Proposed St. Vital Transmission Complex

Similar documents
Alternative Route Selection

Alternative Routes. St. Vital to La Verendrye Station - Southern Loop Transmission Corridor. 20 different segments 4 segments common to all routes

Alternative Routes Determined

Presentation August 20, 2013

Inform you of the purpose and scope of the study for PTH 100 and a proposed future St. Norbert Bypass;

Rapid Transit Implementation Working Group September 14, 2017

Rapid Transit Implementation Working Group

NORTHEAST RIVER CROSSING FUNCTIONAL PLANNING STUDY

CONSULTING SERVICES FOR THE WHITEBELT VISIONING EXERCISE ADDENDUM TO THE GTA WEST LAND USE STUDY WORK PROGRAM

Letter of Notification For East Lima Station Expansion Project

Application for Certificate of Environmental Compatibility and Public Need

AMENDMENT NO. 30 TO THE OFFICIAL PLAN OF THE TOWN OF MILTON

Leaside to Main Infrastructure Refurbishment Project

Vaughan Metropolitan Centre (VMC) Black Creek Renewal CLASS ENVIRONMENTAL ASSESSMENT

Project 6 All-Season Road Linking Manto Sipi Cree Nation, Bunibonibee Cree Nation & God s Lake First Nation

COUNTY OF LAMBTON OFFICIAL PLAN UPDATE BACKGROUND REPORT NO.

Parks, Trails, and Open space Element

CALA Homes is preparing a planning application for a development of up to 36 new homes, including a mix of properties to meet local demand.

APPENDIX I Presentations

Project 6 All-Season Road Linking Manto Sipi Cree Nation, Bunibonibee Cree Nation & God s Lake First Nation

Appendix A. Planning Processes. Introduction

APPENDIX F: EXTERNAL APPROVALS

Canyon Lake Master Plan Revision Public Information Meeting March 18, 2016

Cape Environmental Assessment Practitioners(Pty)

Parks, Trails, and Open Space Element

TERRESTRIAL NATURAL HERITAGE SYSTEM STRATEGY APPENDIX F: MODEL POLICIES FOR THE IMPLEMENTATION OF THE TARGET TERRESTRIAL NATURAL HERITAGE SYSTEM

PURPOSE OF MEETING MEETING GUIDELINES PROJECT BACKGROUND ESKOM CLOCOLAN-FICKSBURG 88 KV POWERLINE, FREE STATE

April Parker Lands Major Redevelopment Site Environmental Overview. Submitted to: Prepared by:

ROSEMONT 138KV TRANSMISSION LINE SITING STUDY PROJECT

DRAFT SECTION 4(f) EVALUATION INTERSTATE 73 FEIS: I-95 to I-73/I-74 in North Carolina

Lake O the Pines Master Plan Revision Public Information Meeting April 25 & 27, 2017

Dorenell Wind Farm 132 kv Grid Connection

I. STAFF POLICY RECOMMENDATIONS. The following RMP policy strategies are proposed by staff in support of a Scenic Resource Protection Program:

Planning and Public Consultation Process for the Preparation of a General Land Use Plan for South Port Kells TERMS OF REFERENCE

SOUTHWEST TRANSITWAY (STAGE 2) PUBLIC OPEN HOUSE

Lewisville Lake Master Plan Revision Public Information Meeting May 2 & 4, 2017

Burloak Drive Grade Separation

A Guide to Open Space Design Development in Halifax Regional Municipality

MAYFIELD WEST SECONDARY PLAN PHASE 2

INTRODUCTION Key Issues and Findings Goals, Objectives, and Policies - Natural Resources - Map M18 - Environmental Resources

Call for Artists for: Design and Construction of Environmental Art Activation Story Mill Community Park, Bozeman, MT

Yadkin River Greenway Feasibility Study Fact Sheet Village of Clemmons, Town of Lewisville, Town of Bermuda Run

Municipal Obligations Archaeological Heritage Screening. Heritage Conservation Branch Ministry of Parks, Culture and Sport November 14, 2018

TOWN OF BRUDERHEIM Report to the capital region board

IMPLEMENTATION STRATEGY: GOAL 1: TO SUSTAIN A HEALTHY NATIVE PRAIRIE GRAZING RESOURCE

TRCA Field Staking Protocol December 2016

Edgeley Pond + Park Public Meeting

The Illinois Department of Transportation and Lake County Division of Transportation. Route 173, including the Millburn Bypass

Further input invited as Colchester Growth Strategy nears final phase

7.0 SOCIAL, ECONOMIC, AND ENVIRONMENTAL ISSUES

APPENDIX 1: SCOPED ENVIRONMENTAL IMPACT STATEMENT (EIS) FORM

APPENDIX L3. Table of Contents. SWP EA Information Sheets

March 21, 2018 ALCA Meeting. March 21, 2018

GTA West Transportation Corridor EA Study Stage 2. Introductory Community Workshop

