Former Truck Maintenance Garage Soil Remediation Report

Similar documents
MW-401B Area Soil Remediation Report

Poisoned Park? How Exide s Lead Contamination Risks Frisco s Grand Park

A D D E N D U M N O. 1 To The Contract Documents Date: Project: Facilities Development & Planning Portable Building Relocation

2016 Annual Inspection Report

Ingram Engineering Services, Inc. 16 Hagerty Blvd. Suite 400 West Chester PA Office Fax

B & W Engineering Laboratories, Inc. P.O. Box Memphis, Tennessee (901)

Test Pit Observation Report. Albertville Business Park 67th Street to 70th Street NE Albertville, Minnesota. Prepared for.

Corn Irrigation and Water Use

The University of Iowa Department of Civil & Environmental Engineering SOIL MECHANICS 53:030 Final Examination 2 Hours, 200 points

Geotechnical Exploration and Evaluation Report

M. Block & Associates Ltd.

Gryme s Dyke, Stanway Green

ATTACHMENT A BIORETENTION SOIL SPECIFICATION

AGRICULTURAL LAND CLASSIFICATION AND STATEMENT OF PHYSICAL CHARACTERISTICS

Advanced Foundation Engineering. Soil Exploration

AGRICULTURAL LAND CLASSIFICATION

Horner-McLaughlin Woods: Soil Types

December 13, 2005 Meeting Status of NPDES Post Fire BMPs

Vineyard Variability Due To Differences in Soil. Ann Tan UC Davis

Sydney Road Reclaimed Water Main, Plant City, Florida. Prepared for: Jones Edmunds & Associates, Inc.

Bratislava, May 2015, Slovakia.

Reference Card S-2, Side A: Delineating Horizon Boundaries

"Welcome to Rough House"

Lesson 1: Identifying Texture in Soil

DO YOU KNOW YOUR SOILS? (Rev. 10/11)

URBAN SOILS & SEATTLE EXAMPLES

27/01/2017. This event is being run by SAC Consulting. What is Soil?

Soil Structure, Density, and Porosity. Laboratory #4

PARCEL EVALUATION DATA SUMMARY PHASE 2A SAMPLING ZONE 16: THE HOUSING ZONE PARCEL 181: MULTIPLE UNIT HOUSING ALAMEDA POINT ALAMEDA, CALIFORNIA

PHYSICAL CHAtlACTERISTICS REPORT FOR THE PROPOSED SAND AND GRAVEL SITE AT MANOR FARM, UFFINGTON

Overview of Soil Properties

Overview of Soil Properties

Piles, Trenching, Inverters, Cables, Material Deliveries

Boston Water and Sewer Commission

THE TENNESSEE VEGETABLE GARDEN

AN ARCHAEOLOGICAL SURVEY FOR THE NAVIDAD RESOURCES, LLC FERGUSON STATE PRISON FARM UNIT PROJECT IN MADISON COUNTY, TEXAS

STATEMENT OF PHYSICAL CHARACTERISTICS AND AGRICULTURAL LAND CLASSIFICATION

Recommended Resources: The following resources may be useful in teaching this lesson:

HEALTH SCIENCES BUILDING REDEVELOPMENT PROJECT

Submitted to. Federal Aviation Administration Alaskan Region, Airports Division Anchorage, Alaska. Juneau International Airport Juneau, Alaska.

Terminology & Soil Science. Andy Spetch

2018 Annual Landfill Inspection Report

SECTION SOIL PREPARATION

Triangle Land Conservancy Conservation Area Monitoring Report Carolina North

2011 Wisconsin Envirothon Soils and Land Use Exam

Soil Colors, Texture & Structure

Annual Update Regarding Utilities on Former Morris Canal and New Jersey City University West Side Campus Jersey City, New Jersey

Triangle Land Conservancy Conservation Area Monitoring Report Carolina North

MONITORING REPORT: No. 276

Geotechnical Exploration and Evaluation Report Revision No. 01

APPENDIX E: UC Berkeley Laboratory Testing and ILIT In-Situ Field Vane Shear Testing

LYTTELTON GRAVING DOCK PUMPHOUSE (M36/327), CYRUS WILLIAMS QUAY, LYTTELTON: REPORT ON ARCHAEOLOGICAL MONITORING

If you are not able to turn in your notebook see me or Dan ASAP

Radon Test Results, Prentis II Apartments, West 10 Mile Road, Oak Park, Michigan (ASTI Project No )

Sydenham Pearl Brownfield Remediation Project

4 January 11, 2012 Public Hearing APPLICANT:

Photographs and Descriptions of Representative Pedons by Site

5 RESULTS FOR THE REJECT EMPLACEMENT AREA

SOILS IN URBAN / SUBURBAN LANDSCAPES. Lisa Krall Soil Scientist CT USDA NRCS Tolland, CT

Table of Contents. Attachments Attachment A Photos Attachment B Site Map. Pages 3 of 9

6.1. INTRODUCTION 6.2. EXISTING CONDITIONS

List of Equipment, Tools, Supplies, and Facilities:

SECTION PLANTING SOIL for SOIL CELLS. This specification defines material and performance requirements for soils which are to be used

