Specifications for Data Network Physical Infrastructure. Version 3.01

Size: px
Start display at page:

Download "Specifications for Data Network Physical Infrastructure. Version 3.01"

Transcription

1 Specifications for Data Network Physical Infrastructure Version th July 2018

2 CONTENTS 1 CONTENTS 1 Contents General Introduction and Scope Document Location Document Version Control Decision Points & Exceptions Recommended Product Models ISS Network Contacts Installation Standards Permit to Work Cable Testing and Acceptance Procedure Communications (Comms) Rooms Definition & Use Planning & Design Location Size Security Finishes Lighting Power UPS Power Distribution Earthing Environmental Acoustics Cabinets Optical Fibre Cables General Points Connection of Buildings to the Campus Fibre Network Internal Building Fibres Ductwork

3 CONTENTS 4.5 Labelling Fire Alarm Fibres Testing and Acceptance Procedure CAT6 Cabling Numbers of Data Lines in New Buildings And Refurbishments Structured Cabling Systems Patch Panels Data Points Installation Cable Containment Labelling Data Points for Wi-Fi Access Points Testing and Acceptance Procedure CW1308 Copper Cable Installation Labelling Testing and Acceptance procedure

4 GENERAL 2 GENERAL 2.1 INTRODUCTION AND SCOPE This document is to assist those planning and/or undertaking the installation of IT network physical infrastructure at Lancaster University. This may be as part of a new building or refurbishment project, or smaller additions or changes to existing infrastructure, such as the installation of additional data lines. IT data network physical infrastructure here means Fibre-optic cables and their containment Structured copper cabling, i.e. CAT6 and CW1308, and its containment Communications ( Comms ) rooms including equipment racks, power, cooling, frames etc. This document is a specification and not a design, the design team(s) for the project must translate these specifications into a final design for written approval by ISS Network Contacts. This document does not specify the characteristics of active (powered) network equipment such as switches, routers, or Wi-Fi access points. It does specify passive infrastructure. This document does not specify network service characteristics, such as data network speeds, throughput capacities, Wi-Fi frequencies or signal strengths. 2.2 DOCUMENT LOCATION The most recent version of this document can always be found at DOCUMENT VERSION CONTROL Upon each revision of this document, it will be issued to the appropriate staff in the Professional Services division. It is the responsibility of each design team to ensure that they are using the most recent revision of the document. With respect to major building and refurbishment projects, if a new revision is released prior to tender stage, then it is expected that the design shall be modified to take account of the most recent specification. Any changes post-tender stage shall only be required following a change control request from ISS. 2.4 DECISION POINTS & EXCEPTIONS This document states the minimum requirements from ISS, all key design decision points must be discussed and accepted by ISS Network Contacts (see below). Where requirements within this document must be confirmed and agreed with ISS Network Contacts, these are marked with a symbol. However, if there is any lack of certainty regarding anything within 4

5 GENERAL this document, or relating to the network infrastructure installations in general, please contact one of the ISS Network Contacts. Should the Contractor identify any discrepancies between this specification and any design package, this shall immediately be drawn to the attention of ISS Network Contacts. For the purpose of any pricing, the Contractor shall allow for the most onerous services installation to meet the requirements. Any deviations of proposed design from the specifications in this document must be agreed in writing by ISS Network Contacts. 2.5 RECOMMENDED PRODUCT MODELS Where a recommended model is specified within the text of this document it is made either on the basis of a technical evaluation or procurement exercise. Any substitutions for the recommended models must be approved in writing by ISS Network Contacts. 2.6 ISS NETWORK CONTACTS Contact must be made with ISS early in the project planning process. ISS want to help all parties achieve successful, timely and high-quality project completion and will assist in any way possible. Where agreements and/or decisions need to be made with the ISS Network Contacts as specified within this document, this means initially the Site & Contractor Liaison staff as shown below, if unavailable the Escalation staff should be contacted Site & Contractor Liaison Paul Boyd Senior Network Specialist p.boyd@lancaster.ac.uk Richard du Feu Senior Network Specialist r.dufeu@lancaster.ac.uk Escalation Craig Macdonald Head of Networking c.macdonald@lancaster.ac.uk Mark Jameson Head of Technical Infrastructure m.jameson@lancaster.ac.uk 2.7 INSTALLATION STANDARDS All components must be installed, as a minimum, to the manufacturer s recommended standards. Where the ISS Specification(s) have a more stringent installation standard then they will take precedence over those of the manufacturer. 5

6 GENERAL 2.8 PERMIT TO WORK Lancaster University Facilities operates a Site Access Pass arrangement which must be completed prior to any works taking place on Campus, if the works are required to run within Plant Rooms, Service Risers or in close proximity to other services a Permit to Work is required. The only exception to this is in areas of campus temporarily under the control of external contractors during building works. In that case the appropriate valid permissions and permits to work must sought from the external building contractor in control of the area concerned and any induction they may deem necessary. Site Access & Permit to Works can be arranged by contacting the following: Site Access & Permit to Work Arrangements Simon Corless or Electrical Engineer s.corless@lancaster.ac.uk Andrew Newsham Electrical Maintenance Supervisor a.newsham@lancaster.ac.uk 2.9 CABLE TESTING AND ACCEPTANCE PROCEDURE In order for data cable installations to be accepted by ISS, three stages must be completed. See later sections for specific testing requirements. 1. On completion of installation, the contractor tests the data cable installations. 2. Contractor sends test results to ISS Network Contacts. 3. Witness testing of data lines by ISS Network Contacts. 6

7 3 COMMUNICATIONS (COMMS) ROOMS COMMUNICATIONS (COMMS) ROOMS 3.1 DEFINITION & USE Comms rooms are sometimes referred to as wiring closets or Premises Wire Distribution rooms. The specification below will clarify why we refer to rooms rather than closets. A comms room forms the termination point of structured copper cabling within a building, and may also contain fibre links to the main data centres on campus. The comms room must only be used for the housing of ISS Networking equipment used to support the delivery of network services to the building. For the avoidance of doubt this excludes anything not in the list below unless approved in writing from ISS Network Contacts; Data Cabinets CAT6 Cabling CAT6 Patch Panels Fibre Cabling Fibre Patch Panels UPS Data Switches CW1308 Cabling Voice Panels 3.2 PLANNING & DESIGN It is acknowledged that indicative sizes and locations of comms rooms are required in early-stage building design. However, the detailed requirements of comms rooms are generally finalised in later design stages, based on other information not available earlier (such as numbers of data lines). 3.3 LOCATION The comms room must be located so that the maximum electrical length of data lines emanating from it do not exceed 90.0 metres. It is strongly preferred that the number of comms rooms within a building is minimised. Where more than one comms room is required in a building, one room will be designated by ISS Network Contacts as the primary comms and the others as secondary. HALO fibre, which connects the building to the main campus datacentres, must be terminated in the primary comms room. All comms rooms within a building must be located so that they are accessed from a corridor or public space. It must not be necessary to access another space such as an office, meeting room or plant room in order to access the comms room, equally, access to other spaces must not be via the comms room. 3.4 SIZE The size of the comms room is a function of the number of lines that will be fed back to the room in the finished building. Each cabinet can house a maximum of 384 data lines. One additional cabinet footprint is required for future expansion. The cabinets in use are 800mm wide x 1000mm deep so by knowing the number of data lines to be installed, the minimum size of the comms room can be calculated. Example: 7

8 COMMUNICATIONS (COMMS) ROOMS 1000 datalines 384 = 2.6 = 3 cabinets required + 1 footprint 5250mm 1000mm 3000mm 1000mm Cabinet A Cabinet B Cabinet C 1000mm 1000mm The clearances in the drawing above must be clear space within the room; any protrusions into the room must be deducted from the available space. The door opening and delivery route to the room must be sized to allow the delivery of an 800 mm wide x 2.2 metre high cabinet. The loading of racks into the comms room should commence at the footprint furthest from the door opening. Cabinet A must be the left hand most cabinet when viewed from in front of the cabinet doors. 3.5 SECURITY The comms room must be fitted with a Grovsenor/Janus IDCe access control system (please refer to the ISS Access Control Specifications for full details). The IDCe must be located within the comms room. The comms room must be fitted with an Abloy EL560 lock mechanism configured to fail secure, no fire alarm interlink is required. A uniquely numbered lock barrel from the ISS Comms room suite must be fitted within the EL560 with internal thumb screw. Two keys must be supplied with each lock. There must be no vision panel fitted to the door. The room must be fitted with at least one heat/smoke detector connected to the main building fire alarm system. The door must only be labelled with room number and not specific function. 3.6 FINISHES Walls must be painted white or cream. Floors must be low dust, anti-static. Carpets will not be accepted. Where a raised floor is in use, prefinished vinyl tiles must be installed. 8

9 COMMUNICATIONS (COMMS) ROOMS 3.7 LIGHTING The room must be provided with high-temperature fluorescent or LED strip lighting to provide 500lux at floor level. Fittings must be positioned parallel to the front and rear of the racks so as to provide good working illumination front and rear of the racks. All light fittings must be installed below any high-level containment, ductwork or other installations so as to avoid shadows. If the lights are controlled by motion sensors the number and position should be such that full room coverage is provided for a single person working at any position or elevation within the room. The minimum number of sensors to provide coverage is 4. The preferred option is manual light switches which must be located adjacent to the entry door; they must not be located to the hinge side of the door opening. Emergency lighting must be provided within the room. 3.8 POWER Cabinet power must be supplied from a building UPS located externally to the comms room. The UPS must be resilient in nature providing 4KVA per occupied or potentially occupied cabinet position. Run time must be a minimum of 30 minutes at full load. Each cabinet footprint must be provided with 2no 16A commando sockets to BSEN each on dedicated circuits, to be protected by 2no 16A Type C MCBs. One commando socket must be fed from the building UPS and the other of the pair must be fed direct from mains (to protect against UPS failure). Each pair of sockets feeding a single cabinet must be fed by a readily accessible 4-pole rotary isolator switch providing simultaneous isolation to both sockets. The isolator switch is to be located on the wall immediately behind each cabinet. The commando sockets must be supplied from a distribution board within the comms room. It is preferred that sockets are located at high-level above the rear of each cabinet and not obstructed by basket, tray work or other services. In addition to the commando sockets, 4no general sockets should be provided to the perimeter of the room to provide general power; these must be provided on a dedicated ring for the comms room from the general building supply. 3.9 UPS If a building UPS is not supplied, then each cabinet must be supplied with a UPS. The requirements are as follows: Capacity of 3300VA On-line, double conversion At least 30 mins runtime at 1000W load 2 C13, 1 C19 Outlets Fitted with a SNMP Management card providing temperature and humidity monitoring. 9