New Brighton Park Shoreline Habitat Restoration Project

Planning Considerations for Wildlife Passage in Urban Environments. (Prepared by Tony Clevenger, PhD)

Riparian Buffer on the Bushkill Creek. Policies

BASIC ASSESSMENT REPORT. Background Information Document

OFFICIAL COMMUNITY PLANS (OCPs) AND ZONING BYLAWS (ZBs): PLANNING FOR THE FUTURE

Baby Point Wastewater Pumping Station Forcemain Class Environmental Assessment Study

EAST SELKIRK SECONDARY PLAN

3-2 Environmental Systems

An Introduction to the Far North Land Use Strategy

MAYFIELD WEST SECONDARY PLAN PHASE 2

What We Heard Public Engagement - Stage 1

TOWN OF BETHLEHEM MEETING SUMMARY LOCAL WATERFRONT REVITALIZATION PROGRAM UPDATE

Background Summary Report

Pittsburgh District Pittsburgh, PA Notice No Closing Date: May 29, 2015

The River Future. San Gabriel River Confluence with Cattle Canyon Creek Improvements Project (the Cattle Canyon Project)

The West Vaughan Employment Area Secondary Plan Policies

SECTION 4(f) DE MINIMIS DOCUMENTATION

Arkansas River Corridor

METROPOLITAN COUNCIL 390 North Robert Street, St. Paul, MN Phone (651) ; TDD (651)

Decision Notice. Proposed Action

Joe Pool Lake Master Plan Revision Public Information Meeting May 23, 2017

CHARLES COUNTY GOVERNMENT RFP NO POPES CREEK RAIL TRAIL DESIGN

ITS Concept Development Activity Descriptions

Pine Flat Lake Master Plan Update FACT SHEET September 2014

HAZARD MITIGATION GOALS AND OBJECTIVES

4.1 LAND USE AND HOUSING

Public Review Draft Oceanside Subarea Habitat Conservation Plan/ Natural Communities Conservation Plan

Artist Call for Expressions of Interest Port Kells Hall Mosaic Project RFEOI #

The Moors at Arne Project, Managing Coastal Change

CALGARY: City of Animals Edited by Jim Ellis

Nine Mile Creek Regional Trail Update. Edina City Council Workshop March 4, 2014

Stormwater Standards. Clackamas County Service District No. 1. Planting Guide for Buffers

ROSEMONT 138kV TRANSMISSION LINE PROJECT. Public Open House Meeting #2 August 27, 2009

Planning and Permitting

Public Information Centre. Welcome

LICENSES FOR UTILITY CROSSINGS OF PUBLIC LANDS AND WATERS ACCORDING TO MINNESOTA RULES CHAPTER [Rules Effective July 1, 2004]

Welcome. Mill Creek Ravine Pedestrian Bridges Rehabilitation. Public Information Session #1. Thursday, October 27, :00 8:00 p.m.

Public Information Centre

McArthur Swamp Planning Unit. Fish, Plant, and Wildlife Habitat MCARTHUR SWAMP PLANNING UNIT

S A C R A M E N T O C O U N T Y JACKSON HIGHWAY & GRANT LINE EAST VISIONING STUDY

Canadian Cataloguing in Publication Data Main entry under title: Managing our heritage resources: impact assessment.

City of Missoula and Missoula County Open Space Planning Open House

Phase I Ecological Network Report Terms of Reference

Red Hill Valley Project More Than A Road October 16, 2006

Thank you for coming. We want to hear your views on proposed improvements to the A1 between junction 65 (Birtley) and junction 67 (Coal House).

WELCOME. Welcome and thank you for visiting today.

Transcription:

Proposed St. Vital Transmission Complex Round 2 Preferred Route for the St. Vital to Letellier Line What is it? Manitoba Hydro is proposing construction of two 230-kilovolt (kv) transmission lines to improve system reliability and accommodate the growth in demand for electricity in southern Manitoba. Both lines will originate at the St. Vital Station, located in southeastern Winnipeg. One line will run west to the La Verendrye Station, located near Oak Bluff. The other will run south to the Letellier Station, located near Letellier. The new transmission line between the St. Vital and La Verendrye stations will be situated on an existing Manitoba Hydro right-of-way, located south of Winnipeg, (see page 3) known as the Southern Loop. The transmission line between the St. Vital and Letellier stations will be routed through southeastern Manitoba, near Steinbach in order to accommodate a potential future 230-kV station. Manitoba Hydro is seeking public input to finalize a route for this line that will be submitted for regulatory approval. How do we choose a route for the St. Vital to Letellier line? Our approach to developing a preferred route for the St. Vital to Letellier transmission line includes early stakeholder input and takes into account engineering considerations as well as the built and natural environment. In the first round of public engagement, we shared information, including alternative routes, with landowners, First Nations, the Manitoba Métis Federation, municipalities and other stakeholders as well as the public. We received feedback on the alternative routes through stakeholder workshops, public open houses, meetings and email and telephone communications. This included completed comment sheets, workbooks, mapped issues and concerns and route preferences. Route selection information was compiled from these sources, along with general comments from key person interviews, and used in development of the preferred route. In addition, discipline specialists evaluated cost, schedule, reliability and environmental considerations in determining the preferred route.