14 Visual Amenity 14-1

Project: Mooney Lake Preserve Received: Location: 300 Sixth Ave. N., Orono Complete: Noticed:

INFILTRATION OF SOILS IN THE PEORIA AREA

Dallas Municipal Archives Archives Collections Finding Guides and Inventories

Knoxville Area Transit (KAT) Transit Development Plan Corridor Analysis

Pontiac Trail 1" = 80' B-1 B-2 B-3 B-4 B-5. to WB S23 C SB U M 14. a c Trl

DRAFT ONONDAGA LAKE CAPPING AND DREDGE AREA AND DEPTH INITIAL DESIGN SUBMITTAL H.3 STATIC SLOPE STABILITY ANALYSES

Acronyms. TRI TRI Environmental, Inc. Table of Contents. iii

ESB Experience of Remediating Asbestos Contaminated Land

Team number Page 1 of Canon Envirothon Soils Station Test. Soils and Climate Change

Archaeological evaluation at Willowdene, Chelmsford Road, Felsted, Essex

ELECTRICAL IMPEDANCE TOMOGRAPHY

MERIDAN PLAINS SAND RESOURCE AREA

1 SITE AND PROJECT DESCRIPTION

City of Stoughton Erosion Control Permit Application (effective 2/6/2018)

Morro Shoulderband Snail Protocol Survey Report for the Parcel at 3093 Beachcomber Drive, Morro Bay, San Luis Obispo County, California

MONITORING REPORT: No. 283

Northern Branch Corridor SDEIS March 2017

Irrigating Olives. Janet Caprile UCCE Farm Advisor Alameda & Contra Costa Counties

JULY 23, 2018 PROJECT REPORT OF GEOTECHNICAL EXPLORATIONS CASS GILBERT MEMORIAL PARK SOLAR GARDEN CAPITOL COMPLEX ST.

Storm Water Basics for Construction Sites Presented by Representatives from the City of Grass Valley and Nevada County

City of Cornwall Municipal Class Environmental Assessment. Proposed Improvement and Extension of Lemay Street

1 Describe the concept of soil texture and its importance. 2 Determine the texture of a soil sample.

6 March 9, 2011 Public Hearing APPLICANT: OLD DOMINION SOCCER CLUB

Learning Objectives Part 1. Chapter 4 Soil Physical Properties. Soil Physical Properties. Color. Physical properties part 1

SOIL SEPARATES. Soil Evaluator Day 2, Presentation 3-3/27/2018. Soil Texture, Page 1 TITLE 5 SOIL EVALUATOR CERTIFICATION TRAINING SOIL TEXTURE

2018 Annual Landfill Inspection Report

SECTION PLANTING SOIL FOR SOIL CELLS (SILVA CELLS)

PHYSICAL CHARACTERISTICS REPORT INCORPORATING AGRICULTURAL LAND CLASSIFICATION LAND AT BOLE INGS, WESTBURTON, NOTTINGHAMSHIRE (SK805875)

Procedural guide to the self-monitoring of trade waste pre treatment devices

2017 Iowa FFA Soil Judging CDE Exam

TAXONOMIC CLASS: Loamy-skeletal, mixed, mesic Vitrandic Durochrepts

HISTORIC RESOURCES INVENTORY - BUILDING AND STRUCTURES

Soil is a Natural Resource. February 12, 2015

NOT PROTECTIVELY MARKED SUB-APPENDIX A2: SOIL ANALYTICAL SUITES

Archaeological Evaluation and Assessment of Land at Kent Cottage, 19 Chapel Street, Hythe, Kent

Soil Physical Properties

Transcription:

Former Truck Maintenance Garage Soil Remediation Report Maine Yankee Decommissioning Project Corrective Measures Study February 2005 Prepared for: Maine Yankee 321 Old Ferry Road, Bailey Point Wiscasset, ME 04578 Prepared by: Dickenson & Associates 45 Falmouth Road Falmouth, ME 04105 And CH2M Hill 25 New Chardon Street, Suite 500 Boston, MA 02114 In association with: Jacques Whitford Co., Inc. 75 Pearl Street, Suite 410 Portland, ME 04101 And Stratex, LLC 100 Middle Street Portland, ME 04101

