Hazardous goods management Latest trends in petroleum industry. C. Sasi Assistant Vice President Total LPG India Limited
|
|
- Jerome Mitchell
- 5 years ago
- Views:
Transcription
1 Hazardous goods management Latest trends in petroleum industry C. Sasi Assistant Vice President Total LPG India Limited
2 Buncefield UK (HOSL) - December 11, 2005
3 Training Behaviour SMS LOPA Risk Analysis Facility Design
4 CURRENT TRENDS IN SAFETY IN PETROCHEMICAL INDUSTRY Risk Analysis Understanding of Methodology LOPA- Layer of Protection Analysis SMS Safety Management System Fire Protection for Oil Tanks Rim Seal Protection Building Inside the Plant New Trends ( Distances and Blast Proof Buildings ) Safety Instrumentation - LPG Plants I-EFSV Internal Excess Flow Check Valve GPS /GPRS For product Tankers
5 Risk Analysis Understanding of Methodology
6 Conventional Understanding Modern Concept
7 Safety barriers are aimed to bring the residual risk associated with potential accident scenarios to acceptable or to ALARP areas of the Total Risk Matrix Likely Unlikely Very unlikely Tolerable if ALARP High priority Extremely unlikely Acceptable risk Remote Moderate Serious Major Catastrophic Disastrous
8 LOPA Layer of Protection Analysis
9
10 What is Layer of Protection Analysis (LOPA) Identify hazardous events Determine initiating event frequencies Establishing tolerable levels of risk Analysing each independent safety layer to see if the overall level of risk can be reached If tolerable level of risk cannot be achieved : Additional safety layer must be added OR Existing layers must be strengthened
11 ACHIEVING ACCEPTABLE RISK Level of Protection Analysis HAZARD IDENTIFICATION 1. Check lists 2. Dow Relative Ranking 3. HAZOP - Hazard and Operability LAYER OF PROTECTION ANALYSIS 1. Express risk target quantitatively 2. Determine risk for system 3. Reduce risk to meet target HAZARD ASSESSMENT - Fault Tree - Event Tree - Consequence analysis - Human Error Analysis More accurate Semi-quantitative analysis to give order-of-magnitude estimate ACTIONS TO ELIMINATE OR MITIGATE - Apply all engineering sciences
12 Safety & Layers of Protection Safety Instrumented Function
13 SMS Safety Management System Important Tool for Optimizing the Operational Safety Selection of various Elements is important criteria After Taking care of Design Human Intervention needs to be taken care of
14 Building the System-use of Loss Causation Model
15 Building the System-use of Loss Causation Model These are nothing but Safety Management System Element, So Loss Casuation Model throws what element your organization requires through analysis of Immediate and basic causes for Loss
16 ISSSRS What it is? I3SRS Éléments Leadership and programme administration Management training Inspections Task Analysis Investigation Emergency preparedness Organisationnel rules Employées training Engineering and change management Heath control Personal Communications Matériels and services management System évaluation + Physical Condition Tour
17 Management of Contractor / contract labourers Significant accidents due to contracted jobs High turnover rates Inadequate training Insufficient instruction Unfamiliar environment Poor communication
18 Stages in the Selection of Contractors Pre-selection / Pre-qualification Assess a Contractor s suitability for a specific type of work with HSE being a prime consideration. Establish a list of approved Contractors Update the Approved List periodically Contractor considered must meet HSE requirements specific to the project or work Tendering and Contract Awarding HSE aspects should weigh equally amongst the other key items (costs, workmanship, timeliness) in making the final choice Avoid awarding the contract to the lowest bidder without regard to its HSE performance Sub-contractors, when employed, should be approved following a similar evaluation as applied for Contractors 18
19 Contractor training-link for proper execution of work through PTW Responsibilities for training of Contractor personnel should be stipulated in the contract Level of training will depend on: Type of work Degree of direct Company supervision Location and duration of the work Induction training for new Contractor on the worksite should be given by competent Company personnel Training must be given in the language of the Contractor personnel Contractor supervisors must receive a more intensive induction training On-the-job Control Contractor is responsible for supervision of its personnel Contractor to consult prior to changing supervisory personnel Company management must visibly demonstrate interests in Contractor s activities, e.g. Verify that HSE-related clauses in the contract are complied with Regular safety review meetings with Contractor Right to stop Contractor s activities for HSE reasons Propose measures to improve Contractor s HSE program For large projects, it may be useful to appoint a dedicated HSE Coordinator Use of work permit system to manage the HSE risks involved Monitor Contractor performance through inspection and auditing Contractor should report accidents in a timely and accurate manner to Total management
20 Fire Protection System Rim Seal Protection for Oil Tanks Working principle System has been divided in the following sub-systems:- a) Linear Heat Detection System. b) The Foam / DCP based Extinguishing System. c) Fire Alarm Panel & Automation a) Linear Heat Detection System Works based on the principle of rate of rise in temperature Maximum temperature beyond the pre-set is sensed by means of a microprocessor based intelligent evaluation unit The sensor element, i.e. the Stainless Steel / Copper Tube, which is in non-pressurized state (ambient pressure only) senses the rate of rise in temperature (pressure) and triggers an audio visual alarm Simultaneously the extinguishing systems are activited.
