Re: Environmental Review for the 210 Hancock Street Redevelopment SEQR Part 3

Size: px
Start display at page:

Download "Re: Environmental Review for the 210 Hancock Street Redevelopment SEQR Part 3"

Transcription

1 May 4, 2015 JoAnn Cornish, Director of Planning and Development Department of Planning and Development City of Ithaca 108 East Green Street Ithaca, NY Re: Environmental Review for the 210 Hancock Street Redevelopment SEQR Part 3 Dear JoAnn: We are pleased to provide the attachments, exhibits, and following information for your consideration and support for the Environmental Review and SEQR Part 3 for the redevelopment of 210 Hancock Street. This information supplements Part 1 of the City of Ithaca s Full Environmental Assessment Form and supporting documentation, which was filed with the City on February 13, 2015 and is based on requests for additional information and/or clarification from the Planning and Development Board during the Board s discussion of the project at its meeting of April 28, Construction Route and Contractor Parking The proposed construction route is described in the attached Construction Route and Contractor Parking diagram. Foundation and Piles The multi family apartment building on First and Hancock is proposed to be supported by driven piles due to existing soil conditions identified via a geotechnical investigation as illustrated by the attached Foundation Plan Diagram. The Geotech Report was submitted February 13, 2015 to the Planning Board appended to the Full Environmental Assessment Form. Pile driving will not be necessary for the Townhomes. Trowbridge Wolf Michaels Landscape Architects LLP 1001 West Seneca Street, Suite 201 Ithaca, New York ph:

2 The site at 210 Hancock Street is underlain by soft clayey and silty soils that extend to below 85 ft from the ground surface. This type of soil is not suitable for supporting the proposed multifamily building on standard footings. If the building was supported on conventional shallow foundations the result would be excessive settlement that would damage the building and inhibit its usefulness. A commonly used method to allow construction of larger buildings on sites like 210 Hancock Street is to support the building on a deeper firmer layer through use of deep foundations or piles. Piles are typically driven into the ground using a crane and hammer and extend from the foundation level of the building, through the soft soils, and into the deeper firmer layer. The load of the building is then transferred via the piles into the deeper layer without increasing the load on the softer soils that would settle. The piles that would be used on this project would likely consist of steel pipe piles that would be filled with concrete. The piles would be driven into the ground using a crane and pile driving hammer. Because most of the soil is soft, we anticipate that much of the installation would go quickly with minimal driving required. Driving would be required once the pile tip entered the firmer soils located below 85 ft. Driving would then continue until the structural capacity of the pile is reached. This capacity is measured in real time. We anticipate the piles would not extend deeper than ft. The anticipated pile driving times for the multi family apartment building will be limited to 7:00 am to 4:00 pm weekdays for a 5 to 6 week duration. Stormwater A Stormwater Management Study was included in the April 1, 2015 submission to the Planning Board, and was submitted directly to Scott Gibson, the City s Stormwater Pollution Prevention Officer. An update to this letter was provided to Scott Gibson on April 9, 2015 and is appended to this transmittal. This study outlines the anticipated stormwater conditions and mitigation measures. This study was executed in advance of the required Full Stormwater Pollution Prevention Plan (SWPPP) which will be developed for the project. Mr. Gibson has reviewed this study and indicated agreement with all of its concepts, analysis, and proposed stormwater strategies and has indicated that he will be providing a review letter to the Planning Board confirming this agreement. We have included earlier correspondence with Mr. Gibson for your reference. 2 of 4

3 Visual Simulations As provided to the Project Review Committee on April 21, 2015, the visual simulations for the project represent architectural and site concepts in the early stages of design. The project has continued to evolve from the date simulations were last generated and submitted. At this time, new visual simulations have not been developed as the changes have been subtle. We anticipate creating new visualizations to be provided to the PRC in advance of May s Board meeting. To supplement the simulations and convey the character of the building, attached are building elevations of the multi family building. Revisions to the buildings have occurred based on comments from Board members at the April 2015 meeting. Parking Lot Screening To more effectively provide visual screening and physical separation between the parking area and the adjacent public way of Hancock Street and Adams Street, a low screening wall has been added to the site plan and supplemented with proposed landscaping as illustrated in the attached updated site plan rendering in response to comments from Board members. Sustainable Design Strategies The planning board referred to a number of potential sustainable design strategies at the April 28 th meeting, including solar power, rainwater storage and re use, and stormwater biofiltration. INHS is planning to investigate the feasibility of those specific practices, and others, through the LEED Certification process. We trust that the Board will find this information helpful as it continues to evaluate the potential environmental impacts of the development. We look forward to appearing before the PRC on May 19, 2015 and, again, before the full Board at its next meeting on May 26, We are hopeful that with this additional information, the Board will be in a position to make the determination of significance. In addition, we will also be asking the Board to make recommendations to the Board of Zoning Appeals on the area variances needed for the project. We anticipate being before the BZA in early June. 3 of 4

4 If you have any questions or require further information, please do not hesitate to call. We are looking forward to presenting the project at the May 26, 2015 meeting. Sincerely, Peter Trowbridge, RLA, FASLA Principal Attachments: 1. Construction Route and Contractor Parking Diagram, May 4, Stormwater management review note from Scott Gibson to Lisa Nicholas, April 30, Memo: Stormwater Management for Hancock Street Redevelopment, April 9, 2015 Exhibits: 1. Site Plan Rendering, May 4, Multi Family Building Elevations, Sheet 1, May 4, Multi Family Building Elevations, Sheet 2, May 4, Foundation Plan Diagram, May 1, of 4

5 Construction Route and Contractor Parking Project Site Contractor Parking and staging Overflow parking if needed

6 Jonathan Peet From: Sent: To: Cc: Subject: Attachments: Scott Gibson Thursday, April 30, :05 AM Lisa Nicholas David Herrick; William Epthimiatos; Skip Schell FW: INHS 201 Hancock Street 210 Hancock Prelim SPR Storm Narrative pdf Lisa, A preliminary review on the stormwater management approach for 210 Hancock street has been conducted by this office. In and of itself, this project meets the definition for a Full Stormwater Pollution Prevention Plan given the large acreage of disturbance anticipated by the work. However, in accordance with the DEC Stormwater Management Design Manual, Chapter 9, Redevelopment Activity, If The plan proposes a reduction of existing impervious cover by a minimum of 25% of the total disturbed, impervious area, a reduction in site imperviousness will reduce the volume of stormwater runoff, thereby achieving, at least in part, stormwater criteria for both water quality and quantity. This project proposes to reduce its cover by up to 28%, which meets this criteria. As such quality and quantity control are waived by definition. That said, the project must still meet four (4) Better Site Design Practices and we have encouraged responsible grading in final design to take advantage of longer flow path runs across green landscaping. The project will require a Notice of Intent sent to the DEC and accompanying municipal certification statements from our office. Should you have any questions or comment concerning this information, please do not hesitate to contact me. Thanks. Scott Gibson, Environmental Engineer 510 First Street Ithaca, NY T: C: F: scottg@cityofithaca.org From: David Herrick [mailto:dah@tgmillerpc.com] Sent: Thursday, April 09, :05 PM To: Scott Gibson Cc: Nathan Brown (nb@holt.com); Scott Reynolds (sreynolds@ithacanhs.org); Joe Bowes (jbowes@ithacanhs.org); Jonathan Peet (jbp@twm.la); Peter J. Trowbridge (pjt@twla.com) Subject: RE: INHS 201 Hancock Street Hi Scott, Attached is an updated summary with revised sheets for the existing/proposed cover types. There is a correction in the Existing Site pervious cover. We also added the cover conditions within the City s rights of way per a recent request of Lisa Nicholas. Although we don t take credit for it, there is a reduction in the existing impervious cover within that portion of Adams Street and Lake Ave being re developed for the pedestrian walk and play area. Let me know if you have any questions. Thanks again. 1

