1 EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT Factory South Panishail, Kashimpur, Joydebpur, Gazipur Joydebpur, Gazipur 04 May 2014 The Alliance for Bangladesh Worker Safety Page 1/17

2 Factory 04 May 2014 Introduction to the Report The following report contains a site profile and summary of non-conformities identified during an onsite assessment commissioned by the Alliance for Bangladesh Worker Safety (Alliance) and conducted by a third-party Qualified Assessment Firm (QAF). The assessment was conducted against the Alliance for Bangladesh Worker Safety Assessment Protocols (APs) and Fire Safety and Structural Integrity Standard, which is harmonized with the factory assessment guidelines developed by Bangladesh University of Engineering and Technology (BUET) for the Bangladesh National Tripartite Plan of Action (NTPA). The goal of the Alliance process is to provide clear and practical technical requirements by which Bangladeshi Ready Made Garment (RMG) Factories producing for Alliance members may be consistently and fairly evaluated for fire, structural, and electrical safety in a non-duplicative manner. Each assessment will prompt action plans that will be used by RMG factories to systematically and sustainably improve safety conditions for garment workers. Beyond tracking and reporting on action steps taken in a transparent manner, the Alliance organization and its members will seek to further support factory improvements through technical assistance, training, implementation support for functional Worker Committees, and in some cases financial assistance and wage support for workers if factories are closed for remediation. The contents of the report do not constitute a guarantee of compliance with the applicable laws, the Alliance Standard or the absolute or continued safety against fire, electrical and/or structural integrity issues that may lead to injury or loss of life. The report is designed to provide a non-exhaustive summary of risk issues, based on a limited sampling and duration of time onsite by the named QAF. Neither the QAF nor the Alliance can certify or guarantee the quality, outcome, or effectiveness of actions taken in response to the report. For more information and report feedback please go to: The Alliance for Bangladesh Worker Safety Page 2/17

3 04 May 2014 GENERAL INFORMATION General Information Factory Country: Province: City: Bangladesh Dhaka Joydebpur, Gazipur Zip Code: 1349 Audit Duration: Re-Audit: 1 Days Re-Audit After 0 Months Draft Report Date : Final Report Date : Are all action items from previous assessment complete? : Buildings in Complex : Is the building(s) owned or rented by the Factory?: Number of Building Levels (Stories) : Approximate Building Area (SF) : Date of Building Construction : Date of Last Building N/A There are 5 buildings on the premises: two are main production buildings and are ancillary buildings. The buildings are named as: 1) Four story RCC main production building, 2) Single story knitting production shed, 3) Single story generator Shed-1, 4) Single story generator Shed-2, 5) Single story Prayer Shed. Rented Information provided below as per following format: est occupied floor level [Height up to roof], Stories above grade, Stories below grade, Occupied levels. 1) Four story RCC main production building: 9.65 m or ft [12.7 m or ft], 4, 0, 4. 2) Single story knitting production shed: 0.15 m or 0.5 ft above grade [4.25 m or ft], 1, 0, 1. 3) Single story generator Shed-1: 0.15 m or 0.5 ft above grade [4.25 m or ft], 1, 0, 1. 4) Single story generator Shed-2: 0.15 m or 0.5 ft above grade [3.05 m or 10 ft], 1, 0, 1. 5) Single story Prayer Shed: 0.15 m or 0.5 ft above grade [3.05 m or 10 ft], 1, 0, 1. Total area of buildings in the factory premises: SF. Building wise breakdown as follows: 1) Four story RCC main production building: SF (Ground floor: SF, 1st floor: SF, 2nd floor: SF, 3rd floor: SF), 2) Single story knitting production shed: SF, 3) Single story generator Shed-1: SF, 4) Single story generator Shed-2: SF, 5) Single story Prayer Shed: SF. Factory personnel informed the date of construction as follows: 1) Four story RCC main production building: Construction completed in No record of date of construction for rest of the buildings were found. No record for date of renovations or additions were found from factory personnel. The Alliance for Bangladesh Worker Safety Page 3/17

4 04 May 2014 Renovation/Addition : Ancillary Structures in Complex : Approximate Ancillary Structures Area (SF) : Number of Occupants : Provide brief description of the electrical system for each building.: Physical location of Substation? : What equipment/loads does the UPS serve? : 1) Single story generator Shed-1, 2) Single story generator Shed-2, 3) Single story Prayer Shed. 1) Single story generator Shed-1: SF, 2) Single story generator Shed-2: SF, 3) Single story Prayer Shed: SF. Total number of occupants: ) Four story RCC main production building: 937 (Ground floor: 116, 1st floor: 198, 2nd floor: 475, 3rd floor: 148), 2) Single story knitting production shed: 60, 3) Single story generator Shed-1: 1, 4) Single story generator Shed-2: 1, 5) Single story Prayer Shed: 1. Source: REB Transformer (500KVA) 1, Generator (1000 KVA) 1; Generator (232KVA) 1; Generator (140KVA) 1; HT Panel 1; LT Panel 1; PFI Panel 1; DB-11; SDB 10. Located in the ground floor main building near main entrance. Computer The Alliance for Bangladesh Worker Safety Page 4/17

5 04 May 2014 ASSESSMENT FINDINGS Electrical System Maintenance Is a periodical Insulation Resistance Measurement Program established and recorded? No periodical Insulation Resistance Measurement Program established. Document Review: No periodical Insulation Resistance Measurement Program. Develop an Insulation Resistance Measurement Program that ensures deterioration of insulation resistance will be identified quickly. Testing should be in compliance with International Electrical Testing Association (NETA). All transformers, switchgears, e Alliance Standard Part 10 Section Insulation Tests and Electrical Inspections Is the electrical switchgear and panel boards inspected on an annual basis to ensure that the equipment is installed in accordance with the listed ratings? The electrical switchgear and panel boards are not inspected on an annual basis to ensure that the equipment is installed in accordance with the listed ratings. Document Review: No annual testing and inspection records of the electrical systems. Develop an electrical maintenance program that includes inspections and testing of the electrical systems. Reference NFPA 70 for example program requirements. Alliance Standards Part 10 Section Electrical Inspections Are thermographic scans of electrical equipment completed at least every three years? The Alliance for Bangladesh Worker Safety Page 5/17

6 04 May 2014 Thermographic scans of electrical equipment has not been done. Document Review: No thermographic scans for electrical equipment. Complete thermographic scans at least on a three year cycle. Thermographic scans should be completed in accordance with the Standard for Infrared Inspection of Electrical Systems & Rotating Equipment and NFPA70B or a comparable standard. Alliance Standards Part 10 Section Electrical Inspections Transformers do not contain harmful substances such as PCBs. No evidence (certificate) was found that can confirm that the transformer does not contain any harmful substances. Document Review: No evidence was found. Consult with a transformer manufacturing company to ensure that the transformer does not contain any harmful substances. Not Applicable Are periodic safety inspections of the electrical system components completed and documented? No periodic safety inspections of the electrical system components have been done. Document Review: No periodic safety inspections of the electrical system. Establish a periodic inspection program to ensure the electrical systems are free from damage, debris, dirt, lint, etc. Maintain records concerning inspections and follow up actions. The Alliance for Bangladesh Worker Safety Page 6/17

