4KV Switchgear Susceptibility to Main Steam Line Break. By: Akbar Moarefy Kyle Millenaar PE

Size: px
Start display at page:

Download "4KV Switchgear Susceptibility to Main Steam Line Break. By: Akbar Moarefy Kyle Millenaar PE"

Transcription

1 4KV Switchgear Susceptibility to Main Steam Line Break By: Akbar Moarefy Kyle Millenaar PE

2 OE Discovery of New Harsh Environment Conditions 10/19/09 Monticello issued LER due to the failure of a HELB door fusible link with potential result of losing 4kV SWGR in case of HELB. 04/18/10 Prairie Island entered LCO after discovering U1 turbine building truck Aisle rollup door security fence was closed. This fence was required to remain open to drain flood water resulting from HELB in the turbine building. 9/16/11 Callaway issued LER due to failure in implementation of HELB defense (HELB doors) challenging equipment operability in areas of the plant that were intended to be mild. 2/10/12 Cooper (Green NCV): Failure to translate design requirements associated with turbine building HELB into design information to demonstrate protection of safety related 4160V switchgear and EDG 2/10/12 Braidwood (Green NCV): Failure to report non-conservative assumption in actuation time for fusible links that protect ESF switchgear room from HELB. 05/08/12 Braidwood (Green NCV): EQ failed to consider temp/humidity changes in EDG, ESG and MEER rooms during a turbine building HELB 06/07/12 Millstone entered TS action statement when they determined that the practice of opening the switchgear room doors as compensatory measure when ventilation was OOS could allow steam from HELB enter the SWGR.

3 DCPP Discovery of New Harsh Environment Conditions In August 2014, Diablo Canyon Power Plant entered Technical Specifications due to non-conservative assumptions in a legacy calculation resulting in the Design Class 1E emergency power supply switchgear (4kV switchgear) being exposed to a high-temperature, high-humidity environment during a main steam line break (MSLB). Corrective action was implemented by closing the fire dampers isolating 4kV SWGR from turbine deck atmosphere. Issue became past operability assessment (29 years)

4 Background Unit 1: Start up date Unit 2: Start up date Legacy calculation dated 1983 (before plant startup) assumed dead volume of air in the 4kV SWGR preventing the entry of steam following HELB. It also made wrong assumptions about fusible links closing the fire dampers, isolating SWGR from HELB environment. Reexamination of calculation of record proved the assumption to be wrong. Following a HELB in turbine building steam can enter the 4kV SWGR when the thermostat controlled HVAC fans are not running causing humidity reach 100%RH. 4kV SWGR components were not qualified for a 100%RH environment.

5 False Assumptions Room HVAC supply fans provide a positive pressure of psi. Model shows steam pressure to be approximately 10x greater than supply fan

6 Background Turbine building ceiling curved First stage high pressure turbine

7 Background 4kV Exhaust duct on Turbine Deck

8 Background 4kV switchgear panel top vent 4kV switchgear panel bottom vent

9 Is it possible to retract entry into 3.0.0? DCPP EQ Group recommended testing all the 4kV SWGR components under the newly discovered adverse condition. Other groups including AREVA suggested to pursue parallel success paths to prove past operability.

10 Is it possible to retract entry into 3.0.0? AREVA was contracted to lead the project. Nutherm was subcontracted to perform qualification tests. Initial proposal was received by AREVA on 8/12 The Test Spec was drafted by DCPP on 9/2/14 Testing was completed on 9/12/14 Final report was issued on 9/19 (5 weeks)

11 Paths to Prove Past Operability ALPHA Path: Elimination of 0.9 sq-ft longitudinal split break Double Ended guillotine break results in a rapid isolation of the steam line and does not create adverse environment in the 4kV SWGR. a 0.9 sq-ft longitudinal split break which is not sufficient in size to isolate the steam line but does expose the vented cabinets in the switchgear room to a 100% humidity environment. STATUS: This success path failed

12 Paths to Prove Past Operability BRAVO Path: Remove conservatism from GOTHIC model using NRC Operability determination guidelines such as IM goal was to prove the environment in the 4kV SWGR would remain mild following a HELB on the turbine deck. STATUS: This success path failed

13 Paths to Prove Past Operability CHARLIE Path: Using Computational Fluid Dynamics (CFD) Analysis for the 4kV SWGR. Use CFD models of the switchgear rooms to simulate the temperature, flow fields and humidity distribution inside the switchgear rooms. These simplified models included the air flow within the switchgear room from the floor to the exhaust duct/turbine building interface. Goal of the model was to demonstrate that the hot humid air entering the room would flow out the normal air inlet without approaching the vented cabinet vent locations. Thus concluding that the SWGR components would not have been subjected to an adverse environment. STATUS: This success path failed

14 Paths to Prove Past Operability DELTA Path: Computational Fluid Dynamics Analysis of Vented Cabinets. The simplified CFD models created in the CHARLIE path were used to extend to model the air flow and humidity distribution within the vented cabinets. Goal of this success path was to demonstrate that the even with 100% humidity in the 4kV SWGR, the components within the cabinets will not be exposed to condensing environment. STATUS: This success path failed

15 Paths to Prove Past Operability ECHO Path: Vented Cabinet Components Already Qualified for 100% humidity conditions. Compare DCPP s component list and HELB qualification requirements to existing industry qualification reports to eliminate or reduce the need to test components in humid environment. STATUS: Only one component was eliminated

16 Paths to Prove Past Operability FOXTROT Path Conduct Qualification Testing on the 4kV SWGR components. STATUS: 35 components representing 756 components used in the 4kV SWGR cabinets were successfully tested. Leakage current on a terminal block with broken barrier wall in a 100%RH condensing environment was measured to be minimal with no adverse impact. Potential for arc flash was eliminated by test on high voltage components.