7 David A. Herrick, P.E. Principal T.G. Miller, P.C. Engineers and Surveyors 203 N. Aurora Street, Ithaca, NY T: x226 F: From: David Herrick Sent: Tuesday, March 31, :57 AM To: 'Scott Gibson' Cc: Nathan Brown Scott Reynolds Joe Bowes Jonathan Peet Peter J. Trowbridge Subject: INHS 201 Hancock Street Hello Scott, Attached for your review is a pdf version of our stormwater management summary. The Preliminary SPR application is being submitted this week. The Planning and Development Board could begin the environmental review at their meeting on April 28 th. We would like to submit the formal Full SWPPP document following preliminary approval. In the interim, I can provide any additional information, details or calculations you may want to review. Thank you for this assistance. David A. Herrick, P.E. Principal T.G. Miller, P.C. Engineers and Surveyors 203 N. Aurora Street, Ithaca, NY T: x226 F: dah@tgmillerpc.com 2

8 April 9, N. Aurora Street Ithaca, NY phone fax Mr. Scott Gibson Stormwater Management Officer City of Ithaca 510 First Street Ithaca NY Re: Ithaca Neighborhood Housing Services Storm Water Management for Hancock Street Redevelopment Dear Mr. Gibson, As we ve discussed previously, Ithaca Neighborhood Housing Services is proposing to redevelop the properties at No. 210 Hancock Street and No. 423 First Street in a mix of townhomes, commercial and multi family apartment buildings. The combined area of the two parcels within the adjacent street lines is 2.01 acres. Soil disturbance will occur on nearly all of this area. With respect to Chapter 282 of the City of Ithaca Code that pertains to stormwater management, the type and scale of the proposed project will require the preparation of a full stormwater pollution prevention plan (Full SWPPP), however as stated in Chapter a redevelopment project should follow Chapter 9 of the New York State Stormwater Management Design Manual to address disturbance and reconstruction of existing impervious surfaces (i.e. redevelopment activities). In support of the City Environmental Quality Review and Preliminary Site Plan Review submission we are providing the following information and mitigation strategies for managing stormwater from the redeveloped site. Existing Conditions Specific to this project, the site condition within the limits of the adjacent street lines is roughly 93 percent impervious cover. The majority of the impervious area is attributable to the two commercial building roof tops and the large contiguous parking lot. The areas of pervious cover are limited to small lawn panels at the northwest corner of the site. Based on the site topography, the parking lot drains in a westerly direction toward First Street. The extent of on site storm sewers is limited to two catch basins in the southerly portion of the main parking area. These catch basins are connected by relatively small diameter pipe (less than 12 inch diameter) to the City s storm sewer at the corner of Hancock and First Street. Runoff collected in gutters and downspouts on the two building roofs is directed principally toward Adams Street. The City s storm sewer system in the immediate vicinity consists of curb inlets, catch basins and 12 inch diameter pipe along both Hancock Street and Adams Street. Other than curbed gutters, there are no storm sewers on First Street or Lake Avenue. Runoff collected in the Hancock Street system is ultimately discharged to an open channel at the intersection of Third Street and N. Meadow Street (NYS Route 13). The short length of storm pipe in the Adams Street system discharges into David A. Herrick, P.E. Frank L Santelli, P.E. Andrew J. Sciarabba, P.E. Steven R. Rowe, P.E. Dondi M. Harner, P.E. LEED A.P., C.P.E.S.C. Lee Dresser, L.S. Darrin A. Brock, L.S. Edward D. Ripic, Jr., L.S.

9 Cascadilla Creek just upstream of the footbridge. The invert of the City system at Hancock Street is feet or roughly 4 feet below the mean site elevation of feet. At the east end of Adams Street the invert of the City pipe is approximately 381 feet. Proposed Improvements Redevelopment of the site will include razing the existing buildings and demolishing all other exterior parking and walkway pavements within the property boundary. Select mature trees around the site periphery will be protected and incorporated into the final landscaping. The footprint of new impervious surfaces, inclusive of the multi family and townhouse developments, will decrease by 0.53 acres, or approximately 28 percent. Given the significant conversion of 0.53 acres of impervious surfaces to lawn and pervious landscape features the State requirements, as described in Chapter Sizing Criteria, to provide permanent stormwater management practices for either quality or quantity control are waived. The City Code does require that at least four strategies for Better Site Design be incorporated into the proposed plan for any Full SWPPP project. The preliminary list of Better Site Design Practices that will be considered for this site includes: 1) Building Footprint Reduction; 2) Parking Reduction; 3) Rooftop Runoff Reduction; 4) Tree Planting; and 5) Open Vegetated Channel. Other categories and specific practices will be reviewed with you and described in the completed Full SWPPP. Standard storm sewer improvements will consist of catch basins spaced in the parking lot as needed to support the site grading. Roof drains can either be routed to the proposed catch basins or be disconnected to drain over adjacent lawn panels. HDPE or PVC pipe will connect the new catch basins to the existing City storm sewers on Hancock and Adams Street. Temporary erosion and sediment control practices to be selected for the construction phase will focus on minimizing tracking soil off site, controlling dust and filtering any foundation dewatering discharges. The completed Full SWPPP, prepared in accordance with the City s regulations will be submitted for your review and approval prior to issuance of any building permit. The Notice of Intent will subsequently be filed with the NYSDEC in order to obtain coverage under the SPDES General Permit for Stormwater Activities. Please contact me with any questions or comments. Thank you. Sincerely, David A. Herrick, P.E. Cc: INHS Enclosures: 2 Sheets

10

11

12 LEGEND 1. COMMERCIAL GROUND FLOOR WITH RESIDENTIAL ABOVE 2. COVERED PARKING WITH RESIDENTIAL ABOVE 3. TOWNHOMES 4. BIKE PARKING 5. BUS STOP 6. INTERIOR STREET 7. BICYCLE AND PEDESTRIAN WAY 8. PLAYGROUND KEY MIXED USE BUILDINGS MULTIFAMLY BUILDINGS TOWNHOMES SCALE CE MIL L ER WA Y 60 ALI CONLEY PARK 8 ADAMS STREET WILLOW AVENUE 4 CASCADILLA CREEK 2 LAKE AVENUE ROW 30 FIRST STREET 0 HANCOCK STREET 210 Hancock Street Redevelopment SITE PLAN MAY 4, 2015