7 04 May 2014 Alliance Standard Part 10 Section Inspection and Testing and Part 13 Section 13.6 Housekeeping A transformer oil analysis is routinely completed on main service transformers. Low Transformer oil analysis is not completed. Worker Interviews: Transformer oil analysis is not completed. Complete an oil analysis on the applicable transformers at the appropriate intervals based on the voltage and power. Alliance Standard Part 10 Section Electrical Inspections Electrical System Conditions The substation room has the required fire rating/protection and is physically separated from the remainder of the building. The door of the substation room is not fire rated. Photograph: No fire rating. Provide adequate fire protection for the substation room and make it separate from rest of the building. Alliance Standard Part 3 Section Are all switchboards and/or distribution boards metal enclosed with a dead front construction? Non-Compliance Level: 2 All distribution boards are metal enclosed, but do not have dead front construction with the exception of four distribution boards. Location: All distribution boards (Except LT-Panel, Substation Room; DB-1, Knitting Section; DB-2, Knitting Section; DB-3, Knitting Section). Photograph: Some distribution boards are metal enclosed, but do not have dead front construction. The Alliance for Bangladesh Worker Safety Page 7/17

8 04 May 2014 Ensure distribution boards are metal enclosed with a dead front construction. 17 Jun 2014 Alliance Standards Part 10 Section 10.7 Main Switch, Switchboards and Metal Clad Switchgear All metal in the building is connected to the building earthing/grounding system such as metal rebar in concrete, metal frame of building, or metal water pipe. Non-Compliance Level: 2 Not all metal in the building is connected to the building earthing system. Unconnected metal includes a cable ladder. Location: Substation room; Generator room-1; Generator room-2; Prayer room. Photograph: Not all of the metal in the building is connected to the building's earthing system. Connect all metal in the building to the building's earthing and grounding system. This should include metal such as the rebar in the concrete, the metal frame of the building, and the metal water pipes. Alliance Standard Part 10 Section Earthing Indications of overheating, overloading, or signs of burning were not observed. Non-Compliance Level: 1 Indications of overheating (89 C) were observed. Location: LT-Panel, Substation Room. Photograph: Indications of overheating were observed. Find out the cause of the overheating and take proper action and consider replacement of conductors and equipment. 07 May 2014 Alliance Standard Part 10 Section The Alliance for Bangladesh Worker Safety Page 8/17

9 04 May 2014 Is electrical wiring/cables sized according to capacity of circuit breakers (No higher rated circuit breakers with lower rated wiring)? Non-Compliance Level: 1 The electrical cables are not sized according to the capacity of the circuit breakers. er rated circuit breakers with lower rated wiring are present. Location: DB, 3rd Floor. Photograph: er rated circuit breakers with lower rated wiring. Consult with a qualified electrical engineer and ensure the electrical wiring and cables are sized according to the capacity of the circuit breakers. Alliance Standard Part 10 Section Electrical Connections. No multi looping of wiring/cables observed at circuit breakers within switchboards and/or distribution boards. Non-Compliance Level: 1 Multi looping of cables was observed at the circuit breakers within the distribution boards. Location: DB, 3RD Floor; DB-4, 2nd floor. Photograph: Multi looping of cables at the circuit breakers. Remove the multi looping of cables at the circuit breakers within the distribution boards. Alliance Standard Part 10 Section 10.3 Electrical Wiring and Cabling The substation room has adequate ventilation. The substation room does not have adequate ventilation. Photograph: Inadequate ventilation in the substation room. Provide a means of ventilation for the substation room. Consult a qualified electrical engineer to determine the required ventilation rates based on the installed equipment. 17 Jun 2014 The Alliance for Bangladesh Worker Safety Page 9/17

10 04 May 2014 Alliance Standard Part 10 Section Inspection of Substation Installations. Do switchboards and/or distribution boards have clear identification markings? Distribution boards do not have clear identification markings. Location: All distribution boards. Photograph: No clear identification markings. Ensure clear and permanent identification marks are painted on all distribution boards, switchboards, sub main boards, and switches. 17 Jun 2014 Alliance Standard Part 10 Section 10.7 BNBC Part 8 Section Do switchboards and/or distribution boards have capacity information labels? Distribution boards do not have capacity information labels. Location: All distribution boards. Photograph: No DB capacity information labels. Provide capacity information labels (Maximum current rating, number of circuit breakers, etc.) for switchboards and/or distribution boards. 17 Jun 2014 Alliance Standard Part 10 Section 10.7 Main Switch, Switchboards And Metal Clad Switchgear and Inspection of the Installation Are switchboards and/or distribution boards provided with physical means to prevent the installation of more over current devices than that number for which the panel board was designed, rated, and listed. Switchboards and distribution boards are not provided with physical means to prevent the installation of more over current devices than that number for which the panel board was designed, rated, and listed. Location: All distribution boards. The Alliance for Bangladesh Worker Safety Page 10/17

11 04 May 2014 Photograph: No means to prevent the installation of more over current devices. Ensure switchboards and/or distribution boards are provided with physical means to prevent the installation of more over current devices than that number for which the panel board was designed, rated, and listed following NFPA 70 section Alliance Standards Part 10 Section 10.7 Main Switch, Switchboards and Metal Clad Switchgear Each circuit is provided with a dedicated neutral. Each circuit is not provided with a dedicated neutral. Location: All Distribution boards. Photograph: No dedicated neutral. Provide a dedicated neutral for each circuit. Alliance Standards Part 10 Section 10.3 Electrical Wiring and Cabling Are electrical wiring/cables properly identified? Electrical cables are not properly identified. Location: All distribution boards. Photograph: Electrical cables are not identified. Ensure that cables are identified by separate color coding, marking tape, tagging, or any other approved means. Bangladesh Electricity Rules 1937 Rule 51 and 56 The Alliance for Bangladesh Worker Safety Page 11/17

12 04 May 2014 Are all internal components of switchboards and/or distribution boards properly concealed (No missing circuit breaker or knockout covers)? Non-Compliance Level: 2 The internal components of the distribution boards are not properly concealed. Location:DB-1, packing, 1st floor; DB-1, knitting, 1st floor; DB-2, knitting, 1st floor; DB-3, knitting, 1st floor. Photograph: Internal components are not properly concealed. Provide covers or blanks to conceal all of the live internal components of the switchboards and/or distribution boards. 04 Jun 2014 Alliance Standard Part 10 Section Sub-Distribution Boards Cable joints are through porcelain/pvc connectors with PIB tape wound around joint. Non-Compliance Level: 2 Cable joints are not through porcelain/pvc connectors with PIB tape wound around the joint. Location: DB-1, Knitting Section, Ground Floor; DB-3, Accessories Section, Ground Floor; DB-4, Accessories Section; SDB-2, HR Office, 1st Floor. Photograph: Improper cable joints were found. Ensure cable joints through porcelain/pvc connectors with PIB tape wound around the joint. Alliance Standards Part 10 Section Cable Joints Are there additional areas of non-compliance to report? Non-Compliance Level: 2 A bunch of cables are connected to the MCCB and the MCB. Location: DB, Sewing Section, 3rd Floor; DB-4, Accessories Section, Ground Floor; LT Panel, Substation Room, Ground Floor; SDB-2, HR Office, 1st Floor; SDB-3, Knitting Section, Ground Floor. Photograph: A bunch of cables are connected to the MCCB and the MCB. The Alliance for Bangladesh Worker Safety Page 12/17

