City of Kearney Capital Improvement Update October 1, TH STREET AND 17TH AVENUE IMPROVEMENTS

Similar documents
PROJECTS UNDER CONSTRUCTION

Town of Yucca Valley Capital Improvement Projects Report July 24, 2014

Project will Replace: Utilities Curb Pavement Lighting. City of Madison

MAIN STREET RECONSTRUCTION PROJECT PRE-CONSTRUCTION PUBLIC INFORMATION SESSION AGENDA

I-70/71 Innerbelt Project

BENJAMIN BANNEKER PARK FRAMEWORK PLAN (PLAN ADOPTION)

BROADVIEW PARK. Projects Status Update February Estimated Investment. Project Status Update Agency Anticipated Completion

Spring 2018 Construction Update

CITY COUNCIL STAFF REPORT

Figure Example of out door dining in the public right-of-way.

DIVISION 32 EXTERIOR IMPROVEMENTS

4.1 Build Alternative 1 Construction Phasing

Benedict Fountain Park Meeting Notes Wednesday, February 15, 2012

Ward Park. Park Land Established: Developed Acres: 9 acres Undeveloped Acres: 4 acres

STANDARD SPECIFICATIONS Book 2 ENGINEERING DRAWINGS INCLUDES ADDENDUMS

Municipality of Anchorage. Community Council Survey Capital Projects Needs Ranking Survey (ALPHABETICAL) Airport Heights

INFRASTRUCTURE EXISTING INFRASTRUCTURE A. Circulation B. Signals C. Drainage D. Utilities

Highway 15 Project - Hutchinson

COMMUNICATION URBAN DESIGN REVIEW BOARD CITY OF DES MOINES, IOWA MAY 16, 2017 MEETING

Index to Projects by Project Name

Kittson Parkway / Watershed Park Parking Lot

Grand River Ravines Georgetown Township

TIRZ 17/Redevelopment Authority Capital Improvements Plan Projects

PRELIMINARY PLAT DESIGN REQUIREMENTS Updated 4/8/2016

4/8/2015 Item #10D Page 1

City of Richmond. Engineering Design Specifications

CITY OF LATHROP. Department of Public Works. DESIGN & CONSTRUCTION Standard Details

TOWN OF JUPITER. Honorable Mayor and Members of Town Council Andrew D. Lukasik, Town Manager

Hunt Highway CELESTE PEMBERTON, CFM, CPM PINAL COUNTY CARLOS SANCHEZ SORIA, PE T.Y. LIN INTERNATIONAL

City of San Juan Capistrano PROJECT PRESENTATION NORTHWEST OPEN SPACE COMMUNITY PARK (CIP 09209) March 22, 2016 FOR THE PROJECT PRESENTATION

Broadway Avenue Streetscape Project City of Albert Lea. Streetscape Design Committee Meeting October 29, 2012

SOUTH UNIVERSITY Street Design Alternatives in Progress

Highway 12 Sibley Avenue Reconstruction. Project Overview and Progress To Date Litchfield City Council April 17, 2017

Canal Road City Limits (East of Van Dyke Ave) to Saal Road

GYPSUM PARKWAY CORRIDOR ENHANCEMENT Gypsum, Colorado. Schematic Design January 2015

Special Revenue Funds

LANDSCAPE MAINTENANCE CONTRACT Detailed Scope of Work

February 17, Sara Ullman Planner I. Sincerley,

Municipality of Anchorage, Alaska Parks & Recreation Department

FY Capital Improvement Program Arroyo Projects - Central Arroyo Summary

#8) T-1409 CENTENNIAL & LAMB TENTATIVE MAP

Oroville Area Urban Greening Plan. Joint Meeting of the Oroville Planning, Park, and Arts Commissions October 12, 2015

CITY OF COCOA BEACH DEPARTMENT OF DEVELOPMENT SERVICES PLANNING BOARD BRIEFING For Meeting Scheduled for April 1, 2013 Agenda Item C2

Master Plan Presentation August 12, 2015

THREE-YEAR CAPITAL IMPROVEMENT PLAN FY

PART TWO: PROJECT SPECIFIC DESIGN GUIDELINES

3.0 master plan concept

MPRD s Keith Mione (Community) Park Midlothian Road Entrance Traffic Signals

Spokane River Forum: City of Spokane Permeable Pavements

Capital Projects impacting Odenton Town Center

Mayor Dave Netterstrom and Members of the City Commission. Anthony Caravella, AICP, Director of Development Services

John Portman Boulevard Corridor

Tampa Palms CDD. Board Of Directors September, 2017

Fall 2017 Construction Update

Town of Millbury Department of Public Works

Wilbur Young Park. Park Land Established: Developed Acres: 15 acres Undeveloped Acres: 25 acres

Y Sports Complex PROGRAMMING Capitol Improvement Plan. Anticipated/Suggested Improvements. Sedgwick County Park: Sports Complex:

Johnson Street Bridge Public Realm Update

Expo Line Transit Project. Project Status Update Meeting West End Corridor Segment C

The bid shall include the following items: 1) Bidder s Name. Address. Telephone Number. Address. 2) The amount of the bid per acre to Mow.