10 The batteries, as supplied must be less than 6 months from date of manufacture. COMMUNICATIONS (COMMS) ROOMS The UPS supply lead must be fitted with a 16A commando plug. The UPS must be installed into the cabinet and connected to one of the provided 16A sockets. The current model recommended by ISS is the Eaton 9PX 3000W RT3U (tower/rack 3U short depth) Part Number 9PX3000IRT3U, must be supplied with Network-MS card POWER DISTRIBUTION Each cabinet must be provided with two power distribution units (PDU). Each PDU must provide 18 C13 and 2 C19 outlets and provide an IP-enabled power meter. The PDU should be zero-u vertically mounted. The current model recommended by ISS is an Eaton EMIB09. Where a UPS is provided within the rack in the comms room, one PDU must be fed from the UPS and the other directly from the mains using the 16A commando socket above the rack. Where the comms room is supplied via a building UPS, then both PDUs must be fed from the 16A commando socket above the rack EARTHING Adjacent to each pair of 16A commando outlets a copper earth bonding bar with a minimum of 4 unused M8 hex-headed bolt attachment points must be provided. Each earth bar must be individually bonded back to the local distribution board with 10mm 2 cable ENVIRONMENTAL Where a building UPS is supplied the comms room environmental conditions must be maintained between 14 C and a maximum 35 C with a humidity range of 15% to 95% non-condensing. Any external ventilation must be filtered to prevent particulate ingress. Passive systems for cooling are preferred. The design of such cooling should be made with discussion and approval from ISS Network Contacts. Where a building UPS cannot be supplied the room will house UPS s containing sealed lead-acid batteries which require controlled environmental conditions and so must be controlled to a minimum temperature of 18 C and a maximum of 24.0 C with a humidity range of 15% % non-condensing. The anticipated heat load per cabinet is estimated to be 2kW. Where UPSs within the comms room are provided duty-only air-conditioning must also be provided ACOUSTICS The room will house equipment which will emit noise. Coordination is required within the design team to mitigate the transference of this noise to surrounding areas. As a guide, the following equipment will be installed within the room: 10

11 Equipment Qty Noise Output (each) Edge Switch 8 per cabinet 53.5 dba Aggregation Switch 2 per comms 58dBA UPS 1 per cabinet 53dBA COMMUNICATIONS (COMMS) ROOMS 3.14 CABINETS Cabinets installed must be Rittal TS IT Cabinet, 800mm wide x 1000mm deep x 42U high with 78% perforated wardrobe doors front and rear with non-self-locking locks. The cabinet must be supplied with the internal earth bonding kit and bar. Cabinets must be installed in a line and bayed together with a divider panel between each cabinet. Side panels at the end of the row must be fitted. All components of the cabinet including doors, rails and side panels must be earth bonded in accordance with the manufacturer s instructions. Each cabinet must be individually earth bonded to the appropriate earth bar (see section 3.11) using 6mm 2 cable. The front pair of rack rails must be positioned to provide 120mm of clearance between the face of the rails and the face of the closed cabinet door. An example cabinet layout is shown on the following page. Individual cabinet layouts must be discussed and agreed with ISS during the detailed design and construction phase. If the last rack to be populated is going to be more than 50% full by the completion of the building project, then an additional rack must be installed in the spare expansion footprint, along with appropriate baying and cable basket. 11

12 COMMUNICATIONS (COMMS) ROOMS U SpliceUK Chassis Horizontal Cable Management 9 24 Port Voice Panel 10 Horizontal Cable Management Port CAT6 Panel PP Port CAT6 Panel PP15 13 Space for 48 port switch Port CAT6 Panel PP Port CAT6 Panel PP13 16 Space for 48 port switch Port CAT6 Panel PP Port CAT6 Panel PP11 19 Space for 48 port switch Port CAT6 Panel PP Port CAT6 Panel PP9 22 Space for 48 port switch Port CAT6 Panel PP Port CAT6 Panel PP7 25 Space for 48 port switch Port CAT6 Panel PP Port CAT6 Panel PP5 28 Space for 48 port switch Port CAT6 Panel PP Port CAT6 Panel PP3 31 Space for 48 port switch Port CAT6 Panel PP Port CAT6 Panel PP1 34 Space for 48 port switch Space for 48 port switch Port Voice Panel UPS

13 4 OPTICAL FIBRE CABLES LANCASTER UNIVERSITY DATA NETWORK PHYSICAL INFRASTRUCTURE SPECIFICATIONS OPTICAL FIBRE CABLES 4.1 GENERAL POINTS Bespoke Fibre Solutions Some projects will require bespoke fibre solutions that may deviate from this specification; check with ISS Network Contacts early on in the project Containment All fibre must be installed into its own dedicated containment. 4.2 CONNECTION OF BUILDINGS TO THE CAMPUS FIBRE NETWORK The Lancaster University campus has a network of duct containing fibre that runs around the perimeter road known as the Halo. Depending on the size, location and purpose of the building, a building may require to be connected to the Halo. Alternatively, the building may connect to an adjacent building that is already connected to the Halo. The decision concerning which of these two options is chosen needs to be taken in early stage discussions with ISS Network Contacts so that appropriate designs can be produced for duct routes into the building Option 1 Direct Connection to Campus Halo Fibre The building will need ductwork that connects to the Halo ductwork (see Ductwork, Main Duct & Subduct sections below). Fibre must then be run to the following locations: Faraday Building LA31 ISS Building B18 As a minimum, the fibre installed must be a hybrid, 96 core OS1 G.652, 24 core OM2 loose tube, 12f per tube internal/external grade cable. The current cable recommended by ISS is Brand Rex HF(96x008+24x050)S120WLU. Final fibre count must be agreed with ISS Network Contacts. One cable will be routed in a clockwise direction around the Halo to get to its destination location; the other will go anti-clockwise. Routes and subduct allocations will be advised by ISS Network Contacts Termination Termination of the fibre must be performed by fusion splicing onto factory-made 600µm LC pigtails. In the Faraday and ISS building locations, the fibre will be terminated into pre-existing Optical Distribution frames (ODF). The contractor must supply an appropriate number of SpliceUK 24f LC splicing cassettes to install into the ODF, (note: cassettes are ordered in right and left-handed orientation. The space allocated for the project in the ODF must be confirmed by ISS Network Contacts so that the correct cassettes can be specified) In the building comms room, a SpliceUK 6U chassis must be installed to terminate the fibre along with an appropriate quantity of 24f LC cassettes. 13

14 OPTICAL FIBRE CABLES Option 2 Link to Adjacent Building The building will connect to an adjacent building specified by ISS (note: this option will only be used for small buildings where a Halo connection is not appropriate). Blown fibre microduct must be installed between the building comms room and an existing comms room in another building identified by ISS. The microduct to be installed is Emtelle FibreFlow 24 LFH x 5/3.5mm tubes (part codes 6513, 6612, 6612L as appropriate for the distance) between the 2 locations. The FibreFlow bundle must be terminated into a suitable enclosure mounted on the wall of the comms rooms, and the required number of individual fibre bundles extended from the enclosure to the fibre tray chassis within the racks using SpiceUK f-tube. The microduct must then be populated with 24f OM4 and 24f G652d fibre as a minimum, but the final fibre count must be agreed with ISS Network Contacts. In the new comms room, a 3U SpliceUK chassis with an appropriate number of 24f LC cassettes must be installed. In the existing comms room, it may be possible to utilise an existing SpliceUK chassis only requiring to provide an appropriate number of 24f LC cassettes, or if insufficient space is available then a new 3U SpliceUK chassis will be required. Termination of the fibre must be performed by fusion splicing onto factory-made 600µm LC pigtails. 4.3 INTERNAL BUILDING FIBRES Where there is more than one comms room within a building, one shall be designated by ISS Network Contacts as primary and the others secondary. Normally, the primary comms will be connected to the Halo (either directly using option 1 or indirectly using option 2 above), then the secondary comms room will connect to the primary comms room using the Emtelle FibreFlow system as described in 4.3 (Option 2) above. In some cases, ISS Network Contacts may request that two comms rooms receive their own separate diverse connections to the Halo. 4.4 DUCTWORK Where the building is required to connect to the Halo infrastructure, then new ductwork will be required, this will comprise of main duct and associated subduct Main Duct The Halo infrastructure runs around the perimeter road and down selected avenues on Campus. ISS Network Contacts will identify an appropriate interconnection point on the Halo for the building to link to. A new section consisting of 2no main ducts will be required from the building to the nominated connection point, this must include any required turning or pulling chambers. The duct provided must be suitable for subducting so care must be taken at any point of change of direction to ensure that the minimum bend radius of the subduct can be satisfied. 14

15 OPTICAL FIBRE CABLES The main duct used in the Halo is Emtelle Solidwall upvc duct 96.5 outside diameter, 90mm inside diameter, colour green. The bends used on this ductwork must be suitable for 4-way subducting, the sharpest bends used must be 22.5 over a length of 700mm, so that the minimum bend radius for the subduct is not exceeded. Only full length proprietary bends suitable for use as part of the ductwork system will be acceptable i.e. used as supplied and not cut or modified. Any ductwork installed must be brushed, and then tested with a dumbbell mandrel with a diameter of 7% less than the main duct inner diameter immediately following installation and prior to subducting. This process must be made available for witness testing by ISS. Any main duct not subducted must be provided with a draw rope. The Halo duct systems, either existing or installed as part of a project are only to be used to carry ISS fibre infrastructure Subduct One of the two main ducts installed to the building must be subducted with 4-way subduct. The subduct used in the Halo is Emtelle 32mm outside diameter, 27mm inside diameter in colours; orange, green, blue, black. Each subduct must be provided with a draw rope. Once installed, all subduct sections must be coupled-through with aluminium (not plastic) screw-on couplers. The part number of the Emtelle aluminium screw-on couplers is 3650M.Unused subducts must be capped. The lowest free main duct must always be subducted first. Any subduct installed must be tested with a dumbbell mandrel with a diameter of 7% less than the subduct inner diameter immediately following installation. This process must be made available for witness testing by ISS Network Contacts. It may be necessary for the project to subduct a section of the main Halo; this requirement must be discussed and agreed with ISS Network Contacts early in project design Access Chambers Any chambers used for pulling or turning must be standard BT F4, F6, or F10 or their carriageway equivalent. Chambers must be constructed of in-situ poured concrete. Pre-cast or plastic chambers are not acceptable. Chamber frames and lids appropriate to the expected traffic loading must be fitted. All duct entries into chambers must be either cast or core-drilled in. Ducts must enter chambers at right angles to the wall. Care should be taken when selecting entry and exit points to a chamber to ensure the minimum bend radius of the subduct within the chamber can be satisfied. A minimum of 100mm clearance must exist between the bottom of the lowest duct and the finished chamber floor. 15