Introduction The former Truck maintenance Garage (FTMG) was located east of the former Plant Access Road adjacent to the ISFSI (Figure 1). The garage was used to conduct maintenance activities on concrete trucks and other vehicles during construction of the Maine Yankee facility. The location of the garage was confirmed by both aerial and project photographs taken during plant construction from 1968 to 1972. The garage was removed prior to operation of the Maine Yankee facility. Soil sampling conducted as part of the RCRA Facility Investigation (RFI) identified three areas of petroleum-contaminated soil, one directly adjacent to the former location of the garage, and two areas approximately 80 feet east of the garage location (Figure 1) (Reference 1). To support the soil remediation for FTMG, Maine Yankee developed a remediation plan (Reference 2), which was approved by MDEP in June 2004. The plan described the soil removal approach, field screening, and confirmatory sampling activities. Soil Removal Activities Soil removal activities at the FTMG were initiated on July 14, 2004 and completed on August 9, 2004. Soil removal was conducted using a track-mounted John Deere 892 excavator with a 1.5- yard bucket. Soil was excavated from the three soil contamination areas using the excavator and placed in a large dump truck that was used to stockpile the excavated soil. A total of approximately 730 cubic yards of soil was removed from the three excavations. Initial soil removal activities were conducted between July 14, 2004 and July 19, 2004 and approximately 660 cubic yards of petroleum-contaminated soil was removed from the three soil contamination areas. Based on preliminary confirmatory soil results an additional 50 cubic yards of soil was removed from Area 2 and 20 cubic yards was removed from both Area 1 and Area 3. The additional soil removal activities increased the total amount of excavated soil to 730 cubic yards in the three soil removal areas. The soil profile in the excavations consisted of two to three feet of fill material over glaciomarine soils. The upper portion of the glaciomarine soils consisted of fine-grained, silty glaciomarine material. The fine-grained glaciomarine soils included thin sandy lenses. At depths in excess of eight feet silty fine to medium sand was present beneath the silty glaciomarine material. The fine-grained glaciomarine soils were olive to dark gray, clayey silt with a blocky structure. Vertical fracture planes were evident and manganese staining was observed on these vertical surfaces. The coarse-grained glaciomarine soils at the base of the excavation consisted of yellow brown to dark gray brown silty fine to medium sand. Confirmatory Sample Results Following excavation of contaminated soil, confirmatory soil samples were taken from the circumference and base of each excavation. A total of 37 sampling stations were established at FTMG Soil Removal 1 February 2005

approximate ten foot intervals around each excavation (MY05TP340 through MY05TP376) (Figure 2). At each sampling station soil samples were taken from the sidewall of the excavation from the ground surface to the base of the excavation at two-foot intervals. Additionally, two samples were taken from the base of each excavation (MY05TP380 through MY05TP385) (Figure 2). Each of the total 188 soil samples was screened with a PID using MDEP-approved headspace techniques. The PID soil screening results are summarized in Table 1, and PID values ranged from 1.0 ppm to 138.2 ppm. Two samples from each of the sidewalls and one sample from each end of the excavation with the highest PID values were collected for laboratory analysis. Two samples from the base of each excavation were also included for laboratory analysis. The 24 soil samples were analyzed for diesel range organics (DRO) using Maine DEP Method 4.1.25. Three duplicate samples and matrix spike and matrix spike duplicate samples were also taken to support data validation. The laboratory analysis and data validation activities were conducted consistent with the Maine Yankee Quality Assurance Project Plan (Reference 3). The validated results of the laboratory analysis are presented in Table 2. Most of the confirmatory DRO results were below 100 mg/kg and the concentrations ranged from non-detect to 5,000 mg/kg. Each of the three soil remediation areas had confirmatory sample locations with elevated DRO values. The southeast corner of Area 1(MY05TP366(6-8)) and the southern bottom sample (MY05TP384(8)) in Area 1 had 700 mg/kg and 1,500 mg/kg DRO, respectively. The sidewalls in the central portion of Area 2 (MY05TP349(6-8), MY05TP350(6-8), and MY05TP357(8-10)) had DRO values ranging from 520J mg/kg to 3,300 mg/kg, and the southern bottom sample in Area 2 (MY05TP382(9) had 5,000 mg/kg. The western sidewall and northern end of Area 3 (MY05TP345(4-6), MY05TP341(4-6), and MY05TP340 (2-4)) also had elevated DRO values ranging from 210 mg/kg to 790 mg/kg. To address these focused areas of remaining petroleum contamination, approximately 70 additional cubic yards of soil was removed from the three excavations. Approximately 50 cubic yards of additional soil was removed from the sidewalls and southern bottom of Area 2, and approximately 20 cubic yards of soil was removed from the focused areas of elevated DRO in Areas 1 and 3. A total of eight confirmatory soil samples were taken following the additional soil excavation. The samples were analyzed for DRO and the results are included in Table 2. One duplicate sample and a matrix spike and matrix spike duplicate sample were also taken to support data validation. The laboratory analysis and data validation activities were conducted consistent with the Maine Yankee Quality Assurance Project Plan (Reference 3). The DRO concentrations of the follow-up confirmatory samples ranged from non detect to 120 mg/kg. Using a combination of the original confirmatory samples from the locations where no additional soil removal was conducted and the follow-up confirmatory samples from the areas where additional soil was removed, an average DRO value for each excavation was calculated. The average DRO values ranged from 12.9 mg/kg in Area 3 to 57.2 mg/kg in Area 2 (Table 2). FTMG Soil Removal 2 February 2005

Figures 1. Former Truck Maintenance Garage Areas of Petroleum Contamination 2. Former Truck Maintenance Garage Remediation Area Tables 1. PID Screening Results FTMG Soil Remediation 2. DRO Laboratory Results FTMG Soil Remediation FTMG Soil Removal 4 February 2005

Figures FTMG Soil Removal October 2004

Tables FTMG Soil Removal October 2004

FTMG Soil Removal October 2004