17 TEST CABINET TEST CHAMBER

18 Questions?

Union County Vocational - Technical Schools Scotch Plains, New Jersey

Union County Vocational - Technical Schools Scotch Plains, New Jersey SECTION 230593 - TESTING, ADJUSTING, AND BALANCING FOR HVAC PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Balancing Air Systems: a. Constant-volume air systems. b. Variable-air-volume systems. 2.

More information

City of Duluth Festival Center 04/25

City of Duluth Festival Center 04/25 SECTION 230593 - TESTING, ADJUSTING, AND BALANCING FOR HVAC PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and

More information

Flexible and efficient: Close Climate Control for IT equipment

Flexible and efficient: Close Climate Control for IT equipment GEA Multi-DENCO Flexible and efficient: Close Climate Control for IT equipment engineering for a better world GEA Heat Exchangers GEA Multi-Denco at a glance: Multiple functions and applications High flexibility

More information

Submitted to. Texas A&M University-Corpus Christi The Texas A&M University System. Submitted by. Yeqiao Zhu Dan Turner David Claridge

Submitted to. Texas A&M University-Corpus Christi The Texas A&M University System. Submitted by. Yeqiao Zhu Dan Turner David Claridge ESL-TR-99/12-04 Report of Energy Efficiency Study and Metering/Utilities Profile for Electricity Deregulation at the Texas A&M University-Corpus Christi (TAMU-CC) Corpus Christi, Texas Submitted to Texas

More information

Brown University Revised June 29, 2012 Facilities Design & Construction Standards SECTION ELECTRICAL DESIGN CRITERIA

Brown University Revised June 29, 2012 Facilities Design & Construction Standards SECTION ELECTRICAL DESIGN CRITERIA PART 1 - GENERAL 1.1 Background SECTION 26 00 10- ELECTRICAL DESIGN CRITERIA A. Brown University maintains it own campus electrical distribution system which serves the majority of the buildings and facilities

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017 SECTION 23 0594 - TESTING, ADJUSTING, AND BALANCING (TAB) PART 1 - GENERAL 1.1 SUMMARY A. This Section includes testing, adjusting and balancing HVAC systems to provide design conditions as indicated by

More information

HAP e-help. Modeling Induction Beams in HAP v4.8 QB TIP 001

HAP e-help. Modeling Induction Beams in HAP v4.8 QB TIP 001 This HAP e-help provides a high-level overview of induction beams, how they work and how to model them in HAP 4.8 (and later versions). The first half of the article explains how induction beams work.

More information

Air Distribution Fan and Outside Air Damper Recycling Control

Air Distribution Fan and Outside Air Damper Recycling Control building science.com 2008 Building Science Press All rights of reproduction in any form reserved. Air Distribution Fan and Outside Air Damper Recycling Control Research Report - 0991 5-July-1999 Armin

More information

SECTION TESTING, ADJUSTING AND BALANCING

SECTION TESTING, ADJUSTING AND BALANCING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Specification Sections, apply to this Section. B. Related Sections

More information

SECTION AIR DUCT ACCESSORIES

SECTION AIR DUCT ACCESSORIES SECTION 23 33 00 AIR DUCT ACCESSORIES PART 1 - GENERAL 1.1 SUMMARY A. Section includes back-draft dampers, combination fire-and-smoke dampers, duct access doors, fire dampers, smoke dampers, volume control

More information

Tunnel Fire Dynamics and Evacuation Simulations

Tunnel Fire Dynamics and Evacuation Simulations Tunnel Fire Dynamics and Evacuation Simulations James Priest, PhD & James Niehoff DGS-SEE Seminar on Fire Protection for Physics Research Facilities 7 & 8 October 2015 Introduction (Background) Presentation

More information

CxA to Answer this Section

CxA to Answer this Section EXHIBIT 01 91 13-3, SAMPLE Construction checklist items are to be completed as part of initial checkout and subsequent startup, preparatory to Functional testing. This checklist does not take the place

More information

S and SF Inverted Bucket Steam Traps Installation and Maintenance Instructions

S and SF Inverted Bucket Steam Traps Installation and Maintenance Instructions 0772150/4 IM-P077-02 ST Issue 4 S and SF Inverted Bucket Steam Traps Installation and Maintenance Instructions 1. General safety information 2. General product information 3. Installation 4. Commissioning

More information

INVESTIGATION FINDINGS III IMPACT OF INADEQUATE VENTILATION AND DISCHARGE SYSTEMS

INVESTIGATION FINDINGS III IMPACT OF INADEQUATE VENTILATION AND DISCHARGE SYSTEMS INVESTIGATION FINDINGS III IMPACT OF INADEQUATE VENTILATION AND DISCHARGE SYSTEMS SUMMARY Ammonia odours were reported in the community close to the time of the incident (Appendix D) and firefighters reported

More information

Company Directive STANDARD TECHNIQUE : SP1N

Company Directive STANDARD TECHNIQUE : SP1N Company Directive STANDARD TECHNIQUE : SP1N Heating, Dehumidification and Ventilation of Switch Rooms and Control Rooms at Grid, Primary and Major Network Substations ST:SP1N October 2013-1 of 9 - Document

More information

Job Name Control Systems Description Date

Job Name Control Systems Description Date Job Name Control Systems Description Date Project Overview The project is a describe the building and its major HVAC systems (e.g. three-story office building, served by a rooftop unit VAV system ). In