13 04 May 2014 Need to remove the bunch of cables from the MCCB and the MCB. Not Applicable Are electrical insulation mats provided in front of substation, switchboards and/or distribution boards? Low Adequate electrical insulation mats are not provided in front of the substation, switchboards, and distribution boards. Location: All switchboards and distribution boards. Photograph: Non-graded insulation mats. Provide electrical insulation mats in front of the substation, switchboards, and distribution boards. Alliance Standard Part 10 Section Inspection of the Installation. Phase separators are provided between terminals on circuit breakers. Low Non-Compliance Level: 2 Phase separators are not provided between the terminals on the circuit breakers. Location: DB-1, Canteen, 3rd Floor; DB-2, Iron section, 3rd Floor; DB-2, Sample Section, 3rd Floor; DB-3, Sewing Section, 2nd Floor; DB-4, 2nd Floor, Sewing Section. Photograph: No phase separators. Install phase separators between terminal connections at the noted locations. 17 Jun 2014 Alliance Standard Part 10 Section Electrical Connections Signage indicating the prohibition of light fixtures without protective covers is installed at required locations. Low Non-Compliance Level: 2 The Alliance for Bangladesh Worker Safety Page 13/17

14 04 May 2014 No signage indicating the prohibition of light fixtures without protective covers is installed at the required locations. Location: Store Room, Ground floor. Photograph: No signage indicating the prohibition of the installation of naked light fixtures at the required location. Ensure signage indicating the prohibition of light fixtures without protective covers is installed at the required locations. 04 Jun 2014 Alliance Standards Part 10 Section Naked Lights Emergency Power System Is the generator room properly rated and physically separated from the remainder of the building? The generator room is not properly fire rated. Location: Generator room -1, Generator room -2. Photograph: Generator room is not rated. Ensure the generator room is properly rated and physically separated from the remainder of the building. 17 Jun 2014 Alliance Standards Part 10 Section Generator Room Are cable trenches properly covered? Cable trenches are not covered properly. Location: Generator Room-1. Photograph: Inadequate cable trench covering. Provide adequate cover on the cable trench. 04 Jun 2014 Alliance Standard Part 10 Section Inspection of the Installation Are emergency power switchboards, distribution boards, and circuits properly The Alliance for Bangladesh Worker Safety Page 14/17

15 04 May 2014 identified? Emergency power switchboards, distribution boards, and circuits are not properly identified. Worker Interviews: As discussed with the factory's concerned person, no identification of emergency DBs/CKTs. Ensure proper identification of emergency power switchboards, distribution boards, and circuits. 04 Jun 2014 NFPA 70 Chapter 7 Article Wiring, Emergency System Is the generator room appropriately sized in order to properly access the generator to perform routine maintenance activities? The size of generator room is not appropriate. Location: Generator Room-1 and Generator Room-2. Photograph: Inadequate generator room size. Ensure that the generator room is sized so that the generator can be properly accessed for routine maintenance activities. 30 Jul 2014 Alliance Standard Part 10 Section Generator Room Are inspection, maintenance, and testing procedures of the emergency generator being completed and documented? Low Inspection, maintenance, and testing procedures of the emergency generator are not completed. Document Review: Inspection, maintenance, and testing procedures of the emergency generator are not completed and documented. Ensure that inspection, maintenance, and testing procedures of the emergency generator are being completed and documented. The Alliance for Bangladesh Worker Safety Page 15/17

16 04 May 2014 NFPA 110 Chapter 8 Are inspection, maintenance, and testing procedures of the UPS being completed and documented? Low Inspection, maintenance, and testing procedures of the UPS are not completed. Document Review: No documentation on UPS testing and maintenance is available. Ensure that inspection, maintenance, and testing procedures of the UPS are completed and documented. Alliance Standard Part 13 Section NFPA 111 Chapter 8 NFPA 70B Chapter 28 Is the appropriate type and number of firefighting equipment installed inside the generator room? Low Non-Compliance Level: 1 An appropriate type and number of firefighting equipment is not installed inside the generator room. Location: Generator Room - 2. Photograph: Inadequate firefighting equipment. Install the appropriate type and number of firefighting equipment inside the generator room. 04 Jun 2014 Is the appropriate type and number of firefighting equipment installed inside the generator room? Lightning Protection System The appropriate number of down conductors are installed based on the building size. The Alliance for Bangladesh Worker Safety Page 16/17

17 04 May 2014 The appropriate number of down conductors are not installed based on the building size. Photograph: Inadequate number of down conductors. Ensure an appropriate number of down conductors are installed based on the building size. 17 Jun 2014 Alliance Standards Part 10 Section Lightning Protection The Alliance for Bangladesh Worker Safety Page 17/17

EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT

EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT Factory 50-60, Dakkhin Panishail. N.K. Link Road, Kashimpur, Gazipur Gazipur 08 May 2014 The Alliance for Bangladesh Worker Safety Page 1/23 08 May 2014

More information

EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT

EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT Hatimara Road, Barenda, Kashimpur, Gazipur, Gazipur Dhaka The Alliance for Worker Safety Page 1/18 Introduction to the Report The following report contains

More information

INITIAL ELECTRICAL ASSESSMENT REPORT (EAR)

INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) Factory C-13, South Badda, Gulshan-1, Badda, Dhaka Dhaka Dhaka 22 May 2014 The Alliance for Worker Safety Page 1/21 22 May 2014 Introduction to the Report The

More information

EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT

EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT Factory Kunia, K.B.Bazar, Joy Bangla Road, Barabari, Gazipur Gazipur Dhaka 12 May 2014 The Alliance for Worker Safety Page 1/14 Factory 12 May 2014 Introduction

More information

INITIAL ELECTRICAL ASSESSMENT REPORT (EAR)

INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) Factory Name: 4 YOU CLOTHING LTD 367/1 Senpara Parbata, Mirpur-10, Dhaka Dhaka Dhaka Bangladesh 27 May 2014 The Alliance for Bangladesh Worker Safety Page 1/18

More information

EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT

EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT Factory Sharoj Tower, Plot No, M-4/2, Section-14, Mirpur, Dhaka Dhaka Dhaka 20 May 2014 The Alliance for Worker Safety Page 1/18 20 May 2014 Introduction

More information

EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT

EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT Factory 169-171 Tetulzhora Union, Hemayetpur, Savar Savar Dhaka 24 May 2014 The Alliance for Worker Safety Page 1/20 24 May 2014 Introduction to the Report

More information

INITIAL ELECTRICAL ASSESSMENT REPORT (EAR)

INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) Factory Name: Plot 33-35, Dhaka (EPZ), Savar Savar Dhaka Bangladesh 06 Jul 2014 The Alliance for Bangladesh Worker Safety Page 1/19 06 Jul 2014 Introduction to

More information

INITIAL ELECTRICAL ASSESSMENT REPORT (EAR)

INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) Factory Name: AJ Super Garments Ltd (Woven) Aj Garden, Goshbagh Zirabo Zirabo, Savar Savar Dhaka Bangladesh 23 Mar 2014 The Alliance for Bangladesh Worker Safety

More information

INITIAL ELECTRICAL ASSESSMENT REPORT (EAR)

INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) Factory Plot No. 60&61, Sector-3, KEPZ, North Patenga, Chittagong Chittagong 11 Feb 2015 The Alliance for Bangladesh Worker Safety Page 1/17 11 Feb 2015 Introduction

More information

INITIAL ELECTRICAL SAFETY ASSESSMENT - EXPANSION

INITIAL ELECTRICAL SAFETY ASSESSMENT - EXPANSION INITIAL ELECTRICAL SAFETY ASSESSMENT - EXPANSION Assessor: Nalzani, Chandana Joydebpur, Gazipur Joydebpur, Gazipur Dhaka Emkay Enterprises The Alliance for Worker Safety Page 1/13 Introduction to the Report

More information

INITIAL ELECTRICAL ASSESSMENT REPORT (EAR)

INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) Assessor: Karardi, Shibpur, Narsingdi Narsingdi Dhaka Bangladesh Emkay Enterprises The Alliance for Bangladesh Worker Safety Page 1/15 10 Apr 2016 Introduction

More information

INITIAL ELECTRICAL ASSESSMENT REPORT (EAR)

INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) Factory SFB 2 Adamjee EPZ, Siddergonj, Narayangonj, Siddhirgonj Dhaka 22 Feb 2017 The Alliance for Worker Safety Page 1/18 Factory 22 Feb 2017 Introduction to

More information

INITIAL ELECTRICAL SAFETY ASSESSMENT - EXPANSION

INITIAL ELECTRICAL SAFETY ASSESSMENT - EXPANSION INITIAL ELECTRICAL SAFETY ASSESSMENT - EXPANSION Yunusco (BD) Ltd(Formerly Shore To Shore Textiles Ltd.) Plot# 224-233, Adamjee EPZ, Shiddirgonj, Narayangonj Siddirgonj The Alliance for Bangladesh Worker

More information

EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT

EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT Factory Assessor: Thakurbari TEAC, Masumabad, Bhulta, Rupganj, Narayangonj Rupgonj Uttaron 18 Nov 2013 The Alliance for Bangladesh Worker Safety Page 1/12

More information

INITIAL ELECTRICAL ASSESSMENT REPORT (EAR)

INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) Factory Assessor: 5th floor, Ehasan Tower, 227/B, Hafez Nagar, Bakalia, Chittagong. Uttaron 22 Jul 2014 The Alliance for Bangladesh Worker Safety Page 1/19 Factory

More information

INITIAL ELECTRICAL ASSESSMENT REPORT (EAR)

INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) Factory Address: 687, Al-Haj Nurl Amin Sowdagar Lane CDA, R/A, Road No 20, South Agrabad Chittagong Chittagong Bangladesh 03 Apr 2014 The Alliance for Bangladesh

More information

INITIAL ELECTRICAL ASSESSMENT REPORT (EAR)

INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) Factory Name: Tetlabo, Rupgonj, Narayangonj Rupgonj Dhaka Bangladesh 27 May 2014 The Alliance for Bangladesh Worker Safety Page 1/22 27 May 2014 Introduction

More information

EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT

EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT Factory Assessor: 33/1, Darail, Shataish Tongi, Gazipur Tongi, Gazipur Dhaka Emkay Enterprises 26 Feb 2014 The Alliance for Worker Safety Page 1/12 26 Feb

More information

INITIAL ELECTRICAL ASSESSMENT REPORT (EAR)

INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) Address: Plot 61-64 & 70-73, Sector 02, KEPZ Karnafully, North Patenga, Chittagong Chittagong Chittagong Bangladesh The Alliance for Bangladesh Worker Safety

More information

EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT

EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT Factory Assessor: Plot #92 (Partial) DEPZ Extention Area-02 Ganakbari, Ashulia, Savar Uttaron 10 Feb 2014 The Alliance for Bangladesh Worker Safety Page

More information

EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT

EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT Factory Address: Assessor: 1Plot # 4 (half) 8, 12 (half)-16, DEPZ (Old), Dhaka EPZ, Ganakbari, Ashulia, Savar Ashulia, Savar Dhaka Bangladesh Uttaron 25

More information

INITIAL ELECTRICAL ASSESSMENT REPORT (EAR)

INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) Assessor: N. Islam Center, Mazar Road, Dhakkhin Khan Uttara, Dhaka Dhaka Emkay Enterprises The Alliance for Bangladesh Worker Safety Page 1/6 Introduction to

More information

INITIAL ELECTRICAL ASSESSMENT REPORT (EAR)

INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) Factory Name: Maks Fashion Ltd 1 Kapashgola Road Chawkbazar Chittagong Chittagong Bangladesh 19 Apr 2014 The Alliance for Bangladesh Worker Safety Page 1/15 19

More information

INITIAL ELECTRICAL ASSESSMENT REPORT (EAR)

INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) Factory 81, Kalmessar, "Jalal Shopping Complex" Board Bazar, Gazipur. 20 May 2014 The Alliance for Bangladesh Worker Safety Page 1/21 20 May 2014 Introduction

More information

EQUIVALENT INITIAL FIRE SAFETY ASSESSMENT

EQUIVALENT INITIAL FIRE SAFETY ASSESSMENT EQUIVALENT INITIAL FIRE SAFETY ASSESSMENT Factory Plot No. 74, Block -K, Rupnagar Ind. Area, Secti, Dhaka Dhaka Dhaka The Alliance for Worker Safety Page 1/8 Introduction to the Report The following report

More information

INITIAL FIRE SAFETY ASSESSMENT

INITIAL FIRE SAFETY ASSESSMENT INITIAL FIRE SAFETY ASSESSMENT Factory Nishchintapur, Ashulia DEPZ road, Zirabo, Savar Savar Dhaka 08 May 2014 The Alliance for Worker Safety Page 1/8 08 May 2014 Introduction to the Report The following

More information

EQUIVALENT INITIAL FIRE SAFETY ASSESSMENT

EQUIVALENT INITIAL FIRE SAFETY ASSESSMENT EQUIVALENT INITIAL FIRE SAFETY ASSESSMENT Factory Name: 2 New Eskaton Road, Mogbazar, Dhaka Dhaka Dhaka Bangladesh 15 Jun 2013 The Alliance for Bangladesh Worker Safety Page 1/10 Factory Name: 15 Jun 2013

More information

EQUIVALENT INITIAL FIRE SAFETY ASSESSMENT

EQUIVALENT INITIAL FIRE SAFETY ASSESSMENT EQUIVALENT INITIAL FIRE SAFETY ASSESSMENT Factory 154 Kamrabad, Atarar Depot Chittagong Chittagong Chittagong The Alliance for Worker Safety Page 1/7 Introduction to the Report The following report contains

