Fire Prevention Coffee Break Training. February 2016
|
|
- Andrea May
- 5 years ago
- Views:
Transcription
1 Fire Prevention Coffee Break Training February 2016
2 Agenda Flow Tests Phelan Submittals - Phelan Inspection & Testing Dooley Questions and Answers Open Forum
3 Change in Flow Test Policy The responsible and reasonable use of flow test data has recently become a problem with sprinkler submittals. Designs are being based upon flow tests that are years old. Given the rate of development within the city it s unreasonable to expect old data to accurately reflect the supply and demand to the system currently.
4 Change in Flow Test Policy Flow testing has been a topic of study and discussion within the Fire Protection community for a considerable time. Most recently a study was completed by Hopkins et al. for SFPE with a goal of providing a recommendation for flow tests such as a recommended safety factor and/or a procedure for ensuring the flow test reflects accurately the demand in the area. The study was inconclusive, but is useful in framing the conversation.
5 Change in Flow Test Policy Importantly, this study along with recent experience, pointed out that the previously authored policy on flow test data is inconsistent with NFPA 13 requirements for flow test data and best industry practice.
6 Change in Flow Test Policy NFPA contains the following requirement for flow tests * Where a water flow test is used for the purposes of system design, the test shall be conducted no more than 12 months prior to working plan submittal.
7 Change in Flow Test Policy Questions? Practicality? Input? Concerns?
8 Submittal Review Resubmittal Inspection Testing Process Overview
9 Plan submittal Plans and calculations should be submitted as early in the construction/renovation project as possible. While the goal of the FPB is to return initial review comments or approval within 10 business days of submittal that is frequently not possible due to record construction volume over the past 2 years. Also, construction and occupation timelines often fail to contemplate the frequent need for resubmittals and re-testing.
10 Expediting Plans The DMFD does not have a fee based mechanism for expediting plans. Informally, we have a process where a contractor can request to have a submittal reviewed in place of their next submittal due to be reviewed.
11 Resubmittals This fee is 1/2 the permit fee. The fee will be applied when any substantive item is not included in the submittal or requires correction or modification.
12 Expediting Plans The DMFD does not have a fee based mechanism for expediting plans. Informally, we have a process where a contractor can request to have a submittal reviewed in place of their next submittal due to be reviewed.
13 Installation Prior to Receiving a Permit This fee is equal to the permit fee. This fee can be applied to any system installed prior to the issuance of a permit.
14 All Submittals Drawing Size. Drawings shall be submitted on sheets no less than 24x36 inches and shall be drawn to ⅛ =1 scale. Where ⅛ scale is not large enough to show pertinent details, then a ¼ =1 scale shall be used in a detail drawing. Other scales may be accepted on an as-needed basis, please contact the DMFD Fire Protection Engineer if you have questions regarding the use of different scales. Number of Drawing Sets. One set of fire alarm plans shall be submitted. To accommodate existing storage arrangements in our office only folded plans will be accepted.
15 All Submittals Cut Sheets/Specifications. One set of the manufacture s product information (cut sheets) shall be provided for review, they may be provided electronically. This is to include the information on all devices that are part of, or being connected to, the fire protection system. When cut sheets show multiple models/type of devices, the specific item being installed shall be highlighted. As an example, the use of multi-candela horn/strobes shall have the specific model number highlighted and the current draws associated with that model and candela rating highlighted. Cut sheets shall be stapled, bound, placed in a binder or otherwise neatly organized when submitted. Self Addressed Stamped Envelope. Approved plans and permits will be returned in this envelope. If an envelope is not included, the plans and permit will be available for pick up.
16 CONSTRUCTION DOCUMENTS Construction documents shall be of sufficient clarity to indicate the location, nature and extent of the work proposed and show in detail that it will conform to the provision of the IFC, and relevant laws, ordinances, rules and regulations as determined by the DMFD. Refer to the attachments within this packet for a checklist of items to be included on construction drawings.
17 RESUBMITTALS When a resubmittal is required; plans, cutsheets, and calculations shall be clouded with an attached explanation of the changes made to the plans. Only documents required to be altered for the resubmittal shall be resubmitted. 1 set of the required documents shall be provided for review.
18 Upon Permit Approval Two full-size hard copy sets of the final approved documents including drawings and calculations and one electronic copy along with payment for the permit shall be submitted to receive the permit. The hardcopy documents will be stamped at the time of payment and retained by the contractor for their records and for use onsite.
19 Sprinkler Systems Hydraulic Calculations. One set of hydraulic calculations for all remote areas, including standpipes will be included. They may be submitted electronically. Design area Reduction Calculations. When utilizing the design area reduction allowances allowed by reduced ceiling heights and Quick Response sprinklers, be sure to justify your percent reduction by including the calculation procedure.
20 Fire Alarm Submittal Specifics Secondary Power Calculations (Battery Calculations). One set of the secondary power (battery) calculations shall be provided for all power supplies being installed within the system for review. This is to include the voltage and amperage information on all batteries being installed within the main panel and any supplemental power panels being provided. One copy of the battery calculations will be returned to the contractor and must remain with the approved plans, on the job site. Battery calculations shall include the following information: a. Standby and Alarm current draws for each device/appliance connected to the fire alarm system. b. The Model number of each device/appliance. c. Description of each device/appliance. d. Standby time (i.e. 24 hours, 60 hours, etc.) e. Alarm time (i.e. 5 minutes, 15 minutes, 60 minutes etc.) f. Total current draw of the system. g. Batteries provided, size of batteries and whether wired in series or parallel.
