An inspection of the above noted operation was conducted on January 10, 2019 by Resource Management Officers Norm McCowan and Jayda Robillard.

Size: px
Start display at page:

Download "An inspection of the above noted operation was conducted on January 10, 2019 by Resource Management Officers Norm McCowan and Jayda Robillard."

Transcription

1 Telephone: Fax: January 14, 2019 Strategic Oil & Gas Ltd th venue SW Calgary, B T2P 4G8 ttention: lyssa Bruce File Number Type of Operation Location MV OIL ND GS OPERTIONS Cameron Hills area, NT Dear Ms. Bruce, n inspection of the above noted operation was conducted on January 10, 2019 by Resource Management Officers Norm McCowan and Jayda Robillard. Enclosed is a copy of the Environmental Inspection Report. I am pleased to report that your operation appeared satisfactory in all aspects and no environmental concerns were identified during the inspection. Your cooperation is appreciated. If you have any questions, I can be reached at (867) Sincerely, Norm McCowan Resource Management Officer III Department of Lands South Slave Region cc: ngela Love, Regulatory Specialist, Mackenzie Valley Land and Water Board Wendy Bidwell, Water Resource Officer, ENR Derise Rehm Lepine, Regional Superintendent, South Slave Region, Lands Brian Heppelle, Chief Safety Officer, OROGO Charlene Coe, Land Use dvisor, North Slave Region, Lands Ken Petersen, Road and Lease Construction, Strategic Oil and Gas Ltd. 41 Capital Drive #203, Hay River, NT X0E 1G2

2 Permittee: Strategic Oil & Gas Ltd. Permit Expiry September 18, Date: 2020 Land Use Permit No. MV Previous Inspection: December 05, 2018 Quarrying Permit No. 17/0005; 17/0006 Inspection Date: January 10, 2019 Contractor: Rowe's Construction Subcontractor: Winter access from the lberta/nwt Border to the H 03 Battery Location(s) Inspected: Site, Lake Source 3, Main Camp, 21 well sites in the Cameron Hills area. Current Stage of Operation: Winter road construction to south side of the Cameron River Bridge has been completed. Equipment was working on the north side of the bridge to Well Site L 47 at time of inspection. Service rig and slickline truck scheduled to arrive on January 15, 2019 for suspension and abandonment work at twenty one (21) well locations. Program Modifications pproved: Condition of Operation cceptable U Unacceptable N/ Not pplicable N/I Not Inspected Operating Condition spect Inspected Cameron Hills Field Location as Permitted Time as Permitted Equipment as pproved (Type & Size) Methods & Techniques Facilities Erosion (Control or Prevention) Chemicals Wildlife and Fisheries Habitat (Protection) Wastes Historical / rchaeological Sites Fuel Storage Brush Disposal Restoration of Lands Permits Matters not Inconsistent Sections 8 to 12 / 14 to 16 M.V.L.U.R. Explanatory Remarks Cameron Hills Field: n inspection of the winter operation in the Cameron Hills was conducted by Resource Management Officers Norm McCowan and Jayda Robillard on January 10, Ken Peterson, Road and Lease Construction, Strategic Oil and Gas Ltd. was present during the inspection. The inspection was conducted to ensure compliance with the terms and conditions annexed to Land Use Permit MV The entire length of the winter road was inspected and the Inspectors are pleased to report that there appeared to be sufficient icing and/or snow pack along the access in accordance with Permit Condition #29 of the land use permit which requires a minimum of 10cm of coverage. Date: January 10, 2019 Permit #: MV Page No: 1

3 t the time of inspection, the winter road has been completed to all wells requiring work this winter with the exceptions of wells D 49, H 58, and L 47. Equipment including a grader, snow cat and water trucks were working on the section of access west of the airstrip to Well Site L 47. The work was progressing well with no environmental concerns noted. ll well sites scheduled for abandonment, suspension or slickline work this winter have been plowed. The Cameron River ice bridge crossing west of Well Site L 40 at 'N 'W has been completed and appeared satisfactory in all aspects. The Inspectors note that only clean snow and ice was used in the construction in compliance with Permit Condition #56. The following is a summary of work completed as reported by Strategic Oil and Gas Ltd. on the Weekly Progress Report dated January 07, 2019: Service Rig: Well 05: ccess completed; service rig to complete 2 zone suspension. Well C 74: ccess completed; service rig to complete 1 zone suspension. Well E 72: ccess completed; service rig to complete 1 zone abandonment. Well H 03: ccess completed; service rig to complete 1 zone suspension. Well 2H 03: ccess completed; service rig to complete 1 zone suspension. Well J 74: ccess completed; service rig to complete 1 zone suspension. Well K 74: ccess completed; service rig to complete 1 zone suspension. Well L 40: ccess not completed; service rig to complete 2 zone suspension. Well L 47: ccess not completed; service rig to complete 1 zone suspension. Well L 73: ccess completed; service rig to complete 1 zone suspension. Well M 73: ccess completed; service rig to complete 1 zone suspension. Well 2M 73: ccess completed; service rig to complete 1 zone suspension. Slickline: Well 03: ccess completed; slickline to set plug in tubing. Well B 08: ccess completed; slickline to set plug in tubing. Well C 19: ccess completed; slickline to set plug in tubing. Well C 75: ccess completed; slickline to set plug in tubing. Well D 49: ccess not completed; slickline to set plug in tubing. Well H 58: ccess not completed; slickline to set plug in tubing. Date: January 10, 2019 Permit #: MV Page No: 2

4 Well I 16: ccess completed; slickline to set plug in tubing. Well I 73: ccess completed; slickline to set plug in tubing. Well J 62: ccess completed; slickline to set plug in tubing. The service rig and slickline truck are scheduled to arrive in the Cameron Hills on January 15, K Camp: Snow has been plowed from the campsite. The removal of old rig matting, piping, fuel drums and other items noted on the September 2018 inspection report is planned for this winter. Main Camp: The camp is in operation. t time of inspection, sixteen people were staying at the camp which has a capacity of 29 beds. Three camp trailers have been setup beside the main camp for the service rig and slickline crews. The camp trailers are tied into the main camps sewage system and no pump out tanks are required. Water for camp use in being hauled in from Hay River. Lake Source 3: The access to the lake has been completed and water is being used for the winter road construction. total of 6,665 m3 of water has been hauled from the lake this winter. Strategic Oil and Gas Ltd. are working on a plan to address many of the deficiencies noted in the September 2018 inspection report. Work that may occur this winter includes the removal of all chemicals, fuel drums and waste items from the well sites, remediation of the sumps and sections of pipeline and backfilling of rat holes which had been left open. The Inspectors appreciate the efforts of Strategic Oil and Gas Ltd. in addressing these concerns. The Inspectors are pleased to report that this operation appeared satisfactory in all aspects and no environmental concerns were noted. Representative Signature Inspector s Signature Date: January 10, 2019 Permit #: MV Page No: 3