More information

INITIAL FIRE SAFETY ASSESSMENT

INITIAL FIRE SAFETY ASSESSMENT INITIAL FIRE SAFETY ASSESSMENT Factory Bashtoli, Sinabah, Sofipur, Kaliakoir, Gazipur Gazipur Dhaka 08 Sep 2014 The Alliance for Worker Safety Page 1/10 Factory 08 Sep 2014 Introduction to the Report The

More information

INITIAL FIRE SAFETY ASSESSMENT - EXPANSION

INITIAL FIRE SAFETY ASSESSMENT - EXPANSION INITIAL FIRE SAFETY ASSESSMENT - EXPANSION Hatimara Road, Barenda, Kashimpur, Gazipur, Gazipur Dhaka The Alliance for Worker Safety Page 1/11 30 Oct 2016 Introduction to the Report The following report

More information

INITIAL FIRE SAFETY ASSESSMENT

INITIAL FIRE SAFETY ASSESSMENT INITIAL FIRE SAFETY ASSESSMENT Factory 214 Baiozid Bostami Road Nasirabad Industrial Area Chittagong 04 Sep 2016 The Alliance for Bangladesh Worker Safety Page 1/11 Factory 04 Sep 2016 Introduction to

More information

INITIAL FIRE ASSESSMENT REPORT (FAR)

INITIAL FIRE ASSESSMENT REPORT (FAR) INITIAL FIRE ASSESSMENT REPORT (FAR) Factory 94/95 (OLD) 46 NEW (Ground To 5th), BLOCK C TONGI INDUSTRIAL AREA,, TONGI, GAZIPUR, GAZIPUR, 0, BD GAZIPUR Dhaka Bangladesh 11 Apr 2014 The Alliance for Bangladesh

More information

EQUIVALENT INITIAL FIRE SAFETY ASSESSMENT

EQUIVALENT INITIAL FIRE SAFETY ASSESSMENT EQUIVALENT INITIAL FIRE SAFETY ASSESSMENT Assessor: Konabari, Neelnagar, Gazipur Gazipur Dhaka Bangladesh Uttaron The Alliance for Bangladesh Worker Safety Page 1/13 Introduction to the Report The following

More information

INITIAL FIRE ASSESSMENT REPORT (FAR)

INITIAL FIRE ASSESSMENT REPORT (FAR) INITIAL FIRE ASSESSMENT REPORT (FAR) Factory SQ Station, Plot # 221-223, Jamirdia, Valuka, Mymensingh Mymensingh 17 Jun 2014 The Alliance for Bangladesh Worker Safety Page 1/17 Factory 17 Jun 2014 Introduction

More information

INITIAL FIRE SAFETY ASSESSMENT

INITIAL FIRE SAFETY ASSESSMENT INITIAL FIRE SAFETY ASSESSMENT Assessor: N. Islam Center, Mazar Road, Dhakkhin Khan Uttara, Dhaka Dhaka Emkay Enterprises The Alliance for Bangladesh Worker Safety Page 1/10 09 Jun 2014 Introduction to

More information

INITIAL FIRE SAFETY ASSESSMENT

INITIAL FIRE SAFETY ASSESSMENT INITIAL FIRE SAFETY ASSESSMENT Factory Plot No -246-249, Adamjee EPZ, Siddhirganj, Narayanganj Narayanganj 17 Jul 2016 The Alliance for Bangladesh Worker Safety Page 1/17 Factory 17 Jul 2016 Introduction

More information

EQUIVALENT INITIAL FIRE SAFETY ASSESSMENT

EQUIVALENT INITIAL FIRE SAFETY ASSESSMENT EQUIVALENT INITIAL FIRE SAFETY ASSESSMENT Factory Address: Plot # 59-87, Adamjee Export Processing ZONE, Adamjee Nagar, Siddergonj, Narayangonj, Siddirgonj, Narayangonj Dhaka Bangladesh 09 Jun 2014 The

More information

INITIAL FIRE SAFETY ASSESSMENT - EXPANSION

INITIAL FIRE SAFETY ASSESSMENT - EXPANSION INITIAL FIRE SAFETY ASSESSMENT - EXPANSION Factory Mogorkhal, Chowrasta, National University, Gazipur Gazipur Dhaka 09 May 2016 The Alliance for Worker Safety Page 1/13 09 May 2016 Introduction to the

More information

INITIAL FIRE SAFETY ASSESSMENT

INITIAL FIRE SAFETY ASSESSMENT INITIAL FIRE SAFETY ASSESSMENT Assessor: 28 S.S. Tower, Vogra, Joydebpur, Gazipur Joydebpur, Gazipur Dhaka Uttaron The Alliance for Worker Safety Page 1/17 12 Apr 2015 Introduction to the Report The following

More information

EQUIVALENT INITIAL FIRE SAFETY ASSESSMENT

EQUIVALENT INITIAL FIRE SAFETY ASSESSMENT EQUIVALENT INITIAL FIRE SAFETY ASSESSMENT B.K. Bari, Taltoli, Mirzapur Bazar, Gazipur Sadar Gazipur Gazipur Dhaka The Alliance for Worker Safety Page 1/11 Introduction to the Report The following report

More information

EQUIVALENT INITIAL FIRE SAFETY ASSESSMENT

EQUIVALENT INITIAL FIRE SAFETY ASSESSMENT EQUIVALENT INITIAL FIRE SAFETY ASSESSMENT Factory Nayabari, Kanchpur, Sonargaon, Narayanganj. Sonargaon Dhaka 14 Nov 2013 The Alliance for Worker Safety Page 1/15 Factory 14 Nov 2013 Introduction to the

More information

INITIAL FIRE SAFETY ASSESSMENT

INITIAL FIRE SAFETY ASSESSMENT INITIAL FIRE SAFETY ASSESSMENT Factory Assessor: 180, Baizid Bostami Road Nasirabad I/A Area-1, Building -1, Chittagong Chittagong Chittagong Bangladesh Emkay Enterprises 31 Jan 2015 The Alliance for Bangladesh

More information

INITIAL FIRE SAFETY ASSESSMENT

INITIAL FIRE SAFETY ASSESSMENT INITIAL FIRE SAFETY ASSESSMENT Cha 72/1/C, Ground-4th FL, Progoti Swarani, Uttar Badda, Dhaka Dhaka The Alliance for Bangladesh Worker Safety Page 1/16 Introduction to the Report The following report contains

More information

EQUIVALENT INITIAL FIRE SAFETY ASSESSMENT

EQUIVALENT INITIAL FIRE SAFETY ASSESSMENT EQUIVALENT INITIAL FIRE SAFETY ASSESSMENT Factory Name: 4 YOU CLOTHING LTD 367/1 Senpara Parbata, Mirpur-10, Dhaka Dhaka Dhaka Bangladesh 27 May 2014 The Alliance for Bangladesh Worker Safety Page 1/20