21 Fire Alarm Submittal Specifics Voltage Drop Calculations. Two (2) sets of voltage drop calculations shall be submitted with the plans. Sample calculations may be obtained from the DMFD Fire Protection Engineer. One copy of the voltage drop calculations will be returned to the contractor and must remain with the approved plans, on the job site. These calculations are to include the following information: a. The total number of devices on each wiring circuit. b. The current draw of each device. c. The maximum length of wire utilized on each circuit. d. The wire size being used. e. The voltage remaining at the last device. f. Intelligent Horn/Strobes must show the manufactures information of how the voltage drops shall be calculated. g. Adjustable Multi-Candela Horn/Strobes - the battery calculations shall be calculated according to the candela rating on the fire alarm plans. For example, if the fire alarm plans indicate the candela rating is 110, the battery calculation shall be calculated for 110 candela.
22 Fire Alarm Submittal Specifics Sequence of Operations. The sequence of operation of the fire alarm system shall be provided in matrix format. An example of the typical input/output matrix format is located in the 2002 edition of NFPA 72: Figure A (9). The sequence of operations shall be specific to each submittal and shall not include functions that do not pertain to the specific submittal.
23 Fire Alarm Submittal Specifics Other stuff that is frequently forgotten Ceiling heights Smoke detector above the panel Voice Acoustically Distinguishable Spaces Intelligibility Test Locations
24 Testing No system testing will be conducted prior to the issuance of a permit. Some preliminary inspection of the system may be accomplished prior to issuance of a permit, for example sprinkler rough-in. However, this would likely mean the application of the fee for installation prior to a permit. If you call for a test be prepared with your permit number. Tests will not be scheduled without a permit number.
25 Testing If the GC wants to schedule a test they will be required to complete a newly developed form, available on our website. This form includes the basics about the job, scope, and contact information for the appropriate sub-contractors. It also includes blanks for the system permit numbers. This form shall be completed in its entirety prior to scheduling a test. All tests must be requested by , call, or voice mail to Captain Dooley s office phone. Requests for scheduling made to any mobile phone will not be honored.
26 Sprinkler Testing Receive Permit. Schedule test by providing permit number.
27 Sprinkler Testing Sprinkler type and location Pipe and sprinkler support Occupancy and Use Design placard Monitoring Standpipe Full fire pump flow test Standpipe flow test Flow switches
28 Fire Alarm Testing Receive Permit. Schedule test by providing permit number. NFPA 72 record of submittal submitted at least 24 hours in advance or test may be cancelled.
29 Fire Alarm Testing Candela Setting Wire Gauge Circuit routing Notification appliance settings and layout Occupancies and uses Notification devices synced Audibility & Intelligibility Any or all initiating devices Monitoring and loss of signal Battery Backup Pull station location
30 Fire Alarm Testing Receive Permit. Schedule test by providing permit number. NFPA 72 record of submittal submitted at least 24 hours in advance or test may be cancelled. Tests may include but are not limited to the following:
31 Kitchen Hood Testing Appliance Layout Pull station Detection Line Lines Clear (Balloon/Cap blow off test) Electrical/Gas shutoff Nozzle Aim Points Make up and Exhaust air operation Fire alarm interconnection
32 Clean Agent Testing Witnessed door fan tests are required
33 Questions and Discussion What else do we need to talk (more) about?
Fire Prevention Coffee Break Training. February 2017
Fire Prevention Coffee Break Training February 2017 Agenda FDC s - Lund Standpipes - Phelan Fire Alarm Testing Phelan/Dooley Questions and Answers Open Forum Standpipe requirement Standpipes are required
More informationFIRE ALARM SYSTEMS INFORMATION PACKET. Des Moines Fire Department Fire Prevention Bureau
FIRE ALARM SYSTEMS INFORMATION PACKET Des Moines Fire Department February 2011 TABLE OF CONTENTS PURPOSE... 3 SCOPE... 3 ACRONYMS... 3 GUIDELINES... 3 I. INTRODUCTION... 3 A. APPLICABLE CODES AND STANDARDS.
More informationFIRE ALARM PLAN REVIEW PERMIT REQUIREMENTS
FIRE ALARM PLAN REVIEW PERMIT REQUIREMENTS Town of Brighton Office of the Fire Marshal October 2018 Fire Alarm Plan Review and Permit Submittal Requirements Purpose This information packet has been developed
More informationSeptember 30, Dear Fire Suppression System Contractor/Designer:
CITY OF BOZEMAN FIRE DEPARTMENT P.O. Box 1230 Bozeman, Montana 59771-1230 Phone (406) 582-2350 CITY OF BOZEMAN BUILDING DEPARTMENT 20 E Olive St, STE 208 Bozeman, Montana 59715-4790 Phone (406) 582-2375
More informationMay 1, Dear Fire Suppression System Contractor/Designer:
CITY OF BOZEMAN FIRE DEPARTMENT P.O. Box 1230 Bozeman, Montana 59771-1230 Phone (406) 582-2350 Fax (406) 582-2355 CITY OF BOZEMAN BUILDING DEPARTMENT 20 E Olive St, STE 208 Bozeman, Montana 59715-4790
More informationFire Prevention Coffee Break Training November 2014
Fire Prevention Coffee Break Training November 2014 Agenda Introduction/ What do we want? - Fire Marshal Lund FAQ s and Alternative Design FPE Phelan Permit to Inspect, Maintain, & Service FP Appliances
More informationYou are required to READ ALL PAGES. of this application
Fire/Smoke/Heat/CO Application Checklist You are required to READ ALL PAGES of this application NEW ROCHELLE FIRE DEPARTMENT 90 Beaufort Pl, New Rochelle, NY 10801 - (914) 654-2213 APPLICATION FOR FIRE/SMOKE/HEAT/CO
More informationMinimum Standards for Engineers Practicing Fire Protection Engineering in the State of Oklahoma September 14, 2016
1. Introduction The intent of this document is to establish minimum standards for the practice of fire protection engineering within the State of Oklahoma as conducted by licensed professional engineers.