5 Inspection Images: Figure 1 Figure 2 Main access facing north near the Battery Site. Winter access to Lake Source 3. Figure 3 Figure 4 Water is being pumped from Lake Source 3 for Fish screen on water intake in compliance with winter road construction. Permit Condition #86. Figure 5 Figure 6 ccess and Well Site K 74 has been plowed. Winter access to Well Site J 74. Date: January 10, 2019 Permit #: MV Page No: 4

6 Figure 7 Figure 8 Well Site J 74. Equipment parked at the K Camp. Figure 9 Figure 10 Drip tray has been placed under the back hoe in Fuel drums located on the west side of the garage compliance with Permit Condition #125. building. Figure 11 Figure 12 No bung on the 45 gallon drum full of oil. Drums Well Site 05. are slated for removal this winter. Date: January 10, 2019 Permit #: MV Page No: 5

7 Figure 13 Figure 14 Winter access north of Well Site 05. Winter access at Km 45 south of the Cameron River Bridge. Figure 15 Figure 16 Winter access east of Well Site B 08. Well Site B 08. Figure 17 Figure 18 Winter access to Well Site C 19. Well Site C 19. Date: January 10, 2019 Permit #: MV Page No: 6

8 Figure 19 Figure 20 Well Site N 28. Winter access north of Well Site N 28. Figure 21 Figure 22 Winter access to Well Site L 40. Well Site L 40. Figure 23 Figure 24 Winter access facing west near the Cameron River. Snow & ice bridge constructed across the Cameron River west of Well Site L 40. Date: January 10, 2019 Permit #: MV Page No: 7

9 Figure 25 Figure 26 Winter access north of D 49. Well Site D 49. Figure 27 Figure 28 Winter access to Well Site H 58. Winter access near Well Site L 47. Figure 29 Figure 30 Well site L 47. Winter access north of Well Site L 47. Date: January 10, 2019 Permit #: MV Page No: 8

10 Figure 31 Figure 32 Main camp in operation located at the Battery Site. Crew trailers have been tied into the main camps Three new crew trailers have been hauled in. sewage system. ll sewage is pumped into the sewage lagoon. Figure 33 Figure 34 Battery site has been cleared of snow for this 50,000 L double walled fuel tank with spill kit. winters operation. Date: January 10, 2019 Permit #: MV Page No: 9

/s/ Michael T. Loeffler. Michael T. Loeffler Senior Director, Certificates and External Affairs. Attachment. September 14, 2018.

/s/ Michael T. Loeffler. Michael T. Loeffler Senior Director, Certificates and External Affairs. Attachment. September 14, 2018. Northern Natural Gas Company P.O. Box 3330 Omaha, NE 68103-0330 402 398-7200 September 14, 2018 Via efiling Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington,

More information

Explosion at Battery Site Date of Incident: Type of Incident: Fatal

Explosion at Battery Site Date of Incident: Type of Incident: Fatal Explosion at Battery Site Date of Incident: 99 07 26 Type of Incident: Fatal SUMMARY On 99 07 26 a relief operator and site consultant were assisting a flush-by crew at an oil well located about 200 meters

More information

2014 Officers and Committee Chairs Next SHOA Meeting Secretary: Kurt Simon Architectural: Laura Bishop

2014 Officers and Committee Chairs Next SHOA Meeting Secretary: Kurt Simon Architectural: Laura Bishop July 2014 SADDLEBACK EXPRESS A publication for the home and lot owners of Saddleback Estates President: Bob Ferber 885-1706 2014 Officers and Committee Chairs Next SHOA Meeting Secretary: Kurt Simon 305-0265

More information

Peoria Riverfront Development (Ecosystem Restoration) Upper Mid-sized Island Critical Restoration Project (September 2011)

Peoria Riverfront Development (Ecosystem Restoration) Upper Mid-sized Island Critical Restoration Project (September 2011) Peoria Riverfront Development (Ecosystem Restoration) Upper Mid-sized Island Critical Restoration Project (September 2011) Description The Corps of Engineers, Rock Island District (District) and the Illinois

More information

SECTION SECURITY TESTING AND COMMISSIONING

SECTION SECURITY TESTING AND COMMISSIONING SECTION 280800 - SECURITY TESTING AND COMMISSIONING PART 1 - GENERAL 1.1 WORK INCLUDES A. General Description: This specification section covers the provision of preliminary testing, acceptance testing,

More information

Information for File # JTF

Information for File # JTF Information for File # 2013-04665-JTF Applicant Corps Contact Enbridge Energy, Limited Partnership Josh Fitzpatrick Address 1554 Highway 2, Suite 2, Two Harbors, MN 55616 E-Mail joshua.t.fitzpatrick@usace.army.mil

More information

Trinity River Authority of Texas

Trinity River Authority of Texas Trinity River Authority of Texas Central Regional Wastewater System 3110.005.100 November 19, 2015 Attention: Contractors / Suppliers / Delivery Personnel Subject: Central Regional Wastewater System Risk

More information

Construction Progress Report

Construction Progress Report Report Date: 4/8/2017 Subject: Construction Week 2 70% Complete Project: Sunset Pond EWP Stream Reclamation, Fourmile Creek, Boulder County, CO Report By: TJ Burr, Civil Engineer/Stream Restoration Specialist,

More information

EC Certificate - Full Quality Assurance System Directive 93/42/EEC on Medical Devices, Annex II excluding Section 4

EC Certificate - Full Quality Assurance System Directive 93/42/EEC on Medical Devices, Annex II excluding Section 4 Directive 93/42/EEC on Medical Devices, Annex II excluding Section 4 No. CE 00999 In respect of: The design and manufacture of diagnostic X-Ray tubes, CT tubes and mammography tubes, and the design and

More information

Coquitlam River Riparian Planting

Coquitlam River Riparian Planting Coquitlam River Riparian Planting Year Four Year Four Report, March 2016 Prepared for: Fish and Wildlife Compensation Program Prepared by: Watershed Watch Salmon Society and the Kwikwetlem First Nation

