River Mile 10.9 Removal Action Overview

Similar documents
Phase 1 Habitat Replacement & Reconstruction

Jack Creek Park Capital Improvement Project

Peoria Riverfront Development (Ecosystem Restoration) Upper Mid-sized Island Critical Restoration Project (September 2011)

Kootenai River Habitat Restoration Program June 18, 2018 Kootenai Valley Resource Initiative Update

2016 Annual Inspection Report

Adaptive Management Strategies for Resilient Coastlines: A Case Study on the Ft. Pierce, FL Breakwater Project

BEACH AND INLET PROJECTS UPDATE

Ashbridges Bay Erosion and Sediment Control Project

Citywide Integrated Stormwater Management Plan (ISMP) DRAFT ACTION PLAN REVIEW Public Consultation November 16 th, 2016

Construction Progress Report

Construction of upgraded stormwater outfall at the Ozone Road Jetty

Specification and Construction Plans For: South Bethany Landscaping Improvement Plan Contract Number T

Analyzing the Bioretention Construction Sequence

MAINTENAING YOUR RAIN GARDEN

Urban Conservation Practice Physical Effects ESTABLISHMENT, GROWTH, AND HARVEST NUTRIENT MANAGEMENT

EROSION CONTROL Professional Development Training. Sean Crimmins, President Brian Barker, Southeastern Consultant

Wallkill River. Floodplain Bench Project Phase 1. OCSWCD Kevin Sumner. October 2016 Orange County. Wendell Buckman

Wellsite Clay Pad Removal and Peat Inversion

GREEN INFRASTRUCTURE DESIGNS RAIN GARDEN

Scarborough Waterfront Project

Improvement of the Atlantic Coast of New York City,

EROSION & SEDIMENT CONTROL

ALTERNATIVE SHORELINE MANAGEMENT IN COASTAL MISSISSIPPI

A. Install all temporary erosion control measures (in accordance with MNDOT General Conditions 2573) prior to site disturbance.

Wisconsin NRCS Direct Volume Method Bank Recession Rate Categorizations

NOTICE OF INTENT. Submitted To: Bremo Power Station 1038 Bremo Bluff Road Bremo Bluff, VA 23022

Case Study Bioretention Installation and Maintenance

Old Mill Community Association Bioretention Facility

SUPPORTING DOCUMENT STORMWATER POLLUTION PREVENTION PLAN (SWPPP) NARRATIVE

Coastal Engineer IV, Mott MacDonald, Morado Circle, Suite 300, Austin, TX 78759, USA, T: ,

Sconset Geotextile Tube Update Sconset Bluff, Nantucket. Maria Hartnett, Associate

Arroyo Grande Creek Flood Control Channel Vegetation Management: A Photo Series

Pine Flat Lake Master Plan Update FACT SHEET September 2014

Site Formation Excavation - 6' depth square yard $8.00 $0.00 Grading square yard $1.50 $0.00 Hauling off-site - 6' depth square yard $10.00 $0.

B511 - RIP-RAP, ROCK PROTECTION AND GRANULAR SHEETING - OPSS 511

NORTH KINGSTOWN PILOT PROJECT May 9, 2016 North Kingstown Town Council

Karen A. Duhring Marine Advisory Scientist Center for Coastal Resources Management Virginia Institute of Marine Science College of William & Mary

SECTION 02230BP AGGREGATE BASE

Stormwater Master Plan Update. City Council Briefing January 8, 2019

SECTION 900 TURF ESTABLISHMENT

MASTER PLAN for the EARL NEWHOUSE WATERFRONT

Sierra Club Comments on ACOE Public Notice NAE Re: Proposed Town Neck Beach Project at Sandwich, Massachusetts

4.5 City of Indianapolis Stormwater Green Infrastructure Guidance: Bioretention (rain gardens) Bioretention Fact Sheet Bioretention Technical Design