Long Branch-Wayne Local Park Renovation Project

STREETSCAPE IMPROVEMENTS - RECOMMENDATIONS

Lowe Park Master Plan Update Marion, IA August 25 th, 2011

Long Lost Allies? Walking Advocates & Business District Organizations. Matt Kazinka Lake Street Council. Shaina Brassard Seward Redesign

The Auburn Plan Designing the Future of Auburn February 28, 2005

Carson Street Streetscape Improvements. Request for Proposals

TOWN OF PALM BEACH FOR IMMEDIATE RELEASE. Patricia Strayer, P.E., Town Engineer Phone: ,

DRAFT. CITY OF ESCONDIDO 11th Avenue Park WORKSHOP SUMMARY December 17, 2008

GUIDELINES FOR PERMEABLE SIDEWALK-LANDSCAPING PERMIT

FOR IMMEDIATE RELEASE DATE: FRIDAY, AUGUST 31, Road Commission of Kalamazoo County Weekly Project Updates HAVE YOU SIGNED UP?

Prince William Street Project (Grant Avenue to Wellington Road)

REPORT TO COUNCIL City of Sacramento

TA B L E O F C ON T EN T S

DIVISION 32 EXTERIOR IMPROVEMENTS

Woods Chapel Park. Park Amenities: Playground, basketball court, single table shelter, small pond and multi-use trail.

CRA Five Year Capital Improvement Plan. September 2, 2015

Improve the appearance of off-street parking areas, vehicular use areas, and property abutting public and private roads;

Blue Springs Park. Park Land Established: Developed Acres: 12 acres Undeveloped Acres: 2 acres

MEMORANDUM. I2 District Downtown Parking Overlay District 24,000 square feet /.55 acres. Industrial Employment District North Loop Small Area Plan

Design Services for Wiles Road Broward County Project #104026

JOB CREATION PROJECTS

January 11, New benches installed. Paving of parking lot adjacent to piers and the canoe put-in. Near complete with clean up remaining.

ROAD PAVING VARIOUS LOCATIONS LANE KM

Abbott Loop. Community Council Survey Capital Projects Needs Ranking Survey. Comm Council Priority Rank. Rank # ABBOTT LOOP COMMUNITY PARK

LITTLE ELM CAPTIAL IMPROVEMENT BOND STREET PRESENTATION

Chain Bridge Road Sidewalk Improvements Citizen Council Work Session

TOWNSHIP OF HOWELL TOWNSHIP OF HOWELL ENGINEERING PROJECTS STATUS REPORT OCTOBER 19, Resurfacing of Aldrich Road West Contract # 11-06

July 12, Columbus City Council City Hall 90 West Broad Street Columbus, OH RE: I-70/71 Columbus Crossroads Project

Coffey Neighborhood Park Master Plan/Design/Rebuild Workshop. August 4, :00pm 4:00pm

FY Capital Improvement Program Parks and Landscaping. 8 - Summary

Exhibit A. Scope of Work

County of El Dorado Standard Plans

Fifth and Detroit Street Design May 2017 Capital Improvements Committee. DOWNTOWN Street Design

City Commission Agenda Cover Memorandum

Monroe Street Reconstruction. Public Preconstruction Meeting February 21, 2018

Town of Cornelius Bond Update August, 2017

DESIGN CRITERIA PACKAGE

OPPORTUNITIES AND CONSTRAINTS - OXBOW PARK ENTRANCE AND PUT-IN

Main Street Reconstruction From Ninth Line to Stouffer Street. Town of Whitchurch-Stouffville. Public Information Centre

BOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM

Transcription:

56TH STREET AND 17TH AVENUE IMPROVEMENTS FUNDING: Bonded ESTIMATED COST: $3,885,000 COMPLETION DATE: Fall 2018 SCOPE OF PROJECT: Widening of 56th Street from 6th Avenue to 19th Avenue, and widening 17th Avenue from existing 4-lane to north of 56th Street 250 feet, including a traffic signal at 56th Street and 17th Avenue intersection. STATUS OF PROJECT: NPPD has installed all of the street lights on 17th Avenue south of 56th Street, and only have the street lights north of 56th Street left to install. FIXED BASE RADIO READ WATER METER READING FUNDING: Water Revenue ESTIMATED COST: $1,500,000 COMPLETION DATE: Fall 2018 STAFF CONTACT: Tony Jelinek, Director of Utilities SCOPE OF PROJECT: Install antennae, computer hardware and software, and radio equipment to read water meters. STATUS OF PROJECT: The contract for this project has been closed out. On Tuesday September 25, 2018 the system read the entire city. In total, the city has 11,103 accounts that it reads and bills. Out the 11,103 only 25 accounts were unable to be read by the system. These accounts were either dead meters or a communication failure between the meter, radio, or tower. 11TH STREET: from 7th Avenue to 14th Avenue FUNDING: Bonded ESTIMATED COST: $1,325,000 COMPLETION DATE: October 2018 SCOPE OF PROJECT: Remove and replace the existing 46 foot wide four lane road section with new 48 foot wide concrete surface. STATUS OF PROJECT: A request was sent to property owners to complete sprinkler system repair work by October 1st. Sodding operations are to be completed after the 1st of October. NPPD will be installing the street lights. -1-

PATRIOT PARK PLAYGROUND FUNDING: Park Development Fund ESTIMATED COST: $100,000 COMPLETION DATE: Fall 2018 SCOPE OF PROJECT: Construction of playground at Patriot Park to be used by children when their brothers or sisters are playing ball. The playground would include sidewalks and a concrete border. STATUS OF PROJECT: Installation of the playground was completed on September 28. City Staff will then add certified wood chips, place benches, and perform turf and irrigation restoration. COUNTRY CLUB LANE: from 37th Street to 39th Street FUNDING: Developer, City ESTIMATED COST: $420,000 COMPLETION DATE: October 2018 SCOPE OF PROJECT: Extending Country Club Lane from the existing concrete north of 37th Street to 39th Street. This work involves water, storm sewer, and paving. STATUS OF PROJECT: We are waiting for NPPD to install the street light. 55th STREET PLACE FUNDING: Developer ESTIMATED COST: $279,000 COMPLETION DATE: September 2018 SCOPE OF PROJECT: Construction of water, sewer and paving on W 55th Street Pl, from 15th Ave west to end of cul de sac, approximately 460. STATUS OF PROJECT: The project is completed. Seeding establishment remains. CURB and ADA Ramp REPLACEMENT PROJECT FUNDING: Special Sales Tax ESTIMATED COST: $47,232 COMPLETION DATE: October 2018 SCOPE OF PROJECT: Replacement of curb/gutter and associated ADA ramps along 29th Street, between 2nd Avenue and 6th Avenue. STATUS OF PROJECT: Nielsen Construction has started the project and is working on removals of existing curbs. -2-

ADA INTERSECTION RAMP IMPROVEMENTS & SIDEWALK REPLACEMENTS FUNDING: Special Sales Tax ESTIMATED COST: $23,660 COMPLETION DATE: October 2018 SCOPE OF PROJECT: Installation of ADA curb ramps at various intersections between 31st Street and 37th Street north to south and B Avenue to E Avenue east to west. There are approximately 13 intersections in total. STATUS OF PROJECT: The contractor is currently working on the construction of the ramps at these locations. 11th AVENUE FUNDING: District ESTIMATED COST: $270,000 COMPLETION DATE: November 2018 SCOPE OF PROJECT: Construct 36 foot wide concrete street including storm sewer, water main, curb and cutter. STATUS OF PROJECT: Contractor has completed mainline paving. Downtown Improvements - Phase II FUNDING: CDBG Grant and Special Sales Tax ESTIMATED COST: $700,000 COMPLETION DATE: November 2018 STAFF CONTACT: Eric Hellriegel, Assistant City Manager SCOPE OF PROJECT: Phase II improvements will primarily involve sidewalk removal & replacement, pedestrian light replacement, installation of in ground planter beds, installation of underground irrigation, and a new electrical service near 24th and Central. The majority of this work will be focused from 22nd Street south to North Railroad Street on Central Avenue. STATUS OF PROJECT: Contractors are currently working on the east side of Central Avenue, from 21st Street to North Railroad. Electrical conduit, light pole bases, and underground irrigation work is underway at this time, with concrete flatwork to follow. -3-

