Fall 2017 Construction Update

Similar documents
Spring 2018 Construction Update

COMMUNICATION URBAN DESIGN REVIEW BOARD CITY OF DES MOINES, IOWA MAY 16, 2017 MEETING

STREET IMPROVEMENT AND MAINTENANCE PROGRAMS

City of Cedar Rapids Public Works Tentative Bid Schedule Issued December 4, 2017 *Subject to Change*

Cottage Grove Road Reconstruction. City of Madison Engineering

PROJECTS UNDER CONSTRUCTION

Derby-Shelton Bridge Pedestrian and Bicyclist Enhancements [1]

Public Works Project Delivery Report

THREE-YEAR CAPITAL IMPROVEMENT PLAN FY

2018 Primary Road Capital Improvement Plan (CIP) Projects Preservation / Structural Improvement, Non-motorized and Engineering Design Projects

Highway 15 Project - Hutchinson

FOR IMMEDIATE RELEASE DATE: FRIDAY, AUGUST 31, Road Commission of Kalamazoo County Weekly Project Updates HAVE YOU SIGNED UP?

INFRASTRUCTURE EXISTING INFRASTRUCTURE A. Circulation B. Signals C. Drainage D. Utilities

ROAD PAVING VARIOUS LOCATIONS LANE KM

WELCOME! 8 8:30 6: TH STREET IMPROVEMENTS. Open House. Presentation & Q&A

Capital Projects in and near Odenton Town Center

Index to Projects by Project Name

Downtown Redevelopment Project Update

IOWA HIGHWAY 57 / WEST 1 ST STREET STUDY PUBLIC INFORMATIONAL MEETING APRIL 22, 2014

Municipality of Anchorage. Community Council Survey Capital Projects Needs Ranking Survey (ALPHABETICAL) Airport Heights

FY 2018 TRANSPORTATION CAPITAL PROGRAM New Jersey Department of Transportation Projects

STANDARD SPECIFICATIONS Book 2 ENGINEERING DRAWINGS INCLUDES ADDENDUMS

TOWNSHIP OF HOWELL TOWNSHIP OF HOWELL ENGINEERING PROJECTS STATUS REPORT OCTOBER 19, Resurfacing of Aldrich Road West Contract # 11-06

TIRZ 17/Redevelopment Authority Capital Improvements Plan Projects

2016 REVISIONS COMMENT FORM RULES AND REGULATIONS FOR CONSTRUCTION IN THE PUBLIC WAY COMMENT PERIOD: JUNE 1 TO JUNE 30, 2015

MPRD s Keith Mione (Community) Park Midlothian Road Entrance Traffic Signals

Project will Replace: Utilities Curb Pavement Lighting. City of Madison

FOR IMMEDIATE RELEASE DATE: FRIDAY, SEPTEMBER 21, Road Commission of Kalamazoo County Weekly Project Updates HAVE YOU SIGNED UP?

Project Status. Construction is underway for Phase 3. Overall Project Area and Schedule. Schedule of Current Construction Phases.

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Projects

startup. Construction of contractor entrance off University City Blvd connecting to Lot 8 has started.

WELCOME TO OPEN HOUSE TWO November 28, 2018

FDOT D4 Complete Streets

Victoria Bridge Municipal Class EA Civic Works Committee

Construction Engineering & Inspection

FY 2005 TRANSPORTATION CAPITAL PROGRAM

Town of Yucca Valley Capital Improvement Projects Report July 24, 2014

CTH C RESURFACING Douglas County, Wisconsin

Memorandum CITY OF DALLAS. Riverfront Boulevard Design From Continental Avenue to Cadiz Street

8 October 14, 2015 Public Hearing

DESIGN PUBLIC HEARING MAY 10, 2018 GRANBY TOWN HALL FIRST FLOOR CONFERENCE ROOM 10 WEST STATE STREET GRANBY, MASSACHUSETTS 7:00 PM FOR THE PROPOSED

I-25 / Rio Bravo Interchange. I-25 / Rio Bravo Interchange. Presenters 11/30/2016 THIRD PUBLIC MEETING DECEMBER 1, 2016 NMDOT CN A300280

Welcome to the. Open House

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Project Descriptions ($ millions)

From local initiatives to some of the largest and most complex projects, KOA leads the field in:

Open House RIVER DES PERES GREENWAY: LANSDOWNE SHREWSBURY METROLINK TO FRANCIS R. SLAY PARK

Capital Projects impacting Odenton Town Center

Prince William Street Project (Grant Avenue to Wellington Road)

Kankakee River Bridge & Track Improvements Supplemental Environmental Assessment. May 5, 2016

EXHIBIT A 2019 FINANCING: PROJECT AUTHORIZATIONS

Moving The Metro. A special construction update for the metro Omaha area.