WEED MANAGEMENT PLAN

Appendix G. Detailed Design

Intelligence Community Campus- Bethesda (ICC-B)

Restoration of Riparian Buffer at the Former Smelt Hill Dam Site, Falmouth, Maine

Design methods for geosynthetics used for erosion control in channel and river banks

PERMANENT SEEDING. Overview of Sedimentation and Erosion Control Practices. Practice no. 6.11

FOR PROJECTS INITIATED AFTER FEBRUARY 1, 2010 REVISION 1 ITEM 709 TRIANGULAR FILTER FABRIC FENCE

Banking on Natural Fibers Products made from coir and jute play a key role in stabilizing a restored stream for a commercial stream mitigation bank.

HUDSON VALLEY REGIONAL COUNCIL 3 Washington Center, Newburgh NY

Stormwater Standards. Clackamas County Service District No. 1. Planting Guide for Buffers

THE ROLE OF GREEN ROOFS IN URBAN DRAINAGE A REVIEW OF THE CASE FROM AUGUSTENBORG ECO-CITY

Commercial Launch Site Addendum to Wetland Mitigation Plan. Revision 2. April 25, SpaceX Proprietary

Juneau Watershed Partnership

Revetting and Supporting River Banks 4.7 Bank revetment using low steel sheet piling and coir rolls

Key Topics. Bioretention Crime Scene Investigation The Bioretention Construction and Maintenance Sequence

Tentatively Selected Plan within Harlem River, East River and Western Long Island Sound Planning Region. First Level Costs. Federal Non-Federal Total

EROSION & SEDIMENT CONTROL

Lawrencetown Beach & Rainbow Haven Beach

CLACKAMAS COUNTY ZONING AND DEVELOPMENT ORDINANCE

WET PONDS INSPECTION & MAINTENANCE CHECKLIST

Landfill Closure, Intermediate Cover & Post-Closure Care. Municipal League Meeting

Dauphin Island s East End Beach and Barrier Island Restoration Project. April 16, :00 PM Dauphin Island Sea Lab, Shelby Hall

Appendix B. Tentative Silt Curtain Layouts

Port of San Diego Sea Level Rise Ad Hoc Committee Meeting 1 of 3.. September 18, 2018

Piles, inverters, trenching, cabling, assembly.

KENT COUNTY STORMWATER MAINTENANCE DISTRICT STORMWATER BMPs MAINTENANCE TASKS AND RESPONSIBILITIES GUIDANCE DOCUMENT BIO-RETENTION FACILITIES

Infiltration / Soakaway Systems CASE STUDY PROJECTS

Grand River Ravines Georgetown Township

5 TH ANNUAL CAPE COASTAL CONFERENCE COONAMESSETT RIVER RESTORATION PROJECT. Elizabeth H. Gladfelter, Ph.D. Conservation Commission Town of Falmouth

Shoreline Master Program Town of La Conner, Washington

A Collection and Removal System for Water in the Final Cover Drainage Layer

Poisoned Park? How Exide s Lead Contamination Risks Frisco s Grand Park

STREAM BANK STABILIZATION THORPS MORTIMER RECREATION AREA Grandfather Ranger District SITE LOCATION & DRAINAGE AREA

STREAM ALTERATION PRACTICES

E R O S I O N C O N T R O L

Final Report: Appendix G. LID Driveway Retrofit and Teaching Tool at Bristol County Agricultural High School, Dighton - Supporting Information

July 22, 2013 REQUEST FOR PROPOSALS TO PROVIDE ENGINEERING DESIGN SERVICES FOR A PROJECT ALONG THE WESTERN SHORE OF MOBILE BAY

INSTALLATION GUIDELINES FOR GEOTEXTILES USED IN FILTRATION AND DRAINAGE APPLICATIONS

Alternate Green Stream Bank Stabilization Methods

Bioengineered designs

Attention: Ray Tardiff,

DRAFT TIMETABLE FOR STOUR MUSSEL TRIAL

Joint Public Notice. Public Notice Date: February 9, 2015 Expiration Date: March 11, 2015