21 b) The Foam Based extinguishing system 100% proven substitute of Halon system and is environmental friendly The foam module is of 250 liter charged with 200 liters of pre-mixed foam solution Each foam module can cater 40 Meter Circumference of rim seal area Foam Discharge Manifold with Spray Nozzles are evenly spaced along the Rim Seal and are designed to discharge required Foam solution to control the fire completely. On detection of smallest fire the detection triggers an alarm & immediately actuates the extinguishing system.
22
23 Safety Instrumentation for LPG bottling Plants
24 Buildings inside the Plants Distances / Blast Proof Protection Severity of Pressure wave PSI 10% window broken PSI -90% of window broken PSI 50% of non reinforced building destroyed PSI 1% Probability of Eardrum Rupture PSI -1% probability of fatality 0.12PSI 90% probability of fatality General Strength of Blast pressure Wave in explosion is -3 PSI
25 Risk Analysis is first step to properly place buildings inside the plant Building such as Fire water Pump House and Control Room shall be reinforced with sufficient safety factor to sustain blast pressure wave OISD Distance norm shall be followed to place various buildings inside the plants Purta Cabin erected during project phase Need to be careful in Placing these buildings as many accidents happen during construction phase
26 LPG Tanker Internal Excess Flow Check Valve (I-EFSV) I-EFSV IS ONE OF THE RECOMMENDATIONS
27 RESULTS OF PILOT STUDY BY OISD Trials on LPG Tanker by OISD successful Model Used Fischer Make C400 Series ( 2 Nos 2 on Liquid Line and 1.25 on Vapour Line ) Loading time reduced by 10 minutes Unloading time reduced by 30 minutes ( 20 minutes + 10 minutes for vapor) Average time for unloading - one hour & vapour recovery 45 minutes Differential pressure maintained for tank lorry unloading around 2 kg/sq.cm to 3kg/sq.cm Features & Benefits Perform functions of three different units: 1. Primary Shutoff, 2. Excess Flow and 3. Back Check.. Effective leak resistance with TFE spring loaded packing.. Complies with NFPA 58 requirements.. Three closing systems: 1. Manual, 2. Cable or 3. Air. Built-in excess flow valve offers closure when flow exceeds the valve's rated capacity or piping is sheared off at the valve.. Fusible links or plugs melt at 212 F F (100 C C) and allow valve closure in the event of a fire at the valve.
28 Principle of Operation The operational schematic below depicts threaded valves, however flanged styles operate in the same manner. View #1 View #2 The valve is held closed permitting a tight seal by both tank pressure and the valve's closing spring. Move the operating lever in its70 angle travel that allows the cam to place the rapid equalization portion of the valve stem in the pilot opening. This permits a larger amount of product to bleed downstream than if the operating lever were moved into the full open position. View #3 View #4 After a few seconds, when the tank and the downstream pressure equalize, the excess flow spring pushes open the main poppet. The operating lever is moved to the full open position to ready the system for transfer operation. The pump or compressor should not be engaged until the valve is fully opened. During the transfer operation, a flow, or sufficient flow surge, greater than the valve's excess flow spring rating will force the main poppet closed. A small amount of product will continue to bleed through the downstream side, but much less than in View #2. Should this occur, the operating lever should be moved to the full closed position in View #1 and the steps repeated.
29 GPS/GPRS For Tanker Trucks ( Product Fleet ) Monitors Driver on route behaviour Speed can be controlled by checking speed report generated Real time positioning can be known Reports can through data on harsh breaking / stoppage report Fatigue levels can also be monitored by finding continuous driving trends Driver can be counseled /cautioned through SMS or Telephone call Meets PESO requirement for tachograph Can be integrated with alcohol control device to stop engine in case Driver is under influence of alcohol GPS /GPRS Facilitates Control on Drivers Behavior
30 GPS/GPRS For Tanker Trucks ( Product Fleet )
31 GPS/GPRS For Tanker Trucks ( Product Fleet )
32
33
34
35
36 Thank You
AVOID CATASTROPHIC SITUATIONS: EXPERT FIRE AND GAS CONSULTANCY OPTIMIZES SAFETY
AVOID CATASTROPHIC SITUATIONS: EXPERT FIRE AND GAS CONSULTANCY OPTIMIZES SAFETY World-class services help reduce incidents, protect the environment, and keep people and plants safe White Paper PAGE 1 Introduction
More informationAVOID CATASTROPHIC SITUATIONS: EXPERT FIRE AND GAS CONSULTANCY OPTIMIZES SAFETY
AVOID CATASTROPHIC SITUATIONS: EXPERT FIRE AND GAS CONSULTANCY OPTIMIZES SAFETY World-class services help reduce incidents, protect the environment, and keep people and plants safe White Paper PAGE 1 Introduction
More informationAssessment of the Safety Integrity of Electrical Protection Systems in the Petrochemical Industry
Assessment of the Safety Integrity of Electrical Protection Systems in the Petrochemical Industry 1. Introduction Author: Colin Easton ProSalus Limited ~ Independent Safety Consultants Within the United
More informationProcess Safety - Market Requirements. V.P.Raman Mott MacDonald Pvt. Ltd.