Project Timelines Round 1 - August Introduce the project Present alternative routes Answer questions Identify and document concerns Use input to guide preferred route selection process We are here. Round 2 - October / November Present findings of Round 1 Present the preferred route Answer questions Identify and document outstanding concerns Provide opportunity to discuss potential effects and possible mitigation measures to minimize effects Next steps Submission of the Environmental Assessment Report Regulatory authorities review report Receipt of licence Construction In-service for St. Vital to Letellier line: Fall 2016 Final project completion: 2017 The preferred route for the St. Vital to Letellier line The preferred route was determined by considering information supplied by specialists and feedback received throughout Round 1. Many alternative segments were presented by stakeholders, landowners and the general public. In total, four segments not initially presented during Round 1 are now considered part of the preferred route for the project. These have become part of the preferred route to address local concerns regarding aerial application, land use, current and future development, proximity to livestock operations and other concerns. We are seeking comments and feedback on the preferred route in order to refine it further. Upon completion of Round 2, we will file a final preferred route with Manitoba Conservation and Water Stewardship. What s next? Information gathered during round two of the public engagement process will assist in the identification of a final preferred route that balances technical, biophysical, and socioeconomic considerations. We will continue to: inform the public regarding the project, timelines and route selection process. utilize a variety of mechanisms to receive and share information with interested individuals. gather feedback on the local environment to help finalize the route as well as the environmental assessment. discuss mitigation measures to minimize potential impacts. provide the public with the opportunity to have their questions answered and concerns addressed by Manitoba Hydro representatives.

Tower Design For the St. Vital to La Verendrye transmission line, we will utilize a self-supporting steel lattice tower. These towers will be located on a 137 metre (m), (450 ft.) right-of-way and will vary in height from 30 to 40 m (98 to 131 ft.). They will be similar to existing transmission lines in the Sage Creek area of Winnipeg. For the St. Vital to Letellier transmission line, we will utilize a tubular steel H-frame structure. These towers will be located on a 23.75 m (78 ft.) right-of-way when following a road or mile line, or 40 m (131 ft.) when placed in a field. These towers will vary in height up to 27 m (89 ft.), depending on terrain and road and river crossings. Typical Tubular Steel Structure* Typical cross-section of transmission line structure adjacent to road allowance Self Supporting Suspension Lattice Steel Structure* Typical cross-section of transmission line structure located on 1/4 section line * Tower height and design are estimations and are dependent on terrain and final placement of the transmission line. Southern Loop The Southern Loop is a dedicated transmission corridor that will accommodate the multiple transmission lines necessary to provide system reliability and to meet future energy demands. This corridor will reduce the number of independent rights-of-way on the landscape. Situated between the Dorsey Converter Station (located near Rosser) and Riel Station (located east of Winnipeg), this transmission corridor follows the western and southern boundaries of the City of Winnipeg. It connects to the LaVerendrye Station, which is near Oak Bluff. Sage Creek Transmission Corridor Cross section looking north Potential Future Existing 115kV Future 230kV LaVerendrye - St.Vital Future 230kV St.Vital - Letellier This cross section is based on matching existing tower locations and right-of-way width. The numbers (in metres) below the transmission lines indicate the complete right-of-way width for the transmission line in that area.