More information

August 15, 2013 Page 1 of 19

August 15, 2013 Page 1 of 19 Section C401 Application Compliance with C402, C403, C404 and C405 AND (either C406.2, C406.3 or C406.4) Compliance with C402, C403, C404 or C405 Section C402 Building Envelope (Climate Zone 5A) Space-Conditioning

More information

Fire, Smoke and Control Dampers

Fire, Smoke and Control Dampers MANUAL Fire, Smoke and Control Dampers v100 Issue Date: 04/02/15 2015 Price Industries Limited. All rights reserved. TABLE OF CONTENTS Maintenance, Testing and Inspection Recommendations Recommended Maintenance

More information

Development of standards for MV Switchgear for Arc Flash protection. ABB Group May 20, 2013 Slide 1

Development of standards for MV Switchgear for Arc Flash protection. ABB Group May 20, 2013 Slide 1 Development of standards for MV Switchgear for Arc Flash protection May 20, 2013 Slide 1 Development of standards for MV Switchgear for Arc Flash protection Bryan Johnson ABB South Africa Shaping the world

More information

Control of temperature and humidity surrounding the stone chamber of Takamatsuzuka tumulus during its dismantlement

Control of temperature and humidity surrounding the stone chamber of Takamatsuzuka tumulus during its dismantlement Control of temperature and humidity surrounding the stone chamber of Takamatsuzuka tumulus during its dismantlement Daisuke Ogura 1, Masahide Inuzuka 2, Shuichi Hokoi 1, Takeshi Ishizaki 2, Hiroyuki Kitahara

More information

FEATURES AND BENEFITS

FEATURES AND BENEFITS FEATURES AND BENEFITS Product Features and Benefits Full Product Line Offering Feature All models are 80% thermally efficient Blower performance up to 3.0 W.C. DX or chilled water section with factory

More information

AIR-CONDITIONING SYSTEMS AND APPLICATIONS. Abdullah Nuhait Ph D. King Saud University

AIR-CONDITIONING SYSTEMS AND APPLICATIONS. Abdullah Nuhait Ph D. King Saud University AIR-CONDITIONING SYSTEMS AND APPLICATIONS Abdullah Nuhait Ph D. King Saud University AIR-CONDITIONING SYSTEMS Earliest air conditioning system used only for heating (winter) Provided heated air for comfort

More information

RAMAPO COLLEGE OF NEW JERSEY CCA0803 PHASE II HOUSING REHABILITATION 2012

RAMAPO COLLEGE OF NEW JERSEY CCA0803 PHASE II HOUSING REHABILITATION 2012 SECTION 230593 - TESTING, ADJUSTING, AND BALANCING FOR HVAC PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and

More information

PALO VERDE NUCLEAR GENERATING STATION

PALO VERDE NUCLEAR GENERATING STATION PALO VERDE NUCLEAR GENERATING STATION HVAC Classroom Lesson HVAC Training Date: 01/13/2005 LP Number: NMH10X000502 Rev Author: Paula Stapleton Title: PAMU AC Units Technical Review: Duration : 1.5 Hours

More information

1.1 DESCRIPTION A. The purpose of this section is to specify Division 23 responsibilities in the commissioning (Cx) process.

1.1 DESCRIPTION A. The purpose of this section is to specify Division 23 responsibilities in the commissioning (Cx) process. SECTION 239950 MECHANICAL COMMISSIONING SYSTEMS PART 1 - GENERAL 1.1 DESCRIPTION A. The purpose of this section is to specify Division 23 responsibilities in the commissioning (Cx) process. B. Commissioning

More information

Submitted to. Texas A&M University at Galveston The Texas A&M University System. Submitted by. Yeqiao Zhu Dan Turner David Claridge

Submitted to. Texas A&M University at Galveston The Texas A&M University System. Submitted by. Yeqiao Zhu Dan Turner David Claridge ESL-TR-99/12-05 Report of Energy Efficiency Study and Metering/Utilities Profile for Electricity Deregulation at the Texas A&M University at Galveston (TAMU-G) Galveston, Texas Submitted to Texas A&M University

More information

COMcheck Software Version Review Mechanical Compliance Certificate

COMcheck Software Version Review Mechanical Compliance Certificate COMcheck Software Version 4.0.7.2 Review Mechanical Compliance Certificate Section 1: Project Information Energy Code: 2014 Oregon Energy Efficiency Specialty Code Project Title: Benton County Health Project

More information

Heating and Cooling Coils

Heating and Cooling Coils Heating and Cooling Coils Coils for All Comfort, Commercial and Industrial Applications Delta-Flo Fin Design The Delta-Flo coil features a staggered 1/2-inch tube pattern and unique fin design allowing

More information

SECTION TESTING, ADJUSTING, AND BALANCING FOR HVAC INTRODUCTORY INFORMATION

SECTION TESTING, ADJUSTING, AND BALANCING FOR HVAC INTRODUCTORY INFORMATION SECTION 15990 TESTING, ADJUSTING, AND BALANCING FOR HVAC INTRODUCTORY INFORMATION The purpose of this guide specification is to assist the Specifier in correctly specifying Mechanical System Testing Adjusting

More information

INSTALLATION INSTRUCTIONS AH12 WALL MOUNT HOOD

INSTALLATION INSTRUCTIONS AH12 WALL MOUNT HOOD Read and Save These Instructions All Hoods Must Be Installed By A Qualified Installer INSTALLATION INSTRUCTIONS AH12 WALL MOUNT HOOD Read All Instructions Thoroughly Before Beginning Installation WARNING

More information

LOW-NOX BURNER RETROFIT CHALLENGE

LOW-NOX BURNER RETROFIT CHALLENGE LOW-NOX BURNER RETROFIT CHALLENGE By Craig Lieb Applications Engineer Zeeco, Inc. Rutland, UK Ryan Roberts Project Engineering Manager Zeeco, Inc. Broken Arrow, OK, U.S.A. Ryan Roberts has more than 20