Process Safety - Market Requirements V.P.Raman Mott MacDonald Pvt. Ltd. Objective of Process Safety Protect personnel Protect the environment Protect the plant equipment / production. Multiple Layers
More informationFUNCTIONAL SAFETY IN FIRE PROTECTION SYSTEM E-BOOK
FUNCTIONAL SAFETY IN FIRE PROTECTION SYSTEM E-BOOK USEFUL TERMINOLOGY BASIC PROCESS CONTROL SYSTEM (BPCS) System which responds to input signals from the process, its associated equipment, other programmable
More information2015 Functional Safety Training & Workshops
HAZAN RISK SIS SIF - IEC 61508/61511 - SIL PFD SFF CCF 2015 Functional Safety Training & Workshops Select the right course for your organisation from our extensive choice of Functional Safety related training
More informationThe SIL Concept in the process industry International standards IEC 61508/ 61511
The SIL Concept in the process industry International standards IEC 6508/ 65 Chris M. Pietersen MSc Safety Solutions Consultants BV (SSC) Director pietersen@safety-sc.com th Urea Symposium 9- May 008,
More informationSINGLE INTERLOCK, SUPERVISED PREACTION SYSTEM WITH WET PILOT ACTUATION
SINGLE INTERLOCK, SUPERVISED PREACTION SYSTEM WITH WET PILOT ACTUATION HD FIRE PROTECT TECHNICAL DATA SIZE DELUGE VALVE CHECK VALVE SPRINKLER ALARM RELEASE PANEL 50, 80, 100, 150 & 200 NB Model H3, UL
More informationANALYSIS OF HUMAN FACTORS FOR PROCESS SAFETY: APPLICATION OF LOPA-HF TO A FIRED FURNACE. Paul Baybutt Primatech Inc. and
ANALYSIS OF HUMAN FACTORS FOR PROCESS SAFETY: APPLICATION OF LOPA-HF TO A FIRED FURNACE by Paul Baybutt Primatech Inc. and Joel Haight The Pennsylvania State University Abstract Layers of Protection Analysis
More informationSafety Integrity Verification and Validation of a High Integrity Pressure Protection System to IEC 61511
TÜV Rheinland International Symposium in China Functional Safety in Industrial Applications October 18 19, 2011 in Shanghai China Safety Integrity Verification and Validation of a High Integrity Pressure
More informationinnova-ve entrepreneurial global 1
1 www.utm.my innova-ve entrepreneurial global 1 Using redundant sensors and final redundant control elements Using multiple sensors with voting systems and redundant final control elements Testing the
More informationRetrospective Hazard Review
Managing Fire Risks, Abu Dhabi Men s College, 12 th November 2014 Retrospective Hazard Review Identifying fire hazards/risks and typical weaknesses Texas City US, 2005 Baker Report Jan 2007 The passing
More informationNew requirements for IEC best practice compliance
New requirements for IEC 61511 best practice compliance Proof testing and a SIL study may no longer be enough by Sven Grone Schneider Electric Safety Services Practice Leader Executive summary Since its
More informationIs your current safety system compliant to today's safety standard?
Is your current safety system compliant to today's safety standard? Abstract It is estimated that about 66% of the Programmable Electronic Systems (PES) running in the process industry were installed before
More informationDesign & Use of Ground Based Pumps Guidance Document
Design & Use of Ground Based Pumps The information and recommendations in this guidance are given in good faith and belief in their accuracy at the time of publication, but do not imply any legal liability
More informationIEC61511 Standard Overview
IEC61511 Standard Overview Andre Kneisel Instrumentation Engineer Chevron C.T. Refinery SAFA Symposium 2011 August 5 th, 2011 Presentation Overview Provide some understanding of the key aspects of Functional
More informationSINGLE INTERLOCK, SUPERVISED PREACTION SYSTEM WITH ELECTRIC RELEASE
SINGLE INTERLOCK, SUPERVISED PREACTION SYSTEM WITH ELECTRIC RELEASE HD FIRE PROTECT TECHNICAL DATA SIZE DELUGE VALVE CHECK VALVE SPRINKLER ALARM RELEASE PANEL 50, 80, 100, 150 & 200 NB Model H3, UL Listed
More informationLOPA. DR. AA Process Control and Safety Group
LOPA DR. AA Process Control and Safety Group LOPA LOPA is a semi-quantitative risk analysis technique that is applied following a qualitative hazard identification tool such as HAZOP. Similar to HAZOP
More informationThe agri-motive safety performance integrity level Or how do you call it?