More information

Information for File # ARC

Information for File # ARC Information for File # 2015-02781-ARC Applicant Corps Contact Enbridge Energy, Limited Partnership Andrew R Chambers Address 600 South Lake Avenue, Suite 211, Duluth, MN 55802 E-Mail Andrew.R.Chambers@usace.army.mil

More information

Subject: Hendry County Evaluation and Appraisal Report Letter of Understanding - Identification of Major Issues

Subject: Hendry County Evaluation and Appraisal Report Letter of Understanding - Identification of Major Issues HENDRY COUNTY PLANNING & ZONING DEPARTMENT POST OFFICE BOX 2340 165 S. LEE STREET LABELLE, FLORIDA 33975 (863) 675-5240 FAX: (863) 675-5317 SUNCOM 744-4750 November 16, 2007 Mr. Mike McDaniel, Chief Office

More information

Hadleigh Woods Gazette

Hadleigh Woods Gazette Hadleigh Woods Gazette www.hadleighwoods.com October 2018 Volume 120 President's Notes Over the past few weeks we have had a number of noteworthy events take place. On September 26th Power Up replaced

More information

Mowing and Haying in the Right of Way AMC Transportation & Infrastructure Policy Committee

Mowing and Haying in the Right of Way AMC Transportation & Infrastructure Policy Committee Mowing and Haying in the Right of Way AMC Transportation & Infrastructure Policy Committee Nancy Daubenberger Assistant Commissioner- Engineering Services March 1, 2018 Roadway Miles and Green Space MnDOT

More information

NORTHEAST RIVER CROSSING FUNCTIONAL PLANNING STUDY

NORTHEAST RIVER CROSSING FUNCTIONAL PLANNING STUDY WELCOME Northeast River Crossing Functional Planning Study Phase 2 Public Meeting 4 to 8 PM Informal drop-in format and discussion tables Meeting Purpose Introduce the Northeast River Crossing Functional

More information

MUNICIPAL SEPARATE STORM SEWER SYSTEM 2008 ANNUAL REPORT

MUNICIPAL SEPARATE STORM SEWER SYSTEM 2008 ANNUAL REPORT MUNICIPAL SEPARATE STORM SEWER SYSTEM 2008 ANNUAL REPORT Permit Number 85-03-0-04 March 2009 Prepared by: Iowa State University Department of Environmental Health and Safety 2809 Daley Drive Ames, Iowa

More information

RE: Quarterly Inspection conducted on September 6, 2017 AFIN Permit Number 0180-SG-WTX

RE: Quarterly Inspection conducted on September 6, 2017 AFIN Permit Number 0180-SG-WTX Document ID 099278 September 25, 2017 Ms. Robyn Reed Boston Mountain RSWMD 11398 Bond Road Prairie Grove, AR 72753 RE: Quarterly Inspection conducted on September 6, 2017 AFIN 72-00778 Permit Number 0180-SG-WTX

More information

CITY OF KELOWNA MEMORANDUM. Date: June 20, 2001 File No.: Z City Manager Planning and Development Services Department

CITY OF KELOWNA MEMORANDUM. Date: June 20, 2001 File No.: Z City Manager Planning and Development Services Department CITY OF KELOWNA MEMORANDUM Date: June 20, 2001 File No.: Z00-1033 To: From: City Manager Planning and Development Services Department Subject: APPLICATION NO. Z00-1033 OWNER: ELDORADO RANCH LTD. AT: JIM

More information

The Dresden Sustainable Urban Mobility Plan (SUMP)

The Dresden Sustainable Urban Mobility Plan (SUMP) The Dresden Sustainable Urban Mobility Plan (SUMP) photo: Frank Fiedler UN-Habitat III Regional Meeting Side-event Sustain and clean mobility for the New Urban Agenda Prague, 16.03.2016 Dipl.-Ing. Frank

More information

R E S O L U T I O N. Designation: R-2A (1-Family, 2-acre Minimum Lot Size)

R E S O L U T I O N. Designation: R-2A (1-Family, 2-acre Minimum Lot Size) PLANNING BOARD Arthur Adelman, Chair TOWN OF NORTH CASTLE WESTCHESTER COUNTY 17 Bedford Road Armonk, New York 10504-1898 R E S O L U T I O N Telephone: (914) 273-3542 Fax: (914) 273-3554 www.northcastleny.com

More information

Agenda Item # Action: x Agenda Title: Settler s Village Fourth Filing Minor Subdivision

Agenda Item # Action: x Agenda Title: Settler s Village Fourth Filing Minor Subdivision TOWN OF MILLIKEN TOWN BOARD AGENDA MEMORANDUM To: Mayor Lichtfuss and Board of Trustees Meeting Date: From: Steve House, Community Development Director Via: Jim Burack, Town Administrator Wednesday, December

More information

Celtic Exploration Ltd. Well Servicing Incident: Blowout and Fire August 9, 2005

Celtic Exploration Ltd. Well Servicing Incident: Blowout and Fire August 9, 2005 Celtic Exploration Ltd. Well Servicing Incident: Blowout and Fire August 9, 2005 EUB Post-Incident Report February 6, 2006 ALBERTA ENERGY AND UTILITIES BOARD EUB Post-Incident Report: Celtic Exploration

More information

Keizer Fire District Annual Report. Keizer firefighters saw a 16% increase in calls during Protecting Lives, Property and the Environment

Keizer Fire District Annual Report. Keizer firefighters saw a 16% increase in calls during Protecting Lives, Property and the Environment Keizer Fire District Protecting Lives, Property and the Environment 2017 Annual Report 661 Chemawa Road NE Keizer, Oregon 97303 503-390-9111 Keizer firefighters saw a 16% increase in calls during 2017.