More information

Senior Thesis Centre Community Hospital East Wing Addition - Proposal Keith Beidel Mechanical Option 12/05/02 1

Senior Thesis Centre Community Hospital East Wing Addition - Proposal Keith Beidel Mechanical Option 12/05/02 1 Table of Contents Page Number(s) Executive Summary 2 Project Background 3 Proposed Depth Alternatives 4 Proposed Depth Redesign 5-7 Justification of Proposed Depth Redesign 8 Proposed Breath Redesign 9

More information

Submitted to. Texas A&M University at Commerce The Texas A&M University System. Submitted by. Guanghua Wei Craig Campbell David Claridge Dan Turner

Submitted to. Texas A&M University at Commerce The Texas A&M University System. Submitted by. Guanghua Wei Craig Campbell David Claridge Dan Turner ESL-TR-99/12-09 Report of Energy Efficiency Study and Metering/Utilities Profile for Electricity Deregulation at the Texas A&M University at Commerce (TAMU-Commerce) Commerce, Texas Submitted to Texas

More information

INTRODUCTION. Special Applications of Package Air Conditioners. Instant Cooling Requirement in Wedding Ceremonies

INTRODUCTION. Special Applications of Package Air Conditioners. Instant Cooling Requirement in Wedding Ceremonies Pakistan s Largest Manufacturers of Air-Conditioners PACKAGE TYPE UNIT FOR MOBILE APPLICATIONS Provides Turnkey Projects Conceptual Planning to Commissioning of HVACR Projects THE LARGEST MANUFACTURER

More information

Soot Mitigation Strategies

Soot Mitigation Strategies Soot Mitigation Strategies Walter P. Drosjack, P.E. David L. Oar, P.E., F.S.F.P.E. 32 nd Nuclear Air Cleaning Conference June 18-19, 2012 Who is URS? URS is one of the world s largest engineering, construction

More information

Guide Spec Summary. Option List. Date: 05/21/2001. EarthWise VAV Terminal Units Full Spec. Prepared by: Phone Number: Prepared for:

Guide Spec Summary. Option List. Date: 05/21/2001. EarthWise VAV Terminal Units Full Spec. Prepared by: Phone Number: Prepared for: Date: 05/21/2001 Time: 02:57:44 PM Job Name: EarthWise VAV Terminal Units Full Spec Location: AnyTown, Earth Prepared by: Phone Number: Prepared for: Guide Spec Summary Option List SINGLE & DUAL DUCT UNIT

More information

Instrumentation for Nuclear Applications

Instrumentation for Nuclear Applications Instrumentation for Nuclear Applications Nuclear Instrumentation Overview Delta Controls has been designing and manufacturing instrumentation for the power and process industries for over 65 years and

More information

Steam Trap Inspection Methods And Steam Cost Analysis

Steam Trap Inspection Methods And Steam Cost Analysis Steam Trap Inspection Methods And Steam Cost Analysis 14 Hayes Street, Elmsford NY 10523-2536 USA Tel: 914-592-1220 Toll Free USA & Canada 24 Hour Fax Email: Internet 800-223-1325 914-347-2181 info@uesystems.com

More information

INSTRUMENTATION AND CONTROL DEVICES FOR HVAC

INSTRUMENTATION AND CONTROL DEVICES FOR HVAC PART 1 GENERAL 1.01 RELATED REQUIREMENTS SECTION 23 0913 INSTRUMENTATION AND CONTROL DEVICES FOR HVAC A. Section 26 2717 - Equipment Wiring: Electrical characteristics and wiring connections. 1.02 ADMINISTRATIVE

More information

March 2014 AHRI Presents Research Findings at Low-GWP AREP Conference

March 2014 AHRI Presents Research Findings at Low-GWP AREP Conference March 2014 AHRI Presents Research Findings at Low-GWP AREP Conference In addition to its regular research activities, AHRI is conducting the Low-Global Warming Potential Alternative Refrigerants Evaluation

More information

RESNET HERS Rater Sample Test Questions 2

RESNET HERS Rater Sample Test Questions 2 RESNET HERS Rater Sample Test Questions 2 1. Which of the following is the best device for removing standing water from a crawl space? A. Dehumidifier B. Sump pump C. Air-to-air heat exchanger D. Crawl-space

More information

Technical Presentation on

Technical Presentation on Technical Presentation on PID _00012345 Heating and refrigeration system using waste heat energy Photo (Author 1) Photo (Author 2) Author 1 Name Author 2 Name Restricted Circulation L&T Technology Services

More information

YARWAY NON-REPAIRABLE DRIP AND TRACER STEAM TRAPS SERIES PB, 29, 129Y AND 29S

YARWAY NON-REPAIRABLE DRIP AND TRACER STEAM TRAPS SERIES PB, 29, 129Y AND 29S SERIES PB, 29, 129Y AND 29S Economical and simplified solutions that offer quality and optimum steam trap service FEATURES 29S 29 Thermostatic traps Pressure assisted fail-open design Freeze proof Easy

More information

Steam Trap Presentation for IDEA Distribution Workshop. Presenter: Joe Radle

Steam Trap Presentation for IDEA Distribution Workshop. Presenter: Joe Radle Steam Trap Presentation for IDEA Distribution Workshop Presenter: Joe Radle Proper Piping when Reducing Pipe Size Concentric reducer Eccentric reducer Correct Wrong Typical Steam Main Drip Station D Size