TÜV Rheinland InterTraffic GmbH Safety in Transportation 4 The agri-motive safety performance integrity level Or how do you call it? Dipl.-Ing. Sebastian Gräfling, TÜV Rheinland InterTraffic GmbH Contents
More informationFire and Gas Detection and Mitigation Systems
Fire and Gas Detection and Mitigation Systems Dr. Lawrence Beckman, PE, TÜV FSExp SafePlex Systems, Inc., Houston, Texas ABSTRACT Fire and Gas Detection systems are key components in the overall safety
More informationLEARNING FROM TEXAS CITY REFINERY ( BP )
LEARNING FROM TEXAS CITY REFINERY ( BP ) Raffinate Splitter Blow down Drum and Stack Blowdown Drum and ISOM Unit, After the Incident Aerial Photograph of Isomerization Unit Isomerization Unit Satellite
More informationRisk Assessment of large Hydrocarbon Storage tanks. G. Unnikrishnan, Kuwait Oil Company
Risk Assessment of large Hydrocarbon Storage tanks G. Unnikrishnan, Kuwait Oil Company What QRAs can tell Incident/failure frequencies Location Specific Individual Risk Identification Of incident scenarios
More informationADIPEC 2013 Technical Conference Manuscript
ADIPEC 2013 Technical Conference Manuscript Name: Heidi Fuglum Company: ABB AS Job title: Deployment Manager Address: Ole Deviksvei, Oslo, Norway Phone number: +47 91 36 98 70 Email: Heidi.Fuglum@no.abb.com
More informationElectrical Management
5 WHS PROCEDURE P23-01 Page 1 of 9 Issue: 2 1. Intent The Salvation Army Australia Eastern Territory (TSA-AUE) is committed to the provision of a safe, healthy and injury free environment within the mission
More informationProcess Safety Workshop. Avoiding Major Accident Hazards the Key to Profitable Operations
CC & technical support services www.silsupport.com Process Safety Workshop Avoiding Major Accident Hazards the Key to Profitable Operations A two (2) day workshop with many practical methods, case studies
More informationSafety Instrumented Systems
Safety Instrumented Systems What is a Safety Instrumented System? A Safety Instrumented System SIS is a new term used in standards like IEC 61511 or IEC 61508 for what used to be called Emergency Shutdown
More informationDOUBLE INTERLOCK, PREACTION SYSTEM WITH ELECTRIC/PNEUMATIC RELEASE
DOUBLE INTERLOCK, PREACTION SYSTEM WITH ELECTRIC/PNEUMATIC RELEASE HD FIRE PROTECT TECHNICAL DATA SIZE DELUGE VALVE CHECK VALVE SPRINKLER ALARM RELEASE PANEL 50, 80, 100, 150 & 200 NB Model H3, UL Listed
More informationFORT MYERS BEACH FIRE DEPARTMENT JOB DESCRIPTION
This Position Description is established by the Fort Myers Beach Fire Department ( Department ) to outline the basic requirements, duties, and general responsibilities of the Deputy Fire Marshal, Fire
More informationSIL DETERMINATION AND PROBLEMS WITH THE APPLICATION OF LOPA
SIL DETERMINATION AND PROBLEMS WITH THE APPLICATION OF LOPA Alan G King Hazard & Reliability Specialist, ABB Engineering Services, Billingham, Cleveland UK. TS23 4YS For a number of years, industry has
More informationLIST OF STANDARDS S. NO. STANDARD NO. STANDARD NAME. Recommended Practices on Oil Storage and Handling OISD-STD-109
LIST OF STANDARDS S. NO. STANDARD NO. STANDARD NAME 1. OISD-STD-105 Work Permit System 2. OISD-STD-106 Pressure Relief & Disposal System 3. OISD-RP-108 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17.
More informationApplying Layer of Protection Analysis (LOPA) to Accelerator Safety Systems Design. Feng Tao
Applying Layer of Protection Analysis (LOPA) to Accelerator Safety Systems Design Feng Tao Outline LOPA Methodology LCLS-II Oxygen Deficiency Monitoring (ODM) LCLS Personnel Protection System (PPS) LCLS
More informationStrathayr, Rhu-Na-Haven Road, Aboyne, AB34 5JB, Aberdeenshire, U.K. Tel: +44 (0)
Strathayr, Rhu-Na-Haven Road, Aboyne, AB34 5JB, Aberdeenshire, U.K. Tel: +44 (0)1339 886618 www.silsupport.com 2012 TRAINING TÜV FS Engineer Certification Training (4 days) This 4 day course is run in
More informationLIST OF OISD STANDARDS (April 2016)
LIST OF OISD STANDARDS (April 2016) 1. OISD-STD-105 Work Permit System 2. OISD-STD-106 Pressure Relief & Disposal System 3. OISD-RP-108 Recommended Practices on Oil Storage and Handling 4. OISD-STD-109
More informationBeyond Compliance Auditing: Drill til you find the pain points and release the pressure!