More information

Northeast Anthony Henday Drive Manning Freeway to Whitemud Drive Welcome to this Construction Information Session

Northeast Anthony Henday Drive Manning Freeway to Whitemud Drive Welcome to this Construction Information Session Manning Freeway to Whitemud Drive Welcome to this Construction Information Session Purpose To inform interested residents and businesses about the plans accommodation. Background: The Government of Alberta

More information

Evaluation of the Red Jacket Fx1, Fx2, Fx1V and Fx2V Line Leak Detectors For Hourly Monitoring on Rigid Pipelines. Final Report

Evaluation of the Red Jacket Fx1, Fx2, Fx1V and Fx2V Line Leak Detectors For Hourly Monitoring on Rigid Pipelines. Final Report Evaluation of the Red Jacket Fx1, Fx2, Fx1V and Fx2V Line Leak Detectors For Hourly Monitoring on Rigid Pipelines Final Report PREPARED FOR: Marley Pump a United Dominion Company March 14, 1994 (Revised

More information

UNIVERSITY OF NORTHERN IOWA

UNIVERSITY OF NORTHERN IOWA UNIVERSITY OF NORTHERN IOWA Municipal Separate Storm Sewer System September 2008 Report Permit Number 07-09-0-04 August 2008 Prepared by: University of Northern Iowa Environmental Health and Safety Office

More information

BUSHFIRE MANAGEMENT PLAN (BMP)

BUSHFIRE MANAGEMENT PLAN (BMP) Established 1907 BUSHFIRE MANAGEMENT PLAN (BMP) December 2015 Version Date Section Modified 1 February 2005 All 2 3 December 2010 December 2015 All All Reason for Modification Original Management Plan

More information

138 ATTACHMENT 17. DEPARTMENT OF THE ARMY WlLMlNGTON DISTRICT, CORPS OF ENGINEERS

138 ATTACHMENT 17. DEPARTMENT OF THE ARMY WlLMlNGTON DISTRICT, CORPS OF ENGINEERS 138 ATTACHMENT 17 DEPARTMENT OF THE ARMY WlLMlNGTON DISTRICT, CORPS OF ENGINEERS B. EVERETT JORDAN DAM AND LAKE P.O. Box 144 MONCURE, NORTH CAROLINA 27559 April 11, 2007 Mr. Scott Radway Radway Design

More information

Apartment Recycling & Green Bin Handbook

Apartment Recycling & Green Bin Handbook Apartment Recycling & Green Bin Handbook For Superintendents & Property Managers Questions? Call: 705-325-3522 E-mail: enviroservices@orillia.ca Website: Orillia.ca (look under Living in Orillia tab) Visit

More information

MUCKLESHOOT INDIAN TRIBE Fisheries Division nd Avenue SE. Auburn, Washington

MUCKLESHOOT INDIAN TRIBE Fisheries Division nd Avenue SE. Auburn, Washington MUCKLESHOOT INDIAN TRIBE Fisheries Division 39015-172nd Avenue SE. Auburn, Washington 98092-9763 Phone: (253) 939-3311. Fax: (253) 931-0752 Mr. David Radabaugh Shoreline Planer W A Dept. of Ecology 3190

More information

BCCO TRAINING FOR CONTRACTORS

BCCO TRAINING FOR CONTRACTORS BCCO TRAINING FOR CONTRACTORS Printed or Saved Mygov Virtual Inspections PERMITS 2 APPLYING FOR PERMITS Please visit our Website at buildingcodecompliance.ocps.net for valuable information regarding the

More information

Town of Vershire Road Erosion Inventory Report

Town of Vershire Road Erosion Inventory Report Town of Vershire Road Erosion Inventory Report Taylor Valley Road. Photo taken by TRORC staff. Prepared by: 128 King Farm Road Woodstock, VT 05091 Inventory and report funded by the Vermont Agency of Transportation

More information

SOLUT SPREAD 8. Calgary, AB, Canada T2R 0K1

SOLUT SPREAD 8. Calgary, AB, Canada T2R 0K1 MANITOBA METIS FEDER ATION MATRIX SOLUT IONS INC. PARTNERSHIP INDIGENOUS CONSTRUCTION MONITORING WEEKLY REPORT SPREAD 8 SEPTEMBER 4 TH TO SEPTEMBER 8 TH Suite 600, 214 11 Ave. SW Calgary, AB, Canada T2R

More information

FOR THE PERIOD JANUARY 1, TO DECEMBER 31, GENERAL INFORMATION

FOR THE PERIOD JANUARY 1, TO DECEMBER 31, GENERAL INFORMATION 3850-PM-BCW0083h Rev. 11/2016 COMMONWEALTH OF PENNSYLVANIA DEPARTMENT OF ENVIRONMENTAL PROTECTION BUREAU OF CLEAN WATER PAG-03 NATIONAL POLLUTANT DISCHARGE ELIMINATION SYSTEM (NPDES) GENERAL PERMIT FOR

More information

COASTAL CONSERVANCY. Staff Recommendation March 25, 2004 LOS ANGELES GREEN VISION PLAN. File No.: Project Manager: Marc Beyeler

COASTAL CONSERVANCY. Staff Recommendation March 25, 2004 LOS ANGELES GREEN VISION PLAN. File No.: Project Manager: Marc Beyeler COASTAL CONSERVANCY Staff Recommendation March 25, 2004 File No.: 04-014 Project Manager: Marc Beyeler RECOMMENDED ACTION: Authorization to disburse up to $50,000 to the University of Southern California

More information

Attention: Ray Tardiff,

Attention: Ray Tardiff, D B 1A 1750 S.Quinn Prince George, B.C. V2N 1X3 PHONE: (250) 562-5541 FAX: (250) 562-5561 E-MAIL: dwbpg@mag-net.com August 30, 2007 PC: MOF-05-001 Ray Tardiff, Regional Roads Specialist Ministry of Forest,

More information

a) Establishment of emergency procedures to be followed at the time of an emergency;

a) Establishment of emergency procedures to be followed at the time of an emergency; 5.10 Fire Safety 5.10.1 Introduction The Corporation is responsible for carrying out the provisions of the Ontario Fire Code. This section outlines our responsibilities as well as inspections and testing

More information

Agenda Item # Action: x Agenda Title: Settler s Village Fourth Filing Minor Subdivision

Agenda Item # Action: x Agenda Title: Settler s Village Fourth Filing Minor Subdivision TOWN OF MILLIKEN TOWN BOARD AGENDA MEMORANDUM To: Chairman Ekwall and Members of the Planning Commission From: Steve House, Community Development Director Meeting Date: Wednesday, November 19, 2008 Agenda

More information

Conditional Use Permit Application and Narrative

Conditional Use Permit Application and Narrative Conditional Use Permit Application and Narrative View looking south at proposed tower location from Canal Rd., I-70 is beyond the treeline in the back Submitted by: Darren Hunter CENTERLINE SOLUTIONS 16360