More information

White Paper. The Victaulic Vortex Fire Suppression System Fire Suppression for Electrical and Electronic Applications

White Paper. The Victaulic Vortex Fire Suppression System Fire Suppression for Electrical and Electronic Applications White Paper The Victaulic Vortex Fire Suppression System Fire Suppression for Electrical and Electronic Applications Matthew Puzio, Senior Project Engineer, Fluid Control Technology, Victaulic updated

More information

UNIVERSITY OF MISSOURI Heating Ventilating and Air-Conditioning (HVAC) 2016 Q1

UNIVERSITY OF MISSOURI Heating Ventilating and Air-Conditioning (HVAC) 2016 Q1 GENERAL: This section provides general standards for overall sizing and design of Heating, Ventilating, and Air Conditioning (HVAC) systems. Other sections contain specific standards for each system per

More information

1080 Marina Village Parkway, Suite 501 Alameda, CA (510) Fax (510) HVAC DESIGN INTENT

1080 Marina Village Parkway, Suite 501 Alameda, CA (510) Fax (510) HVAC DESIGN INTENT Taylor Engineering 1080 Marina Village Parkway, Suite 501 Alameda, CA 94501-1142 (510) 749-9135 Fax (510) 749-9136 LLC HVAC DESIGN INTENT PART 1 - GENERAL 1.1 Overview A. The project consists of a 3-story

More information

CHAPTER 3 BASIC STEAM CYCLE

CHAPTER 3 BASIC STEAM CYCLE CHAPTER 3 BASIC STEAM CYCLE To understand steam generation, you must know what happens to the steam after it leaves the boiler. A good way to learn the steam plant on your ship is to trace the path of

More information

INSTY-PAC INTERNAL MOUNT WELDED MULTIPLE TUBE ASSEMBLY

INSTY-PAC INTERNAL MOUNT WELDED MULTIPLE TUBE ASSEMBLY Read and Save These Instructions Sheet No. LSIP-IM INSTY-PAC INTERNAL MOUNT WELDED MULTIPLE TUBE ASSEMBLY INSTALLATION AND ASSEMBLY INSTRUCTIONS Fig. 1 Strainer Secure to AHU/duct casing with 3/8-16 UNC

More information

Screw Compressors AS SERIES. Capacities from: 59 to 124 cfm Pressures from: 80 to 217 psig

Screw Compressors AS SERIES. Capacities from: 59 to 124 cfm Pressures from: 80 to 217 psig Screw Compressors AS SERIES Capacities from: 59 to 124 cfm Pressures from: 80 to 217 psig Rotary Screw Compressor Maximum Reliability and Efficiency For years, customers have relied on Kaeser for reliable

More information

INTRODUCTION. JAU /JCC/JVC Series Jet Fans - for car park ventilation

INTRODUCTION. JAU /JCC/JVC Series Jet Fans - for car park ventilation JAU /JCC/JVC Series Jet Fans - for car park ventilation INTRODUCTION Pacific HVAC Engineering is able to offer a complete solution in car park ventilation at a competitive price with in house developed

More information

AIRPORT OFFICE BUILDING. Smoke Control System. Testing Procedures Manual. September 10, 2016

AIRPORT OFFICE BUILDING. Smoke Control System. Testing Procedures Manual. September 10, 2016 IMPACT ENGINEERING, INC. AIRPORT OFFICE BUILDING Smoke Control System Testing Procedures Manual September 10, 2016 All Rights Reserved This manual is protected by the U.S. Copyright Law (Title 17 United

More information

Tunnel Axial Flow Fan

Tunnel Axial Flow Fan Tunnel Axial Flow Fan TUNNEL AXIAL FLOW FAN Tunnel fans are an axial flow fans and moves an airstream along the axis of the fan. The air is pressurized by the aerodynamic lift generated by the fan blades,

More information

Indirect Gas-Fired Make-Up Air

Indirect Gas-Fired Make-Up Air Indirect Gas-Fired Make-Up Air Model IG 800 to 7,000 cfm Up to 400,000 Btu/hr Multiple Furnace Control Options Optional Evaporative Cooling May 20041 Product Features Model IG Indirect Gas-Fired Make-Up

More information

Installation Guide IM 1248

Installation Guide IM 1248 Installation Guide IM 1248 BACnet Thermostat for Heat Pump Units Group: Controls Part Number: IM 1248 Date: August 2015 Table of Contents Installation Guide Heat Pump.... 2 Applicable Models... 2 Mounting

More information

TESTING STEAM TRAPS TO KEEP YOUR SYSTEM OPERATING EFFECTIVELY AND EFFICIENTLY

TESTING STEAM TRAPS TO KEEP YOUR SYSTEM OPERATING EFFECTIVELY AND EFFICIENTLY TESTING STEAM TRAPS TO KEEP YOUR SYSTEM OPERATING EFFECTIVELY AND EFFICIENTLY A steam trap, which is a fully automated condensate drainage device, generally does not require routine maintenance. Steam

More information

SPECIFIC APPLIANCES, FIREPLACES AND SOLID FUEL-BURNING EQUIPMENT

SPECIFIC APPLIANCES, FIREPLACES AND SOLID FUEL-BURNING EQUIPMENT CHAPTER 9 SPECIFIC APPLIANCES, FIREPLACES AND SOLID FUEL-BURNING EQUIPMENT SECTION 901 GENERAL 901.1 Scope. This chapter shall govern the approval, design, installation, construction, maintenance, alteration

More information

Worried aboutthe air quality in your schools?