More information

EQUIVALENT INITIAL FIRE SAFETY ASSESSMENT

EQUIVALENT INITIAL FIRE SAFETY ASSESSMENT EQUIVALENT INITIAL FIRE SAFETY ASSESSMENT Factory Plot # 33-36 Sector # 07, Chittagong Chittagong Chittagong 08 Jun 2014 The Alliance for Worker Safety Page 1/18 08 Jun 2014 Introduction to the Report

More information

EQUIVALENT INITIAL FIRE SAFETY ASSESSMENT

EQUIVALENT INITIAL FIRE SAFETY ASSESSMENT EQUIVALENT INITIAL FIRE SAFETY ASSESSMENT 171-181, Baizid Bostami Road Nasirabad I/A, Chittagong Chittagong The Alliance for Bangladesh Worker Safety Page 1/14 Introduction to the Report The following

More information

EQUIVALENT INITIAL FIRE SAFETY ASSESSMENT

EQUIVALENT INITIAL FIRE SAFETY ASSESSMENT EQUIVALENT INITIAL FIRE SAFETY ASSESSMENT Vill: Golora, Post: Kaitta P.S. Saturia, Manikgonj Manikgonj, Dhaka The Alliance for Bangladesh Worker Safety Page 1/14 Introduction to the Report The following

More information

INITIAL FIRE SAFETY ASSESSMENT

INITIAL FIRE SAFETY ASSESSMENT INITIAL FIRE SAFETY ASSESSMENT Factory Address: Plot 1175 & 1179, Bashan Sarak, Vogra, PO. National University, Gazipur Sadar, Gazipur Gazipur Dhaka Bangladesh 15 Jun 2016 The Alliance for Bangladesh Worker

More information

INITIAL FIRE SAFETY ASSESSMENT

INITIAL FIRE SAFETY ASSESSMENT INITIAL FIRE SAFETY ASSESSMENT Factory Mouza Chandra, Shafipur, Kaliakoir, Gazipur Gazipur Dhaka 24 Mar 2014 The Alliance for Worker Safety Page 1/12 24 Mar 2014 Introduction to the Report The following

More information

INITIAL FIRE SAFETY ASSESSMENT

INITIAL FIRE SAFETY ASSESSMENT INITIAL FIRE SAFETY ASSESSMENT Factory Name: Maks Fashion Ltd 1 Kapashgola Road Chawkbazar Chittagong Chittagong Bangladesh 19 Apr 2014 The Alliance for Bangladesh Worker Safety Page 1/16 19 Apr 2014 Introduction

More information

INITIAL FIRE SAFETY ASSESSMENT

INITIAL FIRE SAFETY ASSESSMENT INITIAL FIRE SAFETY ASSESSMENT Factory Assessor: Plot no. A102, BSCIC Industrial Estate, Tongi, Gazipur Tongi, Gazipur Emkay Enterprises 06 Jul 2014 The Alliance for Bangladesh Worker Safety Page 1/22

More information

INITIAL FIRE SAFETY ASSESSMENT

INITIAL FIRE SAFETY ASSESSMENT INITIAL FIRE SAFETY ASSESSMENT Dhanpur, Chapapur, Kotwali, Comilla COMILLA Chittagong The Alliance for Worker Safety Page 1/16 Introduction to the Report The following report contains a site profile and

More information

EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT

EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT Factory RR Washing Limited (previously Freshtex Pvt Ltd (Washing)) Beximco Industrial Park Sarabo, Kashimpur, Gazipur Gazipur Dhaka 12 Jun 2014 The Alliance

More information

INITIAL FIRE SAFETY ASSESSMENT - EXPANSION

INITIAL FIRE SAFETY ASSESSMENT - EXPANSION INITIAL FIRE SAFETY ASSESSMENT - EXPANSION 228/1, Tin Sharak, Luxmipura, Joydevpur, Gazipur Joydebpur, Gazipur The Alliance for Bangladesh Worker Safety Page 1/18 Introduction to the Report The following

More information

INITIAL FIRE SAFETY ASSESSMENT - EXPANSION

INITIAL FIRE SAFETY ASSESSMENT - EXPANSION INITIAL FIRE SAFETY ASSESSMENT - EXPANSION Factory Plot 47-52 & 68-73, KEPZ North Patenga Chittagong Chittagong 06 Mar 2017 The Alliance for Bangladesh Worker Safety Page 1/23 06 Mar 2017 Introduction

More information

INITIAL FIRE SAFETY ASSESSMENT

INITIAL FIRE SAFETY ASSESSMENT INITIAL FIRE SAFETY ASSESSMENT Factory Anowara, Plot # G1 and G2, Korean EPZ, Chittagong Chittagong 21 May 2015 The Alliance for Bangladesh Worker Safety Page 1/22 21 May 2015 Introduction to the Report

More information

INITIAL FIRE SAFETY ASSESSMENT

INITIAL FIRE SAFETY ASSESSMENT INITIAL FIRE SAFETY ASSESSMENT Factory Assessor: 107/112 Nazrul Market 1st & 2nd floor, Chawk Bazar, Chittagong Emkay Enterprises 09 Apr 2014 The Alliance for Bangladesh Worker Safety Page 1/28 Factory

More information

INITIAL FIRE SAFETY ASSESSMENT

INITIAL FIRE SAFETY ASSESSMENT INITIAL FIRE SAFETY ASSESSMENT Factory Name: Assessor: Anzir Apparels Limited, Unit-1 Karim supermarket, Baipal, Baipal, Savar Savar Dhaka Bangladesh Emkay Enterprises 30 Apr 2014 The Alliance for Bangladesh

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT SIKDER APPAREL HOSIERY LTD. Khadun (Dug No. 342/343), Tarabo, Rupgonj, Narayanganj, Bangladesh. Factory List: 1. Sikder Apparel Hosiery Ltd. Inspected by: Pema Wangdi

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT SIDKO LIMITED PLOT NO. 36, ROAD NO. 46, GULSHAN NORTH C/A, DHAKA. Factory List: 1. N. A. Garments 2. 3. Sidko Apparels 4. Delta Ties Ltd. Inspected on April 17, 2014

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT FOPTEX (PVT.) LTD. PLOT# A/24-25, VSCIC HOSIERYFATULLAH, CHITTAGONG, BANGLADESH. Factory List: 1. Foptex (Pvt.) Ltd. Inspected by: Tashi Penjor Report Generated by:

More information

ELECTRICAL SAFETY INSPECTION REPORT ANLIMA TEXTILE LTD, DHAKA, BANGLADESH

ELECTRICAL SAFETY INSPECTION REPORT ANLIMA TEXTILE LTD, DHAKA, BANGLADESH ELECTRICAL SAFETY INSPECTION REPORT ANLIMA TEXTILE LTD, DHAKA, BANGLADESH January 14, 2014 Anlima Textile Ltd. PAGE 1 SUMMARY The Anlima compound located in Dhaka, Bangladesh was surveyed for Electrical

More information

for Walmart suppliers. About Bureauu Veritas laboratories in building and Phase 1: Pre- Assessment until the factory Phase 2: Initial Assessment

for Walmart suppliers. About Bureauu Veritas laboratories in building and Phase 1: Pre- Assessment until the factory Phase 2: Initial Assessment WALMART SUPPLIER FACTORY SAFETY ASSESSMENT OVERVIEW Wal-Mart Stores, Inc. ( Walmart ) engaged Bureau Veritas to conduct fire, building and electrical safety assessments at factories in Bangladesh designated

