 SELECTED AWARDS NET REVENUES BY MARKET SEGMENT (%) 2016 ANNUAL REPORT TRANSPORTATION & INFRASTRUCTURE 25 PROPERTY & BUILDINGS 19

Public Art Plan. We have elected to submit Public Art Plans before or concurrently with the CSP Submittal per the FDP Manual

DEVELOPMENT MANAGEMENT REPORT

THE ARCHITECTURAL POLICY OF ESTONIA. Passed at the Parliamentary sitting , protocol no. 43, item no. 5

Report to: Development Services Committee Report Date: April 24, 2017

Comprehensive Plan ADOPTED APRIL 2014

CITY OF WEST PALM BEACH DOWNTOWN ACTION COMMITTEE Meeting Date: December 13, 2017

ENGINEERING CONSULTANTS (PVT.) LIMITED

Former Rockcliffe Airbase Community Design Plan Guiding Design Vision and Principles December 4, 2013

Ryoko Iizuka Finance, Economics and Urban Department

Brian Peterson, AIA, LEED-AP, CNU-A Introduction: the Art of Urban Design

MULTI-MODAL INTEGRATION

City of Heath. Town Center Concept

Fostering metropolitan cooperation for sustainable urban development THE MONTRÉAL DECLARATION ON METROPOLITAN AREAS

Social Screening and Impact Assessment for Sub Projects

BOARD OF ADVISORS Biographies

Ghent Neighborhood League Briefing Living at Sea Level & Flooding Risks

Proposed Amendment to the

A Study on Landscape Design Paradigm from the Perspective of Visual Impact and Experience

SOUTH AFRICA S PREPARATIONS FOR HABITAT III COMMON AFRICAN POSITION FOR HABITAT III. Habitat III Urban Breakfast 5 October 2016

E x E C U T I v E S U M M A R y / P L A N N I N G C O N T E x T 14 //

Purpose of the Master Plan

Public Consultation. Land at Monks Farm, North Grove. Welcome

CITY OF FARGO PARKING RAMP SITE EVALUATION

TREASURE COAST REGIONAL PLANNING COUNCIL M E M O R A N D U M. To: Council Members AGENDA ITEM 5H

Purpose of the Master Plan

HEALTH SCIENCES BUILDING REDEVELOPMENT PROJECT

18 21 July 2018 Sands Expo and Convention Centre, Marina Bay Sands, Singapore

Neeru, a Rainwater Harvesting Project for Rural India By Bharath Gowda(1&2)

Port Marigny TND Planning and Zoning Commission Workshop September 1, 2015 Preliminary Observations - David Bailey, AIA, AICP

Introduction. Introduction

DRAFT FOR PUBLIC REVIEW. Game Plan for a Healthy City

Implementing sustainable water strategy through development industry engagement

3 Urban Design and the State Highway Network

"Porte des Alpes" Urban Development

URBAN PLANNING IN ASEAN DEVELOPING COUNTRIES: THE MALAYSIAN CASE Foziah Johar Ph.D

1.0 Purpose of a Secondary Plan for the Masonville Transit Village

WELCOME. Land North of STEVENAGE. We would like to thank you for attending our public exhibition today.

INTRODUCTION TO TOWN PLANNING

Urban planning and Public Transport

INTRODUCTION BACKGROUND

TRANSPORTATION AND LAND USE

Green Roofs and Stormwater Management Virginia Stovin

RFP/RFQ. for Concept & Schematic Design Services. for Outdoor Garden Enhancements. to Cleveland Botanical Garden

Parish of Repton NEIGHBOURHOOD DEVELOPMENT PLAN

Uusimaa Regional Land Use Plan Summary

Task Force on Kai Tak Harbourfront Development

Horwood Map of London, Westminster & Southwark First edition

CITYWIDE PLANNING DIVISION

Municipal Development Plan 2013

Welcome to our exhibition

Keyport. Vision for Keyport

Integrated urban policies and land management The URBACT Experience Didier Vancutsem

WELCOME GYPSY LANE. Wider Site Location plan. Proposals for the development of LAND OFF FOXLYDIATE LANE WEBHEATH. Proposals for the development of