Worried aboutthe air quality in your schools? Worried aboutthe air quality in your schools? Now you can breathe a little easier. (And so can everyone else.) EMA Chicago, Inc. The Situation The Environmental Protection Agency Documented that in 1995

More information

KINGS COUNTY JAIL EXPANSION PHASE III COUNTY OF KINGS SECTION

KINGS COUNTY JAIL EXPANSION PHASE III COUNTY OF KINGS SECTION SECTION 237433, PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to

More information

EL-TSTAT-8820 Safety & Installation Instructions

EL-TSTAT-8820 Safety & Installation Instructions EL-TSTAT-8820 Safety & Installation Instructions TABLE OF CONTENTS WI-FI SETUP Wi-Fi Setup 2 INSTALLATION Installation location recommendations 3 Outdoor temperature sensor (included) 3 Remote temperature

More information

Put the V back in HVAC

Put the V back in HVAC Put the V back in HVAC V is for Ventilation A system or means of providing fresh air. Webster New Collegiate Dictionary Benjamin Franklin so unwholesome as air in a closed room that has been often breathed

More information

SIMPLICITY FULL MODULARITY?

SIMPLICITY FULL MODULARITY? D E S I G N I N G I N N O V A T I V E S O L U T I O N S AIR CONDITIONING & HEATING SOLUTIONS OR SIMPLICITY FULL MODULARITY? IDROFAN, BECAUSE YOU SHOULD NOT HAVE TO CHOOSE. Hydronic ducted fan coils Cooling

More information

Effects of Kitchen Ventilation on Residential Dwellings

Effects of Kitchen Ventilation on Residential Dwellings Effects of Kitchen Ventilation on Residential Dwellings Anthony C. Jellen Engineering i Projects Incorporated 1 Personal Background U.S.N. (1994 2000) BS B.S. in Civil Engineering (2005) PHRC employee

More information

DOCUMENT TABLE OF CONTENTS

DOCUMENT TABLE OF CONTENTS DOCUMENT 00003 June 16, 2005 TABLE OF CONTENTS DOCUMENT NO. INTRODUCTORY INFORMATION DOCUMENT 00003 TABLE OF CONTENTS DIVISION 1 GENERAL REQUIREMENTS SECTION 01011 SECTION 01025 SSP21.1-1 SECTION 01026

More information

Model: 400E-5M. Bermad Hydraulically Controlled Anti-Columning Deluge Valve, with Easylock Manual Reset. Installation Operation Maintenance

Model: 400E-5M. Bermad Hydraulically Controlled Anti-Columning Deluge Valve, with Easylock Manual Reset. Installation Operation Maintenance Model: 400E-5M Bermad Hydraulically Controlled Anti-Columning Deluge Valve, with Easylock Manual Reset Installation Operation Maintenance Application Engineering Bermad 1. Safety First BERMAD believes

More information

Energy Saver 101: Home Energy Audits

Energy Saver 101: Home Energy Audits Energy Saver 101: Home Energy Audits Take the first step to improving your home s energy efficiency: get a home energy audit. What is a home energy audit? A home energy audit helps you pinpoint where your

More information

CARRIER edesign SUITE NEWS. Interpreting High (Low) Peak Design Airflow Sizing Results for HVAC. Equipment Selection.

CARRIER edesign SUITE NEWS. Interpreting High (Low) Peak Design Airflow Sizing Results for HVAC. Equipment Selection. Volume 5, Issue 1 CARRIER edesign SUITE NEWS Interpreting High (Low) Peak Design Airflow Sizing Results for HVAC Equipment Selection A design challenge sometimes occurs when computing design loads using

More information

Rapid transfer port technology

Rapid transfer port technology Rapid transfer port technology High Purity day Vught, NL 04 June 2014 1 Objective Presentation of rapid transfer port technology AGENDA What is an RTP History of RTP s How do they work and where are they

More information

TMB Baking TSV Gas Oven TAG Series. Contractor s Utility Requirements

TMB Baking TSV Gas Oven TAG Series. Contractor s Utility Requirements TMB Baking TSV Gas Oven TAG Series Contractor s Utility Requirements NATURAL GAS FIRED - INSTALL INSTRUCTIONS - This Manual is prepared for the use of licensed utility contractors. All gas, electrical,

More information

Basic Input Data Needed to Develop a High Performance Fan/Blower with Low Noise, Energy Saving and High Efficiency

Basic Input Data Needed to Develop a High Performance Fan/Blower with Low Noise, Energy Saving and High Efficiency Basic Input Data Needed to Develop a High Performance Fan/Blower with Low Noise, Energy Saving and High Efficiency Haiye Lou TurboMoni Applied Dynamics Lab Abstract It is often happened, when a project

More information

DEMAND CONTROLLED VENTILATION WITHOUT WIRES

DEMAND CONTROLLED VENTILATION WITHOUT WIRES DEMAND CONTROLLED VENTILATION WITHOUT WIRES With increased demand for intelligent climate control systems, more and more HVAC installations deploy VAV/VAQ terminals that allow temperature control in such

More information

HVAC OUTDOOR AIR VENTILATION STANDARD. ASHRAE Standard ASHRAE Standard

HVAC OUTDOOR AIR VENTILATION STANDARD. ASHRAE Standard ASHRAE Standard ASHRAE Standard 62.1-2013 BuildingsOne February 4, 2016 Landlord s HVAC system design capacity shall equal or exceed outdoor air ventilation requirements specified in ASHRAE Standard 62.1-2013 (prospect

More information

SECTION AIR COILS

SECTION AIR COILS PART 1 - GENERAL 1.1 DESCRIPTION SECTION 23 82 16 AIR COILS SPEC WRITER NOTE: Delete between //---// if not applicable to project. Also delete any other item or paragraph not applicable in the section