More information

Inspection Report: Berryville Collection System, AFIN: , Permit #: AR FACILITY TYPE: 1 - Municipal

Inspection Report: Berryville Collection System, AFIN: , Permit #: AR FACILITY TYPE: 1 - Municipal FACILITY INFORMATION NAME: Berryville Collection System LOCATION: CITY: Berryville RESPONSIBLE OFFICIAL NAME: / TITLE Honorable Tim McKinney / Mayor COMPANY: City of Berryville MAILING ADDRESS: P.O. Box

More information

December 11, December 10, 2015

December 11, December 10, 2015 December 11, 2015 December 10, 2015 2 Welcome & Introductions Project Overview Discussion Questions Group Insights Key Takeaways Next Steps 3 4 5 6 7 8 9 Governed by multiple layers of policy UNESCO World

More information

Appendix P. Long Beach Fire Department Service Information

Appendix P. Long Beach Fire Department Service Information Appendix P Long Beach Fire Department Service Information CITY OF LONG BEACH FIRE DEPARTMENT 3205 Lakewood Boulevard Loog Beach, CA 90808-1733 Telephone (562) 570-2500 FAX (562) 570-2506 MICHAEL DuREE

More information

September 14, Ken Cunningham, Chief a I. Conservation Services Division ti9 r< New Mexico Department of Game and Fish. P0 Box

September 14, Ken Cunningham, Chief a I. Conservation Services Division ti9 r< New Mexico Department of Game and Fish. P0 Box September 14, 2011 j Conservation Services Division ti9 r< Ken Cunningham, Chief a I fl4j Richardson Building www.urscorp.com Fax: 575-526-1390 Phone: 575-526-1180 Las Cruces, NM 88005-2610 101 North Alameda,

More information

Evaluation of the Incon TS-LLD Line Leak Detection System

Evaluation of the Incon TS-LLD Line Leak Detection System Evaluation of the Incon TS-LLD Line Leak Detection System (for Hourly Testing, Monthly Monitoring, and Annual Line Tightness Testing) EPA Forms PREPARED FOR Incon (Intelligent Controls) July 6, 1995 Ken

More information

KWA. Evaluation of the Morrison Bros. Co. Liquid Sensor, Adjustable Level Sensor and Multi-Level Sensor. Final Report

KWA. Evaluation of the Morrison Bros. Co. Liquid Sensor, Adjustable Level Sensor and Multi-Level Sensor. Final Report Evaluation of the Morrison Bros. Co. Liquid Sensor, Adjustable Level Sensor and Multi-Level Sensor 924LS, 924 and 925 Sensor for use with the 918AC, 918S, 918D and 918Q Alarm Consoles Final Report PREPARED

More information

TREASURE COAST REGIONAL PLANNING COUNCIL M E M O R A N D U M. February 19, 2010 Regional Planning Council Meeting

TREASURE COAST REGIONAL PLANNING COUNCIL M E M O R A N D U M. February 19, 2010 Regional Planning Council Meeting TREASURE COAST REGIONAL PLANNING COUNCIL M E M O R A N D U M To: Council Members AGENDA ITEM 5H From: Date: Subject: Staff February 19, 2010 Regional Planning Council Meeting Local Government Comprehensive

More information

LE ROI DANIELS SCHOOL CALGARY, ALBERTA

LE ROI DANIELS SCHOOL CALGARY, ALBERTA LE ROI DANIELS SCHOOL CALGARY, ALBERTA School Facility Evaluation Project Calgary School Board, District 19 Prepared For Alberta Infrastructure March 2000 Prepared By Bernbaum Architect Ltd. Rae Mclean

More information

PRE-CONSTRUCTION CONFERENCE AGENDA 2:00 PM October 8, Type of Work: Grading, Concrete/Bituminous Paving, Storm Sewer, Watermain, Signal/Lighting

PRE-CONSTRUCTION CONFERENCE AGENDA 2:00 PM October 8, Type of Work: Grading, Concrete/Bituminous Paving, Storm Sewer, Watermain, Signal/Lighting Project No.: SAP 055-622-050 / SAP 055-633-003 Location: CSAH 22 / CSAH 33 Type of Work: Grading, Concrete/Bituminous Paving, Storm Sewer, Watermain, Signal/Lighting Contractor: Hoffman Construction Company

More information

COMMERCIAL OFFICE TENANT RECYCLING PROCEDURES MANUAL

COMMERCIAL OFFICE TENANT RECYCLING PROCEDURES MANUAL COMMERCIAL OFFICE TENANT RECYCLING PROCEDURES MANUAL FOR: 800 Gessner Rd. 820 Gessner Rd. 840 Gessner Rd. 9821 Katy Frwy. 920 Memorial City Way 945 Bunker Hill Rd. 9805 Katy Frwy. 9807 Katy Frwy. 9811

More information

CITY of RIDGEFIELD TYPE I DECISION SITE PLAN REVIEW (SPR 99-10) PDM MOLDING INC. PHASE II EXPANSION

CITY of RIDGEFIELD TYPE I DECISION SITE PLAN REVIEW (SPR 99-10) PDM MOLDING INC. PHASE II EXPANSION Page 1 CITY of RIDGEFIELD TYPE I DECISION SITE PLAN REVIEW (SPR 99-10) PDM MOLDING INC. PHASE II EXPANSION TO: Mayor, and Members of the Ridgefield City Council and Planning Commission FROM: Eric Eisemann

More information

DRAFT Anan Wildlife Observatory Recreation Site Master Plan. Prepared by: Wrangell Ranger District Tongass National Forest Alaska

DRAFT Anan Wildlife Observatory Recreation Site Master Plan. Prepared by: Wrangell Ranger District Tongass National Forest Alaska DRAFT Anan Wildlife Observatory Recreation Site Master Plan Prepared by: Wrangell Ranger District Tongass National Forest Alaska December, 2015 Signature Sheet Approved: James King Director of Recreation,

More information

September 30, Dear Fire Suppression System Contractor/Designer:

September 30, Dear Fire Suppression System Contractor/Designer: CITY OF BOZEMAN FIRE DEPARTMENT P.O. Box 1230 Bozeman, Montana 59771-1230 Phone (406) 582-2350 CITY OF BOZEMAN BUILDING DEPARTMENT 20 E Olive St, STE 208 Bozeman, Montana 59715-4790 Phone (406) 582-2375

More information

Growing Forward 2. A Summary Report of the Small Scale Foods Program 2013/14. Canada/Northwest Territories