Beyond Compliance Auditing: Drill til you find the pain points and release the pressure! Laura Ankrom, P.E. aesolutions, Inc. 250 Commonwealth Drive, Ste. 200, Greenville, SC 29615 Laura.ankrom@aesolns.com
More informationElectrical Safety Compliance: NFPA 70E
Electrical Safety Compliance: NFPA 70E From Graybar and Schneider Electric Risks associated with shock and electrocution from inadvertent contact with energized parts have long been recognized as a threat
More informationFunctional Safety Application of IEC & IEC to asset protection
Functional Safety Application of IEC 61508 & IEC 61511 to asset protection Paulo Oliveira Engineering Manager Engineering Safety Consultants Ltd Engineering Safety Consultants Limited Page 1 Agenda Agenda
More informationBRIDGING THE SAFE AUTOMATION GAP PART 1
BRIDGING THE SAFE AUTOMATION GAP PART 1 Angela E. Summers, Ph.D., P.E, President, SIS-TECH Solutions, LP Bridging the Safe Automation Gap Part 1, Mary Kay O Conner Process Safety Center, Texas A&M University,
More informationASSESSMENT INTRODUCTION
RISK ASSESSMENT INTRODUCTION LONI LPG Plant was set up to meet the increasing market demands for the districts of Ghaziabad, GB Nagar, Shamli, Hapur, Meerut, Saharanpur, Bijnore, Muzaffarnagar, Baghpat,
More informationTOTALPAC2 Integrated Fire Protection System
TOTALPAC2 Integrated Fire Protection System Page 1 of 8 General 1. Applicable Standards The TOTALPAC2 Surefire complies with the following standards: - NFPA-13 Sprinkler Systems; - NFPA-15 Water Spray
More informationOptions for Developing a Compliant PLC-based BMS
Options for Developing a Compliant PLC-based BMS Jack Boone aesolutions Greenville, South Carolina, United States of America ABSTRACT Facilities are focusing on improving the reliability of their burner
More informationSafety Instrumented Systems Overview and Awareness. Workbook and Study Guide
Safety Instrumented Systems Overview and Awareness Workbook and Study Guide V 1.0 Preface Copyright Notice and Disclaimer Copyright 2017, Kenexis Consulting Corporation All Rights Reserved 3366 Riverside
More informationJournal of Faculty of Engineering & Technology
JFET 21(3) (2014) 62-69 Journal of Faculty of Engineering & Technology Journal homepage: www.pu.edu.pk/journals/index.php/jfet/index Fire and Their Mitigation Efforts in Gas Processing Facilities M.K.
More informationLinear Heat Detection Engineering Specifications
Linear Heat Detection Engineering Specifications July, 2007 SAFE Fire Detection Inc. 5915 Stockbridge Dr. Monroe, NC 28110 Phone: (704) 821-7920 Fax: (704) 821-4327 Website: www.safefiredetection.com E-mail:
More informationGASTEC QA. Approval Requirements 31-2
KE 31-2 March 2012 GASTEC QA Approval Requirements 31-2 for the GASTEC QA product certificate for Sealing materials for metallic threaded joints in contact with 2nd and 3rd family gases and hot water Part
More informationPRIMATECH WHITE PAPER CHANGES IN THE SECOND EDITION OF IEC 61511: A PROCESS SAFETY PERSPECTIVE
PRIMATECH WHITE PAPER CHANGES IN THE SECOND EDITION OF IEC 61511: A PROCESS SAFETY PERSPECTIVE Summary From the perspective of process safety, the most notable change is the addition of requirements for
More informationGASTEC QA. Approval Requirements 31-1
KE 31-1 March 2012 GASTEC QA Approval Requirements 31-1 for the GASTEC QA product certificate for Sealing materials for metallic threaded joints in contact with 2nd and 3rd family gases and hot water Part
More informationSECTION DIGITAL, ADDRESSABLE FIRE-ALARM SYSTEM
SECTION 283111 - DIGITAL, ADDRESSABLE FIRE-ALARM SYSTEM PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division
More informationInternational Safety Guide Chapter 30 for Inland Navigation Tank-barges and Terminals. Chapter 30 FIRE-FIGHTING
Chapter 30 FIRE-FIGHTING This Chapter discusses events which may follow cargo spillage and the procedures which can be adopted to protect life and property in such circumstances. It also describes the
More informationPART 1 GENERAL Quality Assurance A. Fire Alarm Contractor Qualifications:
PART 1 GENERAL 1.01 Quality Assurance A. Fire Alarm Contractor Qualifications: 1 The Fire Alarm contractor shall be an Edwards Systems Technology (EST) designated representative and authorized to sell,
More informationWhere Process Safety meets Machine Safety
Where Process Safety meets Machine Safety A document to aid understanding between the end-user and machine builder for functional safety issues. by The 61508 Association Overriding key principle...it must
More informationTECHNICAL DATA OBSOLETE
January 27, 2012 311a 1. DEsCrIpTIoN (Refer to Figures 1-3.) Viking supervised Single Interlocked Preaction Systems utilize a Viking Deluge Valve and a pneumatically pressurized automatic sprinkler system.
More informationFunctional Safety: the Next Edition of IEC 61511
HazAus2015/1507 Functional Safety: the Next Edition of IEC 61511 Mirek Generowicz Engineering Manager I&E Systems Pty Ltd Level 2, 445 Hay Street Perth WA 6000 Abstract The functional safety standard IEC
More informationApplying Buncefield Recommendations and IEC61508 and IEC Standards to Fuel Storage Sites
Applying Buncefield Recommendations and IEC61508 and IEC 61511 Standards to Fuel Storage Sites John Joosten Global Product Manager Radar and Safety John.Joosten@Honeywell.com Applying Buncefield Recommendations
More informationC. ASME Compliance: Fabricate and label water chiller heat exchangers to comply with ASME Boiler and Pressure Vessel Code: Section VIII, Division 1.