13 210 Hancock Street Redevelopment May 4, 2015 ELEVATIONS

14 210 Hancock Street Redevelopment May 4, 2015 ELEVATIONS

15 /1/2015 2:33:57 PM G Architecture Planning Interior Design 217 North Aurora Street Ithaca NY p f G F F ' - 1 3/8" 7' /16" 20' - 2 3/16" 19' - 9 3/16" 8' - 4 5/8" 18' - 4 7/8" 18' - 9 3/4" 18' - 9 3/4" 1' - 1" 11' - 8 3/8" 10' - 0" 6' - 9" 21' - 9" 21' - 9" 21' - 9" 10' - 0" 16' - 0" 16' - 0" 16' - 0" 8' - 0" Elwyn & Palmer CONSULTING ENGINEERS, PLLC 213 East Seneca Street Ithaca, New York E D C B W V U T S Y R Q P O N M L K J I H G F E D C B A 81' - 0 1/8" 7' - 4 1/4" 21' - 3 5/8" 1 40 KIPS 80 KIPS 80 KIPS 120 KIPS 225 KIPS 225 KIPS 90 KIPS 95 KIPS 35 KIPS 25 KIPS 19' - 9 3/16" 30 KIPS 10" SLAB W/ #6 AT 12" O.C. E.W. TOP AND BOT. GB2 265 KIPS 275 KIPS GB2 FOUNDATION PLAN DIAGRAM 3/32" = 1'-0" 105 KIPS 135 KIPS 17' - 6" 32' - 9 1/4" 24' - 4 5/8" 45 KIPS 130 KIPS 165 KIPS 90 KIPS 75 KIPS 130 KIPS 130 KIPS 110 KIPS 110 KIPS 195 KIPS 10" SLAB W/ #6 AT 12" O.C. E.W. TOP AND BOT. 195 KIPS 195 KIPS 195 KIPS 75 KIPS 20 KIPS 135 KIPS 40 KIPS 40 KIPS 135 KIPS 40 KIPS 75 KIPS 110 KIPS 110 KIPS 75 KIPS 17' - 6" 4' - 5 7/16" 12' /4" 12' - 4 1/16" 10' - 7 7/8" 6' /8" 20 KIPS 30 KIPS 70 KIPS 60 KIPS 80 KIPS 40 KIPS 25 KIPS 65 KIPS 50 KIPS 40 KIPS 90 KIPS 10 KIPS 115 KIPS 115 KIPS 115 KIPS 60 KIPS 45 KIPS 85 KIPS 10" SLAB W/ #6 AT 12" O.C. E.W. TOP AND BOT. 130 KIPS 85 KIPS 65 KIPS 70 KIPS 125 KIPS 115 KIPS 80 KIPS 130 KIPS 85 KIPS 125 KIPS 18' - 11" 8' - 8 1/4" 7' - 4 7/8" 11' - 1 5/16" 18' /16" 105 KIPS 75 KIPS 60 KIPS 100 KIPS 10" SLAB W/ #6 AT 12" O.C. E.W. TOP AND BOT. 105 KIPS 120 KIPS 120 KIPS 85 KIPS 25 KIPS 30 KIPS 30 KIPS 25 KIPS 10 KIPS 60 KIPS 75 KIPS 45 KIPS 85 KIPS 90 KIPS 85 KIPS 85 KIPS 95 KIPS 110 KIPS 95 KIPS 110 KIPS 18' /16" 10' - 7 7/16" 6' - 0" 29' - 5 1/4" 14' - 0" 60 KIPS 75 KIPS 55 KIPS 55 KIPS 45 KIPS 45 KIPS 55 KIPS 55 KIPS 95 KIPS 95 KIPS 45 KIPS 70 KIPS 80 KIPS 25 KIPS 50 KIPS 50 KIPS WARNING: It is a violation of New York State Law for any person, unless acting under the direction of a licensed Architect, to alter this document in any way. If a document bearing the seal of an Architect is altered, the altering Architect shall affix to such document his seal and the notation "altered by" followed by his signature, the date of such alteration, and a specific description of the alteration. Revision Schedule Rev. Number HANCOCK STREET REDEVELOPMENT Rev. Descr. ITHACA NEIGHBORHOOD HOUSING SERVICES Rev. Date 210 HANCOCK STREET, ITHACA, NY E D C B DATE: PROJECT: OTHER: DRAWN BY: Issue Date Project Number Author A FOUNDATION PLAN DIAGRAM A S0

A. INTRODUCTION AND SUMMARY OF FINDINGS B. EXISTING CONDITIONS. Table 10-1 Adjacent Storm Drains

A. INTRODUCTION AND SUMMARY OF FINDINGS B. EXISTING CONDITIONS. Table 10-1 Adjacent Storm Drains Chapter 10: Stormwater Management A. INTRODUCTION AND SUMMARY OF FINDINGS This chapter describes existing and proposed stormwater management on the Site. Potential impacts to stormwater infrastructure

More information

Advance Engineering & Surveying PLLC

Advance Engineering & Surveying PLLC Advance Engineering & Surveying, PLLC Consulting in: Civil & Environmental Engineering Land Surveying Land Development 11 Herbert Drive Phone: (518) 698-3772 Latham, N.Y. 12110 Email:ncostape@gmail.com

More information

STORMWATER GREEN INFRASTRUCTURE AND PLANNING/ZONING BOARDS

STORMWATER GREEN INFRASTRUCTURE AND PLANNING/ZONING BOARDS STORMWATER GREEN INFRASTRUCTURE AND PLANNING/ZONING BOARDS Source: Center for Watershed Protection, 2007 Southern Tier Central Regional Planning & Development Board Chemung County Stormwater Team OUTLINE

More information

Chapter 4 - Preparation of Stormwater Site Plans

Chapter 4 - Preparation of Stormwater Site Plans Chapter 4 - Preparation of Stormwater Site Plans The Stormwater Site Plan is the comprehensive report containing all of the technical information and analysis necessary for the City to evaluate a proposed

More information

4. Contractor (and subcontractors if applicable) certification statement(s)

4. Contractor (and subcontractors if applicable) certification statement(s) CHEMUNG COUNTY STORMWATER COALITION STORMWATER POLLUTION PREVENTION PLAN (SWPPP) SUBMITTAL CHECKLIST GENERAL INFORMATION: 1. Owner/Operator name, legal address, phone number 2. Copy of signed Notice of

More information

CHAPTER 9 STORM DRAINAGE. Minimum Requirements for New Development and Redevelopment

CHAPTER 9 STORM DRAINAGE. Minimum Requirements for New Development and Redevelopment CHAPTER 9 STORM DRAINAGE 9.01 General The standards established by this chapter are intended to represent the minimum standards for the design and construction of storm drainage facilities. 9.02 Design

More information

PLANNED UNIT DEVELOPMENT & SUBDIVISION STAFF REPORT Date: May 18, 2017

PLANNED UNIT DEVELOPMENT & SUBDIVISION STAFF REPORT Date: May 18, 2017 & PUD-0000102-2017 PLANNED UNIT DEVELOPMENT & SUBDIVISION STAFF REPORT Date: May 18, 2017 NAME SUBDIVISION NAME Dauphin Creek Estates Subdivision Dauphin Creek Estates Subdivision LOCATION CITY COUNCIL

More information

6.1. INTRODUCTION AND SUMMARY OF FINDINGS

6.1. INTRODUCTION AND SUMMARY OF FINDINGS Chapter 6: Stormwater Management 6.1. INTRODUCTION AND SUMMARY OF FINDINGS A Stormwater Pollution Prevention Plan (SWPPP) has been prepared for the Proposed Project in accordance with the requirements

More information

New Development Stormwater Guidelines

New Development Stormwater Guidelines New Development Stormwater Guidelines CITY OF MOUNTLAKE TERRACE Table of Contents Introduction... 2 Ecology s Minimum Requirements for stormwater management... 2 Description of the 9 Minimum Requirements...