16 OPTICAL FIBRE CABLES When it is necessary to create a chamber onto an existing section of the Halo Infrastructure, it must only be done when that route is agreed with ISS. The works to create that chamber must be coordinated with, and performed by, a contractor approved by ISS to ensure minimal risk to the live services contained within the existing ducts. Chamber plans can be found on the following pages. 16

17 F4 Access Chamber LANCASTER UNIVERSITY DATA NETWORK PHYSICAL INFRASTRUCTURE SPECIFICATIONS OPTICAL FIBRE CABLES 17

18 F6 Access Chamber LANCASTER UNIVERSITY DATA NETWORK PHYSICAL INFRASTRUCTURE SPECIFICATIONS OPTICAL FIBRE CABLES 18

19 F10 Access Chamber LANCASTER UNIVERSITY DATA NETWORK PHYSICAL INFRASTRUCTURE SPECIFICATIONS OPTICAL FIBRE CABLES 19

20 OPTICAL FIBRE CABLES 4.5 LABELLING Where the fibre/microduct/sub-duct passes through a barrier or riser opening, and immediately prior to entry into the ODF, the fibre/sub-duct must be clearly labelled with the A and B end of the fibre with an engraved traffolyte label. This must be black text on yellow background and comply with regulations BS EN for all labels: The splice cassettes in both comms room chassis and Datacentre ODF must be labelled with the source of the fibre and the fibre numbers contained within they tray, fibre numbers must always count-up starting at the rear of the tray: 4.6 FIRE ALARM FIBRES A SpliceUK 2-tube f-tube microduct must be installed from the comms room to the main Gent Vigilon fire alarm panel to allow it to be linked to the fibre network. This must be populated with 8f OM2 fibres. In the comms room, there may be capacity in the newly installed chassis to accommodate a 24f LC tray to terminate the fibre onto; otherwise a new SpliceUK chassis will be required. At the fire alarm end, an appropriate proprietary housing must be used to allow patch leads of a length no longer than 3 metres to be routed to the fire alarm panel. This item will require close coordination with the ISS Network Contacts and all other interested parties so as to meet aesthetic requirements of the building entrance whilst maintaining easy access for future maintainability. The current recommended termination panel to be used inside the proprietary housing adjacent to the Fire Alarm panel is the Optibox4 by Huber & Suhner. 4.7 TESTING AND ACCEPTANCE PROCEDURE In order for fibre optic cables lines to be accepted by ISS, three stages must be completed, with details below: Contractor tests the fibre optic cables Contractor sends test results to ISS Network Contacts Witness testing of fibre optic cables by ISS Network Contacts if required Contractor tests the fibre optic cables Newly installed and spliced optical fibre cable must be fully tested using calibrated test equipment. 20

21 OPTICAL FIBRE CABLES Each individual fibre must be tested with both an OTDR and calibrated light source/power meter (ILM). Testing of each individual fibre must be carried out from both ends of the fibre. For OTDR testing where the fibre length is less than 3km in length the pulse width used for testing must be 3ns or less. High quality fibre patch leads of the correct modal type must be used for all testing, the connectors of which must be cleaned before each insertion with a one-click fibre cleaner. During OTDR testing high quality launch and receive leads of the correct modal type must be used at the appropriate ends of the fibre under test. The connectors on these leads must be cleaned prior to each insertion with a one-click fibre cleaner. Multi mode fibre must be tested at both of 850nm 1300nm. Single mode fibre must be tested at both 1310nm 1550nm. The tabulated results must be presented in a common spreadsheet format and must include as a minimum: Serial number of testers used. Fibre type. Number of connectors. (Normally 2) Number of splices. (Normally 2) Fibre length km (from OTDR measurement). Manufacturers quoted loss figures for each of the test wavelengths as detailed above, db/km. For each wavelength, loss budget for fibre under test (total allowed connector loss + total allowed splice loss+ (measured length in km * manufacturers quoted loss figures for each of the test wavelengths as detailed above, db/km)) For each fibre and each wavelength. Fibre identification (fibre number and type (sm or mm)). ILM loss direction A ILM loss direction B ILM average of loss in direction A and direction B ILM headroom (ILM budget average ILM) Loss at each connector and at each splice from direction A Loss at each connector and at each splice from direction B For each connector loss, the mean average loss in both directions For each splice loss, the mean average loss in both directions Additionally, the OTDR traces must be provided Test Limits At all times the maximum individual splice loss must be less than or equal to 0.250dB. At all times individual connector loss must be less than or equal to 0.50dB and must be repeatable across multiple remove insert cycles. Return loss for single mode connections must be greater than or equal to 26.0dB with a mean average value of 50.0dB. 21

22 OPTICAL FIBRE CABLES Return loss for multi-mode connections must be greater than or equal to 20.0dB with an mean average value of 30.0dB Return loss per splice must be greater than or equal to 40.0dB Contractor sends test results to ISS Network Contacts The results are to be tabulated (example spreadsheet linked below) and supplied to ISS Network Contacts prior to witness testing. Test results, along with in-date calibration certificates, must be ed to A copy of the in-date calibration certificates for each piece of test equipment used must be supplied with the test results. The calibration must have been performed by a manufacturer-approved calibration centre. Test results will not be accepted without an in-date calibration certificate. An example sheet of test results is available at Witness testing by ISS Network Contacts The contractor should be prepared to undertake 100% witness testing of installed lines. Any reduction in this will be at the discretion of ISS Network Contacts. If ISS deem witness testing to be necessary, the contractor will be informed and requested to attend for the witness testing within 2 working days. A time and date will be agreed during this contact. The contractor must supply at least 2 staff to perform witness testing which will be observed by ISS staff. The testing must be undertaken with the contractors test equipment which, whilst it does not have to be the same set used for the original tests, must be in calibration and supplied with valid calibration certificates. 22

23 5 CAT6 CABLING LANCASTER UNIVERSITY DATA NETWORK PHYSICAL INFRASTRUCTURE SPECIFICATIONS CAT6 CABLING The campus standard for data cabling is CAT6, any additional lines or relocations must be CAT6 regardless of any other cabling systems or standards in place. This includes additional telephone sockets, these must now be presented as a CAT6 line with associated RJ45 BT adaptor; no additional BT-style sockets are to be installed. All cabling systems in use must conform to and follow EN : NUMBERS OF DATA LINES IN NEW BUILDINGS AND REFURBISHMENTS ISS Network Contacts must be informed by the project manager of the projected total number of data lines terminating in each comms room, as soon as the number has been finalised, and must be kept updated with any changes throughout the project. Gathering requirements for data line numbers and positions Equipment Requiring Network Connection Printers Wi-Fi Access Points PCs, phones and audio-visual equipment in lecture theatres, seminar/meeting rooms, public spaces. Telephones for general or emergency (not individual) use. PCs and telephones in staff offices Open access PCs and PC labs. BMS equipment Lab/research equipment Who Supplies Requirement ISS Faculty IT Contacts ISS Network Contacts Will annotate a floor plan with positions of data points for Wi-Fi. ISS Faculty IT Contacts and Building users Building users Building users; though ISS network team advises and encourages 2 data lines per occupant of an office or open-plan area. ISS Faculty IT Contacts Facilities/M&E Contractor Building users 5.2 STRUCTURED CABLING SYSTEMS ISS have performed an evaluation and have selected the following cabling systems, which must be used for any data line installation. The components installed must be part of a single-manufacturer system and must be installed by an approved installer for that manufacturer Patch Panels Hellermann Tyton GSTPP-1U24RS Panel GSTJC6U-BK Jack Brand-Rex MMCPNLX24SIJ2MIL Panel C6CJAKU002 Jack 23

24 CAT6 CABLING CAT6 Cable Hellermann Tyton Category 6 U/UTP Unshielded Cable CCA Brand-Rex C6UR-Cca-RIB-305GN Data Points and Faceplates Hellermann Tyton GigaBand CAT6 Single EuroModule AS08IDCNGB/WH Single Gang Alpha Snap Bevelled Faceplate - ASFP01 Alpha Snap Half Blank (Full Module) - AS050 6C 45 Degree 6c CAT6 Outlet - 6C-ANG-C6/WH - 6c form factor for floor boxes Brand-Rex C6CJAKU002 Jack MMCWDOUNI030 Faceplate MMCWDOUNI062 25mm * 50mm shuttered module. MMCWDOUNI042 25mm * 50mm blank MMCWDO06C001 25mm * 38mm angled floor box shuttered module. MMCBLK06C3 25mm * 38mm blank 6c form factor for floor boxes Cabinet Layout Cabinets will be laid out as shown in section Panels must always be installed beginning at the bottom of the cabinet. Contractors must submit detailed cabinet layouts to ISS Network Contacts for written approval prior to the commencement of installation 5.3 PATCH PANELS The patch panels must be one of the listed models in section 5.2 Structured Cabling Systems. Data lines must be terminated to TIA568B standard (fig2), using a cabling system manufacturerapproved tool for the type of panel in use. 24