SECTION 236426 - ROTARY-SCREW WATER CHILLERS PART 1 - GENERAL 1.1 SUMMARY A. This Section includes packaged, water cooled or air cooled as scheduled, electric-motor-driven, rotary-screw water chillers
More informationIEC an aid to COMAH and Safety Case Regulations compliance
IEC 61511 an aid to COMAH and Safety Case Regulations compliance C R Timms, Director, C&C Technical Support Services Limited INTRODUCTION There are specific safety related regulations for the UK offshore
More informationVerification of hydrocarbon refining and petrochemical facilities
SERVICE SPECIFICATION DNVGL-SE-0469 Edition August 2017 Verification of hydrocarbon refining and petrochemical facilities The electronic pdf version of this document, available free of charge from http://www.dnvgl.com,
More information1.3 REFERENCES A. ANSI/NFPA 70 - National Electrical Code. B. ARI Commercial and Industrial Humidifiers.
PART 1 GENERAL 1.1 Section Includes Low Pressure Nozzle and Evaporative Media Humidifier/Cooler 1.2 RELATED SECTIONS A. Section 08310 - Access Doors and Panels. B. Section 15052 - Common Work Results for
More informationMNEC NFPA 72 WHITE PAPER
MNEC NFPA 72 WHITE PAPER In 2010, the National Fire Protection Assocation (NFPA), significantly changed their code # 72 (National Fire Alarm Code) and has forever improved the importance of communicating
More informationHIPPS High Integrity Pressure Protection System
HIPPS High Integrity Pressure Protection System L&T Valves L&T Valves Limited (Formerly Audco India Limited) is a wholly owned subsidiary of Larsen & Toubro. Backed by a fifty-year track-record of excellence
More informationScandinavian Shipyard / 2011 Vessel Fire whilst in Dry Dock. Major Incident Investigation
Scandinavian Shipyard / 2011 Vessel Fire whilst in Dry Dock Major Incident Investigation 1 Slide Agenda 1. Introduction 2. Sequence of Events 3. Investigation Analysis 4. Recommendations 5. Recommendations
More informationMeasurement of Safety Integrity of E/E/PES according to IEC61508
Measurement of Safety Integrity of E/E/PES according to IEC61508 Mr. Chen Zhenkang TUV Rheinland Singapore 18. May. 2018 Singapore World Metrology Day 2018 1 Agenda 1. TÜV Rheinland: a Certification Body
More informationManaging Fire Safety To Ensure Legislative Compliance
Managing Fire Safety To Ensure Legislative Compliance Facilities Management Ireland RDS 2013 Presented By Aidan O Connor HSE Estate Manager Fire Safety Presentation Objectives Background Inspecting Agencies
More informationDust Hazard Assessments
2017 NFPA Conference & Expo Dust Hazard Assessments The Importance of DHAs in Establishing Work Practices and Facilities Presented by: Jason Reason, CIH, CSP, CHMM Lewellyn Technology, LLC Learning Objectives
More informationLoss Prevention Standard
Loss Prevention Standard LPS 1500: Issue 2.1 provide compartmentation in buildings This standard defines the requirements for companies installing fire resisting compartment systems approved by LPCB to
More informationFire protection on chemical manufacturing sites
CFPA-E No 18:2008 Fire protection on chemical manufacturing sites FOREWORD The European fire protection associations have decided to produce common guidelines in order to achieve similar interpretation
More informationFire Protection for Printing Machines with High Pressure Water Mist
Fire Protection for Printing Machines with High Pressure Water Mist Dipl.-Ing. Rüdiger Kopp FOGTEC Fire Protection ruediger.kopp@fogtec.com 1 Case Study PRINOVIS Printing Company - PRINOVIS is Europe s
More informationSession Four Functional safety: the next edition of IEC Mirek Generowicz Engineering Manager, I&E Systems Pty Ltd
Abstract Session Four Functional safety: the next edition of IEC 61511 Mirek Generowicz Engineering Manager, I&E Systems Pty Ltd The functional safety standard IEC 61511 provides a framework for managing
More informationLoss Prevention Standard
Loss Prevention Standard LPS 1531: Issue 1.1 companies installing or applying passive fire protection This Loss Prevention Standard is the property of BRE Global Ltd. and is made publicly available for
More informationRIM SEAL SYSTEMS E-BOOK
RIM SEAL SYSTEMS E-BOOK RIM SEAL SYSTEMS Rim Seal floating roof tank fires represent one of the most dangerous threats for chemical and petrochemical storage farms. Industry data base shows that the oil
More informationNFPA 70E Edition Update
NFPA 70E- 2018 Edition Update Paul Colangelo- STSC, CHST, CET, CRIS National Director of Compliance Programs ClickSafety 1 ASSE Construction Practice Specialty Quarterly Meeting 11/17/2017 Agenda Overview
More informationSECTION Fire Pumps
SECTION 21 30 00 Fire Pumps PART 1 GENERAL 1.1 WORK INCLUDED A. Furnish, install and test a motor-driven fire pump, jockey pump, and controllers in the space provided and as shown in the contract drawings.