More informationBold items are particular to the City of Euless
EULESS FIRE DEPARTMENT FIRE MARSHAL S OFFICE INFORMATION LINE: Revised 8/2004 Fire Chief Lee Koontz Fire Marshal Paul Smith EFD-FMO 3-1 2003 International Fire & Building Code as Amended NFPA Standards
More informationBrighton Area Fire Authority
615 W. Grand River Ave. Brighton, MI 48116 o: 810-229-6640 f: 810-229-1619 January 14, 2019 Fire Alarm Contractors RE: Fire Alarm Credential & Submittal Requirements To Whom It May Concern: The following
More informationAPPENDIX H (DESIGN SUBMISSION CRITERIA)
APPENDIX H (DESIGN SUBMISSION CRITERIA) FIRE ALARM SYSTEM As per ACCORD standard Part 5, section 5.7 Fire Alarm System Design to be verified by ACCORD Chief Safety Inspector. Testing of the installation
More informationFIRE ALARM APPLICATION CITY OF MADISON HEIGHTS
FIRE ALARM APPLICATION CITY OF MADISON HEIGHTS www.madison-heights.org COMMUNITY DEVELOPMENT DEPARTMENT BUILDING DIVISION 300 W. THIRTEEN MILE RD. MADISON HEIGHTS, MICHIGAN 48071 (248) 583-0831 FAX (248)
More informationValuation: # of Plans Submitted: # of pages: Type of Work (select one): New Addition Existing System/Modification Project Name: Scope of Work:
PERMIT FEE: $ 907 Billy Mitchell Blvd. P: (210) 228-1022 Fire Alarm Permit Application PAYMENT TYPE: Check Credit Card Charge to Job #: (Please complete all of the following information. Please PRINT).
More informationFire Permit Application
Fire Permit Application FOR STAFF USE ONLY Case Permit Number: Plan Number: Related permits: Project #: Responsibility for information Although designated Department staff members will help you with general
More informationInternational Fire Code 2006 Requirements for Construction Plan Reviews of Commercial and Multi-Family Structures
International Fire Code 2006 Requirements for Construction Plan Reviews of Commercial and Multi-Family Structures Please note this is not an all-inclusive list. The type and complexity of your project
More informationNORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017
SECTION 21 0800 - COMMISSIONING OF FIRE SUPPRESSION SYSTEMS GENERAL 1.1 SUMMARY General 1. Work under this contract shall meet the requirements of Division 01, General Requirements, Conditions of Contract,
More informationMoreno Valley Fire Department Fire Prevention Bureau. New and Existing Fire Alarm & Signaling Systems Guideline
Moreno Valley Fire Department Guideline Approved and Authorized By: Adria Reinertson, Fire Marshal Issued: May 8, 2017 Alarm & Signaling Systems PURPOSE Fire alarm and signaling systems are designed to
More informationCOMMERCIAL (IBC) FIRE ALARM SUBMITTAL GUIDE
COMMERCIAL (IBC) FIRE ALARM SUBMITTAL GUIDE SUPERVISION OF AUTOMATIC FIRE SPRINKLER SYSTEMS SUPERVISION OF ALTERNATIVE AUTOMATIC FIRE-EXTINGUISHING SYSTEMS FIRE ALARM AND DETECTION SYSTEMS The Fire Alarm
More informationFIRE ALARM SYSTEMS & 780 CMR. Dave LeBlanc, PE, FSFPE March 17, 2015
FIRE ALARM SYSTEMS & 780 CMR Dave LeBlanc, PE, FSFPE March 17, 2015 BIOGRAPHY David J. LeBlanc, PE, FSFPE BS EE & MS FPE - WPI 23 Years PE Technical Committee Member NFPA72 - National Fire Alarm Code NFPA3
More informationFlorida Building Code 2010
Introduction Florida Building Code 2010 Chapter 9 Fire Protection Systems This course will cover specific sections of Chapter 9 that relate to fire alarm systems. While many contractors are familiar with
More informationFire Sprinkler Plan Submittal Form
Contents Fire Sprinkler Plan Submittal Form... 2 Standpipe Plan Review Submittals... 4 Fire Pump Plan Submittal Requirements... 6 Fire Alarm Plan Submittal Form... 8 Kitchen Hood Wet Chemical Submittal...10
More informationSANTA CLARA COUNTY Winchester Blvd., Los Gatos, CA (408) (408) (fax)
FIRE DEPARTMENT SANTA CLARA COUNTY 14700 Winchester Blvd., Los Gatos, CA. 95032-1818 (408) 378-4010 (408) 378-9342 (fax) www.sccfd.org STANDARD DETAILS & SPECIFICATIONS Spec No C-4 Rev. Date 03/10/10 SUBJECT:
More informationCLARK COUNTY FIRE DEPARTMENT Fire Prevention Bureau
CLARK COUNTY FIRE DEPARTMENT Fire Prevention Bureau 575 E. Flamingo Road, Las Vegas, NV 89119 (702) 455-7316 FAX (702) 455-7347 Permit Type: 105.7.1 Control Number: I.0 Effective Date: 12/15/11 TITLE:
More informationAUTOMATIC FIRE SPRINKLER SYSTEMS
MCKINNEY FIRE DEPARTMENT FIRE MARSHAL S OFFICE AUTOMATIC FIRE SPRINKLER SYSTEMS These guidelines are to be followed when a business, facility or organization installs an automatic fire sprinkler system
More informationNarrative Reports As Regulated by 780 CMR, Section 903.0
EXHIBIT 20 Narrative Reports As Regulated by 780 CMR, Section 903.0 903.1.1 - FIRE PROTECTION CONSTRUCTION DOCUMENTS a. Basis (methodology) of design for the protection of the occupancy and hazard for
More informationFlorida Building Code Chapter 9 Fire Protection Systems Advanced Course
Florida Building Code 2010 Chapter 9 Fire Protection Systems Advanced Course 1 Introduction This course will cover specific sections of Chapter 9 that relate to fire alarm systems. While many contractors
More informationCITY OF LONG BEACH Department of Development Services BUILDING AND SAFETY BUREAU FIRE ALARM / ELECTRICAL FIRE PLAN REVIEW CHECKLIST
CITY OF LONG BEACH Department of Development Services BUILDING AND SAFETY BUREAU FIRE ALARM / ELECTRICAL FIRE PLAN REVIEW CHECKLIST DATE: PROJECT NO.: EXPIRATION DATE: STATUS: INFORMATION PROJECT ADDRESS:
More informationFIRE & LIFE SAFTEY STANDARD
Title: Effective Date: 01/01/14 Revised Date: 1/1/14 Code References: Title 16, Chapter 16.16 of the Roseville Municipal Code, NFPA 72 Note: This standard is a summary of Fire Department clarifications
More informationCLARK COUNTY FIRE DEPARTMENT Fire Prevention Bureau
CLARK COUNTY FIRE DEPARTMENT Fire Prevention Bureau 575 E. Flamingo Road, Las Vegas, NV 89119 (702) 455-7316 FAX (702) 455-7347 Permit Type: 105.7.13 Control Number: A.0 Effective Date: 11/15/11 TITLE:
More informationSTATE FIRE MARSHAL S REQUIRED FIRE PROTECTION SYSTEMS NARRATIVE REPORT
STATE FIRE MARSHAL S REQUIRED FIRE PROTECTION SYSTEMS NARRATIVE REPORT The interaction of fire protection systems can be extremely complex. The detection of a fire in a building by an automatic device
More informationRancho Cucamonga Fire Protection District Prevention Bureau Standard
Rancho Cucamonga Fire Protection District Prevention Bureau Standard Title: Fire Alarm and Monitoring Systems Standard # 9-3 Effective: May 2002 Number of Pages: 7 Updated: December 2016 for consistency
More informationCLARK COUNTY FIRE DEPARTMENT Fire Prevention Bureau
CLARK COUNTY FIRE DEPARTMENT Fire Prevention Bureau 575 E. Flamingo Road, Las Vegas, NV 89119 (702) 455-7316 FAX (702) 455-7347 Code Sections: 105.7.18 Control Number: A.0 Effective Date: TITLE: SCOPE:
More informationNFPA 72 Code Changes vs 2013
NFPA 72 Code Changes - 2010 vs 2013 AFAA-NE Westborough, MA February 7, 2018 Richard Roux NFPA 72 National Fire Alarm and Signaling Code Overview and 2013 Changes NFPA 72 1993 Edition Aug 20, 1993 1996
More informationCommercial Application/Plan Review Submittal Checklist
Commercial Application/Plan Review Submittal Checklist The following checklist has been compiled to assist in expediting the commercial plan review and permit issuance process. Please take a moment to
More informationMINOOKA FIRE PROTECTION DISTRICT Fire Prevention Bureau Fire Inspector Rodney Bradberry
MINOOKA FIRE PROTECTION DISTRICT Fire Prevention Bureau Fire Inspector Rodney Bradberry Fire Alarm Systems Plan Review Checklist Date: Permit Number: Business Name: Address: Fire Alarm System Submittal
More informationFire Prevention Coffee Break Training. May 2017
Fire Prevention Coffee Break Training May 2017 Agenda Introduction Submittals - Phelan Changes to NFPA 13 - Phelan Questions and Answers Open Forum Please welcome our S ummer Intern Charlie Poppe Small
More informationCAN/ULC S Integrated Systems Testing of Fire Protection and Life Safety Systems and Fire Protection Commissioning
CAN/ULC S1001-11 Integrated Systems Testing of Fire Protection and Life Safety Systems and Fire Protection Commissioning Presentation To: Canadian Fire Alarm Association (CFAA) National Capital Region
More informationFull Service Central Station Fire Alarm Listing Evaluation
Full Service Central Station Fire Alarm Listing Evaluation Listing Evaluation A UL Listing project includes: 1. Evaluating the central station facility for compliance with UL 827, Central-Station Alarm