More information

MANUAL OF DESIGN, INSTALLATION, AND MAINTENANCE REQUIREMENTS FOR STORMWATER MANAGEMENT PLANS

MANUAL OF DESIGN, INSTALLATION, AND MAINTENANCE REQUIREMENTS FOR STORMWATER MANAGEMENT PLANS MANUAL OF DESIGN, INSTALLATION, AND MAINTENANCE REQUIREMENTS FOR STORMWATER MANAGEMENT PLANS May 2007 SECTION 1 Responsibility of Applicant TABLE OF CONTENTS A. Stormwater Management Plan Required Information

More information

CITY OF CYPRESS 5275 Orange Avenue Cypress, California (714) DESIGN REVIEW COMMITTEE PERMIT PROCESS

CITY OF CYPRESS 5275 Orange Avenue Cypress, California (714) DESIGN REVIEW COMMITTEE PERMIT PROCESS CITY OF CYPRESS 5275 Orange Avenue Cypress, California 90630 (714) 229-6720 DESIGN REVIEW COMMITTEE PERMIT PROCESS 1. Discuss project with Planning staff to determine zoning regulations, any unusual characteristics

More information

Huntington Stormwater Utility

Huntington Stormwater Utility Huntington Stormwater Utility Stormwater Management & Sediment and Erosion Control Requirements for Construction Sites Authorized by Huntington City Code Articles: 971, 970, 930, 935, 955, Revised April

More information

CITY OF ST. AUGUSTA STEARNS COUNTY MINNESOTA ORDIANCE NO AN ORDINANCE ESTABLISHING REGULATIONS FOR STORMWATER MANAGEMENT

CITY OF ST. AUGUSTA STEARNS COUNTY MINNESOTA ORDIANCE NO AN ORDINANCE ESTABLISHING REGULATIONS FOR STORMWATER MANAGEMENT CITY OF ST. AUGUSTA STEARNS COUNTY MINNESOTA ORDIANCE NO. 2017-05 AN ORDINANCE ESTABLISHING REGULATIONS FOR STORMWATER MANAGEMENT In the interest of the health, safety, and welfare of its citizens, the

More information

PLANNED DEVELOPMENT (MASTER PLAN & UNIT PLAN)

PLANNED DEVELOPMENT (MASTER PLAN & UNIT PLAN) Central Permit Center 555 Santa Clara Street Vallejo CA 94590 Business License Building Fire Prevention Planning Public Works 707.648.4310 707.648.4374 707.648.4565 707.648.4326 707.651.7151 PLANNED DEVELOPMENT

More information

PRELIMINARY PROJECT REVIEW PROCESS

PRELIMINARY PROJECT REVIEW PROCESS CITY OF CYPRESS 5275 Orange Avenue Cypress, California 90630 (714) 229-6720 PRELIMINARY PROJECT REVIEW PROCESS 1. Discuss project with Planning staff to determine zoning regulations, unusual characteristics

More information

Review Zone Application for D&R Canal Commission Decision

Review Zone Application for D&R Canal Commission Decision Review Zone Application for D&R Canal Commission Decision MEETING DATE: July 20, 2016 DRCC #: 16-4803 Latest Submission Received: June 13, 2016 Applicant: Robert McCarthy, PE PSE&G 4000 Hadley Road, 2

More information

DECISION CRITICAL AREAS ALTERATION AND DETERMINATION OF NONSIGNIFICANCE (DNS)

DECISION CRITICAL AREAS ALTERATION AND DETERMINATION OF NONSIGNIFICANCE (DNS) DECISION CRITICAL AREAS ALTERATION AND DETERMINATION OF NONSIGNIFICANCE (DNS) Development Services Department 17301 133rd Avenue NE Woodinville, WA 98072 425-489-2754 www.ci.woodinville.wa.us Project Name:

More information

Draft Rhode Island Stormwater Design and Installation Standards Manual

Draft Rhode Island Stormwater Design and Installation Standards Manual Draft Rhode Island Stormwater Design and Installation Standards Manual Summary The May 2009 Public Review Draft version of the RI Stormwater Design and Installation Standards Manual consists of approximately

More information

PepsiCo R & D Facility Expansion Town of Mount Pleasant, Westchester County, NY Draft Environmental Impact Statement Scoping Outline

PepsiCo R & D Facility Expansion Town of Mount Pleasant, Westchester County, NY Draft Environmental Impact Statement Scoping Outline PepsiCo R & D Facility Expansion Town of Mount Pleasant, Westchester County, NY Draft Environmental Impact Statement Scoping Outline 10-17-2016 This document identifies the issues to be addressed in the

More information

THE CITY OF MOBILE, ALABAMA

THE CITY OF MOBILE, ALABAMA THE CITY OF MOBILE, ALABAMA LETTER OF DECISION Ark of Safety, Inc. Mobile, AL 36617 Re: (Northwest corner of Main Street and First Avenue, extending to the Southwest corner of Esau Avenue and Main Street.)

More information

MASTER DEVELOPMENT DRAINAGE PLAN FOR MONUMENT HEIGHTS

MASTER DEVELOPMENT DRAINAGE PLAN FOR MONUMENT HEIGHTS MASTER DEVELOPMENT DRAINAGE PLAN FOR MONUMENT HEIGHTS DRAINAGE REPORT STATEMENT ENGINEER'S STATEMENT: The attached drainage plan and report were prepared under my direction and supervision and are correct

More information

Gloucester County PLAN SUBMITTER'S CHECKLIST

Gloucester County PLAN SUBMITTER'S CHECKLIST Page 1 of 9 Gloucester County PLAN SUBMITTER'S CHECKLIST FOR EROSION AND SEDIMENT CONTROL PLANS Please fill in all blanks and please reference the plan sheets/pages where the information may be found,

More information

5. FINAL DEVELOPMENT PLAN APPROVAL MENORAH MEDICAL CENTER OFFICE BUILDING Vicinity of the southwest corner of 119 th Street and Nall Avenue

5. FINAL DEVELOPMENT PLAN APPROVAL MENORAH MEDICAL CENTER OFFICE BUILDING Vicinity of the southwest corner of 119 th Street and Nall Avenue 5. FINAL DEVELOPMENT PLAN APPROVAL MENORAH MEDICAL CENTER Avenue 1. APPLICANT: Hoefer Wysocki Architects, L.L.C., is the applicant for this request. 2. REQUESTED ACTION: The applicant is requesting final

More information

Boston Water and Sewer Commission

Boston Water and Sewer Commission Boston Water and Sewer Commission 980 Harrison Avenue Boston, MA 02119-2540 617-989-7000 March 27, 2017 Michael Rooney Boston Planning & Development One City Hall Square Boston, MA 02201 Re: 159-20 1 Washington

More information

STORMWATER SITE PLAN INSTRUCTIONS AND SUBMITTAL TEMPLATE Medium and Large Projects

STORMWATER SITE PLAN INSTRUCTIONS AND SUBMITTAL TEMPLATE Medium and Large Projects DEPARTMENT OF COMMUNITY DEVELOPMENT 621 Sheridan Street, Port Townsend, WA 98368 Tel: 360.379.4450 Fax: 360.379.4451 Web: www.co.jefferson.wa.us/communitydevelopment E-mail: dcd@co.jefferson.wa.us STORMWATER

More information

APPLICATION FOR REZONING PROPERTY CITY OF HOLLAND, MICHIGAN. Name of Applicant. Address, and Phone # of Applicant

APPLICATION FOR REZONING PROPERTY CITY OF HOLLAND, MICHIGAN. Name of Applicant. Address,  and Phone # of Applicant APPLICATION FOR REZONING PROPERTY CITY OF HOLLAND, MICHIGAN Name of Applicant Address, Email and Phone # of Applicant Name and Address of Owner (if other than applicant) Ownership Interest of Applicant

More information

Project Applicant Checklist for NPDES Permit Requirements SAN MATEO COUNTYWIDE STORMWATER POLLUTION PREVENTION PROGRAM