More information

FIRE SAFETY INSPECTION REPORT

FIRE SAFETY INSPECTION REPORT FIRE SAFETY INSPECTION REPORT DANNY'S KNITWEAR LTD. ACCORD ID: 12228 SURABARI, GAZIPUR, SADAR, GAZIPUR Other Factories: ne October 17, 2015 Page 2 Fire Safety Inspection Report Introduction manufacturing

More information

for Walmart suppliers. About Bureauu Veritas laboratories in building and Phase 1: Pre- Assessment until the factory Phase 2: Initial Assessment

for Walmart suppliers. About Bureauu Veritas laboratories in building and Phase 1: Pre- Assessment until the factory Phase 2: Initial Assessment WALMART SUPPLIER FACTORY SAFETY ASSESSMENT OVERVIEW Wal-Mart Stores, Inc. ( Walmart ) engaged Bureau Veritas to conduct fire, building and electrical safety assessments at factories in Bangladesh designated

More information

for Walmart suppliers. About Bureauu Veritas laboratories in building and Phase 1: Pre- Assessment until the factory Phase 2: Initial Assessment

for Walmart suppliers. About Bureauu Veritas laboratories in building and Phase 1: Pre- Assessment until the factory Phase 2: Initial Assessment WALMART SUPPLIER FACTORY SAFETY ASSESSMENT OVERVIEW Wal-Mart Stores, Inc. ( Walmart ) engaged Bureau Veritas to conduct fire, building and electrical safety assessments at factories in Bangladesh designated

More information

Brown University Revised June 29, 2012 Facilities Design & Construction Standards SECTION ELECTRICAL DESIGN CRITERIA

Brown University Revised June 29, 2012 Facilities Design & Construction Standards SECTION ELECTRICAL DESIGN CRITERIA PART 1 - GENERAL 1.1 Background SECTION 26 00 10- ELECTRICAL DESIGN CRITERIA A. Brown University maintains it own campus electrical distribution system which serves the majority of the buildings and facilities

More information

TIME KNITWEAR (PVT) LTD.

TIME KNITWEAR (PVT) LTD. ELECTRICAL SAFETY INSPECTION REPORT TIME KNITWEAR (PVT) LTD. Baribogh, Enayetnagar, Fatullah, Narayangonj-1400, Bangladesh Factory List: 1. Time Knitwear (Pvt) Ltd. Inspected by: Dawa Report Generated

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT MUAZUDDIN TEXTILES LTD. Plot # 235/236, East Chandura, Shafipur, Kaliakor, Gazipur, Bangladesh. Factory List: 1. Inspected by: Younten Jamtsho Report Generated by: Stabak

More information

Nirmal Chandra Sinha. Supposed to complete(dd/ MM/YYYY) Comments after Physical Inspection

Nirmal Chandra Sinha. Supposed to complete(dd/ MM/YYYY) Comments after Physical Inspection Factory Name Address Fire Safety Follow up INTIMATE APPARELS LTD Karnaphuli EPZ, Plot no. 91-93, rth Patenga Date 05/20/2014 Date Report Received 11-August/15 Date of 1 st Follow-up 08-vember/15 Date of

More information

Property risk solutions

Property risk solutions Property risk solutions Inside this issue Welcome to this edition of the Property risk solutions newsletter. This quarterly publication focuses on fixed fire protection and human element safety solutions

More information

Delta T Alert: Wireless Temperature Monitoring of Electrical Enclosures

Delta T Alert: Wireless Temperature Monitoring of Electrical Enclosures Delta T Alert: Wireless Temperature Monitoring of Electrical Enclosures Fred Baier, Level III Certified Infrared Thermographer Delta T Engineering, LLC 136 Main Street Metuchen, NJ 08840 Ph: 877-321-0576

More information

NATIONAL ELECTRICAL CODE (NEC) & NFPA 70E ARC FLASH ELECTRICAL SAFETY

NATIONAL ELECTRICAL CODE (NEC) & NFPA 70E ARC FLASH ELECTRICAL SAFETY A new twist on the National Electrical Code - a practical application workshop. If you sign up in this class, prepare to work! Day 1: Fundamentals of OSHA requirements for performing electrical work -

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT MILLENNIUM TEXTILES (SOUTHERN) LTD., Bara Rangamatia, Ashulia, Savar, Dhaka 1341, Bangladesh Factory List: MILLENNIUM TEXTILES (SOUTHERN) LTD., Inspected on April 8,

More information

Changes to NFPA 70E. - The Role of PdM &Safe PdM Work Practices. Tim Rohrer Exiscan LLC

Changes to NFPA 70E. - The Role of PdM &Safe PdM Work Practices. Tim Rohrer Exiscan LLC Changes to NFPA 70E - The Role of PdM &Safe PdM Work Practices Tim Rohrer Exiscan LLC Tim@Exiscan.com 585-705-7775 Joe Gierlach ABM Joseph.Gierlach@ABM.com 412-394-4678 Preview Electrical Safety Risk Management

More information

FIRE SAFETY INSPECTION REPORT

FIRE SAFETY INSPECTION REPORT FIRE SAFETY INSPECTION REPORT TOYO COMPOSITE KNIT GARMENTS LTD 1, SOUTH KAMALAPUR SARDER COMPLEX, DHAKA Other Factories: Pure Cotton Ltd, Knit and Knitwear Ltd June 7, 2014 Page 2 Fire Safety Inspection

More information

Safety Systems Review Retail Guidance and specification Version

Safety Systems Review Retail Guidance and specification Version Systems Review Retail Guidance and specification Version 1 2014 Membership Training Qualifications Audit and Consultancy Policy and Opinion Awards Contents Page Systems Review 1 1 Specification for Systems

More information

Interim Life Safety Measures. Healthcare Construction Certificate - Level 1

Interim Life Safety Measures. Healthcare Construction Certificate - Level 1 Interim Life Safety Measures Purpose of Interim Life Safety Management BASIC SAFETY: During renovations projects in healthcare occupancies, the basic level of protection for the occupants must be maintained

More information

Electrical Management

Electrical Management 5 WHS PROCEDURE P23-01 Page 1 of 9 Issue: 2 1. Intent The Salvation Army Australia Eastern Territory (TSA-AUE) is committed to the provision of a safe, healthy and injury free environment within the mission

More information

Electrical Safety Requirements

Electrical Safety Requirements Electrical Safety Requirements Purpose This document defines the minimum required control measures to reduce the risk of injury or illness related to electricity. Scope Applicable to all Coca-Cola system

More information

Assessing Your Airfield Electrical Distribution System

Assessing Your Airfield Electrical Distribution System Assessing Your Airfield Electrical Distribution System PRESENTED AT The 2017 Airports Conference March 30, 2017 Hershey, PA PRESENTED BY Samuel Mullen, III - Burns Engineering, Inc. 1 Presentation Objective