I-95 Girard Avenue Interchange Near Neighbors Meeting. Project Status

Grand River Ravines Georgetown Township

CITY OF SIMI VALLEY MEMORANDUM

Planning Districts INTRODUCTION

Municipality of Anchorage, Alaska Parks & Recreation Department

Shell Beach Road Streetscape Frequently asked Questions

FOR IMMEDIATE RELEASE DATE: FRIDAY, SEPTEMBER 28, Road Commission of Kalamazoo County Weekly Project Updates HAVE YOU SIGNED UP?

CONFORMED AGREEMENT INCORPORATED REVISIONS PER AMENDMENT DATED: APRIL 2, 2013 FOR REFERENCE

2017 General Obligation Bond

City of Grande Prairie Development Services Department

Proposed FY 2004 TRANSPORTATION CAPITAL PROGRAM New Jersey Department of Transportation Projects

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Projects

Concluding Improvement Recommendations and Opinions of Probable Cost (calculated in may 2010 construction rates).

Overall Map. Chicago. St. Louis. Summit. Joliet. Dwight. Pontiac. Bloomington-Normal Lincoln. Springfield. Carlinville. Alton EXPERIENCE IT YOURSELF.

WHEREAS, the CCSD has agreed to reimburse the City for the cost of the sidewalk, trail, and the bioretention area

COMPLETE GREEN STREET CHECKLIST

Rt. 29 Solutions Project Delivery Advisory Panel. December 3, 2015

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Projects

TRANSPORTATION COMMITTEE

Rt. 29 Solutions Project Delivery Advisory Panel. January 7, 2016

CAMPUS PLANNING COMMITTEE STAFF REPORT SAMARITAN SPORTS MEDICINE INSTITUTE AT OSU 10/21/2013

GYPSUM PARKWAY CORRIDOR ENHANCEMENT Gypsum, Colorado. Schematic Design January 2015

4.1 Build Alternative 1 Construction Phasing

Alternatives Development Three conceptual alternatives were developed for the Race Road/Jessup Village Planning Study and are described below:

Public Information Centre. Welcome

Project Goal. RRRC Living Towns Planning Workshp. Town of Halifax Revitalization Project. Dynamic Planning & Management Duo: July 12, 2006

Engineering Department

JOB CREATION PROJECTS

Clay Street Bridge Replacement Project

DESIGN CRITERIA PACKAGE

Ames City Hall Campus: Stormwater Improvements

2017 Investment in Infrastructure Expo February 28, 2017 Jason Jonas, P.E. Public Works Director

Creative Engineering Group Inc, (Creative) Construction Engineering and Inspection (CEI) Professionals

ALTERNATIVE STATION AREA -

Waukee. City of. The Key to Good Living

The open space system should provide connective elements, relate to natural resources, and enhance the suburban character of the landscape..

WELCOME TO THE PUBLIC INFORMATION CENTRE. Please Sign In

Michigan State University Barrier-Free/Accessibility Project Status Summary March 2017

2040 Long Range Transportation Plan

East Whiteland Township Current Land Development Projects

City of Miami MIAMI RIVER BASIN WATER QUALITY IMPROVEMENT REPORT FOR FIRST AND SECOND QUARTER 2010

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Projects

2017 Asphalt Contractors Association of Florida Pavement Awards

Monroe Street Reconstruction. Public Preconstruction Meeting February 21, 2018

University Park Subdivision Street Assessment Report

PROJECT UPDATE BON AIR ROAD BRIDGE REPLACEMENT AND MAGNOLIA AVENUE WATER QUALITY FACILITIES

CURRICULUM VITAE REZA MARSHAL, MECE, PE, PTOE

PennDOT Public Meeting. S.R. 3044, Section A01 Castle Shannon Boulevard Roadway Improvement Project

Johnson Street Bridge Public Realm Update

Transcription:

Fall 2017 Construction Update Ward 4 Southeast Engineering Department Riverwalk Red Multi-Use Trail Bridge Rehabilitation The Riverwalk Red Multi Use Trail Bridge was awarded to Cramer and Associates, Inc. for $2,458,787.30. This project has raised the bridge 4.5 feet, added LED lights, and ADA ramps at each end. The bridge was opened for use on May 26 th, 2017. The only item remaining to be completed is a handrail on the west end of the bridge.