Project Applicant Checklist for NPDES Permit Requirements SAN MATEO COUNTYWIDE STORMWATER POLLUTION PREVENTION PROGRAM Project Applicant Checklist for NPDES Permit Requirements SAN MATEO COUNTYWIDE STORMWATER POLLUTION PREVENTION PROGRAM I. PROJECT DATA Project Name Bay Meadows Development Phase II Project Address 2600

More information

Green Infrastructure Planning Design Guidelines

Green Infrastructure Planning Design Guidelines A resource for planning boards in Monroe County September 2016 Green Infrastructure Planning Design Guidelines September 2016 Jayme Breschard Thomann, AICP, CFM David Zorn, Executive Director Genesee/Finger

More information

ST. MARY S SOIL CONSERVATION DISTRICT (SMSCD) AND DPW&T CONCEPT EROSION AND SEDIMENT CONTROL AND STORMWATER MANAGEMENT GUIDELINES AND CHECKLIST

ST. MARY S SOIL CONSERVATION DISTRICT (SMSCD) AND DPW&T CONCEPT EROSION AND SEDIMENT CONTROL AND STORMWATER MANAGEMENT GUIDELINES AND CHECKLIST St. Mary s Soil Conservation District 26737 Radio Station Way, Suite B Leonardtown, MD 20650 Phone: 301-475-8402 ext. 3 Fax: 301-475-8391 www.stmarysscd.com St. Mary s County Government Department of Public

More information

CITY OF SIGNAL HILL Cherry Avenue Signal Hill, CA PROCEDURES RELATIVE TO CITY COUNCIL PUBLIC HEARINGS

CITY OF SIGNAL HILL Cherry Avenue Signal Hill, CA PROCEDURES RELATIVE TO CITY COUNCIL PUBLIC HEARINGS Ordinance Amendment Storm Water / Urban Runoff and Low Impact Development CITY OF SIGNAL HILL 2175 Cherry Avenue Signal Hill, CA90755-3799 PROCEDURES RELATIVE TO CITY COUNCIL PUBLIC HEARINGS 1. At the

More information

New York State Department of Environmental Conservation

New York State Department of Environmental Conservation New York State Department of Environmental Conservation Division of Environmental Permits, Region 3 21 South Putt Comers Road, New Paltz, New York 12561-1620 Phone: (845) 256-3054 FAX (845) 255-4659 Website:

More information

12 January 12, 2011 Public Hearing APPLICANT: TAILWIND DEVELOPMENT GROUP,LLC PROPERTY OWNER: CITY OF VIRGINIA BEACH

12 January 12, 2011 Public Hearing APPLICANT: TAILWIND DEVELOPMENT GROUP,LLC PROPERTY OWNER: CITY OF VIRGINIA BEACH 12 January 12, 2011 Public Hearing APPLICANT: TAILWIND DEVELOPMENT GROUP,LLC PROPERTY OWNER: CITY OF VIRGINIA BEACH STAFF PLANNER: Faith Christie REQUEST: Conditional Change of Zoning (from PD-H1 Planned

More information

CITY OF MOBILE MOBILE CITY PLANNING COMMISSION LETTER OF DECISION. November 5, 2012

CITY OF MOBILE MOBILE CITY PLANNING COMMISSION LETTER OF DECISION. November 5, 2012 SAMUEL L. JONES MAYOR CITY OF MOBILE LETTER OF DECISION OFFICE OF THE CITYCOUNCIL COUNCIL MEMBERS REGGIE COPELAND, SR. PRESIDENT-DISTRICT 5 FREDRICK D. RICHARDSON, JR. VICE PRESIDENT-DISTRICT 1 WILLIAM

More information

The Engineer/Developer s Perspective on Storm Water Management

The Engineer/Developer s Perspective on Storm Water Management The Engineer/Developer s Perspective on Storm Water Management CASE STUDY: An Innovative Approach to Storm Water Management for Small Parcel Site Development Presented by: James B. Leedom, P.E. The Sigma

More information

Department of Planning & Development Planning Unit

Department of Planning & Development Planning Unit May 20, 2005 Department of Planning & Development Planning Unit Website: www.cityofmadison.com Madison Municipal Building 215 Martin Luther King, Jr. Boulevard P.O. Box 2985 Madison, Wisconsin 53701-2985

More information

APPENDIX C: STORMWATER CONTROL PLAN

APPENDIX C: STORMWATER CONTROL PLAN APPENDIX C: STORMWATER CONTROL PLAN STORM WATER MANAGEMENT PLAN FOR PLEASANT HILL, CALIFORNIA Prepared for Compliance with the Clean Water Program (C.3) and the San Francisco Bay Regional Water Quality

More information

Erosion & Sediment Control Plan Application Form & Checklist

Erosion & Sediment Control Plan Application Form & Checklist Erosion & Sediment Control Plan Application Form & Checklist GENERAL INFORMATION Application Date: Project Address: Tax Map / Parcel Number(s): PROPERTY OWNER / DEVELOPER Firm Name: Contact Person: Title:

More information

Project phasing plan (if applicable) 12 copies of site plan

Project phasing plan (if applicable) 12 copies of site plan SITE PLAN REVIEW PERMIT APPLICATION City of Grand Haven, 11 N. Sixth Street, Grand Haven, MI 49417 Phone: (616) 847-3490 Fax: (616) 844-2051 Website: www.grandhaven.org 1. Project Information Address/location

More information

APPLICATION BRIEFING Prepared For: Submitted by: Date: Subject:

APPLICATION BRIEFING Prepared For: Submitted by: Date: Subject: Planning & Development APPLICATION BRIEFING Prepared For: Submitted by: Date: Subject: Planning Advisory Committee Jason Fox, Director of Planning & Development Development Agreement application by Godfrey

More information

R E S O L U T I O N. Designation: R-2A (1-Family, 2-acre Minimum Lot Size)

R E S O L U T I O N. Designation: R-2A (1-Family, 2-acre Minimum Lot Size) PLANNING BOARD Arthur Adelman, Chair TOWN OF NORTH CASTLE WESTCHESTER COUNTY 17 Bedford Road Armonk, New York 10504-1898 R E S O L U T I O N Telephone: (914) 273-3542 Fax: (914) 273-3554 www.northcastleny.com

More information

Checklists. Project Name: Location: File Number: Date of Submittal: Reviewer: Date: Applicant: Contact Name: Phone Number:

Checklists. Project Name: Location: File Number: Date of Submittal: Reviewer: Date: Applicant: Contact Name: Phone Number: Applicant: Contact Name: Phone Number: Email: Project Name: Location: File Number: Date of Submittal: Reviewer: Date: Concept Plan Requirements: I. General Project Information 1. Address or parcel number

More information

We have reviewed the proposed concept plans for Beehive Homes and have the following comments:

We have reviewed the proposed concept plans for Beehive Homes and have the following comments: 12800 Arbor Lakes Parkway, P.O. Box 1180, Maple Grove, MN 55311-6180 FIRE-RESCUE DEPARTMENT Fire Operations Fire Prevention 763-494-6300 763-494-6090 763-494-6421 Fax 763-494-6439-Fax August 22, 2018 RE:

More information

Article 20 Stormwater Management

Article 20 Stormwater Management Article 20 Section 20.01 Intent Article 20 The purpose of this Article is to protect the health, safety, and general welfare of the citizens by requiring compliance with accepted standards and practices