25 CAT6 CABLING Lines are to be grouped on the patch panels according to the area in the building to which they run, i.e. all lines to room a together, all lines to room b together etc. For each 24 data lines, 1 patch panel will be required. Patch panels must be fully occupied before starting terminations on the next panel up, i.e. no unterminated (empty) ports. No more than 8 lines feeding Wi-Fi data points are to be installed in each pair of adjacent 24 port patch panels. Check with ISS Network Contacts if there is a problem. Patch panels must be laid-out as shown in section 3.12 unless a variation is instructed in writing from ISS. Patch panels must be attached to the rack rails using all metal cage nuts with M6 thread PZ3 machine screws. Washers must NOT be used. A cage nut and bolt must be fitted for each corresponding mounting hole in the patch panel. Patch panels must be correctly aligned within rack U boundaries; they must not cross U boundaries. 5.4 DATA POINTS Where not fully populated the unused module positions must be fitted with half-width (one module) blanking covers. Wiring must be arranged so that expansion to the full capacity of the face plate is not restricted. Self-closing shutters on data point modules must be checked as part of the installation/testing procedure. Any modules with sticking shutters must be replaced and the line re-tested before witness testing. Sufficient depth must be allowed behind the module to prevent crushing or over-bending of the cable as the faceplate is installed. Care must be taken to ensure that the faceplate fixing screws do not impinge upon the cable. The cable must enter the back box or floor box from a direction that minimises cable bending. 25

26 CAT6 CABLING 5.5 INSTALLATION All fixed wiring between patch panel and room outlet must be installed to TIA/EIA568-B.2-1 CAT6 standard. All cable installed must be as per section 5.2 Structured Cabling Systems above. In accordance with CAT6 specification the maximum electrical length of cable between patch panel and data point is 90.0m. During installation the manufacturer s minimum bend radius must be adhered to. The manufacturer s specifications as to whether the cable can be installed by pulling or laying must be followed. Where the manufacturer specifies the cable is suitable for pulling the manufacturer s pulling tension must be adhered to. Where additional cables are to be fitted to an existing patch panel the new cables must be loomed with and follow the route of any existing cables. As the new cables are installed any existing cable fasteners must be removed and replaced by new to prevent the embedding of multiple fasteners within cable bundles. All cable fasteners must be fitted so as not to crush the outer jacket of the cable. All cable ties must have any excess length removed by cutting flush to the body of the ratchet mechanism leaving no sharp edges exposed (see figure 2 below): Figure 2 Within equipment cabinets, cables must be loomed together in groups of 24, all 24 cables must be associated with the same 24 port patch panel. Throughout the horizontal sections of cable routes the cables must be loose-laid. Cable bundles must leave the patch panel in the horizontal plane and be routed through the cabinet so as not to encroach into any equipment space. 26

27 CAT6 CABLING Cable bundles must not me covered with cable sock or similar materials. 5.6 CABLE CONTAINMENT Cable must not be run within the same containment as any power cable at any point. Minimum separation distances within EN50173 and the latest IET wiring regulations (BS7671) must be maintained for any crossing of cabling routes. At all times cables must be supported on top of tray/basket. Cables must not be hung from inverted tray/basket. Metallic cable ties must not be used. Where additional cable containment is required the sizing of the components should be such that at least 50% of the newly installed containment remains free for further cable following the completion of the installation. Where additional tray is installed only hot dipped, post galvanised steel return edge tray of a minimum width of 100mm must be used. All cut edges must be smoothed, no sharp edges are to remain. Lengths of tray must be jointed using appropriate fastenings; e.g. Hex-headed nuts, bolts of the correct length, washers must be used, sharp, cut edges not acceptable. Where additional cable basket is installed only bright zinc plated product of a minimum width of 100mm must be used. Cut ends of basket wire must be either cut flush to the nearest weld point and filed smooth and flush or cut approximately 10mm from the nearest weld point and the cut end covered with a tight fitting PVC or similar protective cap. Where runs of tray/basket change direction proprietary components rather than on site manufactured items must be used. 90 degree bends must be achieved with the use of 2 successive 45 degree bends. Any cable tray/basket supports must not reduce the cable carrying capacity of the tray/basket. In general supports should be external to the cable carrying area of the tray/basket. Where support is via threaded rod this must be M10 BZP steel. The threaded rod must be sleeved over its full length with white 20mm, heavy gauge, high-impact upvc conduit. This protects cable from damage when routing past the threaded rod. Where fitted threaded rod must be cut flush with the end fixing and filed smooth or the ends covered with a tight fitting PVC or similar protective cap. Cable tray/basket must not be used to carry power circuits. However, all sections of tray/basket must be electrically bonded and the whole assembly earthed. Where circular conduit is used for CAT6 cabling, the following maximums for capacity must be observed; 2no CAT6 cables within 20mm conduit, 4no CAT6 cables within 25mm conduit. 5.7 LABELLING Any reference to room number should be the Lancaster University room number as advised by Facilities and not the architectural or construction room number. 27

28 CAT6 CABLING Patch Panel Labelling The patch panel labelling must adhere to the pitch spacing of the panel so that each port label aligns accurately with each port. Labels that do not accurately align with the port or overlap adjacent ports will not be accepted. The label on the patch panel should be of the form (not including < or > characters): <RoomNo> An example for a single label for one port on a patch panel is shown below. The remote end of this port will be in room A23: Figure 3 Each patch panel must be clearly labelled on the left hand side with its correct patch panel number, eg PP Data Point Outlet The label on the outlet must be directly attached to the module, and must take the form <Comms room number>/<rack ID> <Patch Panel No>/<Port No> Where rack ID is the identifier for the rack in the comms room, A,B,C etc. A data point label for Comms room B48, Rack C, patch panel 1, port 21 is shown below. Figure 4 Patch panel number is the number of the patch panel within the identified rack, where each CAT6 patch panel in the rack has a unique identifier, starting at the bottom of the rack with panel number 01, and 28

29 CAT6 CABLING port number is the number of the port on the identified patch panel in the identified rack where the other end of the data line presents Labels - General Labels must be typed or printed, not hand written. Text to be black on a white background. Labels must use the label-mounting locations and not overlap adjacent port areas nor obscure port numbers. 5.8 DATA POINTS FOR WI-FI ACCESS POINTS Wireless networking (Wi-Fi) must be provided in any new building or refurbishment. Aside from major building or refurbishment projects, there are often smaller Wi-Fi deployments to boost signal strength where required. For early-stage building design and budgeting, it should be assumed that there will be one wireless access point for every 90m 2 of open floor area Responsibilities The technical design of the wireless network service in building and refurbishment projects will be done by ISS. This means that the ISS Network Contacts will Annotate floor plans to show the required positions of CAT6 data points for use by Wi-Fi access points Decide which model of Wi-Fi access point is to be deployed Instruct on orientation and positioning of Wi-Fi access points relative to other objects, some of which is documented below and some of which will be undertaken on site during the installation phase. ISS staff will also Undertake procurement of the Wi-Fi access points for use in the project. This procurement is funded by the building project, not by ISS. Configure and install the Wi-Fi access points. These arrangements mean that from the point of view of project managers, electrical engineers and data line installers, installation of Wi-Fi is usually just the installation of specially placed CAT6 data lines, 29

30 CAT6 CABLING as directed by ISS. In some cases, there are additional requirements such as IP-rated housing for the Wi- Fi access points in certain environments. Once the CAT6 data lines for Wi-Fi are tested and accepted by ISS Network Contacts, ISS staff will then mount the wireless access points over the pattress boxes, covering them. The only equipment in view is then the wireless access point Data Line Installation For Wi-Fi For each wireless access point location, a single CAT6 data line must be terminated in a minimum 49mm deep single pattress box e.g. MK8901ALM (surface or flush mounted, facing downward). The front of the pattress box must have at least 150mm clear on all sides, at least 75mm clearance must be available to the front (i.e. below) with no metallic materials in front (i.e. below). Positioning arrangements of data points for Wi-Fi are critical to avoid obstructions to the wireless signal propagation, and to allow staff access to maintain the wireless access points. Discussions with ISS Network Contacts are required in order to determine the most appropriate positioning arrangement in each location. Following are examples of acceptable data line installations Figure 5 Wi-Fi data point before installation of access point 30

31 CAT6 CABLING Figure 6 Wi-Fi access point mounted over data point Figure 7 Access point mounted over data point on the end of steel conduit to bring the AP down just below the level of obstructions. 31

32 CAT6 CABLING Figure 8 Wi-Fi data point with AP adjacent to wall 5.9 TESTING AND ACCEPTANCE PROCEDURE Contractor tests the data lines Data wiring contractor must test and certify all newly installed copper data lines to the full CAT6 specification. Data wiring test equipment must be calibrated and have a current calibration certificate. Marginal or starred passes will not be accepted Contractor sends test results to ISS Network Contacts An electronic copy of the full test results must be supplied to ISS immediately following the testing phase. Test results, along with a copy of the test equipment s calibration certificate, must be submitted by to networking-testresults@lancaster.ac.uk. Once received the results will be reviewed by ISS within a maximum of 5 working days. The test results must be supplied as a spread sheet or.csv file. If Fluke testers are used, then the original.flw results file must also be supplied. These results will be used as the basis for subsequent witness testing to verify the quality of results. 32

33 CAT6 CABLING A copy of the calibration certificate for the test equipment used must also be supplied with the results. The calibration must have been performed by a manufacturer-approved calibration centre. All test equipment must be within a valid calibration period when both testing and witness testing takes place. Test results must contain as a minimum: Make model and serial numbers and valid calibration period of the test equipment used. The velocity factor parameter (NVP) entered into the test equipment. For each line o Overall pass/fail with respect to the CAT6 specification. o Line length in metres. o NEXT (Near end crosstalk) o PSNEXT (power sum near-end crosstalk) o FEXT (Far end crosstalk) o Attenuation o Return loss o ACR (attenuation to crosstalk ratio) Where the pass-margin deviates substantially from the value expected for the line length in question, then further investigations may be undertaken during witness testing. An example sheet of test results is available at Witness testing by ISS Network Contacts The contractor should be prepared to undertake 100% witness testing of installed lines. Any reduction in this will be at the discretion of ISS Network Contacts. If ISS deem witness testing to be necessary, the contractor will be informed and requested to attend for the witness testing within 2 working days. A time and date will be agreed during this contact. The contractor must supply at least 2 staff to perform witness testing which will be observed by ISS staff. The testing must be undertaken with the contractors test equipment which, whilst it does not have to be the same set used for the original tests, must be in calibration and supplied with valid calibration certificates. 33