More informationCAN/ULC-S INTEGRATED SYSTEMS TESTING OF FIRE PROTECTION AND LIFE SAFETY SYSTEMS
2013 Randal Brown & Associates Engineering Ltd. 1 RANDAL BROWN & ASSOCIATES ENGINEERING LTD. CONSULTING ENGINEERS LIFE SAFETY & FIRE PROTECTION 105 6 LANSING SQUARE TORONTO, ONTARIO CAN/ULC-S1001-11 INTEGRATED
More informationLiberty Township Fire Department Fire Prevention Bureau. Clean Agent Fire Protection Plan Submittal Checklist
Liberty Township Fire Department Fire Prevention Bureau Clean Agent Fire Protection Plan Submittal Checklist Project Name: Date: Project Address: Designers Name: Company Name: Phone Number: Email: Fax:
More informationFire Protection Coffee Break Training May 2016
Fire Protection Coffee Break Training May 2016 Introduction High-Rise Requirements Questions and Answers Agenda Overview Site Fire Access Aerial Access Power/Back-up Power Elevators and Access Sprinklers
More information1.3 REFERENCE STANDARDS
SECTION 28 4600 FIRE DETECTION AND ALARM PART 1 -GENERAL 1.1 SECTION INCLUDES A. Fire alarm system design and installation, including all components, wiring, and conduit. B. Circuits from protected premises
More information1. Floor above/floor below notification. 2. Private alarm notification. 3. Not Used 4. Voice alarm notification. 5. Not Used.
PART 1 GENERAL 1.01 Scope of Standard A. This Standard is intended to assure that fire alarm and signaling systems at Sam Houston State University provide the highest level of life safety possible. This
More informationMOBILE FIRE - RESCUE DEPARTMENT FIRE CODE ADMINISTRATION
MOBILE FIRE - RESCUE DEPARTMENT FIRE CODE ADMINISTRATION Fire Alarm System Plan Review 2009 International Fire Code and 2010 NFPA 72 Date of Review // BLD201 - Project Address: Project Name: _ Professional
More informationCLARK COUNTY FIRE DEPARTMENT Fire Prevention Bureau
CLARK COUNTY FIRE DEPARTMENT Fire Prevention Bureau 575 E. Flamingo Road, Las Vegas, NV 89119 (702) 455-7316 FAX (702) 455-7347 Permit Type: 105.6.54 Control Number: A.0 Effective Date: TITLE: PROPRIETARY
More informationCAN/ULC-S1001, INTEGRATED SYSTEMS TEST OF FIRE PROTECTION AND LIFE SAFETY SYSTEMS
RANDAL BROWN & ASSOCIATES ENGINEERING LTD. CONSULTING ENGINEERS LIFE SAFETY & FIRE PROTECTION 105 6 LANSING SQUARE TORONTO, ONTARIO CAN/ULC-S1001, INTEGRATED SYSTEMS TEST OF FIRE PROTECTION AND LIFE SAFETY
More informationCOMMERCIAL KITCHEN SUPPRESSION SYSTEMS INFORMATION PACKET
COMMERCIAL KITCHEN SUPPRESSION SYSTEMS INFORMATION PACKET Colorado Springs Fire Department Division of the Fire Marshal October 2013 Table of Contents PURPOSE... 3 SCOPE... 3 DEFINITIONS... 3 GUIDELINES...
More informationFire Protection Coffee Break Training August 2016
Fire Protection Coffee Break Training August 2016 Agenda Introduction - Phelan NFPA 13 versus NFPA 13R systems for Residential Occupancies - Homa NFPA 72 Record of Completion - Homa Questions and Answers
More informationCarrollton Fire Rescue
Carrollton Fire Rescue Fire Prevention Division Guide for Construction 2016 edition 2 Carrollton Fire Rescue Prevention Division Table of Contents Fire Prevention Division... 3 General Guidelines... 4
More informationPlan Submittal Checklist
City of Aurora Public Works Department HIGH-PILED COMBUSTIBLE STORAGE Plan Submittal Checklist Building Division 15151 E. Alameda Parkway, Ste 2400 Aurora, CO 80012 303-739-7420 Fax: 303-739-7551 Project
More informationCommercial Remodel/ Add On Rules and Regulations
Commercial Remodel/ Add On Rules and Regulations Public Works and Community Development Department City of Shenandoah 29955 I-45 North Shenandoah, Texas 77381 281-298-5522 www.shenandoahtx.us Construction
More informationCITY OF MADISON FIRE DEPARTMENT (MFD) FIRE PROTECTION SYSTEM PLANS
CITY OF MADISON FIRE DEPARTMENT (MFD) FIRE PROTECTION SYSTEM PLANS Fire Protection Systems includes the following: Alternate Fire Suppression Systems Atrium Fire Protection Systems Automatic Fire Sprinkler
More informationPRIVATE FIRE SERVICE INSTALLATION PACKET
PRIVATE FIRE SERVICE INSTALLATION PACKET The 2017 Edition supersedes all previous versions for Private Fire Service Installation To Whom It May Concern: SUBJECT: PRIVATE FIRE SERVICE INSTALLATION Illinois