2ND AVENUE TRAFFIC SIGNAL IMPROVEMENTS FUNDING: City ESTIMATED COST: $150,000 COMPLETION DATE: 2018 SCOPE OF PROJECT: Install protected left turn arrow on existing traffic signals at 48th, 52nd, and 56th Streets. STATUS OF PROJECT: Olsson & Associates is currently analyzing traffic poles and mast arms at 48th Street and 52nd Street. PIONEER PARK SHELTER: FUNDING: City & Donation ESTIMATED COST: $35,000 ($15,000 donation by Sertoma Club) COMPLETION DATE: Fall 2018 SCOPE OF PROJECT: Replace existing shelter is at the end of its lifespan with a new shelter, grills, drinking fountain, and access pathway. Staff is utilizing a committee from the Pioneer Park Neighborhood Association to assist with selection of shelter design and amenities. STATUS OF PROJECT: The shelter pad and footings have been poured. Electrical lines have been run to the footing. Shelter installation expected to occur in early October. City Staff will follow with turf and irrigation restoration, lighting, grill and grill pad installation, tables, and pathway leading to the shelter. BRAD BOWMAN ACCESS. SPORTS FIELD AT PATRIOT PARK FUNDING: City, Donations, Grants ESTIMATED COST: $466,000 COMPLETION DATE: Spring 2019 SCOPE OF PROJECT: Construction of a baseball/softball/soccer field to be accessible to those with special needs. STATUS OF PROJECT: Earthwork has been completed. The concrete base to the field has been poured. The fence mow strip has been poured along with the fence posts. Turf installation is expected to begin the week of Sept. 24. Dugout shelters, spectator shade awnings, and additional concrete work for the spectator shade area will follow. Weather permitting; the contractor hopes to complete the field this year. -4-

MEMORIAL FIELD BALLFIELD LIGHTS FUNDING: Special Sales Tax ESTIMATED COST: $350,000 COMPLETION DATE: Feb. 2019 SCOPE OF PROJECT: Removal of existing ballfield lights and poles, and replacing with new LED lights and taller, galvanized poles. STATUS OF PROJECT: Bids have been let for the removal and installation of the lights. Work is expected to be conducted between November-February 1. HIGHWAY 30 (COLLEGE CURVES) FUNDING: 90% State Safety Funds & 10% City ESTIMATED COST: $2,000,000 COMPLETION DATE: 2019 STAFF CONTACT: Rod Wiederspan, Director of Public Works SCOPE OF PROJECT: Eliminate the left turn movements onto Hwy. 30 at 9th Avenue, install medians across the 6th and 8th Avenue intersections, install left turn lanes at 7th Avenue, move the pedestrian signal at 12th Avenue west to a midblock location, eliminate access onto Hwy. 30 from the south at 9th Avenue, and extend a left turn lane off of Hwy. 30 onto 9th Avenue on the north. STATUS OF PROJECT: The project bid was done in August 2018 for construction in 2019. 17th STREET AND AVENUE P MARLATT SUBDIVISION FUNDING: District / CRA ESTIMATED COST: $610,000 COMPLETION DATE: 2019 SCOPE OF PROJECT: Construct water, sewer, and paving to serve Habitat for Humanity Subdivision STATUS OF PROJECT: Preconstruction was held September 19, 2018. NORTHRIDGE ESTATES 54th Street, 17th Ave Pl, 18th Ave Pl FUNDING: District ESTIMATED COST: $700,000 COMPLETION DATE: 2019 SCOPE OF PROJECT: Construction of water, sewer and paving infrastructure for the Northridge Estates residential subdivision addition. Location includes beginning at the current terminus of 54th Street west of 17th Avenue and extending it west to the city limits approximately 400. Additionally, adding two cul-de-sac s to the south of 54th St. known as 17th Avenue Place and 18th Avenue Place. STATUS OF PROJECT: A delivery order was issued to Brungardt Engineering for the project design. -5-

19th STREET FUNDING: District ESTIMATED COST: $55,000 COMPLETION DATE: 2019 SCOPE OF PROJECT: A district was requested for the completion of paving on the current gravel portion of 19th Street from 1st Avenue approximately 150 west. STATUS OF PROJECT: Currently working with Miller & Associates Engineering on the creation of the 19th Street paving district. Central Kearney Sidewalks FUNDING: CDBG Grant and Special Sales Tax ESTIMATED COST: $700,000 COMPLETION DATE: 2019 STAFF CONTACT: Eric Hellriegel, Assistant City Manager SCOPE OF PROJECT: Construction of 58,000 S.F. of sidewalks and installing 65 detectable ADA warning panels from 16th Street north to South Railroad Street, and Avenue C west to 2nd Avenue. STATUS OF PROJECT: Currently working with Miller & Associates Engineering on preliminary design for the project. -6-