34 6 CW1308 COPPER CABLE LANCASTER UNIVERSITY DATA NETWORK PHYSICAL INFRASTRUCTURE SPECIFICATIONS CW1308 COPPER CABLE 6.1 INSTALLATION A suitably-rated 100 pair cable to BT specification CW1308b must be installed to the comms room from the nearest main distribution frame (MDF) as advised by ISS Network Contacts. The cable must be installed as a single continuous run, with no joints. The conductor in the cable must be solid 0.5mm copper, jelly-filled cables must not be used, the earth continuity conductor must be connected to the common earth block at both the originating and supplied DP. Within the comms room the cable must be installed onto an Austin Taylor 108A double vertical frame (AT-108A) with Krone 237A disconnect terminal strips. At the MDF location, the cable must be terminated onto Krone 237A disconnect terminal strips to be installed into an existing frame or housing, or a new 108A vertical frame or other appropriate housing as advised by ISS Network Contacts. From the vertical frame in the comms room, 2no 25 pair CW1308 cables should be taken to each cabinet, both in the primary and secondary comms rooms. One vertical on the frame should be designated to inbound circuits, and the other designated to the cabinet-bound circuits. Modules are to be installed beginning at the base of each vertical, pair 1 is bottom-left. These should be terminated onto Krone 237A terminal strips on the frame and onto 1u, 25 port voice panels in each of the cabinets layout as per the cabinet drawing in section Note: Only original Krone parts will be accepted. The pair-layout and colour coding used must conform to CW1308 specifications. 34

35 CW1308 COPPER CABLE 6.2 LABELLING Where the telephone cable passes through a barrier, riser opening and immediately prior to entry into the DP the cable should be clearly labelled with an engraved traffolyte label, white text on red background and comply with regulations BS EN for all labels, text of label will be advised by ISS. Each Krone disconnection module must be fitted with a label holder and labelled, labels must be printed, black text on white background and not handwritten, text for labels to be advised by ISS. 6.3 TESTING AND ACCEPTANCE PROCEDURE In order for CW1308 cables to be accepted by ISS, three stages must be completed, with details below: Contractor tests all cable pairs Contractor sends test results to ISS Network Contacts Witness testing of data lines by ISS Network Contacts if required Contractor tests the data lines The Contractor must undertake a 100% test of all cable pairs. The results must be supplied as a spread sheet or.csv file. Cable pair tests shall be made to ascertain the following: Loop resistance < 200Ω/km Polarity Correct Labelling; The Contractor must provide a certificate of compliance to BS6701 Parts 1 and 2 upon completion of the cabling scheme Contractor sends test results to ISS Network Contacts CW1308 test results must be submitted by to networking-testresults@lancaster.ac.uk. Once received the results will be reviewed by ISS within a maximum of 5 working days Witness testing by ISS Network Contacts The contractor should be prepared to undertake 100% witness testing of installed cables. Any reduction in this will be at the discretion of ISS Network Contacts. If ISS deem witness testing to be necessary, the contractor will be informed and requested to attend for the witness testing within 2 working days. A time and date will be agreed during this contact. The contractor must supply at least 2 staff to perform witness testing which will be observed by ISS staff. An example sheet of test results is available at 35

Special Provision No. 683S28 December 2017

Special Provision No. 683S28 December 2017 FIBRE OPTIC COMMUNICATION CABLES, AERIAL ON MESSENGER CABLE - Item No. FIBRE OPTIC COMMUNICATION CABLES, AERIAL ON MESSENGER CABLE (TEMPORARY) - Item No. Special Provision No. 683S28 December 2017 1. SCOPE

More information

FIBRE OPTIC COMMUNICATION CABLES, IN DUCTS - Item No. FIBRE OPTIC COMMUNICATION CABLES, IN DUCTS (TEMPORARY) - Item No.

FIBRE OPTIC COMMUNICATION CABLES, IN DUCTS - Item No. FIBRE OPTIC COMMUNICATION CABLES, IN DUCTS (TEMPORARY) - Item No. FIBRE OPTIC COMMUNICATION CABLES, IN DUCTS - Item No. FIBRE OPTIC COMMUNICATION CABLES, IN DUCTS (TEMPORARY) - Item No. Special Provision No. 683S01 December 2017 1. SCOPE This Special Provision covers

More information

ECP OPTICAL FIBRE SPLICING, TESTING AND COMMISSIONING REQUIREMENTS

ECP OPTICAL FIBRE SPLICING, TESTING AND COMMISSIONING REQUIREMENTS Network(s): Summary: ENGINEERING COMMISSIONING PROCEDURE ECP 11-0009 OPTICAL FIBRE SPLICING, TESTING AND COMMISSIONING REQUIREMENTS EPN, LPN, SPN This standard details the requirements for the splicing,

More information

A. General: Horizontal and backbone cabling shall be verified in accordance with ANSI/TIA/EIA-568-C and the addendum for fiber optic testing.

A. General: Horizontal and backbone cabling shall be verified in accordance with ANSI/TIA/EIA-568-C and the addendum for fiber optic testing. 3.4 TESTING OF FIBER OPTICS CABLING A. General: Horizontal and backbone cabling shall be verified in accordance with ANSI/TIA/EIA-568-C and the addendum for fiber optic testing. B. General: In the event

More information

Telephone and Data Structured Wiring

Telephone and Data Structured Wiring Data Specification Category 6A General Telephone and Data Structured Wiring The Electrical Sub-Contractor shall employ a specialist sub-contractor to provide the following systems:- Manufacturer System

More information

HELKAMA. Optical Fibre Cables

HELKAMA. Optical Fibre Cables 1 Contents Optical fibres and their characteristics Cable constructions Cable tests Installation, jointing and terminating Manufacturing (pictures) 2 Multimode Fibre (GK) Attenuation and Bandwidth Fibre

More information

SECTION COMMUNICATIONS FIBER CABINETS, ADAPTERS AND CONNECTORS

SECTION COMMUNICATIONS FIBER CABINETS, ADAPTERS AND CONNECTORS SECTION 27 11 20 COMMUNICATIONS FIBER CABINETS, ADAPTERS AND CONNECTORS PART 1 GENERAL 1.01 DESCRIPTION A. The work covered by this section of the Specifications includes all labor necessary to perform

More information

SOUTH DUBLIN COUNTY COUNCIL Traffic Management Centre Roads (Traffic and Transportation) Department

SOUTH DUBLIN COUNTY COUNCIL Traffic Management Centre Roads (Traffic and Transportation) Department SOUTH DUBLIN COUNTY COUNCIL Roads (Traffic and Transportation) Department TECHNICAL SPECIFICATION 4 SDCC-TS-04 SIGNAL INSTALLATION REQUIREMENTS REQUIREMENTS FOR THE DESIGN AND INSTALLATION OF TRAFFIC CONTROL

More information

MT-RJ Optical Fiber System Field Testing

MT-RJ Optical Fiber System Field Testing MT-RJ Optical Fiber System Field Testing Table of Contents INTRODUCTION... 3 TEST JUMPERS... 4 LAUNCH CONDITIONS... 4 MT-RJ TEST KITS... 5 MT-RJ SYSTEM TESTING: Fixed transmit and receive (SC or ST-style)

More information

2016 CDM Smith All Rights Reserved July 2016 SECTION FIBER OPTIC DATA NETWORK

2016 CDM Smith All Rights Reserved July 2016 SECTION FIBER OPTIC DATA NETWORK PART 1 GENERAL 1.01 SCOPE OF WORK SECTION 27 12 23 FIBER OPTIC DATA NETWORK A. Furnish, install, terminate, and test all fiber optic equipment and cabling necessary for a complete and functional data highway

More information

DSCR Communications Room Standards

DSCR Communications Room Standards Document number: 0203 Status: Classifications: Published Project Restricted New Builds Deep Refurbishments Design Performance Standard Date: April 2010 Version: 1.3 Issue number Date Description 0.1 July

More information

Compact Module. Category 6A FTP Cabling System 1.1

Compact Module. Category 6A FTP Cabling System 1.1 Updated 24/09/12 Compact Module Cat 6A performance Suitable for 10-Gigabit Ethernet Ultra-slimline design Euro style module Interchangeable with other Euro Modules and blanks Individually QA tested Easy

More information

Fibre (TIA) Field Test Specification

Fibre (TIA) Field Test Specification This document has been prepared to aid consultants or engineers in developing contractual specifications covering the testing of duplex fibre optic cabling installations. It is offered as a general guide.

More information

Carbon Film Installation Instructions

Carbon Film Installation Instructions Contents Page 2 Page 3 Page 4 Page 5 Page 8 Product Overview Pre-Installation & Electrical Provision Depron Underlay Installation Carbon Film Installation - Under Wood/Laminate Flooring Notes & Trouble

More information

STATE OF NEW JERSEY DEPARTMENT OF TRANSPORTATION TRENTON, NEW JERSEY SPECIFICATIONS FOR FUSION SPLICE AND SPLICE ENCLOSURE FIBER OPTIC CABLE

STATE OF NEW JERSEY DEPARTMENT OF TRANSPORTATION TRENTON, NEW JERSEY SPECIFICATIONS FOR FUSION SPLICE AND SPLICE ENCLOSURE FIBER OPTIC CABLE STATE OF NEW JERSEY DEPARTMENT OF TRANSPORTATION TRENTON, NEW JERSEY 08625 SPECIFICATIONS FOR FUSION SPLICE AND SPLICE ENCLOSURE FIBER OPTIC CABLE N.J. Specification No. Effective Date: July 1, 2001 New

More information

GEM-C Wireless User & Installation Manual. Revision October Apollo Solar Electric Limited. Documentation

GEM-C Wireless User & Installation Manual. Revision October Apollo Solar Electric Limited. Documentation Documentation GEM-C Wireless User & Installation Manual Revision October 2014 Apollo Solar Electric Limited Contents GEM-C Wireless User Manual 3 Important Safety Information 3 Introduction 4 The GEM-C

More information

Instruction Manual WARNINGS

Instruction Manual WARNINGS Instruction Manual LARGE COMMERCIAL RECESSED AIR CURTAIN HSACR9000, 12000 & 18000 ELECTRICALLY HEATED RECESSED AIR CURTAINS WITH ENERGY SAVING CONTROLS INSTALLATION AND OPERATING MANUAL INDEX Section General

More information

This is a preview - click here to buy the full publication

This is a preview - click here to buy the full publication ISO/IEC 14763-3 CONSOLIDATED VERSION Edition 2.1 2018-08 colour inside Information technology Implementation and operation of customer premises cabling Part 3: Testing of optical fibre cabling INTERNATIONAL