More informationRiverside County Fire Department Office of the Fire Marshal Market St., Ste. 150, Riverside, CA Ph. (951) Fax (951)
Riverside County Fire Department Office of the Fire Marshal 2300 Market St., Ste. 150, Riverside, CA 92501 Ph. (951) 955-4777 Fax (951) 955-4886 Technical Policy Title: Plant Processing and Extraction
More informationGLENDALE FIRE DEPARTMENT FIRE MARSHAL S OFFICE
GLENDALE FIRE DEPARTMENT FIRE MARSHAL S OFFICE To: Contractors From: Charles Jenkins, Fire Marshal Subject: Contractor s Guide This guide is provided by the Fire Marshal as a service to the construction
More informationSANTA ROSA FIRE DEPARTMENT FIRE PREVENTION BUREAU INSPECTION GUIDELINE RESIDENTIAL CARE FACILITIES 2007 CBC/CFC (R-3.1)
July 1, 2010 SANTA ROSA FIRE DEPARTMENT FIRE PREVENTION BUREAU INSPECTION GUIDELINE RESIDENTIAL CARE FACILITIES Address: Permit #: Inspector: Date: Status: Inspector: Date: Status: This Checklist outlines
More informationNASSAU COUNTY FIRE PROTECTION PERMIT APPLICATION
BUILDING PERMIT# Revised 6/30/15 AP# PERMIT # Cost $ Check# Receipt# NASSAU COUNTY FIRE PROTECTION PERMIT APPLICATION 5 TH EDITION (2014) OF THE FLORIDA BUILDING CODE IS IN EFFECT THE 2012 FLORIDA FIRE
More informationPLAN REVIEW SUBMITTAL GUIDE
PLAN REVIEW SUBMITTAL GUIDE Plans, specifications and other construction documentation for the initial plan review should be as complete as possible at the time of submittal. Use this convenient guide
More information1 Exam Prep Fire Alarm Signaling Systems Tabs and Highlights
1 Exam Prep Fire Alarm Signaling Systems Tabs and Highlights These 1 Exam Prep Highlights are based on the Fire Alarm Signaling Systems, 4th Edition. Each Tabs sheet has five rows of tabs. Start with the
More informationEl Reno Fire Department Fire Alarm Plan Review Worksheet
El Reno Fire Department Fire Alarm Plan Review Worksheet This Fire Alarm Plan Review Checklist is provided as a guide to assist with your Fire Alarm Plan Review Submittal requirements. Please contact us
More informationNew Construction Fire Inspection Process
New Construction Fire Inspection Process This document is intended to provide the Owner, Designer, and/or Contractor of new construction with an outline of required fire inspections and with the specific
More informationSECTION DIGITAL, ADDRESSABLE FIRE-ALARM SYSTEM
SECTION 283111 - DIGITAL, ADDRESSABLE FIRE-ALARM SYSTEM PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division
More informationSTUDY AND TEST MATERIAL FOR THE. FA2 and FA4 ASSESSMENTS. (Fire Alarm On-Site and Business Cert. Holder) June 14, 2017
STUDY AND TEST MATERIAL FOR THE FA2 and FA4 ASSESSMENTS (Fire Alarm On-Site and Business Cert. Holder) June 14, 2017 This document contains sample questions to help participants study for the FA2 and FA4
More information1. New development including where permanent in-ground irrigation systems are installed.
CHAPTER 900. SECTION 905. DEVELOPMENT STANDARDS GREEN SPACE REQUIREMENTS AND STANDARDS 905.4. Irrigation A. Intent and Purpose As landscape irrigation comprises a significant portion of water use, the
More informationFire - Rescue. November 2016
Fire - Rescue Fire Alarm and Central Station Monitoring Plan Submittal Guidelines November 2016 Plan Submittal Guidelines are provided based on the 2015 International Fire Code, Policies, and Local Amendments.
More informationCAN/ULC-S1001, INTEGRATED SYSTEMS TESTING OF FIRE PROTECTION & LIFE SAFETY SYSTEMS Simon Crosby, LEL, CET, CFPS October 21, 2015
CAN/ULC-S1001, INTEGRATED SYSTEMS TESTING OF FIRE PROTECTION & LIFE SAFETY SYSTEMS Simon Crosby, LEL, CET, CFPS October 21, 2015 Fire Commissioning in Canadian Codes and Standards BACKGROUND Why Commissioning?
More informationSECTION WET-PIPE SPRINKLER SYSTEMS
SECTION 21 13 13 WET-PIPE SPRINKLER SYSTEMS PART 1 - GENERAL 1.1 SCOPE OF WORK A. Design, installation and testing shall be in accordance with NFPA 13 except for specified exceptions. B. The demolition
More information2. HVAC and smoke control systems; fire, smoke, and combination fire/smoke dampers. 5. Central control and monitoring system.