What we heard Round 1 Comment/Concern Potential impacts to aerial application. How was the feedback incorporated? Structure height in agricultural areas will be minimized to the extent possible to mimic heights of distribution lines. Air strip locations were identified, incorporated into early planning and avoided as much as possible in final route selection. Impacts to agricultural operations. We will avoid half-mile (quarter section) alignments where possible. Guyed-wire structures are not being considered for this project. A tubular steel H-frame design, which has a smaller footprint than self supporting or guyed structures, will be utilized. Potential affect on livestock, particularly dairy cattle, e.g., tingle voltage. Tingle voltage tends to occur with faulted distribution lines as opposed to transmission lines. Livestock operators are encouraged to contact Manitoba Hydro if they notice tingle voltage occurring so that the source can be identified. Loss of high-quality farm land. We will route the line adjacent to road allowances to minimize the land area used for the transmission line and the related impact on farming activities. Will I be compensated if the transmission line is on my land? Manitoba Hydro provides a one-time compensation payment for transmission line easements (75 per cent of market value), as well as one-time structure payment related to loss of annual production. We also compensate landowners for any damages which may occur through the construction and operation of the line. Proximity to farmsteads and shelterbelts. During routing, we avoid residences and shelterbelts as to the extent possible. Many areas are flood prone. The potential for flooding was taken into account but does not hinder operation of the transmission line. Locate transmission lines within existing Hydro transmission line corridors. This is being done where feasible; a portion of the line passing through Sage Creek is in an existing Manitoba Hydro corridor as is the Southern Loop. Locate transmission line infrastructure adjacent to linear infrastructure such as provincial and municipal highways and roads and drains in order to reduce land requirements. Existing corridors and linear features were identified as routing opportunities in the route selection process and are being taken advantage of where possible. We will consult with Manitoba Infrastructure and Transportation (MIT) on future planning before developing alignments near PTH 75, PTH 59 and PTH 52. Minimize transmission line crossings of major highways and rail lines, as well as stream crossings. Concern that stream crossings impact riparian habitat. Such crossings, which require higher and more costly towers, were minimized.

Comment/Concern Avoid landfills, lagoons and cemeteries. How was the feedback incorporated? Locations of landfills, lagoons and cemeteries were noted. Structure placement will avoid these areas. Transmission tower aesthetics. Towers that will be placed adjacent to existing towers will have similar spacing and heights. Potential impact on wildlife, including birds, vegetation, riparian area, endangered species and wetlands The environmental assessment process will identify potential environmental sensitivities and will prescribe appropriate mitigation measures. Concern that construction will disrupt fur-bearing animals and affect trapping. The environmental assessment process will identify potential sensitivities related to fur-bearing animals and will prescribe appropriate mitigation measures such as modifications to construction scheduling. Avoid heritage sites. The environmental assessment process will identify heritage resources, including archaeological sites, which will be avoided. Perceived health effects due to electric and magnetic fields (EMF). Information will continue to be provided in the public engagement process and these concerns will be addressed in the environmental assessment process. Health Canada, the World Health Organization, and other international health entities have noted that no scientific evidence suggests that exposure to EMF will cause any negative health effects on humans, vegetation and wild or domestic animals. Transmission line rights-of-way become areas for growth of noxious weeds and potential bio-security issues. We will take necessary precautions as part of construction of the project to minimize the risk of invasive plants and diseases spreading. Manitoba Hydro is currently developing a bio-security policy. Noise, dust and disruption of traffic, particularly related to emergency services, during construction. Construction operations will minimize noise and dust. Construction traffic routes and detours will be identified and made available to local police, fire and emergency services. City, municipal and business and industry stakeholders, in particular, noted beneficial effects of a more secure power supply on their operations and growth. Agricultural stakeholders also noted that they are impacted by electrical power system reliability. The beneficial effect on power system reliability and capacity is a fundamental reason for this project.

What happens after a final preferred route is selected? Following the determination of a preferred route and the filing of the environmental assessment report to Manitoba Conservation and Water Stewardship, we are planning to meet with affected landowners. These meetings will be held exclusively for affected landowners and will outline the following: Manitoba Conservation and Water Stewardship s public review process for the environmental assessment report submitted by Manitoba Hydro. Manitoba Hydro s compensation policy. What to expect during the land surveying process. What to expect throughout construction of the project. We encourage all affected landowners to attend this meeting to learn: How the project will unfold after Manitoba Hydro files the environmental assessment report. How to participate in the regulatory review process. What to expect once a project is licensed. The environmental assessment process The development of both transmission lines requires a Class 2 licence under The Environment Act (Manitoba). The environmental assessment report for the project includes: How can you participate? There are a number of ways you can participate in a review of this project and provide your input: Attend an open house You are invited to attend one of four open houses to gather project information and share your local knowledge. Your input will help us determine a final preferred route for the project. Manitoba Hydro and consultant staff will be available to provide project information and answer your questions. Refreshments will be provided. Dominion City November 4 Dominion City Community Hall 31 McKercher St. Ile des Chenes November 6 Trans Canada Centre 1 Rivard St. Submit a comment sheet, available at the open houses or on our website at www.hydro.mb.ca/stvital. Contact us directly: Winnipeg November 7 Winakwa Community Centre 980 Winakwa Road St. Pierre Jolys November 5 Cabane a Sucre 432 Joubert St. Trevor Joyal Licensing & Environmental Assessment Department Toll-free: 1-877-343-1631 In Winnipeg: 204-360-7888 email: LEAprojects@hydro.mb.ca Website: www.hydro.mb.ca/stvital documentation of public engagement activities. characterization of the environment. identification of potential effects on people and the environment. determination of ways to avoid or reduce potential adverse effects.