More informationYour Turnkey Solution for Mitigating the Hazards of Arc Flash Incidents in the Workplace
Your Turnkey Solution for Mitigating the Hazards of Arc Flash Incidents in the Workplace ith today s powerful, complex electrical distribution systems, shock isn t the only danger facing those who work
More informationSubject: Fire Protection Impairment Program Reference: NFPA (see bottom of page 5) Effective Date: August 2014 Distribution All YC Employees
Subject: Fire Protection Impairment Program Reference: NFPA (see bottom of page 5) Effective Date: August 2014 Distribution All YC Employees Purpose: To establish procedures to be followed when a fire
More informationLANDSCAPE ARCHITECTURAL ASSISTANT, 7931 LANDSCAPE ARCHITECTURAL ASSOCIATE, 7932 LANDSCAPE ARCHITECT, 7929
2-24-84 LANDSCAPE ARCHITECTURAL ASSISTANT, 7931 Summary of Duties : Performs professional landscape architectural work in the design and preparation of plans, sketches, and drawings for the development
More informationANNEX I. Technical specifications for: Supply of various Trace Explosive Detection Systems
EUROPEAN COMMISSION JOINT RESEARCH CENTRE Institute for Reference Materials and Measurements (Geel) ANNEX I Technical specifications for: Supply of various Trace Explosive Detection Systems TABLE OF CONTENTS
More informationThomasville fire rescue
Thomasville Fire Rescue Firefighter Professional Qualifications 2014 Thomasville fire rescue As part of our overall mission, the fire department continually strives to improve structural fire protection
More informationInteraction of Water Extinguishing Systems and Smoke and Heat Exhaust Ventilation Systems (SHEVS)
Fire Protection Leaflet Interaction of Water Extinguishing Systems and Smoke and Heat Exhaust Ventilation Systems (SHEVS) 0 General Regulations and recommendations missing from this leaflet do not entitle
More informationrisk management and assessment for business Lessons Learned from Real World Application of Bow-tie Method 2010 International Symposium
risk management and assessment for business Risktec Solutions Lessons Learned from Real World Application of Bow-tie Method 2010 International Symposium BEYOND REGULATORY COMPLIANCE, MAKING SAFETY SECOND
More informationICHEME SYMPOSIUM SERIES NO. 144 A METHODOLOGY FOR ASSESSING AND MINIMISING THE RISKS ASSOCIATED WITH FIREWATER RUN-OFF ON OLDER MANUFACTURING PLANTS
A METHODOLOGY FOR ASSESSING AND MINIMISING THE RISKS ASSOCIATED WITH FIREWATER RUN-OFF ON OLDER MANUFACTURING PLANTS Christopher J, Beale, Ciba Speciality Chemicals Pic, Water Treatments Division, PO Box
More informationUnion County Vocational - Technical Schools Scotch Plains, New Jersey
SECTION 230593 - TESTING, ADJUSTING, AND BALANCING FOR HVAC PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Balancing Air Systems: a. Constant-volume air systems. b. Variable-air-volume systems. 2.
More informationUNIVERSITY OF ROCHESTER ENVIRONMENTAL HEALTH & SAFETY
Revision No.: 3 Page 1 of 6 I. PURPOSE This policy establishes the steps required for performing the monthly fixed systems inspections and the semi-annual systems testing. Fixed systems include; wet chemical
More informationConducting a NFPA 652 Dust Hazard Analysis (DHA): Practical Tips & Approaches
Conducting a NFPA 652 Dust Hazard Analysis (DHA): Practical Tips & Approaches Pulp & Paper Safety Association Safety & Health Conference June 18, 2018 Mike Snyder PE CSP CFPS Executive Vice President,
More informationCONTENTS AUTOMATIC TRANSFER SWITCHES
CONTENTS AUTOMATIC TRANSFER SWITCHES PART 1 GENERAL 1.1 Related Documents 1.2 Summary 1.3 References 1.4 Quality Assurance 1.5 Submittals 1.6 Delivery, Storage and Handling 1.7 Instructions And Training
More informationFire Safety Plan (FSP) Review Checklist 1
Fire Inspection & Prevention Initiative Fire Safety Plan (FSP) Review Checklist 1 (Component of a BC Fire Code (BCFC) compliance inspection) Date: COMPANY INFORMATION Company Name: Building Name: Address:
More informationSTANDARDS FOR VAPOUR EMISSION CONTROL SYSTEMS ( MARPOL reg VI/15 )
STANDARDS FOR VAPOUR EMISSION CONTROL SYSTEMS ( 92-98 MARPOL reg VI/15 ) MSC/Circ.585 16 April 1992 1 The Maritime Safety Committee, at its sixtieth session, recognized the necessity of the international
More informationYour Global Automation Partner. Minimizing Arc Flash Exposure in Industrial Applications. White Paper - W1000