Grand Avenue Bridge over the Des Moines River Replacement The new and improved Grand Avenue Bridge over the Des Moines River was open to traffic on Monday, November 20 th. As work is continuing on the bridge through the winter, only vehicular traffic is open on the bridge at this time, as well as access on the south sidewalk. A majority of the bridge is completed, however the aesthetic metal panels on the exterior of the bridge remain to be installed. These aesthetic panels will hide the bridge beams and will create a scalloped effect that will sweep across each bridge span. New LED lighting is incorporated into the pedestrian railing and will accent the aesthetic panels when they are installed. Currently, there is no public parking available on the bridge as it is currently reserved for the contractor s access. Also closed at this time are the bike lanes across the bridge, the north sidewalk, and the Principal Riverwalk Trail connections on the west side of the river. The project will be fully complete in summer 2018. Additional information regarding the project, along with detour maps and project updates can be found at https://projects.dmgov.org/.

2017-2018 Expanded Street Resurfacing Program - Contract 1 This project provides for maintenance of residential and arterial streets utilizing surface scarification and hot mix asphalt overlay to improve the surface condition and to extend the useful service life of the streets. The contract was awarded to Des Moines Asphalt & Paving at an estimated cost of $1,583,934.65. Work on this contract began in mid-june and the asphalt work was completed this fall. Sidewalk ramps will be constructed next spring to complete this project. The following streets located in Ward 4 were resurfaced this year: Street From To E. Park Ave South Union Street S.E. 5th Street S.E. 5th Street E. Park Avenue Watrous Avenue E. Grand Avenue Complete Streets Conversion from Des Moines River to E. 7th Street The project is a pilot program that includes restriping E. Grand Avenue from the Des Moines River to Penn Avenue to include protected bike lanes, and one lane of traffic and parking in either direction. The project included enhanced intersections with striped medians and vertical delineators for improved visibility and safety for cyclists. The contractor has completed all the main pavement markings, the green bike lane markings, raised bus stops and the vertical delineator posts. Minor adjustments have been made to the intersections and location of the vertical delineators based on public comments and operational observations from City Staff. Signage and minor traffic signal improvements will be completed in the spring of 2018.

Agrimergent Storm Sewer Phase 1 The Agrimergent Storm Sewer Phase 1 project was awarded to RW Excavating Solutions for $1,059,070. This project will improve storm water drainage along Vandalia Road, provide storm sewer access to the Regional Detention Basin for future Agrimergent Technology Park development, and provide a storm water outlet pipe for the future Southeast Connector project from S.E. 30th to Highway 65. The project included various size storm sewer pipe, storm sewer intakes and manholes, and ditch grading. The project has been substantially completed with only restoration work remaining in the spring. Women of Achievement Bridge Deck Surface Replacement The Women of Achievement Bridge Deck Surface Replacement was completed on October 23, 2017. The project was performed by Iowa State Contractors, Inc. The project included a new nonskid surface for the bridge.

2017-2018 HMA Pavement Scarification and Resurfacing Program This project provides for maintenance of residential and arterial streets utilizing surface scarification and hot mix asphalt overlay to improve the surface condition, and to extend the useful service life of the streets. The contract was awarded to Des Moines Asphalt & Paving at a contract amount of $897,881.45. Work on this citywide project began in July, and is scheduled to be completed by June 30, 2018. The following streets located in Ward 4 have been resurfaced: Street From To SE 5 th Street PCC South of E. McKinley Avenue E. Titus Avenue Park Avenue South Union Street SW 6 th Street City Hall Improvements The improvements include the replacement and/or rehabilitation of HVAC equipment; lighting and controls; installation of a new fire suppression system with upgrades to the fire alarm and detection system; architectural remodeling; data and phone cabling upgrades; new elevator for the south end of the building; remodeling of third floor Legal offices and first floor public restrooms. The project was awarded to Henning Paric Commercial, LLC on June 13, 2016. The City Council approved a second phase of the project to address remodeling of offices to add conference space, and modify offices and hallways in order to reconfigure working spaces to maximize space and service to the public. The project is planned to be completed in early 2018.