PART 1 GENERAL 1.01 Scope of Standard A. This Standard is intended to assure that fire detection/alarm systems at The University of Texas at Austin provide the highest level of fire safety possible.. This
More informationBurnsville Fire Department 100 Civic Center Pky, Burnsville, MN Fire Marshal: FAX:
Burnsville Fire Department 100 Civic Center Pky, Burnsville, MN 55337 Fire Marshal: 952-895-4579 FAX: 952-895-4512 2018 FIRE SUPPRESSION PERMIT APPLICATION PERMIT Wet System Dry System Cooking Hood Clean
More informationCommercial Rules and Regulations
Commercial Rules and Regulations Public Works and Community Development Department City of Shenandoah 29955 I 45 North Shenandoah, Texas 77381 281 298 5522 www.shenandoahtx.us Construction Documents Submit
More informationFIRE DEPARTMENT SYSTEM PERMIT APPLICATION
Permit No:_ FIRE DEPARTMENT SYSTEM PERMIT APPLICATION Thank you for submitting plans for the installation or modification of a required fire protection or detection system. Typical review of system plans
More informationEL DORADO COUNTY REGIONAL FIRE PROTECTION STANDARD
EL DORADO COUNTY REGIONAL FIRE PROTECTION STANDARD Installation of Residential Fire Sprinkler Systems STANDARD #C-002 EFFECTIVE 03-19-2009 PURPOSE: To ensure that sprinkler plans submitted for review contain
More informationFire Alarm Acceptance Testing & On-Going Maintenance with The Joint Comm. Standards / Reporting. Prepared Especially for : OSFM TEC 2016
Fire Alarm Acceptance Testing & On-Going Maintenance with The Joint Comm. Standards / Reporting Prepared Especially for : OSFM TEC 2016 Acceptance Testing 11-2008 Agenda Before you begin Completing the
More informationPlant Processing and Extraction Facilities
Orange County Fire Authority Community Risk Reduction 1 Fire Authority Road, Building A, Irvine, CA. 92602 www.ocfa.org 714-573-6180 Plant Processing and Extraction Facilities Guideline G-16 Serving the
More informationSECTION : FIRE ALARM & DETECTION SYSTEMS
SECTION 28 31 10: FIRE ALARM & DETECTION SYSTEMS 1. GENERAL A. This section applies to fire detection/alarm system and carbon monoxide system components and equipment installed during new construction
More information1. The fire detection and alarm system (including the conduit) shall be a separate bid item and not part of the general electrical contract.
PART 1 - GENERAL SECTION 28 31 11 STANDARD 1.1 FIRE ALARM SYSTEM REQUIREMENTS A. Contractor Requirements 1. The fire detection and alarm system (including the conduit) shall be a separate bid item and
More informationCOMMISSION ORDER. IT IS FURTHER ORDERED that the Request for Bid and Notice to Bidders be displayed on the Franklin County website.
4.e STATE OF MISSOURI County of Franklin ss. COMMISSION ORDER Commission Order No. 2016-316 Third Quarter Term 2016 Tuesday,August,09,2016 Bid Notice IN THE MATTER OF ADVERTISING FOR SEALED BIDS FOR SMOKE
More informationFIRE SPRINKLER SYSTEMS POLICY
FIRE SPRINKLER SYSTEMS POLICY Revised 1/1/17 DESIGN AND SUBMITTAL REQUIREMENTS All new and existing fire sprinkler systems within the jurisdiction of the City Fire Department shall meet all of the applicable
More informationWelcome to the Keys to a Successful Fire / Life Safety Inspection and Sustained Tenant & Building Safety
Welcome to the Keys to a Successful Fire / Life Safety Inspection and Sustained Tenant & Building Safety 2017 Keys to a Successful Fire / Life Safety Inspection and Sustained Tenant & Building Safety First
More informationCLARK COUNTY FIRE DEPARTMENT Fire Prevention Bureau
CLARK COUNTY FIRE DEPARTMENT Fire Prevention Bureau 575 E. Flamingo Road, Las Vegas, NV 89119 (702) 455-7316 FAX (702) 455-7347 Permit Type: 105.7.14 Control Number: A.0 Effective Date: 9/14/11 TITLE:
More informationPART II: New Construction Inspections and Acceptance Testing Procedures
Stafford County Fire Marshal s Office Handbook for Building/Fire Code Policies and Guidelines PART II: New Construction Inspections and Acceptance Testing Procedures Phone: 540-658-8648 Fax: 540-658-9128
More informationSOCIETY OF FIRE PROTECTION ENGINEERS POSITION STATEMENT P THE ENGINEER AND THE TECHNICIAN DESIGNING FIRE PROTECTION SYSTEMS.
SOCIETY OF FIRE PROTECTION ENGINEERS POSITION STATEMENT P-01-05 THE ENGINEER AND THE TECHNICIAN DESIGNING FIRE PROTECTION SYSTEMS October, 2005 Society of Fire Protection Engineers - 1 - Position Statement
More informationSACRAMENTO FIRE DEPARTMENT FIRE PREVENTION DIVISION FIRE DEPARTMENT DEVELOPMENT SERVICES UNIT CONTRATOR INFORMATION PACKET
SACRAMENTO FIRE DEPARTMENT FIRE PREVENTION DIVISION FIRE DEPARTMENT DEVELOPMENT SERVICES UNIT CONTRATOR INFORMATION PACKET 1 SACRAMENTO FIRE DEPARTMENT FIRE PREVENTION DIVISION FIRE DEPARTMENT DEVELOPMENT
More informationUpdate all extract references to NFPA documents (including NFPA 72) in Chapter 3 and related annex material to the latest editions.
11/16/12 TerraView First Revision No. 15-NFPA 720-2012 [ Global Input ] Update all extract references to NFPA documents (including NFPA 72) in Chapter 3 and related annex material to the latest editions.
More informationStandard of Practice - Fire Alarm Systems. NOTE: Significant revisions or additions to the previous standards are highlighted in italics.