Homeowners Guide to Stormwater BMP Maintenance

V. EROSION CONTROL. -Drainage swales separation -Under rip-rap protected -Under rip-rap unprotected

New Brighton Park Shoreline Habitat Restoration Project

City of Rockingham. Local Management Practices, Costs and Strategic Coastal Planning

511 - RIP RAP - OPSS 511 ROCK PROTECTION - OPSS 511 GRAVEL SHEETING - OPSS 511 GEOTEXTILE - OPSS 511

Shelbyville, KY Stormwater Best Management Practices. Section 2 EROSION PREVENTION AND SEDIMENT CONTROL PLAN

Cost Estimating for Landfill Design

Breakthrough Innovations

The Napa River Flood Protection Project

A Review of Green Infrastructure Projects Implemented in the Grand Traverse Region

DRAFT ONONDAGA LAKE CAPPING AND DREDGE AREA AND DEPTH INITIAL DESIGN SUBMITTAL H.3 STATIC SLOPE STABILITY ANALYSES

Storm Water Quality and Shoreline Restoration Improvements - Grant Funding Request City of Mound Carlson Park Bolton & Menk Project No.

ROCKAWAY BOARDWALK Community Board 14 Parks Committee Meeting June 4, 2014

Transcription:

River Mile 10.9 Removal Action Overview November 13, 2014 CAG Meeting Modified from CPG s RM10.9 Removal Action Final Design Report dated Nov. 2013 1

River Mile 10.9 Removal Action Activities Dredging: Approx. 2 feet of contaminated sediment were removed. Capping: A cap of approx. 2 feet was placed over the post dredge sediment. The cap consisted of the following layers in ascending order: Active material/sand mixture was placed above the postdredge sediment (remaining contaminated sediment) to prevent contaminants from migrating to the surface of the cap. Geotextilewas placed over the active material/sand mixture. The geotextile is a fabric layer that keeps the active layer/sand mixture in place and prevents penetration by the armor stones. Armor stones, the sizes of which were determined by an engineer, were placed over the geotextile. Placement of the stones happened after the geotextile panels were placed. Sand (habitat layer) was placed over the armor stones to fill in voids to help reestablish the mudflat ecosystem. 2

August 7, 2013 to October 4, 2013: Dredging operations conducted Approximately 2 feet of contaminated sediments were removed. August 17, 2013 August 28, 2013 3

November to December 2013: Active Material/Sand Mixture Placement Approximately 10 inches of active material/sand mixture placed over post dredge sediment November 13, 2013 A telebelt(device to convey material from barge) is depositing the active material/sand mixture over the post dredge sediment. November 15, 2013 Photo shows an area where active material/sand mixture had been placed. 4

March 2014: Placement of geotextile and armor stone Geotextile:fabric layer used to keep the active layer/sand mixture in place and to prevent penetration. Armor stones: were placed after the geotextile panels were laid down. Keeps the geotextile in place and also helps to protect the underlying cap from erosion due to high river flows and propeller wash from recreational boating. March 15, 2014 Left Photo: geotextile panel being placed near the fire deptartmentboat launch Right Photo: armor stone placement overlying the newly placed down geotextile panel. CPG s contractor can be seen trimming the extra geotextile. 5

April 2014: Placement of geotextile and armor stone April 14, 2014: Photo of armor stones over recently-placed geotextile panel. Two different types of armor stone are seen in this photograph: Type B (the smaller of the two stones used) was used when the underlying substrate was hard pan. Type B armor stones were placed closer to shoreline where the flow rate is expected to be lower (less potential erosion). Type A (the larger of the two stones used) were determined by CPG s engineer to withstand a 100-year storm event. Photograph taken in area south of No Dredge Zone 6