E. 2 nd Street Reconstruction from E. Locust Street to E. Grand Avenue The E. 2 nd Street Reconstruction from E. Locust Street to E. Grand Avenue contract was awarded to MPS Engineers, P.C. in the amount of $659,983.50. The project reconstructed E. 2 nd Street adding additional turning lanes to provide access to the new E. 2 nd Street Parking Garage. The construction activities were coordinated with the parking garage construction and the construction of the new building at 219 E. Grand Avenue. Access to properties east of the street was maintained during construction. E. 2 nd Street was opened this fall when the E. 2 nd Street Parking Garage and a retailer opened in the 219 E. Grand Building. Restoration work along the east side of Robert D. Ray Drive will be completed in the spring of 2018. Des Moines River East Storm Sewer Box Emergency Repair At the end of January, sink holes appeared along the Des Moines River outside of City Hall. With the cooperation of the Army Corps of Engineers, the river was lowered to allow staff to survey the area. It was discovered that there was significant scouring occurring under the storm sewer box. An emergency contract was bid and awarded to Cramer and Associates, Inc. When the contractor started the repairs, additional scour was found north of the Grand Avenue Bridge. The additional scour area has been repaired. The historic balustrade wall was displaced towards the river causing significant structural damage. The construction plan was revised to remove and replace the river wall instead of grouting the eroded soil below the wall. Work on the demolition and replacement of the wall has started and is scheduled to be completed in the summer of 2018.

Park Avenue Elementary Pedestrian Bridge Removal and Site Improvements The Park Avenue Elementary Pedestrian Bridge Removal and Site Improvements project was awarded to TK Concrete for $551,765.75. The project includes the removal of the pedestrian bridge over SW 9 th Street, intersection improvements at SW 9 th and Park Avenue, parking lanes along Park Avenue and SW 7 th Street, and sidewalk improvements around the school site. All work has been completed. BEFORE AFTER Leetown Creekway Box Culvert from Dean Avenue to University Avenue This project includes the construction of a 12-feet by 5-feet box culvert from Dean Avenue to University Avenue, which will alleviate storm water flows to the existing 5-feet by 6-feet concrete box culvert and existing 48-inches diameter culvert. The project has been awarded to S.M. Hentges & Sons Inc. for $7,795,330.07. Construction started in October and the contractor has been working on the relocation of existing utilities. Installation of the box culvert is expected to start this winter and the project completion is anticipated in 2019. E. McKinley Avenue Widening S.E. 7 th Street to S.E. 14 th Street with Access Bridge This project was awarded to Corell Contractor, Inc. for $4,885,816.20. One component of the project includes reconstructing E. McKinley Avenue from a two-lane roadway to a three-lane roadway with center turn lane from just west of SE 7 th Street to the intersection with SE 14 th Street. The reconstruction project also includes sidewalk construction and installation of new storm sewer and water main. Another component of the project includes constructing a new access between Southdale Center and reconstructed E. McKinley Avenue, including a continuous concrete slab (CCS) bridge across Yeader Creek. The new access will replace the existing access road located near the intersection of E. McKinley Avenue and SE 14 th Street. Project construction is anticipated to begin in early 2018.

Evergreen Avenue Bridge This improvement includes the replacement of the Evergreen Avenue Bridge over Easter Lake. The bridge was evaluated and it was recommended that the bridge be replaced due to the existing condition of the bridge. This bridge will be widened to include a sidewalk section for the trail that Polk County is constructing around Easter Lake. The project has been awarded to United Contractors, Inc. for $1,034,338.10. Construction started in June. The contractor has completed the deck of the bridge and is working on the approach paving and railings. The bridge is completed and the roadway was opened on December 8 th. Seeding and restoration will be completed in the spring. 2018 Sewer Lining Program This project provides for the lining of deteriorated sanitary sewers throughout the city. The installation of the liner restores the structural integrity of the pipe to prevent failures and also reduce groundwater infiltration into the sanitary sewer system. This project will bid in December and with construction to begin early in 2018. The work will continue for the rest of the year. The following sewer is planned for Ward 4: Street From To Logan Avenue E. 27 th Street 320 East

Historic Pillar Repair at Chaffee Road South of Army Post Road Construction work has been completed on the repair of the east gate pillar at the northeast entrance to the original Fort Des Moines campus. Located at the intersection of East Army Post Road and Chaffee Road, the pillar suffered damage due to a vehicular accident. Renaissance Restoration, Inc. from Galena, Illinois, was awarded the contract to reconstruct the east stone pillar and clean both the reconstructed pillar and undamaged west pillar. The total construction and cleaning cost was $35,162.33. BEFORE AFTER Ewing Park Lilac Plaza This improvement includes the construction of a plaza in Ewing Park. The plaza will be used as a lilac viewing area and as a venue for small events. The plaza is being funded as a partnership between the City of Des Moines Parks Department and private donations via the Friends of Des Moines Parks. The project was awarded to Cerebral Group, LLC for $263,441.70 as a part of the 2017 PCC Paving and Sidewalk Program. Construction started in October. The contractor has completed the paving and grading. Seeding and restoration will be completed in the spring.