More information

Modular Supply Make-Up Air Unit

Modular Supply Make-Up Air Unit Modular Supply Make-Up Air Unit Model MSX Flexible Design Factory Assembled Heating Options Hot Water Steam Electric Cooling Options Evaporative Direct Expansion Chilled Water November 2009 Product Features

More information

Innovative Boiler & Heat Exchanger Concepts

Innovative Boiler & Heat Exchanger Concepts www.wea-inc.com Wallace Eannace Associates Presents: Innovative Boiler & Heat Exchanger Concepts for Plumbing Applications Bob Barrett, CEM, LEED AP Sales Engineer Wallace Eannace Associates, Inc. www.wea-inc.com

More information

Museum Archive Dehumidification in Hot & Humid Climates

Museum Archive Dehumidification in Hot & Humid Climates Museum Archive Dehumidification in Hot & Humid Climates B. K. Browning, PE Principal Engineer KWR Services Austin, Texas ABSTRACT This paper discusses some of the difficulties found with a desiccant dehumidification

More information

An Overview to Designing Smoke-Control Systems

An Overview to Designing Smoke-Control Systems The following article was published in ASHRAE Journal, June, 2002. Copyright 2002 American Society of Heating, Refrigerating and Air- Conditioning Engineers, Inc. It is presented for educational purposes

More information

SCHULTE & ASSOCIATES Building Code Consultants 880D Forest Avenue Evanston, IL /

SCHULTE & ASSOCIATES Building Code Consultants 880D Forest Avenue Evanston, IL / SCHULTE & ASSOCIATES Building Code Consultants 880D Forest Avenue Evanston, IL 60202 fpeschulte@aol.com 504/220-7475 A CRITIQUE OF HUGHES ASSOCIATES, INC. PAPER TITLED: Analysis of the Performance of Ganged

More information

CARRIER edesign SUITE NEWS. Modeling 100% OA Constant Volume Air Systems. Volume 6, Issue 1. Page 1 Modeling 100% OA Constant Volume Air Systems

CARRIER edesign SUITE NEWS. Modeling 100% OA Constant Volume Air Systems. Volume 6, Issue 1. Page 1 Modeling 100% OA Constant Volume Air Systems Volume 6, Issue 1 CARRIER edesign SUITE NEWS Modeling 100% OA Constant Volume Air Systems This article provides an overview of how to model a stand-alone constant air volume (CAV) 100% OA system in HAP.

More information

Infrared Business Tips & Insight

Infrared Business Tips & Insight Infrared Business Tips & Insight 2010 Infrared Training Center. All rights reserved. Intended for use by Infrared Training Center customers and prospects only Infrared Business Tips & Insight Presenter:

More information

NOx REDUCTION EXPERIENCE ON NATURAL GAS FIRED TURBO FURNACES

NOx REDUCTION EXPERIENCE ON NATURAL GAS FIRED TURBO FURNACES NOx REDUCTION EXPERIENCE ON NATURAL GAS FIRED TURBO FURNACES by D. E. Dorman, Staff Engineer DB Riley, Inc. Presented at the International Joint Power Generation Conference Miami Beach, Florida July 23-25,

More information

Gas-Fired Indoor and Outdoor Duct Furnaces

Gas-Fired Indoor and Outdoor Duct Furnaces July, 2008 Gas-Fired Indoor and Outdoor Duct Furnaces INDOOR GRAVITY VENTED DFG, DBG, DCG INDOOR SEPARATED COMBUSTION DFS, DBS, DCS OUTDOOR GRAVITY AND POWER EXHAUSTED H Series table of contents A complete

More information

Brown University Revised August 3, 2012 Facilities Design & Construction Standards SECTION AIR HANDLING UNITS

Brown University Revised August 3, 2012 Facilities Design & Construction Standards SECTION AIR HANDLING UNITS SECTION 23 70 00 AIR HANDLING UNITS PART 1. GENERAL 1.1 Section includes air-handling units to 15,000 cfm and accessories. 1.2 Related Sections 1 : A. Division 01 - Brown University Standard for Narragansett

More information

How to ensure Thermal Comfort in buildings with CFD

How to ensure Thermal Comfort in buildings with CFD How to ensure Thermal Comfort in buildings with CFD Using CFD Simulations to analyze and improve HVAC Systems Simulation in your browser How to Ensure Thermal Comfort in Buildings with CFD How to use CFD

More information

VALIDATION OF FINITE ELEMENT MODELS OF INJURY RISK IN VEHICLE-ROADSIDE BARRIER CRASHES

VALIDATION OF FINITE ELEMENT MODELS OF INJURY RISK IN VEHICLE-ROADSIDE BARRIER CRASHES VALIDATION OF FINITE ELEMENT MODELS OF INJURY RISK IN VEHICLE-ROADSIDE BARRIER CRASHES Qian Wang, Hampton C. Gabler Virginia Tech-Wake Forest, Center for Injury Biomechanics Blacksburg, VA 24061 ABSTRACT

More information

Economical and simplified solutions that offer quality and optimum steam trap service.