Growing Forward 2. A Summary Report of the Small Scale Foods Program 2013/14. Canada/Northwest Territories TABLED DOCUMENT 150-17(5) TABLED ON OCTOBER 27, 2014 Growing Forward 2 Canada/Northwest Territories A Summary Report of the Small Scale Foods Program 2013/14 A Summary Report of the Small Scale Foods Program

More information

Joe Pool Lake Lake Master Plan Public Information Meeting Presentation of Final Draft Revision July 31, 2018

Joe Pool Lake Lake Master Plan Public Information Meeting Presentation of Final Draft Revision July 31, 2018 Joe Pool Lake Lake Master Plan Public Information Meeting Presentation of Final Draft Revision July 31, 2018 Presented By Jeremy Spencer Lake Manager U.S. Army Corps of Engineers Fort Worth District US

More information

MONTH-BY-MONTH GUIDE TO HVAC MAINTENANCE

MONTH-BY-MONTH GUIDE TO HVAC MAINTENANCE Just like any critical piece of equipment, your heating and cooling systems require regular HVAC maintenance to keep them running properly. Home and business owners should stay on top of maintenance tasks

More information

STANDARD OPERATING GUIDELINE Standard Response

STANDARD OPERATING GUIDELINE Standard Response STANDARD OPERATING GUIDELINE Standard Response Purpose The purpose of the Standards for Response SOG is to provide guidelines for determining what resources are assigned to emergencies, and standards for

More information

Minister of the Environment Representative

Minister of the Environment Representative Page 39 MINUTES OF THE MUNICIPAL PLANNING COMMISSION of the Town of Banff in the Province of Alberta Town Hall Council Chamber Wednesday, at 9:00 a.m. COMMISSION MEMBERS PRESENT Raymond Horyn Public Representative

More information

NEW WATER CONNECTION PROCEDURES

NEW WATER CONNECTION PROCEDURES NEW WATER CONNECTION PROCEDURES For Lincoln, Jerome, Village of Sanford WATER DISTRICT NO. 1 of MIDLAND COUNTY Office Location: 246 E. Price Rd. Midland, MI 48642 Mailing Address: PO Box 320 Sanford, MI

More information

Raystown Lake Master Plan Revision. Public Meeting April 25 & 26, 2018 How does the revision process work?

Raystown Lake Master Plan Revision. Public Meeting April 25 & 26, 2018 How does the revision process work? Raystown Lake Master Plan Revision Public Meeting April 25 & 26, 2018 How does the revision process work? What is a Master Plan? The Master Plan is the strategic land use management document that guides

More information

HIGHLAND HILLS MAINTENANCE COMMISSION. Board of Trustees. BOARD POLICY NO: 3-9 Dated: 28 Sep 2001 Revised: 2 Feb 2005

HIGHLAND HILLS MAINTENANCE COMMISSION. Board of Trustees. BOARD POLICY NO: 3-9 Dated: 28 Sep 2001 Revised: 2 Feb 2005 HIGHLAND HILLS MAINTENANCE COMMISSION Board of Trustees BOARD POLICY NO: 3-9 Dated: 28 Sep 2001 Revised: 2 Feb 2005 TITLE: GREENBELT TREE MANAGEMENT POLICY PRIMARY RESPONSIBILITIES: Greenbelt Committee

More information

INTEGRATED LIFE SAFETY COMPLIANCE TESTING AND ITS PROCEDURES

INTEGRATED LIFE SAFETY COMPLIANCE TESTING AND ITS PROCEDURES INTEGRATED LIFE SAFETY COMPLIANCE TESTING AND ITS PROCEDURES By: Mehrdad Ghods Integrated Engineering Student Sept. 06, 2002 University of British Columbia Vancouver, BC i PREFACE: The purpose of this

More information

startup. Construction of contractor entrance off University City Blvd connecting to Lot 8 has started.

startup. Construction of contractor entrance off University City Blvd connecting to Lot 8 has started. Campus Construction Situation Report #6 March 15, 2012 Hechenbleikner Lake Dam No change from previous notice Dewatering maintenance continues. Major construction activity will begin mid April and with

More information

Storm Water Basics for Construction Sites Presented by Representatives from the City of Grass Valley and Nevada County

Storm Water Basics for Construction Sites Presented by Representatives from the City of Grass Valley and Nevada County September 22nd, 2015 3:30PM Sign up at: www.stormwaterawareness.org Workshop is free! Nevada County Contractor s Association 149 Crown Point Ct. Grass Valley, CA 95945 Storm Water Basics for Construction

More information

BRAMPTON FLOWERTOWN SECONDARY PLAN Area 6

BRAMPTON FLOWERTOWN SECONDARY PLAN Area 6 BRAMPTON FLOWERTOWN SECONDARY PLAN Area 6 October 2018 EXPLANATORY NOTES Brampton Flowertown Secondary Plan Area 6 General i. Secondary plans form part of the Official Plan and are to be read in conjunction

More information

Melrose Fire Department

Melrose Fire Department Melrose Fire Department Office of Fire Prevention Re: 9/20/18 Guidelines for the Type and Placement of Smoke and Carbon Monoxide Alarms Purpose of this guide is to help homeowners protect their homes and

More information

A portion of the fire fighting personnel is continually rotated without a formal orientation regarding the unique characteristics of the island.

A portion of the fire fighting personnel is continually rotated without a formal orientation regarding the unique characteristics of the island. TO: Contra Costa County Grand Jury Report 0908 Surrounded by Water, Bethel Island Has Limited Access for Fighting Fires Inadequate funding leaves ECCFPD communities behind the rest of Contra Costa County

More information

COUNTY OF RIVERSIDE PLANNING DEPARTMENT STAFF REPORT

COUNTY OF RIVERSIDE PLANNING DEPARTMENT STAFF REPORT Agenda Item No.: 5.4 Area Map: Jurupa Zoning District: Prado-Mira Loma Supervisorial District: Second Project Planner: Christian Hinojosa Planning Commission: February 3, 2010 Conditional Use Permit No.