More information

Metropolitan Area Planning Council 60 Temple Place, Boston, Massachusetts fax

Metropolitan Area Planning Council 60 Temple Place, Boston, Massachusetts fax Metropolitan Area Planning Council 60 Temple Place, Boston, Massachusetts 02111 617-451-2770 fax 614-482-7185 www.mapc.org Serving the 101 Cities and Towns in the Metropolitan Boston Region MEMORANDUM

More information

ARTICLE 17 SITE PLAN REVIEW

ARTICLE 17 SITE PLAN REVIEW ARTICLE 17 SITE PLAN REVIEW 17.01 INTENT AND PURPOSE The intent of this section is to provide for consultation and cooperation between the applicant and the township planning commission so that the applicant

More information

Selecting Appropriate Stormwater Control Measures for Your Development Project

Selecting Appropriate Stormwater Control Measures for Your Development Project Phase II Post-Construction Stormwater Requirements Workshop - February 10, 2014 Selecting Appropriate Stormwater Control Measures for Your Development Project Jill Bicknell, P.E., EOA, Inc. Outline of

More information

DCA , Stormwater Quality and Facilities Ordinance June 23, 2009

DCA , Stormwater Quality and Facilities Ordinance June 23, 2009 PROPOSED NEW SECTION 10.486 Stormwater Quality and Detention Facilities, Public Streets. A. Purpose. It is the City s policy to maintain the natural hydrology and preserve water quality by mitigating the

More information

STORMWATER MANAGEMENT CODES ANALYSIS RICHLAND COUNTY, SC SITE PLANNING ROUNDTABLE

STORMWATER MANAGEMENT CODES ANALYSIS RICHLAND COUNTY, SC SITE PLANNING ROUNDTABLE STORMWATER MANAGEMENT CODES ANALYSIS RICHLAND COUNTY, SC SITE PLANNING ROUNDTABLE Codes analyses for each subcommittee were completed to assist participants of the Richland County Site Planning Roundtable.

More information

Plat Requirements CHECKLIST FOR SITE PLAN REVIEW

Plat Requirements CHECKLIST FOR SITE PLAN REVIEW This checklist is to be used as a guide for complying with the Town of Hollis Site Plan Regulations. It is to be used for each individual site plan review application submitted. Applicants are encouraged

More information

Northeast Ohio Regional Sewer District Stormwater Management Plan Review Policy

Northeast Ohio Regional Sewer District Stormwater Management Plan Review Policy Northeast Ohio Regional Sewer District Stormwater Management Plan Review Policy Introduction As a component of the Northeast Ohio Regional Sewer District s (District) Regional Stormwater Management Program,

More information

ORDINANCE NUMBER DRAFT. An ordinance amending Title 12 Environmental Protection of the Los Angeles County

ORDINANCE NUMBER DRAFT. An ordinance amending Title 12 Environmental Protection of the Los Angeles County ORDINANCE NUMBER DRAFT 1 1 1 1 1 1 0 1 An ordinance amending Title 1 Environmental Protection of the Los Angeles County Code, establishing Low Impact Development standards. The Board of Supervisors of

More information

Site Development Plan (SDP) Checklist

Site Development Plan (SDP) Checklist Development Services Department 100 N. Wilcox Street, Castle Rock CO 80104 303-660-1393 or CRGov.com Site Development Plan (SDP) Checklist A complete Site Development Plan (SDP) submittal will contain

More information

Town of Windham. Planning Department 8 School Road Windham, ME voice fax

Town of Windham. Planning Department 8 School Road Windham, ME voice fax Town of Windham Planning Department 8 School Road Windham, ME 04062 voice 207.864-5960 fax 207.892.1916 MEMO DATE: TO: Staff Review Committee FROM: Amanda Lessard, Planner Cc: Ellen Rathbone, St. Germain

More information

SECTION 1 CLEARING /GRADING PERMIT APPLICATION:

SECTION 1 CLEARING /GRADING PERMIT APPLICATION: PLEASE REFER TO THE CLEARING & GRADING PERMIT CHECKLIST BELOW FOR SUBMITTAL REQUIREMENTS. SECTION 1 CLEARING /GRADING PERMIT APPLICATION: PROJECT ADDRESS (Street, Suite #): Parcel(s) #: Total Site Area

More information

County of Fairfax, Virginia

County of Fairfax, Virginia County of Fairfax, Virginia To protect and enrich the quality of life for the people, neighborhoods, and diverse communities of Fairfax County DATE: July 16, 2007 TO: SUBJECT: All Architects, Attorneys,

More information

SUPPORTING DOCUMENT STORMWATER POLLUTION PREVENTION PLAN (SWPPP) NARRATIVE

SUPPORTING DOCUMENT STORMWATER POLLUTION PREVENTION PLAN (SWPPP) NARRATIVE SUPPORTING DOCUMENT STORMWATER POLLUTION PREVENTION PLAN (SWPPP) NARRATIVE Please complete this narrative form and submit with your SWPPP drawings. Refer to Kitsap County Stormwater Design Manual Vol.

More information

Example Stormwater Control Plan For a Residential Subdivision Project. Whispering Pines Lane Anytown, USA

Example Stormwater Control Plan For a Residential Subdivision Project. Whispering Pines Lane Anytown, USA Example Stormwater Control Plan For a Residential Subdivision Project Whispering Pines Lane Anytown, USA December 2, 2015 XYZ Corporation Jane Jones, 707-555-1212 This example prepared by Dan Cloak Environmental

More information

PLAN SUBMITTER'S CHECKLIST

PLAN SUBMITTER'S CHECKLIST Page 1 of 8 PLAN SUBMITTER'S CHECKLIST FOR EROSION AND SEDIMENT CONTROL PLANS Please fill in all blanks and reference the plan sheets/pages where the information may be found, where appropriate, or write

More information

CITY OF TUMWATER 555 ISRAEL RD. SW, TUMWATER, WA (360) (360) (FAX)

CITY OF TUMWATER 555 ISRAEL RD. SW, TUMWATER, WA (360) (360) (FAX) CITY OF TUMWATER 555 ISRAEL RD. SW, TUMWATER, WA 98501 (360) 754-4180 (360) 754-4126 (FAX) Email: cdd@ci.tumwater.wa.us APPENDIX II-C SHORT FORM CONSTRUCTION STORMWATER POLLUTION PREVENTION PLAN (SWPPP)

More information

Example Stormwater Control Plan For a Residential Subdivision Project. Whispering Pines Lane Anytown, USA. February 21, 2018

Example Stormwater Control Plan For a Residential Subdivision Project. Whispering Pines Lane Anytown, USA. February 21, 2018 Example Stormwater Control Plan For a Residential Subdivision Project Whispering Pines Lane Anytown, USA February 21, 2018 XYZ Corporation Jane Jones, 925-555-1212 This example prepared by Dan Cloak Environmental

More information

Three threshold measures will be applied together to capture project scale and scope and impacts:

Three threshold measures will be applied together to capture project scale and scope and impacts: The regulatory consequences to the County from State and Federal water quality regulations if the pollution impacts are not addressed by each project. The extreme difficulty, cost, and equity issues associated

More information

NEORSD Green Infrastructure Grant (GIG) Program Opening Remarks

NEORSD Green Infrastructure Grant (GIG) Program Opening Remarks NEORSD Green Infrastructure Grant (GIG) Program Opening Remarks 2019 NEORSD GIG Eligibility and Technical Requirements Project must be located in the Sewer District s combined sewer area Location Applicant

More information

County of Fairfax, Virginia

County of Fairfax, Virginia County of Fairfax, Virginia To protect and enrich the quality of life for the people, neighborhoods and diverse communities of Fairfax County TO: SUBJECT: All Architects, Builders, Developers, Engineers,