Economical and simplified solutions that offer quality and optimum steam trap service. Economical and simplified solutions that offer quality and optimum steam trap service. It All Comes Down To Protection Regardless of the temperature and pressure characteristics of steam line drips or

More information

Installation Instructions

Installation Instructions FAVXXR6C2100-A01 Vent Damper and Control Installation Instructions FAMILIARIZE YOURSELF WITH THE INSTALLATION INSTRUCTIONS BEFORE STARTING ATTENTION INSTALLER: This product must be installed by a qualified

More information

Fire Engineering in High Rise 15 November 2013

Fire Engineering in High Rise 15 November 2013 Fire Engineering in High Rise 15 November 2013 Neal Butterworth Arup UK www.arup.com Neal.Butterworth@arup.com Contents How do we protect against fire? How do we know this works? Why evacuate? What assumptions

More information

CALIFORNIA MECHANICAL CODE OVERVIEW OF 2016 UPDATES CHANGES AND RAMIFICATIONS

CALIFORNIA MECHANICAL CODE OVERVIEW OF 2016 UPDATES CHANGES AND RAMIFICATIONS CALIFORNIA MECHANICAL CODE OVERVIEW OF 2016 UPDATES CHANGES AND RAMIFICATIONS Presented to: Presented by: Sargon Ishaya, PE www.pragmaticprofessionalengineers.com Introduction Today s Agenda Overview Review

More information

Executive Summary

Executive Summary Prepared by: Proctor Engineering Group, Ltd. San Rafael, CA 94901 (415) 451-2480 Investigation of Coil Failures - A Whole Systems Approach Prepared for: Geothermal Heat Pump Consortium Final Report July

More information

Off Design Operation of Hybrid Noncondensable Gas Removal Systems for Flash Steam Cycle Geothermal Power Plants

Off Design Operation of Hybrid Noncondensable Gas Removal Systems for Flash Steam Cycle Geothermal Power Plants GRC Transactions, Vol. 40, 2016 Off Design Operation of Hybrid Noncondensable Gas Removal Systems for Flash Steam Cycle Geothermal Power Plants Jason Project Engineer, Vooner FloGard Corporation, Charlotte

More information

Life Safety Damper Installation ASHRAE St Louis Chapter Feb. 9,2015. Peter McDonnell, PE, LEED AP BD+C McClure Engineering

Life Safety Damper Installation ASHRAE St Louis Chapter Feb. 9,2015. Peter McDonnell, PE, LEED AP BD+C McClure Engineering Life Safety Damper Installation ASHRAE St Louis Chapter Feb. 9,2015 Peter McDonnell, PE, LEED AP BD+C McClure Engineering UL DAMPER TEST STANDARDS UL 555 - FIRE DAMPERS UL555S SMOKE DAMPERS UL555C CEILING

More information

CONTENTS. B. System Design and Performance Requirements

CONTENTS. B. System Design and Performance Requirements 15625 Water Chillers This document provides design standards only, and is not intended for use, in whole or in part, as a specification. Do not copy this information verbatim in specifications or in notes

More information

Study of Hot-air Recirculation around Off-road Tier-4 Diesel Engine Unit Using CFD Abbreviations Keywords Abstract Introduction and Background

Study of Hot-air Recirculation around Off-road Tier-4 Diesel Engine Unit Using CFD Abbreviations Keywords Abstract Introduction and Background Study of Hot-air Recirculation around Off-road Tier-4 Diesel Engine Unit Using CFD Siddharth Jain, Yogesh Deshpande, Atul Bokane, Arun Kumar Santharam, and Deepak Babar, Halliburton Abbreviations: Computational

More information

Start today and start saving!

Start today and start saving! Northeast Oklahoma REC s Do It Yourself Home Energy Audit Pllattiinum Levell Start today and start saving! First project (circle and initial when completed) Inadequate Ducts Objective: Check your ductwork

More information

Study and Design Considerations of HRSG Evaporators in Fast Start Combined Cycle Plants. Govind Rengarajan, P.E.CEM, Dan Taylor

Study and Design Considerations of HRSG Evaporators in Fast Start Combined Cycle Plants. Govind Rengarajan, P.E.CEM, Dan Taylor Study and Design Considerations of HRSG Evaporators in Fast Start Combined Cycle Plants Govind Rengarajan, P.E.CEM, Dan Taylor CMI Energy, Erie PA 1651 Bernd Pankow P.E, Pankow Engineering Abstract Combined

More information

ISLAND MOUNT RANGE HOOD. This manual is made with 100 % recycled paper. Electronic version of this manual is available at:

ISLAND MOUNT RANGE HOOD. This manual is made with 100 % recycled paper. Electronic version of this manual is available at: ISLAND MOUNT RANGE HOOD This manual is made with 100 % recycled paper. Electronic version of this manual is available at: www.cosmoappliances.com Thank You Thank you for your purchase. We know that you

More information

WESTIN HOTEL. Smoke Control System. Testing Procedures Manual. October 10, Copyright Impact Engineering, Inc All Rights Reserved

WESTIN HOTEL. Smoke Control System. Testing Procedures Manual. October 10, Copyright Impact Engineering, Inc All Rights Reserved IMPACT ENGINEERING, INC. WESTIN HOTEL Smoke Control System Testing Procedures Manual October 10, 2016 Copyright Impact Engineering, Inc. 2016 All Rights Reserved This manual is protected by the U.S. Copyright

More information

UNIVERSITY SERVICES ANNEX James Madison University Harrisonburg, Virginia State Project Code: Architect s Project Number:

UNIVERSITY SERVICES ANNEX James Madison University Harrisonburg, Virginia State Project Code: Architect s Project Number: SECTION 233423 - HVAC POWER VENTILATORS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Provisions of the Contract and of the Contract Documents apply to this Section. 1.2 PERFORMANCE REQUIREMENTS A. Operating

More information

Aqua Balance. AquaBalance TM CONTROL MODULE QUICK START GUIDE LEGEND

Aqua Balance. AquaBalance TM CONTROL MODULE QUICK START GUIDE LEGEND Aqua Balance AquaBalance TM CONTROL MODULE QUICK START GUIDE 10 1 Domestic Hot Water temperature setpoint decreasing button 2 Domestic Hot Water temperature setpoint increasing button 3 Central Heating

More information