More information

Downtown Redevelopment Project Update

Downtown Redevelopment Project Update Downtown Redevelopment Project Update The redevelopment project will begin the week of September 4, 2017. It is anticipated that construction will be approximately 565 days, depending on weather. 7-6-18

More information

CONVENTION DATA SERVICES Technology Park Dr. Bourne, Massachusetts LANDSCAPE PLAN REV. LANDSCAPING L1.1

CONVENTION DATA SERVICES Technology Park Dr. Bourne, Massachusetts LANDSCAPE PLAN REV. LANDSCAPING L1.1 CONVENTION DATA SERVICES Technology Park Dr. Bourne, Massachusetts LANDSCAPE PLAN 1 09-08-16 REV. LANDSCAPING L1.1 CONVENTION DATA SERVICES Technology Park Dr. Bourne, Massachusetts DRAINAGE BASIN & RAIN

More information

City of Westbrook. 2 York Street Westbrook, Maine (207) Fax:

City of Westbrook. 2 York Street Westbrook, Maine (207) Fax: City of Westbrook DEPARTMENT OF PLANNING & CODE ENFORCEMENT 2 York Street Westbrook, Maine 04092 (207) 854-0638 Fax: 1-866-559-0642 WESTBROOK PLANNING BOARD TUESDAY, JANUARY 2, 2018, 7:00 P.M. WESTBROOK

More information

ELIGIBILITY CRITERIA CHECKLIST OPEN SPACE CLASSIFICATION

ELIGIBILITY CRITERIA CHECKLIST OPEN SPACE CLASSIFICATION THURSTON COUNTY DEVELOPMENT SERVICES OPEN SPACE TAX PROGRAM ELIGIBILITY CRITERIA CHECKLIST OPEN SPACE CLASSIFICATION Use this checklist to help you determine whether your property is eligible for open

More information

LTF&R FEBRUARY 2018 MONTHLY REPORT

LTF&R FEBRUARY 2018 MONTHLY REPORT LTF&R FEBRUARY 2018 MONTHLY REPORT Leland Township Fire & Rescue 203 Grand Avenue P.O. Box 578 Leland, MI 49654 (231) 256-7760 Monthly Report for February 2018 Total LTFR Responses in February 2018: 26

More information

LANDSCAPE AND IRRIGATION PLAN PREPARATION GUIDELINES

LANDSCAPE AND IRRIGATION PLAN PREPARATION GUIDELINES LANDSCAPE AND IRRIGATION PLAN PREPARATION GUIDELINES The Parks Planning and Development Division of the City of Modesto s Parks, Recreation and Neighborhoods Department is responsible for the task of reviewing

More information

Outdoor Mall Elmira Maple Syrup Festival 24 Church Street West Elmira, ON. N3B 2Z6

Outdoor Mall Elmira Maple Syrup Festival 24 Church Street West Elmira, ON. N3B 2Z6 Festival Day April 7, 2018 Outdoor Mall Elmira Maple Syrup Festival 24 Church Street West Elmira, ON. N3B 2Z6 Dear Vendor, As a reminder to all food vendors, we have attached a few information bulletins

More information

Heritage Management Plan

Heritage Management Plan Conrad Historic Site Heritage Management Plan This Management Plan represents the best efforts of the Carcross/Tagish First Nation and Yukon Governments to meet the requirements of the Carcross/Tagish

More information

Project phasing plan (if applicable) 12 copies of site plan

Project phasing plan (if applicable) 12 copies of site plan SITE PLAN REVIEW PERMIT APPLICATION City of Grand Haven, 11 N. Sixth Street, Grand Haven, MI 49417 Phone: (616) 847-3490 Fax: (616) 844-2051 Website: www.grandhaven.org 1. Project Information Address/location

More information

Red Hill Valley Project More Than A Road October 16, 2006

Red Hill Valley Project More Than A Road October 16, 2006 Red Hill Valley Project Presented By: More Than A Road October 16, 2006 September, 2007 Gerry Davis, C.M.A., Senior Director, Capital Planning and Implementation Division Public Works Department City of

More information

Checklists. Project Name: Location: File Number: Date of Submittal: Reviewer: Date: Applicant: Contact Name: Phone Number:

Checklists. Project Name: Location: File Number: Date of Submittal: Reviewer: Date: Applicant: Contact Name: Phone Number: Applicant: Contact Name: Phone Number: Email: Project Name: Location: File Number: Date of Submittal: Reviewer: Date: Concept Plan Requirements: I. General Project Information 1. Address or parcel number

More information

CITY OF CYPRESS 5275 Orange Avenue Cypress, California (714) DESIGN REVIEW COMMITTEE PERMIT PROCESS

CITY OF CYPRESS 5275 Orange Avenue Cypress, California (714) DESIGN REVIEW COMMITTEE PERMIT PROCESS CITY OF CYPRESS 5275 Orange Avenue Cypress, California 90630 (714) 229-6720 DESIGN REVIEW COMMITTEE PERMIT PROCESS 1. Discuss project with Planning staff to determine zoning regulations, any unusual characteristics

More information

RV Park/Campground Operator s Manual

RV Park/Campground Operator s Manual RV Park/Campground Operator s Manual Chapter 9 Principles For Designing A New RV Park/Campground The Region The Site (Land) / maps, conditions, climate, topography, drainage, site evaluation Facilities

More information

Plenty Gorge Park Draft Master Plan Consultation Report. Draft Master Plan April 2018

Plenty Gorge Park Draft Master Plan Consultation Report. Draft Master Plan April 2018 Plenty Gorge Park Draft Master Plan Consultation Report Draft Master Plan April 8 Introduction As part of the development of the Plenty Gorge Park Master Plan, Parks Victoria designed a consultation and

More information

FEDERAL ENERGY REGULATORY COMMISSION WASHINGTON, D.C

FEDERAL ENERGY REGULATORY COMMISSION WASHINGTON, D.C FEDERAL ENERGY REGULATORY COMMISSION WASHINGTON, D.C. 20426 OFFICE OF ENERGY PROJECTS August 10, 2018 In Reply Refer To: OEP/DG2E/Gas Branch 3 Mountain Valley Pipeline LLC CP16-10-000 Matthew Eggerding,

More information

Appendix D Fire Safety Requirements

Appendix D Fire Safety Requirements Appendix D Fire Safety Requirements SHASTA COUNTY FIRE DEPARTMENT MEMORANDUM DATE: May 22, 2008 BW TO: FROM: Russ Mull, Director Department of Resource Management Mike Chuchel Shasta County Fire Warden

More information

Posted by Calgary Public Library on November 1, 2012

Posted by Calgary Public Library on November 1, 2012 Call to Artists for Signal Hill Library Public Art Project Posted by Calgary Public Library on November 1, 2012 Eligibility This project is open to local and regional artists. Emerging and established