Your Global Automation Partner Minimizing Arc Flash Exposure in Industrial Applications White Paper - W1000 Industrial environments present multiple safety challenges, including fire hazards that require
More informationFuel and Energy Research Forum
Fuel and Energy Research Forum Operational Hazards Associated with Coal Fired Boilers: Design Requirements of Safety Control Systems FERF Annual Meeting 26 April 2017 1 Objective Highlight some safety
More informationGuide to Compliance with the Electrical Workplace Safety Standards in the United States
Guide to Compliance with the Electrical Workplace Safety Standards in the United States July 2011/1910DB1102 by Joseph H. Weigel, Product Manager Schneider Electric USA, Inc. Make the most of your energy
More informationPART 1 GENERAL Quality Assurance A. Fire Alarm Contractor Qualifications:
PART 1 GENERAL 1.01 Quality Assurance A. Fire Alarm Contractor Qualifications: 1 The Fire Alarm contractor shall be an Edwards Systems Technology (EST) designated representative and authorized to sell,
More informationFire Risks of Loviisa NPP During Shutdown States
Fire Risks of Loviisa NPP During Shutdown States Sami Sirén a*, Ilkka Paavola a, Kalle Jänkälä a a Fortum Power And Heat Oy, Espoo, Finland Abstract: Fire PRA for all 15 shutdown states of Loviisa NPP
More informationNECA S System Approach to Electrical Safety for NFPA 70E
NECA S System Approach to Electrical Safety for NFPA 70E NECA s Systems Approach to NFPA 70E Easy to understand NFPA 70E employer requirements, Provides Supervisors with key on the job information, De
More informationISHRAE. Guideline document to ISO Version 1 Feb Indian Society of Heating, Refrigerating and Air Conditioning Engineers
ISHRAE Guideline document to ISO 5149 Version 1 Feb 2017 Indian Society of Heating, Refrigerating and Air Conditioning Engineers Acknowledgement On behalf of ISHRAE I wish to thank and acknowledge the
More informationFire Safety Management Audit Specification August 2017
Fire Safety Management Audit Specification August 2017 Membership Training Qualifications Audit and Consultancy Policy and Opinion Awards Contents Page 1 Introduction to the Fire Safety Management Audit
More informationGUIDELINES FOR THE APPROVAL OF EQUIVALENT FIXED GAS FIRE-EXTINGUISHING SYSTEMS, AS REFERRED TO IN SOLAS 74, FOR MACHINERY SPACES AND CARGO PUMP-ROOMS
12 December 1996 Ref. T4/4.01 GUIDELINES FOR THE APPROVAL OF EQUIVALENT FIXED GAS FIRE-EXTINGUISHING SYSTEMS, AS REFERRED TO IN SOLAS 74, FOR MACHINERY SPACES AND CARGO PUMP-ROOMS 1 The Maritime Safety
More informationFully configurable SIL2 addressable Fire & Gas Detection solutions
Fully configurable SIL2 addressable Fire & Gas Detection solutions Tyco are able to provide multiple configurations where the solution and devices are certified to meet the Functional Safety requirements
More informationKidde Nitrogen Inert Gas Clean Agent Fire Suppression System
1. GENERAL 1.1 INTENT OF SPECIFICATIONS A. This specification details the requirements for an engineered inert gas fire suppression system Model Kidde Nitrogen. These requirements, combined with good engineering
More informationFEMA RECOMMENDATIONS FOR PROTECTION OF CURTAINED LIMITED FINISHING WORKSTATIONS USING UL 1254 LISTED PRE-ENGINEERED DRY CHEMICAL SYSTEMS
FEMA RECOMMENDATIONS FOR PROTECTION OF CURTAINED LIMITED FINISHING WORKSTATIONS USING UL 1254 LISTED PRE-ENGINEERED DRY CHEMICAL SYSTEMS FEMA RECOMMENDATIONS ARE BASED UPON LIVE FIRE TESTING OF PREP STATIONS
More informationArc Flash Analysis. Arc flash hazard analysis is required to determine the risk to personnel, warn them of the
GROUP Arc Flash Analysis Arc Flash Hazard Analysis : Arc flash hazard analysis is required to determine the risk to personnel, warn them of the hazards, and to instruct working personals as to what kind
More informationRAPID RESPONSE Series LFII Residential Sprinklers 4.2 K-factor Flush Horizontal Sidewall Wet Pipe Systems
Worldwide Contacts www.tyco-fire.com RAPID RESPONSE Series LFII Residential Sprinklers 4.2 K-factor Flush Horizontal Sidewall Wet Pipe Systems General Description LFII Residential Flush Horizontal Sidewall
More informationFacilities and Estates. Hot Works: Standard Operating Procedure. Document Control Summary
Facilities and Estates Hot Works: Standard Operating Procedure Document Control Summary Status: Version: Author/Title: Owner/Title: Approved by: Ratified: Related Trust Strategy and/or Strategic Aims Implementation