More information

Procedures IV. V. Rural Road Design Option

Procedures IV. V. Rural Road Design Option i IV. Procedures A. All applicants required to prepare a Conservation Design Subdivision shall provide the Planning Board with a conceptual conventional subdivision design as well as a proposed layout

More information

3. Are there any projects exempt from the definition of Regulated Projects?

3. Are there any projects exempt from the definition of Regulated Projects? STORMWATER REQUIREMENTS: OVERVIEW OF PROVISION C.3 Background: On October 14, 2009, the Regional Water Quality Control Board, San Francisco Bay Region, issued a municipal regional stormwater permit (MRP)

More information

ARTICLE V PLANNED UNIT DEVELOPMENT DISTRICT

ARTICLE V PLANNED UNIT DEVELOPMENT DISTRICT ARTICLE V PLANNED UNIT DEVELOPMENT DISTRICT A. Purpose and Objective The Planned Unit Development (PUD) procedure provides a flexible land use and design regulation through the use of performance criteria

More information

CITY OF MANHATTAN BEACH DEPARTMENT OF COMMUNITY DEVELOPMENT. TO: Parking and Public Improvements Commission

CITY OF MANHATTAN BEACH DEPARTMENT OF COMMUNITY DEVELOPMENT. TO: Parking and Public Improvements Commission Clay Curtin, Management Analyst (I the same walls at a maximum of 1 foot tall. Section 7.36.150 of the Municipal Code permits BY: Eric Haaland, Associate Planner right-of-way) between walkways leading

More information

CIVIL ENGINEERING PERMIT APPLICATION

CIVIL ENGINEERING PERMIT APPLICATION CIVIL ENGINEERING PERMIT APPLICATION OFFICIAL USE ONLY Engineering Permit # Date: Received By: Staff Contact: FOR STAFF USE ONLY: OFD RSH LOTT Stormwater Planning Water Shop PLEASE SUBMIT TWO (2) SETS

More information

PHASE III DRAINAGE REPORT

PHASE III DRAINAGE REPORT PHASE III DRAINAGE REPORT FOR Eastlake Assisted Living & Memory Care April 20, 2016 June 3, 2016 August 5, 2016 Prepared for: 3301 E 120 th Ave, LLC. 8200 E. Maplewood Ave., Suite 150 Greenwood Village

More information

Chapter 3 Site Planning and Low Impact Development

Chapter 3 Site Planning and Low Impact Development CHAPTER 3 Site Planning and Low Impact Development Chapter 3 Site Planning and Low Impact Development 3.0 Introduction The City of Charleston requires that major residential, large commercial (>1 acre),

More information

Watertown City Council

Watertown City Council City of Watertown Watertown City Council April 14 th, 2015 Agenda Item: City Comment on Sun Share CUP Application Request for Action: Motion to Approve City Comments regarding CUP Application Department:

More information

Example Stormwater Control Plan For a Commercial Project 123 Main Street Anytown, USA

Example Stormwater Control Plan For a Commercial Project 123 Main Street Anytown, USA Example Stormwater Control Plan For a Commercial Project 123 Main Street Anytown, USA January 2017 XYZ Corporation Jane Jones, 805-555-1212 This example prepared by Dan Cloak Environmental Consulting for

More information

Plan Review Checklist

Plan Review Checklist Plan Review Checklist FOR EROSION AND SEDIMENT CONTROL PLANS _ Minimum Standards - All applicable Minimum Standards must be addressed. All minimum Standards must be adhered to during the entire project

More information

Figure 1 Cypress Street Study Area Location Map

Figure 1 Cypress Street Study Area Location Map July 20, 2016 TO: FROM: Jim Massarelli Director of Engineering Jeff Julkowski, PE Michael Burke, PE SUBJECT: Cypress Street Study Area Stormwater Analysis (CBBEL Project No. 16-0058) At the request of

More information

APPLICATION FOR MINOR SITE PLAN REVIEW

APPLICATION FOR MINOR SITE PLAN REVIEW www.appleton.org APPLICATION FOR MINOR SITE PLAN REVIEW Community and Economic Development Department 100 N. Appleton St. PH: 920-832-6468 Appleton, WI 54911 FAX: 920-832-5994 Stamp date received PROPERTY

More information

Appendix I. Checklists

Appendix I. Checklists Appendix I Checklists Town of Greenwich Drainage Manual Department of Public Works - Engineering Division Town Hall - 101 Field Point Road, Greenwich, CT 06836-2540 Phone 203-622-7767 - Fax 203-622-7747

More information

Third Ave CSO Integrated Green Infrastructure

Third Ave CSO Integrated Green Infrastructure Third Ave CSO Integrated Green Infrastructure Neil Myers Williams Creek Consulting OWEA Annual Conference June 2013 For growing municipalities to be perceived as world class communities, each must move

More information

M E M O R A N D U M. Chair and Members of North West Planning Advisory Committee

M E M O R A N D U M. Chair and Members of North West Planning Advisory Committee Item 9.1.1 PO Box 1749 Halifax, Nova Scotia B3J 3A5 Canada M E M O R A N D U M TO: FROM: Chair and Members of North West Planning Advisory Committee Stephanie Salloum, Planner II DATE: June 26, 2017 SUBJECT:

More information

STORM WATER UTILITY FREQUENTLY ASKED QUESTIONS

STORM WATER UTILITY FREQUENTLY ASKED QUESTIONS STORM WATER UTILITY FREQUENTLY ASKED QUESTIONS In 2007, the City Council adopted Ordinance No. 1155 establishing a storm water utility in the City. No fee structure was adopted at that time. The idea of

More information

Chesapeake Bay Critical Area Conservation Plan

Chesapeake Bay Critical Area Conservation Plan The Maryland-National Capital Park and Planning Commission Prince George s County Planning Department Development Review Division 301-952-3530 Note: Staff reports can be accessed at www.mncppc.org/pgco/planning/plan.htm.

More information

REQUEST FOR COUNCIL ACTION 6A AGENDA ITEM

REQUEST FOR COUNCIL ACTION 6A AGENDA ITEM DATE REQUEST FOR COUNCIL ACTION 6A AGENDA ITEM ORIGINATING DEPT. AGENDA ITEM CITY ADMINISTRATOR APPROVAL Community Development PUD Concept & Development Stage Plan Preliminary Plat & Final Plat PREVIOUS

More information

Appendix D - Technical Design Criteria for BMPs

Appendix D - Technical Design Criteria for BMPs Appendix D - Technical Design Criteria for BMPs City of Wayzata Page 3 On-site infiltration features Definitions and Scope: Infiltration facilities are constructed basins or depressions located in permeable

More information

R E S O L U T I O N. Designation: Section 2, Block 17, Lot 20.G-1 ( ) R-2A (1-Family, 2-acre Minimum Lot Size) 46 North Greenwich Road

R E S O L U T I O N. Designation: Section 2, Block 17, Lot 20.G-1 ( ) R-2A (1-Family, 2-acre Minimum Lot Size) 46 North Greenwich Road PLANNING BOARD Arthur Adelman, Chair TOWN OF NORTH CASTLE WESTCHESTER COUNTY 17 Bedford Road Armonk, New York 10504-1898 R E S O L U T I O N Telephone: (914) 273-3542 Fax: (914) 273-3554 www.northcastleny.com