More information

11 CONTRACT AWARD FOR SECURITY SERVICES

11 CONTRACT AWARD FOR SECURITY SERVICES 11 CONTRACT AWARD FOR SECURITY SERVICES The Finance and Administration Committee recommends the adoption of the recommendations contained in the following report dated November 3, 2011, from the Commissioner

More information

By Only to

By  Only to Please refer to: Susan Rosenthal e-mail: susanr@dauieshowe.com direct line: 416.263.4518 File No. 701744 Lawyers The Fifth Floor 99 Spadina Ave Toronto, Ontario M5V 3P8 T 416.977.7088 F 416.977.8931 davieshowe.com

More information

Local Area Key Issues Paper No. 11: Extractive industry - Yandina Creek and Browns Creek Road

Local Area Key Issues Paper No. 11: Extractive industry - Yandina Creek and Browns Creek Road Draft Sunshine Coast Planning Scheme Review of Submissions Local Area Key Issues Paper No. 11: Extractive industry - Yandina Creek and Browns Creek Road Key Issue: No. of submissions: Sites identified

More information

TOWN OF BRUDERHEIM Report to the capital region board

TOWN OF BRUDERHEIM Report to the capital region board TOWN OF BRUDERHEIM Report to the capital region board Introduction to the Town of Bruderheim Municipal Development Plan amendment and Relation to the CRB Evaluation Criteria 02 march 2017 1 Introduction

More information

SUMMER VILLAGE OF SUNRISE BEACH

SUMMER VILLAGE OF SUNRISE BEACH SUMMER VILLAGE OF SUNRISE BEACH Municipal Development Plan Bylaw No. 132-13 ~ 2 ~ Summer Village of Sunrise Beach Municipal Development Plan 1 INTRODUCTION 1.1 SETTING The Summer Village of Sunrise Beach

More information

Norfolk Fire Department Fire Prevention & Information

Norfolk Fire Department Fire Prevention & Information Norfolk Fire Department Fire Prevention & Information For Permits and Inspections Contact (508)528-3207 EFFECTIVE JANUARY 1, 2015, THE NORFOLK FIRE DEPARTMENT, BY STATE REGULATIONS, NO LONGER ISSUES PERMITS

More information

Portland International Airport Storm Water Master Plan April 6, 2016

Portland International Airport Storm Water Master Plan April 6, 2016 Portland International Airport Storm Water Master Plan April 6, 2016 Susan Aha Senior Manager, Water Resources Brian Freeman Manager, Civil Engineering 1 Presentation Overview Why is storm water important

More information

Daylight Energy Ltd. Well Blowout W5M March 4, 2011

Daylight Energy Ltd. Well Blowout W5M March 4, 2011 Daylight Energy Ltd. Well Blowout 10-31-046-10W5M March 4, 2011 ERCB Investigation Report August 12, 2011 ENERGY RESOURCES CONSERVATION BOARD ERCB Investigation Report: Daylight Energy Ltd., Well Blowout,

More information

Caler Cove Lobster Company

Caler Cove Lobster Company File No.: 199800920 City and State: Addison, ME Caler Cove Lobster Company General Impacts: 0.17 acre tidal emergent Functions and Values Lost: Production Export Nutrient Exchange Sediment Filtration Fishery

More information

Using the Updated RI Soil Erosion and Sediment Control Handbook. The Introductory Workshop for RIDEM/CRMC Staff January 23, 2015

Using the Updated RI Soil Erosion and Sediment Control Handbook. The Introductory Workshop for RIDEM/CRMC Staff January 23, 2015 Using the Updated RI Soil Erosion and Sediment Control Handbook The Introductory Workshop for RIDEM/CRMC Staff January 23, 2015 URI Cooperative Extension NEMO URI Cooperative Extension NEMO White Oak,

More information

December 13, 2005 Meeting Status of NPDES Post Fire BMPs

December 13, 2005 Meeting Status of NPDES Post Fire BMPs December 13, 2005 Meeting Status of NPDES Post Fire BMPs Agenda Overview of Current Operations At SSFL Impacts of Fire At SSFL Rebuilding & Improvement of BMPs Future Activities Site Tour Close-out 1 Santa

More information

INSPECTION REPORT Nr IDD/S-09/922

INSPECTION REPORT Nr IDD/S-09/922 Page: 1/7 PROJECT: TPI For Sheet Pile BV Client: Manufacturer: Nanjing Grand Steel Piling Co., Ltd. Inspection requested by: Ref: P/o nr: (client to BV) P/o nr: GP09111101 (client to Manufacturer) SUPPLY

More information

Project 6 All-Season Road Linking Manto Sipi Cree Nation, Bunibonibee Cree Nation & God s Lake First Nation

Project 6 All-Season Road Linking Manto Sipi Cree Nation, Bunibonibee Cree Nation & God s Lake First Nation Project 6 All-Season Road Linking Manto Sipi Cree Nation, Bunibonibee Cree Nation & God s Lake First Nation The Environmental Assessment - Presentation to Bunibonibee Cree Nation December 8, 2016 Why are

More information

SUBCHAPTER 6L - BARBER SHOPS

SUBCHAPTER 6L - BARBER SHOPS SUBCHAPTER 6L - BARBER SHOPS 21 NCAC 06L.0101 RESIDENTIAL BUILDING Authority G.S. 86A-25; Repealed Eff. February 8, 1978. 21 NCAC 06L.0102 MEASUREMENTS OF BARBER SHOP (a) Each barber shop shall be a minimum

More information

Town and Country Planning (Local Planning) (England) Regulations 2012, Regulation 22 Submission of Legacy Corporation Local Plan

Town and Country Planning (Local Planning) (England) Regulations 2012, Regulation 22 Submission of Legacy Corporation Local Plan Level 10, 1 Stratford Place Montfichet Road London E20 1EJ Tel: +44 (0) 20 3288 8821 Fax: +44 (0) 20 3288 1851 alex.savine@londonlegacy.co.uk Stuart Liddington The Planning Inspectorate 3/12 Kite Wing

More information

Fixed plant and mobile equipment fires on surface coal mines

Fixed plant and mobile equipment fires on surface coal mines Fixed plant and mobile equipment fires on surface coal mines Mines safety bulletin no. 158 21 November 2016 Version 1 Background Fires on fixed plant and mobile equipment at mines and quarries continue

More information