April 2014: Placement of geotextile and armor stone continued April 23, 2014 North of the No Dredge Zone Mini excavator is in the background leveling out the armor stone north of the No Dredge Zone South North No Dredge Zone Area South of the No Dredge Zone Type B stone can be seen here Exposed geotextile panel is shown here as it extends beyond the armor stones. When placing the geotextile panel: CPG s contractor laid the panels out flat to extend approx. 5-15 feet off the vegetated shoreline, anchoring it off the trees/brush until the armor stone could be installed. Process resulted in approx. 5 feet excess geotextile in places beyond where dredging/capping occurred CPG s contractors then trimmed back the geotextile to the edge of cap. Exposed geotextile is not a result of erosion 7

May 2014: Sand (habitat layer) placement began Sand layer was applied over the armor stones to fill in voids to help reestablish the mudflat ecosystem. May 8, 2014: Initial test run of sand being applied via a telebelt over the armor stone. Area photographed is south of the No Dredge Zone. May 9, 2014: Photo of an area where one layer of sand was initially applied. 8

May 2014: Sand (habitat layer) placement continued May 9, 2014: Photo of sand layer 24 hours after initial test. Two layers of sand have been placed. May 12, 2014: Photo taken three days after the initial placement of two sand layers (on May 9 th ). 9

May 2014: Sand (habitat layer) placement continued May 27, 2014: Background: The telebeltis conveying first layer of sand in an area just south of the fire department boat launch. Foreground: An area that was covered in the prior week. The row of exposed armor stone in the foreground is outside the dredge line and was not slated to be covered by sand. Helps to anchor the extra geotextile that extends beyond the area dredged/capped. CPG s contractor cut additional fabric once the row of armor stone anchoring the geotextile had been placed. 10

May 29, 2014: Photo taken while standing south of No Dredge Zone looking north. The row of armor stone (acting as an anchor) can be seen on the right side of the photo. May 29, 2014: Photo taken from the southern most cap/dredge location and looking north. The final cap surface post installation can be seen here. May 29, 2014: CPG started to demobilize from RM10.9 11

June 2014 -August 2014 Site visits with EPA, CPG and members of the boating community EPA and CPG discuss and plan for an effort to address high spots of armor stones. EPA and CPG engage in discussions regarding placement of buoy markers CPG and EPA identify areas of elevated armor stones and CPG takes coordinates of the locations September 2014 CPG begins effort on Sept. 29 th to move high spots of armor stones Photo credit: Harvey Morginstin. Photograph titled Lyndhurst LT June 24 2014 037.jpg and was provided to EPA on 6/24/2014 via email. EPA oversees this effort 12

September 29, 2014: CPG effort to move high spots of armor stones Conditions prior to start of work. Row of armor stones anchoring geotextile seen in foreground. A red buoy marker not placed by CPG and EPA is seen. Also, a rower passing by. CPG s contractor removes high spots of armor stones in areas closer to the channel. Area is south of No Dredge Zone. 13

September 30, 2014: CPG effort to move armor stones CPG s contractor continues to manually remove high spots of armor stones. Based on observations that day, it was estimated that approximately 3-4 inches of sediment had accumulated above the sand layer. River level at low tide was higher than anticipated. As such, work was scheduled to resume the following week. 14

October 6, 2014: Last day of effort CPG s contractor utilized a tracked vehicle in effort to remove armor stones in area north of No Dredge Zone. CPG s contractor manually removes armor stones near channel in area north of the No Dredge Zone. Area near fire department boat launch 15

RM10.9 site visits after CPG s efforts to remove high spots of armor stones October 8, 2014: Area south of No Dredge Zone. November 4, 2014: Area north of No Dredge Zone. Row of armor stones anchoring geotextile is in foreground. These stones are outside the dredged/capped area, line almost the entire length of the mudflat, and will remain as they help to anchor the underlying geotextile layer. 16