More information

ATTACHMENT 1 WILSON MINE LECROY AREA SEMIPERMANENT DEWATERING SYSTEM

ATTACHMENT 1 WILSON MINE LECROY AREA SEMIPERMANENT DEWATERING SYSTEM ATTACHMENT 1 WILSON MINE LECROY AREA SEMIPERMANENT DEWATERING SYSTEM Reclamation plans for the Wilson Mine Lecroy area were approved by the Arkansas Department of Environmental Quality with a passive barrier

More information

Approved: CITY OF ARDEN HILLS, MINNESOTA PLANNING COMMISSION WEDNESDAY, AUGUST 5, :30 P.M. - ARDEN HILLS CITY HALL

Approved: CITY OF ARDEN HILLS, MINNESOTA PLANNING COMMISSION WEDNESDAY, AUGUST 5, :30 P.M. - ARDEN HILLS CITY HALL Approved: CITY OF ARDEN HILLS, MINNESOTA PLANNING COMMISSION WEDNESDAY, AUGUST 5, 2015 6:30 P.M. - ARDEN HILLS CITY HALL PLANNING CASES A. Planning Case 15-016; Final Planned Unit Development Arden Plaza;

More information

HEALTH SCIENCES BUILDING REDEVELOPMENT PROJECT

HEALTH SCIENCES BUILDING REDEVELOPMENT PROJECT INTRODUCTION In recent years, the University of Cincinnati (University) has demonstrated a commitment to identifying and implementing sustainable goals and objectives throughout University s Uptown Campuses.

More information

280 Manse Road - Official Plan Amendment, Zoning Amendment, Draft Plan of Subdivision Applications - Preliminary Report

280 Manse Road - Official Plan Amendment, Zoning Amendment, Draft Plan of Subdivision Applications - Preliminary Report STAFF REPORT ACTION REQUIRED 280 Manse Road - Official Plan Amendment, Zoning Amendment, Draft Plan of Subdivision Applications - Preliminary Report Date: March 11, 2014 To: From: Wards: Reference Number:

More information

PRELIMINARY STAFF PLANNING REPORT TO THE WALWORTH COUNTY ZONING AGENCY X CONDITIONAL USE

PRELIMINARY STAFF PLANNING REPORT TO THE WALWORTH COUNTY ZONING AGENCY X CONDITIONAL USE This report was prepared prior to the public hearing. This report may be supplemented or amended to reflect the review of additional information presented at the public hearing and written material submitted

More information

6.1. INTRODUCTION 6.2. EXISTING CONDITIONS

6.1. INTRODUCTION 6.2. EXISTING CONDITIONS Chapter 6: Stormwater Management 6.1. INTRODUCTION This Chapter describes the current drainage patterns on the Project Site, the stormwater management system that is proposed as part of the Proposed Project,

More information

GENERAL INFORMATIONaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa

GENERAL INFORMATIONaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa To: Planning and Zoning Commission From: City Staff Date: November 15, 2016 Re: Case #16026 Raymore Activity Center Site Plan GENERAL INFORMATIONaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa Applicant/ Property Owner:

More information

Planning the BMP. Region 2000 Planning District Commission Lynchburg, VA December 13, 20013

Planning the BMP. Region 2000 Planning District Commission Lynchburg, VA December 13, 20013 Planning the BMP Region 2000 Planning District Commission Lynchburg, VA December 13, 20013 PLANNING THE BMP AGENDA BMP Selection BMP Design SWM Plan Preparation 2 BMP SELECTION Types of BMPs Structural

More information

City of Fort Lupton Administrative Site Plan Process

City of Fort Lupton Administrative Site Plan Process City of Fort Lupton Administrative Site Plan Process Purpose The Site Plan process is meant to promote orderly and sound development standards as they apply to the City. These site development standards

More information

Community and Economic Development Department 100 N. Appleton St. PH: Appleton, WI FAX:

Community and Economic Development Department 100 N. Appleton St. PH: Appleton, WI FAX: www.appleton.org APPLICATION FOR SITE PLAN REVIEW (Off-Street Parking Lot/Loading Expansions, Construction, Reconstruction & Rehabilitation Projects) Community and Economic Development Department 100 N.

More information

PLANNING APPROVAL & PLANNED UNIT DEVELOPMENT Date: April 6, 2017

PLANNING APPROVAL & PLANNED UNIT DEVELOPMENT Date: April 6, 2017 PLANNING APPROVAL & PLANNED UNIT DEVELOPMENT Date: April 6, 2017 DEVELOPMENT NAME LOCATION Mobile Christian School 5900 Cottage Hill Road (North side of Cottage Hill Road, 230 ± West of Freemont Drive

More information

STORMWATER REPORT FOR WALMART SUPERCENTER STORE # SIOUX FALLS, LINCOLN COUNTY, SOUTH DAKOTA BFA PROJECT NO

STORMWATER REPORT FOR WALMART SUPERCENTER STORE # SIOUX FALLS, LINCOLN COUNTY, SOUTH DAKOTA BFA PROJECT NO STORMWATER REPORT FOR WALMART SUPERCENTER STORE # 2443-00 SIOUX FALLS, LINCOLN COUNTY, SOUTH DAKOTA BFA PROJECT NO. 3286 March 1, 2012 I hereby certify that this engineering document was prepared by me

More information

Ref: March 21, Ms. Jody Kablack Director of Planning and Community Development Town of Sudbury 278 Old Sudbury Road Sudbury, MA 01776

Ref: March 21, Ms. Jody Kablack Director of Planning and Community Development Town of Sudbury 278 Old Sudbury Road Sudbury, MA 01776 35 New England Business Center Drive Suite 140 Andover, MA 01810-1066 Office: 978-474-8800 Fax: 978-688-6508 Web: www.rdva.com Ref: 7198 Director of Planning and Community Development Town of Sudbury 278

More information

Leduc Industrial Outline Plan SE W4

Leduc Industrial Outline Plan SE W4 Leduc Industrial Outline Plan SE 1-50-25-W4 Within the North Leduc Industrial ASP Prepared for: Leduc Energy Park Ltd. Prepared by: Stantec Consulting Ltd. File No. 1161 104655 V5 Table of Contents 1.0

More information

BASMAA Development Committee. Guidance for Identifying Green Infrastructure Potential in Municipal Capital Improvement Program Projects May 6, 2016

BASMAA Development Committee. Guidance for Identifying Green Infrastructure Potential in Municipal Capital Improvement Program Projects May 6, 2016 Background BASMAA Development Committee Guidance for Identifying Green Infrastructure Potential in Municipal Capital Improvement Program s May 6, 2016 In the recently reissued Municipal Regional Stormwater

More information

David J. Gellner, AICP, Principal Planner, , PLNSUB Harmons Brickyard Fuel Center Planned Development

David J. Gellner, AICP, Principal Planner, , PLNSUB Harmons Brickyard Fuel Center Planned Development Staff Report PLANNING DIVISION COMMUNITY & NEIGHORHOOD DEVELOPMENT To: From: Salt Lake City Planning Commission David J. Gellner, AICP, Principal Planner, 801-535-6107, david.gellner@slcgov.com Date: January

More information

WATERS EDGE AT DOBBS FERRY DRAFT ENVIRONMENTAL IMPACT STATEMENT VOLUME I

WATERS EDGE AT DOBBS FERRY DRAFT ENVIRONMENTAL IMPACT STATEMENT VOLUME I WATERS EDGE AT DOBBS FERRY DRAFT ENVIRONMENTAL IMPACT STATEMENT VOLUME I Atilda, Fairlawn and Constance Avenues Village of Dobbs Ferry Town of Greenburgh Westchester County, New York Tax Lot Numbers Section

More information