More information

Fiber Optic and CAT 5, 6, 7 and 8 Installer Premise Cabling

Fiber Optic and CAT 5, 6, 7 and 8 Installer Premise Cabling Hands-On Fiber Optic and CAT 5, 6, 7 and 8 Installer Premise Cabling Certification Course Description This Hands-On course is customized to give Technicians the confidence and skills to maintain Fiber

More information

4120 Fire Alarm Network Reference

4120 Fire Alarm Network Reference 4120 Fire Alarm Network Reference Features Autocall 4120 Fire Alarm Network communications are available for wired or fiber optic connections Wired communications are available on Network Interface Cards

More information

Field Testing and Troubleshooting of PON LAN Networks per IEC Jim Davis Regional Marketing Engineer Fluke Networks

Field Testing and Troubleshooting of PON LAN Networks per IEC Jim Davis Regional Marketing Engineer Fluke Networks Field Testing and Troubleshooting of PON LAN Networks per IEC 61280-4 Jim Davis Regional Marketing Engineer Fluke Networks Agenda Inspection and Cleaning APC vs UPC PON basics Wavelengths Architecture

More information

NSP/002/001 Guidance document for the installation of Fibre Optic Underground Cables

NSP/002/001 Guidance document for the installation of Fibre Optic Underground Cables Version: 2.0 Date of Issue: Aug 2015 Page: 1 of 15 NSP/002/001 Guidance document for the installation of Fibre Optic Underground Cables 1. Purpose The purpose of this document is to provide guidance on

More information

Fibre Specification Standards

Fibre Specification Standards Fibre Specification Standards User Manual The most important thing we build is trust Cobham Wireless - Coverage Table of Contents 1. Single-mode Fibre to ITU-T Recommendation G.652 3 2. SC/APC Mated Pair

More information

Project Briefing Document. Section 3 Electrical Services design guide and specifications

Project Briefing Document. Section 3 Electrical Services design guide and specifications ESTATES SUPPORT SERVICE Project Briefing Document Section 3 Electrical Services design guide and specifications Issue 1.1 June 2014 Project Ref. Project Name Project Manager Date issued... Consultant/Contractor...

More information

A. The requirements of this Section and the other Division 26, 27 & 28 Sections apply to all the video surveillance system work.

A. The requirements of this Section and the other Division 26, 27 & 28 Sections apply to all the video surveillance system work. PART 1 GNRAL 1.1. APPLICABL PROVISIONS A. The General, Supplementary and other Conditions of the Contract, modifications to the General Conditions, the Drawings, and the applicable provisions of the other

More information

If a peak space temperature to about 28ºC is acceptable to the occupants then a naturally ventilated solution is a viable option.

If a peak space temperature to about 28ºC is acceptable to the occupants then a naturally ventilated solution is a viable option. Air handling units Aesthetic Not to add significantly to the existing ambient noise levels. Functional requirements If a peak space temperature to about 28ºC is acceptable to the occupants then a naturally

More information

Hands-On CAT 5/6 & Fiber Optic Installer

Hands-On CAT 5/6 & Fiber Optic Installer Hands-On BICSI CECs This course has been approved for CEC credits by BICSI. Please read below for a breakdown of the credits that we offer for this course. For more information regarding BICSI please visit

More information

STANDARD TEST PROCEDURE PRE-TEST QUALITY OF OPTIC FIBRE CABLE ON DRUMS TYPE OF CABLE :

STANDARD TEST PROCEDURE PRE-TEST QUALITY OF OPTIC FIBRE CABLE ON DRUMS TYPE OF CABLE : PROCEDURE PRE-TEST QUALITY OF OPTIC FIBRE CABLE ON DRUMS STANDARD TEST PROCEDURE PRE-TEST QUALITY OF OPTIC FIBRE CABLE ON DRUMS TYPE OF CABLE : 1) SINGLE MODE 2) MULTI-MODE IN EXCESS OF 100 METRES PRC-00107

More information

BOILING UNIT REDITAP. Installation and User Guide. IMPORTANT: This booklet should be left with the user after installation and demonstration

BOILING UNIT REDITAP. Installation and User Guide. IMPORTANT: This booklet should be left with the user after installation and demonstration in tap Boiling water to in tap sink Drain Valve (as high as possible) REDITAP CONNECTION SUMMARY Amp mains supply cold mains water into in tap optional filter cold water in hot water BOILING UNIT Installation

More information

AGA TOTAL CONTROL. Model No s: TC3 & TC5 (ROOM VENT OPTION)

AGA TOTAL CONTROL. Model No s: TC3 & TC5 (ROOM VENT OPTION) AGA TOTAL CONTROL Model No s: TC3 & TC5 (ROOM VENT OPTION) Installation Guide REMEMBER: when replacing a part on this appliance, use only spare parts that you can be assured conform to the safety and performance

More information

Fibre optic media options and trends

Fibre optic media options and trends Fibre optic media options and trends Presented by D Stockton & P Lascelles of Miniflex Ltd, branded as m2fx 23 February 2012 1 Contents Cable constructs Indoor/outdoor LSZH Armouring Micro Bends Singlemode,

More information

SECTION WET-PIPE SPRINKLER SYSTEMS

SECTION WET-PIPE SPRINKLER SYSTEMS SECTION 21 13 13 WET-PIPE SPRINKLER SYSTEMS PART 1 - GENERAL 1.1 SCOPE OF WORK A. Design, installation and testing shall be in accordance with NFPA 13 except for specified exceptions. B. The demolition

More information

SYSTEM MANUAL Description

SYSTEM MANUAL Description SYSTEM MANUAL Description PUCK is a revolutionary fire suppression system offering discrete protection coupled with industry leading pricing, efficient system design and easy install. PUCK s lightweight

More information

SECTION DIGITAL, ADDRESSABLE FIRE-ALARM SYSTEM

SECTION DIGITAL, ADDRESSABLE FIRE-ALARM SYSTEM SECTION 283111 - DIGITAL, ADDRESSABLE FIRE-ALARM SYSTEM PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division

More information

IntelliDoX Operator Manual

IntelliDoX Operator Manual IntelliDoX Operator Manual OPERATOR MANUAL TABLE OF CONTENTS Table of Contents Table of Contents...1 About this Publication...3 Important Safety Information: Read First...4 Getting Started...5 About the

More information

ETSI TS V1.2.1 ( )

ETSI TS V1.2.1 ( ) TS 100 783 V1.2.1 (2004-08) Technical Specification Transmission and Multiplexing (TM); Passive optical components; Fibre optic fusion splices for single-mode optical fibre transmission systems for indoor

More information

Electrical Design Guidelines Table of Contents

Electrical Design Guidelines Table of Contents C: Compliant Rev. 3 Dated June 13 11 NC: Non-Compliant NA: Not Applicable Page1 16.1 General 16.2 Single Line Diagrams 16.3 Electric Motor Equipment and Controls 16.4 Lighting 16.5 Emergency Lighting 16.6

More information

Installation and user manual for the BiWire / Conventional Repeater Panel

Installation and user manual for the BiWire / Conventional Repeater Panel Panel EFBWCV-REPEATER Contents Introduction.... 3 Purpose... 3 The Panel.... 3 Indication Equipment (IE).... 3 Power Supply Equipment (PSE).... 4 System Wiring.... 5 Status Indications.... 5 Repeater I/O....

More information

Networked Access Control Panel. Installation Guide

Networked Access Control Panel. Installation Guide XP2M Networked Access Control Panel V1.0X Installation Guide X P 2 M A C C E S S C O N T R O L S Y S T E M Installation Guide Document Ref: PLAN XP2M Installation Guide V4(G)2010 Access Control Services

More information

VTI Services Technical Bulletin (TB) OTDR Measurement of Installed Optical Fibre Cabling Permanent Links and Links

VTI Services Technical Bulletin (TB) OTDR Measurement of Installed Optical Fibre Cabling Permanent Links and Links VTI Services Technical Bulletin (TB) OTDR Measurement of Installed Optical Fibre Cabling Permanent Links and Links TB Number 004 This bulletin is supplied for information only and is intended to provide

More information

Fiber Optics for Todays Industry Applications

Fiber Optics for Todays Industry Applications Hands-On Fiber Optics for Todays Industry Applications (A Non-Telephone Company Course) Course Description This Hands-On course is designed to provide technicians with a practical understanding and Hands-On

More information

Tumble dryer PT 5136 PT en - GB. Installation plan

Tumble dryer PT 5136 PT en - GB. Installation plan Installation plan Tumble dryer PT 5136 PT 7136 To avoid the risk of accidents or damage to the machine, it is essential to read operating and installation instructions before installation and commissioning

More information

NZQA unit standard version 1 Page 1 of 6. Install, maintain and repair of telecommunications optical fibre network infrastructure

NZQA unit standard version 1 Page 1 of 6. Install, maintain and repair of telecommunications optical fibre network infrastructure Page 1 of 6 Title Install, maintain and repair of telecommunications optical fibre network infrastructure Level 3 Credits 25 Purpose This unit standard covers installation, maintenance and repair of telecommunications

More information

Draft ES V1.1.1 ( )

Draft ES V1.1.1 ( ) Standard Transmission and Multiplexing (TM); Passive optical components; Fibre optic mechanical splices for single-mode optical fibre communications systems; Common requirements and conformance testing

More information

Emergency Voice Communication System (EVCS) Consu ltant s Specific atio n CONTENTS

Emergency Voice Communication System (EVCS) Consu ltant s Specific atio n CONTENTS CONTENTS 100 PERFORMANCE OBJECTIVES 200 DESIGN PARAMETERS 300 SYSTEM DESIGN 310 Design Guidance 320 Outstation Choice 330 Outstation Position 340 Documentation 400 SYSTEM COMPONENTS 410 Master Handsets

More information

NPS/003/030 Technical Specification for Transformer and Switchgear Cable Boxes and their associated Bushing Assemblies

NPS/003/030 Technical Specification for Transformer and Switchgear Cable Boxes and their associated Bushing Assemblies Version:- 2.0 Date of Issue:- May 2015 Page 1 of 17 NPS/003/030 Technical Specification for Transformer and Switchgear Cable Boxes and their associated Bushing Assemblies 1. Purpose The purpose of this

More information

MASTERSPEC TECHNICAL SPECIFICATIONS DIVISION 27 COMMUNICATIONS SECTION PUBLIC ADDRESS AND MASS NOTIFICATION SYSTEMS

MASTERSPEC TECHNICAL SPECIFICATIONS DIVISION 27 COMMUNICATIONS SECTION PUBLIC ADDRESS AND MASS NOTIFICATION SYSTEMS SECTION 275116 - PUBLIC ADDRESS AND MASS NOTIFICATION SYSTEMS PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Preamplifiers. 2. Power amplifiers. 3. Microphones. 4. Control console. 5. Loudspeakers.