7-PARKS, OPEN SPACE & PUBLIC ART

Town of Oakville Streetscape Strategy

China. City and Regional Planning in. Absorbing 50 Years of ISOCARP. Statutory Planning System In China. Planning Legislation in China

arts, culture & Entertainment district

Request for Statement of Interest in Implementation of the Roosevelt Road Redevelopment Plan

CHAPTER 12 IMPLEMENTATION

Policy Manual. Municipality of North Cowichan DEVELOPMENT SERVICES

Chapter 22 Cities and Sustainability

RIGA LATVIA. KEY FEATURES OF THE CITY Demographic Facts. Urban Figures. Heritage. EXISTING GOVERNANCE MECHANISMS Development and Management Plans

Town of Cobourg Heritage Master Plan. Statutory Public Meeting

Table of Allocated Housing Sites

Historic Preservation Element

Appendix A. Planning Processes. Introduction

Municipal Action Teams

10 Principles for a Sustainable Development of Urban Waterfront Areas

The Village of Sugar Grove, in partnership with Kane County, the Illinois Department of Transportation, and the Illinois Tollway welcomes you to the

Transcription:

A Proposal for the Development of an Eco Park in Aya Nagar, New Delhi Greha 1.0. Background 1.1. Aya Nagar is situated on the Southwestern edge of Delhi. It is the last village of Delhi on the Mehrauli Gurgaon Road which connects South Delhi with the rapidly urbanizing city of Gurgaon in the adjoining state of Haryana. Although Aya Nagar is part of the rural fringe of Delhi, it is today a settlement of nearly 100000 people, half of which are the original rural inhabitants while the other half are low-income migrants from all parts of India. The new migrants have settled on the once agricultural lands of the village in an ill- planned manner and without legal sanction. 1.2. This pattern of unauthorized urban expansion has become, in the last few decades, an overriding phenomenon of urban development in the country, in spite of master

plans for urban development being prepared by the authorities for practically all the cities. The internal dynamics of this pattern, both physical and social, have not been adequately understood or addressed. 1.3. A registered non-profit voluntary organization called GREHA, which has been doing research and development work in the area of environmental planning, architecture, and building since1975, established itself in Aya Nagar in 1999 in order to work with the local community for urban transformation. An overall picture of the work done and yet to be done is sketched out in the attached document entitled A proposal for Comprehensive Redevelopment of Aya Nagar Village and its Proto-Urban Extension in New Delhi (Annexure A). 1.4. In the last few decades the rapid urban growth of Delhi has radically altered the habitational morphology of its surrounding areas. Aya Nagar is a typical example of such morphological change since it is situated on one of the major growth axes of the National Capital Territory of Delhi. The inhabitants of Aya Nagar are primarily from the marginalized sections of society, the original villagers being members of the indigenous Gurjar community, while the recent migrants are largely dispossessed landless labour and low-income settlers from economically backward regions of the country. This heterogeneous mix is a good representation of the common (wo) man of India, and the changing morphology of this settlement presents a vivid picture of the social implications of rapid economic growth in our times. 2.0. The Site 2.1. The original village settlement of Aya Nagar developed adjacent to a johar, which is a traditional rainwater harvesting structure (pond) commonly found in this part of the country. As the village habitation grew the johar location became more strategic to the extended settlement and assumed symbolic significance as a central place. AYANAGAR EXTENSION