A28.1 Standard of Practice - Fire Alarm Systems NOTE: Significant revisions or additions to the previous standards are highlighted in italics. OBJECTIVE OF STANDARD To provide compliant smart addressable
More informationSandwich Community Fire Protection District. Plan Review Submittal Guidelines and Requirements
Sandwich Community Fire Protection District Plan Review Submittal Guidelines and Requirements The Sandwich Community Fire Protection District is the Authority Having Jurisdiction for the plan review and
More informationBULLETIN. Permitting Tips (11/10)
BULLETIN Permitting Tips (11/10) This bulletin is to make you aware of issues that have been identified by the City or other retailers and suggests Tenant s architect and engineer pursue further as it
More informationFIRE SPRINKLER SYSTEMS POLICY
FIRE SPRINKLER SYSTEMS POLICY VERSION 1.012/2015 FIRE SPRINKLER SYSTEMS Design and Submittal requirements All new and existing fire sprinkler systems within the jurisdiction of the City of San Mateo Fire
More informationCHAPTER 61G15-32 RESPONSIBILITY RULES OF PROFESSIONAL ENGINEERS CONCERNING THE DESIGN OF FIRE PROTECTION SYSTEMS
CHAPTER 61G15-32 RESPONSIBILITY RULES OF PROFESSIONAL ENGINEERS CONCERNING THE DESIGN OF FIRE PROTECTION SYSTEMS 61G15-32.001 61G15-32.002 61G15-32.003 61G15-32.004 61G15-32.005 61G15-32.006 61G15-32.007
More informationCOUNTY OF KINGS KINGS COUNTY JAIL EXPANSION PHASE III
SECTION 28 3111 - DIGITAL ADDRESSABLE FIRE ALARM SYSTEM PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. General provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification
More informationPACDA Application Forms. 5/15/2018 Aman Fire Protection Consultants 1
PACDA Application Forms 5/15/2018 Aman Fire Protection Consultants 1 PACDA Submission Forms Preliminary Approval Form Final Approval Form Hazards Material Approval Form 5/15/2018 Aman Fire Protection Consultants
More informationH BUTCH BROWNING FIRE MARSHAL BUILDING REHABILITATION
STATE OF LOUISIANA Department of Public Safety and Corrections Office of State Fire Marshal Code Enforcement and Building Safety 8181 Independence Boulevard Baton Rouge, Louisiana 70806 225-925-4920 H
More informationFire Sprinkler Submittal Requirements and Acceptance Testing
Lubbock Fire Marshal s Office 1601 Mac Davis Lane Lubbock, Texas 79401 806-775-2646 Fax 806-775-3508 fireprevention@mylubbock.us Fire Sprinkler Submittal Requirements and Acceptance Testing To all Registered
More informationStandard for the Installation of Carbon Monoxide (CO) Detection and Warning Equipment
NFPA 720 2015 Summary Standard for the Installation of Carbon Monoxide (CO) Detection and Warning Equipment TM, 7Oct14 CODE: Title, Standard, not Code Consistent with recent trend at NFPA, this document
More informationFIRE CODE. Coal City Fire District International Fire Code Update. 35 S. DeWitt Place Coal City, IL
. 2015 FIRE CODE 2015 International Fire Code Update Coal City Fire District 35 S. DeWitt Place Coal City, IL 60416 815-634-4700 Table of Contents SECTION 109 VIOLATIONS... 3 SECTION 111 STOP WORK ORDER...
More informationSPECIFICATION FOR A TOTAL FLOOD ECARO-25 TM CLEAN AGENT FIRE SUPPRESSION SYSTEM FOR USE WITH THE SHP PRO CONTROL PANEL SYSTEM
SECTION 1 - GENERAL CONDITIONS SPECIFICATION FOR A TOTAL FLOOD I. SCOPE: This specification outlines the requirements for a Total Flood ECARO-25 TM clean agent fire suppression system utilizing HFC-125
More informationMECKLENBURG COUNTY FIRE MARSHAL S OFFICE
Effective Date: 11/01/02 Purpose: MECKLENBURG COUNTY To establish a set of guidelines for performance testing of all newly installed or upgraded fire alarm systems in order to ensure that all devices and
More informationTo expedite the plan review and inspection processes, please refer to the information below.
Guidelines: The goal of the Denison Fire Department is to assist its customers in understanding our submittal, plan review and inspection process and policies, as they pertain to new construction. Familiarity
More informationFIRE INSPECTORS GUIDELINES FOR PLAN REVIEWS AND INSPECTIONS OF NEW CONSTRUCTION / ADDITIONS AND CHANGE OF OCCUPANCY
FIRE INSPECTORS GUIDELINES FOR PLAN REVIEWS AND INSPECTIONS OF NEW CONSTRUCTION / ADDITIONS AND CHANGE OF OCCUPANCY PLAN REVIEWS SITE PLANS: 1) Access to buildings (Volume V NC Building Code sections 602.6.1
More informationSANTA ROSA FIRE DEPARTMENT FIRE PREVENTION BUREAU STANDARD
July 1, 2010 SANTA ROSA FIRE DEPARTMENT FIRE PREVENTION BUREAU STANDARD STANDPIPE SYSTEMS PURPOSE This standard outlines the general requirements for the installation of standpipe systems. CODE REFERENCES
More information