More information

Universal Connectivity Platform A Modular Approach to Infrastructure Design

Universal Connectivity Platform A Modular Approach to Infrastructure Design A Modular Approach to Infrastructure Design TE Connectivity s Universal Connectivity Platform (UCP) provides a fully modular approach to designing data centers and telecommunications rooms. This patch

More information

The Rise of Tier 2 Testing

The Rise of Tier 2 Testing The Rise of Tier 2 Testing Why enterprises today demand better visibility into their fiber infrastructure Unprecedented demand for more bandwidth, faster network speeds, lower latency, and improved data

More information

Electromagnetic Locking Devices Performance Requirements

Electromagnetic Locking Devices Performance Requirements Technical Specification Electromagnetic Locking Devices Performance Requirements DHF TS 010:2016 Technical specification produced by dhf www.dhfonline.org.uk Contents Foreword 1. Scope 2 ANNEX A Bodies

More information

INSTALLATION, OPERATION & MAINTENANCE MANUAL

INSTALLATION, OPERATION & MAINTENANCE MANUAL CENTRAL FANS COLASIT LTD Unit 12A, Palmers Road, East Moons Moat, Redditch. Worcs. B98 0RF Tel: 01527-517200 Fax: 01527-517195 Edition 04_13 INSTALLATION, OPERATION & MAINTENANCE MANUAL CIV Fan Range Valid

More information

D-TECT Introduction. Connecting the Unit. Quick Installation. Multi Beam Alignment & Masking. Mounting the Unit

D-TECT Introduction. Connecting the Unit. Quick Installation. Multi Beam Alignment & Masking. Mounting the Unit D-TECT 2 GJD300 Quad PIR Movement Detector Package Contents Package Contains: 1 x D-Tect 2 1 x Drilling template for fixing holes 3 x 31.75mm wall plugs 3 x 31.75mm screws 2 x Spare Sliding Curtains 2

More information

SECTION ELECTRICAL IDENTIFICATION

SECTION ELECTRICAL IDENTIFICATION SECTION 16075 - ELECTRICAL IDENTIFICATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification

More information

B. Configuration of system shall be through Schneider Electric in Homewood, Illinois (Jerry Lanfear ).

B. Configuration of system shall be through Schneider Electric in Homewood, Illinois (Jerry Lanfear ). SECTION 28 13 00 - ACCESS CONTROL PART I - GENERAL 1.1 SUMMARY A. This specification section describes the furnishing, installation, commissioning, and programming of a complete, turnkey, hardwired Andover

More information

Overview Frost Heave Prevention for Freezer floors on ground.

Overview Frost Heave Prevention for Freezer floors on ground. PLEASE NOTE The floor sensor MUST be installed such that it may be REMOVED for service if required! The sensor probe should be installed into a conduit with no more than one wide-angle bend. This should

More information

Installing the Cisco ONS FAP-4 Fuse Alarm Panel

Installing the Cisco ONS FAP-4 Fuse Alarm Panel Installing the Cisco ONS 15454-FAP-4 Fuse Alarm Panel Product Number: 15454-FAP-4= This document explains how to install, test, operate, and maintain the Cisco ONS 15454-FAP-4 fuse alarm panel. This document

More information

The Optical Time Domain Reflectometry and the Fusion Splicer Laboratory exercise

The Optical Time Domain Reflectometry and the Fusion Splicer Laboratory exercise The Optical Time Domain Reflectometry and the Fusion Splicer Laboratory exercise 1 The purpose of the exercise...2 2 Background...2 2.1 Introduction to scattering and attenuation...2 2.2 Introduction to

More information

AirUnit. Installation instructions. mfh systems modern floor heating. Decentralised domestic ventilation

AirUnit. Installation instructions. mfh systems modern floor heating. Decentralised domestic ventilation mfh systems modern floor heating AirUnit Decentralised domestic ventilation Installation instructions List of contents, Installation instructions Page 1. General information... 03 2. Function / planning

More information

Web Pages for Construction and Traveler Information Condition Reporting System 511 Phone Power. Data Processing and Response Formulation

Web Pages for Construction and Traveler Information Condition Reporting System 511 Phone Power. Data Processing and Response Formulation Existing Existing To Be Modified To Be Developed Not Applicable Visual Surveillance (e.g. CCTV) Traffic Detectors (excluding presence detectors at intersections for signal control) Dynamic Message Sign

More information

Fire detection and alarm

Fire detection and alarm Fire detection and alarm Aesthetic Install all cabling and cable containment neatly and unobtrusively, meeting the highest electrical industry installation standards. Neatly lay and securely fix cables.

More information

INTERNATIONAL STANDARD

INTERNATIONAL STANDARD INTERNATIONAL STANDARD IEC 61156-6 First edition 2002-03 Multicore and symmetrical pair/quad cables for digital communications Part 6: Symmetrical pair/quad cables with transmission characteristics up

More information

SECTION COMMUNICATIONS OPTICAL FIBER BACKBONE CABLING

SECTION COMMUNICATIONS OPTICAL FIBER BACKBONE CABLING SECTION 27 13 23 COMMUNICATIONS OPTICAL FIBER PART 1 - GENERAL 1.1 SUMMARY A. Section Includes the following: 1. 50/125-micrometer, optical fiber cabling. 2. Cable connecting hardware, termination panels,

More information

ETSI TS V1.2.1 ( )

ETSI TS V1.2.1 ( ) TS 101 263 V1.2.1 (2004-07) Technical Specification Transmission and Multiplexing (TM); Passive optical components; Fibre optic mechanical splices for single-mode optical fibre communications systems for

More information

SECTION ISOLATED POWER SYSTEMS

SECTION ISOLATED POWER SYSTEMS PART 1 - GENERAL 1.1 DESCRIPTION SECTION 26 20 11 ISOLATED POWER SYSTEMS SPEC WRITER NOTE: Delete between //---// if not applicable to project. Also, delete any other item or paragraph not applicable to

More information

Hands-On Fiber Optics ISP/OSP - Advanced Combo- Tech

Hands-On Fiber Optics ISP/OSP - Advanced Combo- Tech Hands-On Fiber Optics ISP/OSP - Advanced Combo- Tech Course Description This Hands-On 3-day course has been customized to provide technicians with a practical understanding of fiber optic theory and fiber

More information

Industrial Fiber Optic Cables, LSZH Corrugated Armored Cable, Fibers

Industrial Fiber Optic Cables, LSZH Corrugated Armored Cable, Fibers Features and Benefits Corrugated armor Mechanical protection Low-smoke/zero-halogen (LSZH ) sheath Key life-safety benefit Meets cyclic impact and chemical resistance test Superior performance Tray-rated

More information

A Guide To BS Understanding the selection, spacing and siting of detectors

A Guide To BS Understanding the selection, spacing and siting of detectors World Class Leaders in Fire Detection Since 1918 A Guide To BS5839-12017 Understanding the selection, spacing and siting of detectors Welcome to A Guide to BS5839 Part 1 : 2017 from HOCHIKI EUROPE (UK)

More information

Firetuf OFC-UT-CST Fire resistant Armoured Central Tube Cable, variant in red

Firetuf OFC-UT-CST Fire resistant Armoured Central Tube Cable, variant in red OFC-UT-CST Fire resistant Armoured Indoor/Outdoor steel tape armoured (CST) double LSHF-FR sheathed optical cable with 2 24 fibres. VDE: A/I-DQ(ZN)H(SR)H 3rd party verification of the fire tests by BUREAU

More information

Multipurpose Cables (indoor/outdoor), Multipurpose central tube cable (maxibundle) with glass yarn armouring A-DQ(BN)H 4-24

Multipurpose Cables (indoor/outdoor), Multipurpose central tube cable (maxibundle) with glass yarn armouring A-DQ(BN)H 4-24 Features and Benefits Laminated swelling glass yarns Improved rodent resistance and longitudinal water protection UV and microbe resistant Can be directly buried or installed in ducts Metal-free cable

More information

Jan07 Rev B

Jan07 Rev B Qualification Test Report 501-545 05Jan07 Rev B MT-RJ Patch Panel and Outlet Jacks (Standard, XG, SECURE and SECURE XG) 1. INTRODUCTION 1.1. Purpose Testing was performed on Tyco Electronics MT-RJ Jack,

More information

SECTION AUTOMATIC TRANSFER SWITCHES

SECTION AUTOMATIC TRANSFER SWITCHES PART 1 - GENERAL 1.1 DESCRIPTION SECTION 26 36 23 SPEC WRITER NOTE: Use this section only for NCA projects. Delete between //--// if not applicable to project. Also, delete any other item or paragraph

More information

5. Identification products.

5. Identification products. Essex County College - West Essex Campus Addition And Renovations dib # 54292 / 11-14 [SECTION 260523- CONTROL-VOLTAGE ELECTRICAL POWER CABLES PART 1- GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general

More information

Fiber Optic Cable Fence Disturbance Sensor

Fiber Optic Cable Fence Disturbance Sensor Architectural & Engineering Specification for Fiber Optic Cable Fence Disturbance Sensor Purpose of document This document is intended to provide performance specifications and operational requirements

More information

Product Specification EMI Shielded Duplex LC Sealed Receptacle (ODVA Conforming)

Product Specification EMI Shielded Duplex LC Sealed Receptacle (ODVA Conforming) Product Specification EMI Shielded Duplex LC Sealed Receptacle (ODVA Conforming) 02Oct08 Rev A 1. SCOPE 1.1. Content This specification, based on IEC 61753-1 Edition 1.0 tests for Category E (Extreme Environment),

More information

Digital Door Entry System. Specification

Digital Door Entry System. Specification Digital Door Entry System 2 Planit Security Contracts Limited policy is one of continual improvement. The company reserves the right at all times to amend s without prior notification Technical Support

More information

Introduction. Please read the following instructions carefully before commencing installation.