2.2. The Aya Nagar johar is in danger of losing its vitality and character because of illconsidered building development around it which blocks rainwater flow and replaces this with storm water drainage mixed with sewerage flowing in open bricklined drains constructed by the Municipal Corporation. Furthermore the public transport (bus) terminus is located on one of the banks of the johar, thereby directly adding to environmental pollution. 3.0. The Proposition 3.1. The present proposal seeks to transform the johar into an eco park which can be a vital, functioning central place of the settlement. An important part of the proposal is to carefully record the process of transformation, both physical and social, so that an audio-visual document is made available to serve as a guide and a model for other communities facing similar problems across the country. 3.2. An essential feature of this proposal is that the transformation process will be led by the inhabitant community working in partnership with the local government agencies as well as supportive private sector corporations. A team of experts drawn from relevant disciplines like architecture, environmental planning, civil engineering, social sciences, community work, media and the arts coordinated by project management experts of GREHA, will work continuously with the project partners to provide technical guidance and monitor the various interlinked exercises to ensure reasonable compliance with original intentions. 3.3. There is no existing sewerage system functioning in Aya Nagar. Rehabilitation of the johar will be directly dependant on intercepting and treating the sewerage presently flowing in the open storm water drains and into the johar at several places. A full drainage scheme is part of the comprehensive project proposal attached, which envisages a decentralized system of neighborhood treatment plants managed largely by the residents. The present proposal includes a demonstration of this idea in one neighborhood near the johar. This is a neighborhood of 70 households who have expressed interest in being a partner in the demonstration exercise. This neighborhood will become the site for evolving appropriate sanitation and public health techniques which can be sustained by local initiative. 3.4. The physical transformation of the johar will include improving the linkages with the habitation and built fabric around the johar, and appropriate landscaping of the water body and its edges. A preliminary schema for improving linkages has been drawn up as indicated on the drawing below.

4.0 Estimate of Cost and Time 4.1 The physical work to be done in and around the johar has been arrived at after extended discussions with the inhabitants and brainstorming with concerned technical experts. A best judgment cost estimate has been made for the various components identified and represented in the schematic plan above: 4.2 Johar Works Rupees (in lacs) a) Arrival Chowk: 40.00 This is an important road junction between the road connecting to the Mehrauli Gurgaon Road, the village phirni (ring road), and the present bus terminus; the requirement is for road widening, a new bus stop, appropriate street furniture and landscaping. b) Community Centre: 50.00 There is a long standing demand by the inhabitants for a multi-purpose community building in a central place; the present bus terminus, located inappropriately on the edge of the johar needs to move towards the southern end of the settlement so it can serve the majority of users, and the present bus terminus site would be free for use as the community centre.

c) Open Air Theatre 25.00 The western edge of the johar is adjoining the village high school playing field; an amphitheatre here would benefit the school as well as becoming a venue for celebrating festive occasions by the general public. d) Market Interface 65.00 The main market of the settlement starts from the southern edge of the johar, making a tee junction with the village phirni (ring road) around the school and johar ; this edge is most suitable for becoming a craft work zone which can showcase the traditional crafts of the village; aligned with the market road, it is proposed to install a pylon with a large digital notice board, a modern version of the notice board placed in the central chowk of traditional villages. e) Village Windmill 60.00 The johar water body has two significant temples, one within, under the old banyan tree, and the other on the eastern boundary within the village habitation; it is proposed to connect the temples with an earthen dam which will allow the water on its northern side to be raised in level and contain a tube well for water augmentation, and a windmill to be located on the new bund to demonstrate the benefits of eco-friendly and energy conservation practices to the local community. f) Landscape Works 60.00 The johar has interesting existing features like the old banyan tree, other trees and small shrines; these features are to be integrated into a landscape design, after cleaning of the water body and required pitching, as well as plantation of indigenous species all around the water body. 4.3 One Neighborhood Demonstration of Sanitation Works a) Sewerage Intercepting Plant 45.00 One or several septic tanks with bacteria / enzyme dosing will ensure that effluent flowing in storm water drains will be safe for irrigation. b) Solid Waste Management 15.00 Techniques using composting methods and waste segregation practices which can be managed by the neighborhood residents will be advocated and instituted. 4.4 Survey and Audio-Visual Documentation 25.00

4.5 Cost Estimate of Works = Rs. 385.00 Lacs Total of 4.2 + 4.3 + 4.4 + Taxes as applicable 4.6 Contingency costs @ 4% = Rs. 15.00 Lacs 4.7 Time for Implementation After the design / drawings have been approved by local agencies, work on ground will range from six to twelve months, depending on the various components of the scheme outlined above. 4.8 Research, Design, Supervision & Documentation Costs = Rs. 35.00 Lacs + Service Tax as applicable The various experts required to work on the above will include Architects Environmental Planners Product Designers Communications Designers Artists Community Work Experts Civil Engineers Sanitation & Public Health Engineers Solid Waste Management Experts Project Coordination and Supervision Staff 4.9 Estimated Total Cost = Rs. 435.00 Lacs + Taxes as applicable Jan 2008