More information

Substation Signage. Document Number: 1-11-FR-12

Substation Signage. Document Number: 1-11-FR-12 Substation Signage Document Number: 1-11-FR-12 VERSION 1.0 June 2018 This functional requirements document is in line with the organisation's 1-11-ACS-12 Substation Signage Asset Class Strategy Intellectual

More information

APPENDIX - L INTERNATIONAL RESIDENTIAL CODE ELECTRICAL

APPENDIX - L INTERNATIONAL RESIDENTIAL CODE ELECTRICAL This Appendix (2000 IRC Appendix-L) is produced, copyrighted, and maintained by the National Fire Protection Association Association, all rights reserved. Use of this Appendix is pursuant to license with

More information

Electrical Preventive Maintenance (EPM) Program

Electrical Preventive Maintenance (EPM) Program Electrical Preventive Maintenance (EPM) Program Only qualified and properly trained persons may work on electric circuit parts or equipment. Such persons shall be capable of working safely and shall be

More information

Informational Bulletin on Mobile office Units Prepared by Mark Hilbert May 17, 2017

Informational Bulletin on Mobile office Units Prepared by Mark Hilbert May 17, 2017 Informational Bulletin on Mobile office Units Prepared by Mark Hilbert May 17, 2017 It has come to the attention of the electrical authorities having jurisdiction (AHJs) at the DOE sites there is inconsistency

More information

ELECTRICAL/MECHANICAL INFRARED INSPECTION REPORT. The Corporate Facility 2001 Freedom Way United City, USA

ELECTRICAL/MECHANICAL INFRARED INSPECTION REPORT. The Corporate Facility 2001 Freedom Way United City, USA ELECTRICAL/MECHANICAL INFRARED INSPECTION REPORT for The Corporate Facility 2001 Freedom Way United City, USA January 01, 2012 Job Number: 1111-12 TABLE OF CONTENTS I - Introduction to the Report Explains

More information

FIRE SAFETY INSPECTION REPORT

FIRE SAFETY INSPECTION REPORT FIRE SAFETY INSPECTION REPORT BEQ KNIT LTD. ZIRABO, ASHULIA, SAVAR, DHAKA Other Factories: Beq Sweaters Ltd., Tammam Design Ltd. April 22, 2014 Page 2 Fire Safety Inspection Report Introduction manufacturing

More information

FIRE SAFETY INSPECTION REPORT

FIRE SAFETY INSPECTION REPORT FIRE SAFETY INSPECTION REPORT MAHID APPAREL LTD ACCORD ID: 11956 NOWPARA, MADHABDI, NARSINGDI, DHAKA-1604 OTHER FACTORIES: NONE February 20, 2015 Page 2 SUMMARY was surveyed for fire safety on 2/20/2015

More information

SECTION (16075) - IDENTIFICATION FOR ELECTRICAL SYSTEMS

SECTION (16075) - IDENTIFICATION FOR ELECTRICAL SYSTEMS SECTION 26 05 53 (16075) - IDENTIFICATION FOR ELECTRICAL SYSTEMS PART 1 GENERAL 1.01 SUMMARY A. Section Includes: 1. Electrical identification materials and devices required to comply with ANSI C2, NFPA

More information

APPENDIX H (DESIGN SUBMISSION CRITERIA)

APPENDIX H (DESIGN SUBMISSION CRITERIA) APPENDIX H (DESIGN SUBMISSION CRITERIA) FIRE ALARM SYSTEM As per ACCORD standard Part 5, section 5.7 Fire Alarm System Design to be verified by ACCORD Chief Safety Inspector. Testing of the installation

More information

FIRE SAFETY INSPECTION REPORT

FIRE SAFETY INSPECTION REPORT FIRE SAFETY INSPECTION REPORT VINTAGE GARMENTS LTD EAST NARSHINGPUR, BURI PARA, ASHULIA, SAVAR Other Factories: ne June 1, 2014 Page 2 Fire Safety Inspection Report Introduction manufacturing complex was

More information

Energy Management and Controls

Energy Management and Controls As with the Chapter Review Tests and the Final Exam, the tests your understanding of the materials underlying the learning objectives. After you ve reviewed your answers to the Chapter Review Tests, try

More information

NLR ELECTRIC MURRAY HYDRO PLANT NORTH LITTLE ROCK, ARKANSAS

NLR ELECTRIC MURRAY HYDRO PLANT NORTH LITTLE ROCK, ARKANSAS NLR ELECTRIC MURRAY HYDRO PLANT NORTH LITTLE ROCK, ARKANSAS January, 2013 Infrared Inspection Report NLR Electric Murray Hydro Plant Company Contact James Bray Project: 09170113 2605 CHARTER OAK DRIVE,

More information

RVAC-100 VACUUM CLEANER MANUAL. For Household Use Only

RVAC-100 VACUUM CLEANER MANUAL. For Household Use Only VACUUM CLEANER MANUAL RVAC-100 For Household Use Only 790 Rowntree Dairy Road, Woodbridge, ON Canada L4L 5V3 t: 905.851.6701 f: 905-851.8376 e: info@reversomatic.com Toll Free: 1.800.810.3473 (Canada)

More information

The Social Accountability International (SAI) Fire Safety Checklist

The Social Accountability International (SAI) Fire Safety Checklist The Social Accountability International (SAI) Fire Safety Checklist Introduction The Social Accountability International (SAI) Fire Safety Checklist is a guidance tool prepared for SA8000 & BSCI Auditors

More information

Page 1 of 5 1/29/2016 4:08 PM. First Correlating Revision No. 3-NFPA [ Section No ] Submitter Information Verification

Page 1 of 5 1/29/2016 4:08 PM. First Correlating Revision No. 3-NFPA [ Section No ] Submitter Information Verification First Correlating Revision No. 3-NFPA 101-2016 [ Section No. 6.1.8.1.1 ] 6.1.8.1.1* Definition One- and Two-Family Dwelling Unit. A building that contains not more than two dwelling units, with independent

More information

SECTION ELECTRICAL IDENTIFICATION

SECTION ELECTRICAL IDENTIFICATION SECTION 16075 - ELECTRICAL IDENTIFICATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification

More information

This is a preview - click here to buy the full publication. High-voltage switchgear and controlgear

This is a preview - click here to buy the full publication. High-voltage switchgear and controlgear IEC/PAS 62271-109 Edition 1.0 2002-07 High-voltage switchgear and controlgear Part 109: Alternating-current series capacitor by-pass switches PUBLICLY AVAILABLE SPECIFICATION INTERNATIONAL ELECTROTECHNICAL

More information

FIRE SAFETY INSPECTION REPORT REDPOINT JACKETS LTD, DHAKA, BANGLADESH

FIRE SAFETY INSPECTION REPORT REDPOINT JACKETS LTD, DHAKA, BANGLADESH FIRE SAFETY INSPECTION REPORT REDPOINT JACKETS LTD, DHAKA, BANGLADESH January 3, 2014 Redpoint Jackets Ltd. PAGE 1 SUMMARY The four story factory housing Redpoint Jackets Ltd. located in Dhaka Export Processing

More information