Introduction. Please read the following instructions carefully before commencing installation. Introduction Please read the following instructions carefully before commencing installation. Installation involves simple processes. These are explained step by step in the following pages. Should you

More information

University Design Standard Fire Alarm Systems

University Design Standard Fire Alarm Systems 1.0 Overview University Design Standard Fire Alarm Systems This document provides Virginia Tech s standards for the design and installation of fire alarm systems and equipment in new construction, retrofit

More information

Telecity. Table of Contents. Page. Section 3.2

Telecity. Table of Contents. Page. Section 3.2 1 3.2 System Descriptions Table of Contents 3.2 SYSTEM DESCRIPTIONS... 3 3.2.1 General Notes... 3 3.3 Power Distribution MV... 4 3.3.1 Incoming Supply... 4 3.3.2 MV Switch room... 4 3.4 Power Distribution

More information

Document Information Cover Sheet

Document Information Cover Sheet Document Information Cover Sheet Asite/Document Reference Number: LOR-CO-SW-RP-0015 Document Title: Equipment Interface Document Revision: F02 Publisher: Laing O Rourke Published: 23/04/2013 Outline Description/Comments

More information

TABLE OF CONTENTS GENERAL... 2 A. DEFINITIONS DIGITAL, ADDRESSABLE FIRE ALARM SYSTEM... 2

TABLE OF CONTENTS GENERAL... 2 A. DEFINITIONS DIGITAL, ADDRESSABLE FIRE ALARM SYSTEM... 2 Division 28 ELECTRONIC SAFETY AND SECURITY TABLE OF CONTENTS 28 0000 GENERAL... 2 A. DEFINITIONS...2 28 3111 DIGITAL, ADDRESSABLE FIRE ALARM SYSTEM... 2 A. DESIGN REQUIREMENTS...2 B. CONSTRUCTION REQUIREMENTS...2

More information

INTERNATIONAL TELECOMMUNICATION UNION SERIES L: CONSTRUCTION, INSTALLATION AND PROTECTION OF CABLES AND OTHER ELEMENTS OF OUTSIDE PLANT

INTERNATIONAL TELECOMMUNICATION UNION SERIES L: CONSTRUCTION, INSTALLATION AND PROTECTION OF CABLES AND OTHER ELEMENTS OF OUTSIDE PLANT INTERNATIONAL TELECOMMUNICATION UNION ITU-T L.36 TELECOMMUNICATION STANDARDIZATION SECTOR OF ITU (10/98) SERIES L: CONSTRUCTION, INSTALLATION AND PROTECTION OF CABLES AND OTHER ELEMENTS OF OUTSIDE PLANT

More information

Outdoor Enclosures. Outdoor Enclosures Protected like a bunker for all harsh environments

Outdoor Enclosures. Outdoor Enclosures Protected like a bunker for all harsh environments Outdoor Enclosures Outdoor Enclosures Protected like a bunker for all harsh environments sales@mcldatasolutions.co.uk +44(0)1702 443810 mcldatasolutions.co.uk Outdoor enclosures and climate control components

More information

HW3 Handwash Installation and Operating Instructions

HW3 Handwash Installation and Operating Instructions HW3[16]instructions 10/12/15 14:05 Page 1 HW3 Handwash Installation and Operating Instructions IMPORTANT SAFEGUARDS SPECIFICATION: HW3 RATING: 230-240V, 3000W, ~50Hz; DIMENSIONS: 170w x 190h x 80d mm;

More information

Requirements for Electrical Installations

Requirements for Electrical Installations BRITISH STANDARD BS 7671:2018 Corrigendum (December 2018) Requirements for Electrical Installations IET Wiring Regulations Eighteenth Edition The Institution of Engineering and Technology and BSI NO COPYING

More information

U tube models PTU 09, 12, 15, 25, 30, 35, 40, 45. single linear tube models PTS 09, 12, 15, 25, 30, 35, 40, 45

U tube models PTU 09, 12, 15, 25, 30, 35, 40, 45. single linear tube models PTS 09, 12, 15, 25, 30, 35, 40, 45 U tube models PTU 09, 2, 5, 25, 30, 35, 40, 45 & single linear tube models PTS 09, 2, 5, 25, 30, 35, 40, 45 installation, servicing & operating instructions INSTALLATION, SERVICING AND OPERATING INSTRUCTIONS

More information

Developer, new connection and infrastructure charges

Developer, new connection and infrastructure charges Ends of duct to be sealed Pipe clips mounted off to allow for insulation Pipe insulated in accordance with B.S. 6700 against damage from frost Drain Tap Double check valve Copper to Polyethylene fitting

More information

Fan-and-filter units 4.3. Features. Fast assembly. Application diversity and functions

Fan-and-filter units 4.3. Features. Fast assembly. Application diversity and functions Fan-and-filter units Features Fan-and-filter units are ideal for dissipating heat loads costeffectively. The pre-requisite is that the ambient air must be relatively clean and with a temperature below

More information

Architectural and Engineering Specification for a Fiber Optic Perimeter Intrusion Detection System. FiberPatrol FP1100X

Architectural and Engineering Specification for a Fiber Optic Perimeter Intrusion Detection System. FiberPatrol FP1100X Architectural and Engineering Specification for a Fiber Optic Perimeter Intrusion Detection System FiberPatrol FP1100X December 2017 Page 1 of 14 AE-FP-001-IN-R5-E-12/17 This document is intended to provide

More information

CATEGORY 6A FTP RJ45 SOLUTION

CATEGORY 6A FTP RJ45 SOLUTION CATEGORY 6A FTP RJ45 SOLUTION Clipsal titanium Patch Cord Clipsal titanium LSZH Patch Cord Clipsal titanium Keystone Jacks Clipsal titanium Modular Jacks Clipsal titanium Patch Panels Clipsal titanium

More information

F1202 TRACE HEATING. Road & Ramp

F1202 TRACE HEATING. Road & Ramp Trace Heating Specialists Road & Ramp ROAD & RAMP HEATING ESH Trace Heating Ltd provide a comprehensive range of products to prevent the settlement of snow and formation of ice on roads, ramps and stairs.

More information

OWNERS INSTRUCTION MANUAL

OWNERS INSTRUCTION MANUAL OWNERS INSTRUCTION MANUAL 132CM/52 Classic INSTALLATION OPERATION MAINTENANCE CAUTION READ INSTRUCTIONS CAREFULLY FOR SAFE INSTALLATION AND FAN OPERATION. IF UNSURE CONSULT A QUALIFIED ELECTRICIAN SUITABLE

More information

Optical Return Loss Measurement by Gregory Lietaert, Product Manager

Optical Return Loss Measurement by Gregory Lietaert, Product Manager White Paper Optical Return Loss Measurement by Gregory Lietaert, Product Manager Introduction With the increasing frequency of high-speed transmission systems and DWDM deployment, optical return loss (ORL)

More information

Duct Cable GYTS-144B1.3

Duct Cable GYTS-144B1.3 Optical Fibre Cable Technical Specification Duct Cable GYTS-144B1.3 Xcom Ltd All rights reserved 1. Scope This Specification covers the design requirements and performance standard for the supply of optical

More information

Installation Manual PS-225 & PS-275

Installation Manual PS-225 & PS-275 Installation Manual PS-225 & PS-275 Table of Contents Pre-Uncrating Checklist... 1 Verifying System Requirements... 2 Verifying System Direction... 2 Verifying the Electrical Requirements... 2 Removal

More information

FLEXIBLE DUCTS BY SUBSURFACE INSTALLATION FOR MAGNETIC DETECTORS - Item No. RIGID DUCTS, CONCRETE ENCASED FOR MAGNETIC DETECTORS - Item No.

FLEXIBLE DUCTS BY SUBSURFACE INSTALLATION FOR MAGNETIC DETECTORS - Item No. RIGID DUCTS, CONCRETE ENCASED FOR MAGNETIC DETECTORS - Item No. FLEXIBLE DUCTS BY SUBSURFACE INSTALLATION FOR MAGNETIC DETECTORS - Item No. RIGID DUCTS, CONCRETE ENCASED FOR MAGNETIC DETECTORS - Item No. Special Provision No. 682S33 February 2016 Amendment to OPSS

More information

SECTION COMMUNICATIONS PATCH CORDS, STATION CORDS AND CROSS CONNECT WIRE

SECTION COMMUNICATIONS PATCH CORDS, STATION CORDS AND CROSS CONNECT WIRE SECTION 27 16 19 COMMUNICATIONS PATCH CORDS, STATION CORDS AND CROSS CONNECT WIRE PART 1 GENERAL 1.01 DESCRIPTION A. The work covered by this section of the Specifications includes all labor necessary

More information

Title: Room-sealed fanned draught flue systems concealed within voids

Title: Room-sealed fanned draught flue systems concealed within voids Date issued: 11 th June 2007 Author: Jamie Cooper Status: Current Reviewer: 11 th June 2008 Introduction Title: Room-sealed fanned draught flue systems concealed within voids With the advent of modern

More information

The most user friendly Security Alarm System L S Section 1 Overview of System Section 2 Planning your Installation

The most user friendly Security Alarm System L S Section 1 Overview of System Section 2 Planning your Installation The most user friendly Contents Section 1 Overview of System 1.1 Kit Contents 1.2 Tools Required 1.3 System Features Security Alarm System L S 4 0 0 Section 2 Planning your Installation 2.1 Location of

More information

Detection of Solvents using a Distributed Fibre Optic Sensor

Detection of Solvents using a Distributed Fibre Optic Sensor Detection of Solvents using a Distributed Fibre Optic Sensor Alistair MacLean, Chris Moran, Walter Johnstone, Brian Culshaw, Dan Marsh, Paul Parker. A fibre optic sensor that is capable of distributed

More information

MRXBOX95B-LOFT. Mechanical Ventilation Unit with Heat Recovery & Summer Bypass for Loft Mounting. Installation and Maintenance

MRXBOX95B-LOFT. Mechanical Ventilation Unit with Heat Recovery & Summer Bypass for Loft Mounting. Installation and Maintenance MRXBOX95B-LOFT Mechanical Ventilation Unit with Heat Recovery & Summer Bypass for Loft Mounting Installation and Maintenance The EMC Directive 2004/108/EC The Low Voltage directive 2006/95/EC 1.0 Introduction

More information